Noncritical

Summary: Sensors ID: 1


Duration: 2days Complete: 0%
Start: October 12, 2009 Finish: October14, 2009
Noncritical
Task: BuyingSensors ID: 3
Duration: 0.5days Complete: 0%
Start: October 14, 2009 Finish: October14, 2009
Resources: Saeed
Noncritical
Task: SizingSensors ID: 5
Duration: 2days Complete: 0%
Start: October 15, 2009 Finish: October 23, 2009
Resources: Saeed, Abolfazl
Critical
Summary: Aerodynamics ID: 6
Duration: 7days Complete: 0%
Start: 10/12/09 Finish: 10/21/09
Critical Task: AirflowPattern ID: 7
Duration: 7days Complete: 0%
Start: October 12, 2009 Finish: October 21, 2009
Resources: Abolfazl
Noncritical
Summary: Geometry ID: 8
Duration: 0.89days? Complete: 0%
Start: November 12, 2009 Finish: November 13, 2009
Noncritical
Task:
Actuator, Transmission,
Sensor Place ID: 9
Duration: 0.89days? Complete: 0%
Start: November12, 2009 Finish: November 13, 2009
Resources: Abolfazl
Critical Task: AirVent DesignandSizing ID: 10
Duration: 0.89days? Complete: 0%
Start: October 21, 2009 Finish: October22, 2009
Resources: Abolfazl
Critical
Summary: Actuators ID: 11
Duration: 1.89days? Complete: 0%
Start: 10/22/09 Finish: 10/26/09
Critical Task: ChoosingActuators ID: 12
Duration: 1.78days? Complete: 0%
Start: October 22, 2009 Finish: October26, 2009
Resources: Abolfazl, Saeed
Critical Task: BuyingActuators ID: 13
Duration: 0.89days? Complete: 0%
Start: October 27, 2009 Finish: October 27, 2009
Resources: Abolfazl, Saeed
Noncritical
Milestone: TestingActuators
TaskID: 14
Date: October27, 2009
Actual Start: NA
Critical Task: SizingActuatorsandGear ID: 15
Duration: 0.89days? Complete: 0%
Start: October 28, 2009 Finish: October 28, 2009
Resources: Abolfazl
Noncritical
Summary: Circuits ID: 16
Duration: 1day Complete: 0%
Start: October 28, 2009 Finish: October29, 2009
Noncritical
Task: ChoosingCircuits ID: 17
Duration: 1day Complete: 0%
Start: October28, 2009 Finish: October 29, 2009
Resources: Saeed
Noncritical
Task: BuyingCircuits ID: 18
Duration: 1day Complete: 0%
Start: October29, 2009 Finish: October 30, 2009
Resources: Saeed, Abolfazl
Noncritical
Task: Programming ID: 19
Duration: 0.89days? Complete: 0%
Start: October 30, 2009 Finish: November 2, 2009
Resources: Saeed
Noncritical
Milestone: TestingCircuits
TaskID: 20
Date: November 2, 2009
ActualStart: NA
Critical
Summary: Transmission ID: 21
Duration: 0.89days? Complete: 0%
Start: 10/29/09 Finish: 10/29/09
CriticalTask: Buying(Ordering)
TransmissionSystem ID: 23
Duration: 0.89days? Complete: 0%
Start: October30, 2009 Finish: October 30, 2009
Resources: Abolfazl
Critical Task: TestingTransmission ID: 24
Duration: 0.89days? Complete: 0%
Start: November11, 2009 Finish: November 12, 2009
Resources: Abolfazl
Noncritical
Task: SizingTransmission ID: 25
Duration: 0.89days? Complete: 0%
Start: November2, 2009 Finish: November 2, 2009
Resources: Abolfazl
Noncritical
Summary: CATIA ID: 26
Duration: 0.89days? Complete: 0%
Start: October 21, 2009 Finish: October22, 2009
Noncritical
Task: CATIA ID: 27
Duration: 0.89days? Complete: 0%
Start: October 21, 2009 Finish: October22, 2009
Resources: Abolfazl
Noncritical
Task: Sizing ID: 29
Duration: 0.89days? Complete: 0%
Start: November4, 2009 Finish: November 5, 2009
Resources: Abolfazl
Noncritical
Summary: DraftingandDrawing ID: 30
Duration: 0.89days? Complete: 0%
Start: November 5, 2009 Finish: November 6, 2009
Noncritical
Task: DraftingandDrawing ID: 31
Duration: 0.89days? Complete: 0%
Start: November 5, 2009 Finish: November 6, 2009
Resources: Abolfazl
Noncritical
Summary: 3DPrinting ID: 32
Duration: 0.89days? Complete: 0%
Start: November 6, 2009 Finish: November 9, 2009
Noncritical
Task: 3DPrint ID: 33
Duration: 0.89days? Complete: 0%
Start: November 6, 2009 Finish: November 9, 2009
Resources: Abolfazl
Critical
Summary: Assembling ID: 34
Duration: 3days Complete: 0%
Start: 11/12/09 Finish: 11/18/09
Critical Task: Assembling&Final Testing ID: 35
Duration: 2days Complete: 0%
Start: November 12, 2009 Finish: November 16, 2009
Resources: Abolfazl
Critical Task: ChoosingSensors ID: 2
Duration: 2days Complete: 0%
Start: October 12, 2009 Finish: October14, 2009
Resources: Saeed
Critical Task: Design(Choosing)
Transmission ID: 22
Duration: 0.89days? Complete: 0%
Start: October29, 2009 Finish: October 29, 2009
Resources: Abolfazl, Saeed
Noncritical
Task: TestingSensors ID: 4
Duration: 1day Complete: 0%
Start: October 14, 2009 Finish: October 15, 2009
Resources: Abolfazl, Saeed
Critical Task: Show-off ID: 36
Duration: 1day Complete: 0%
Start: November 17, 2009 Finish: November 18, 2009
Resources: Abolfazl
Noncritical
Summary: Sizing ID: 28
Duration: 0.89days? Complete: 0%
Start: November 4, 2009 Finish: November 5, 2009
msproj11
Page 1
Critical Noncritical Critical Milestone Milestone Critical Summary Summary Critical Inserted Inserted Critical Marked Marked Critical External External Project Summary HighlightedCritical HighlightedNoncritical
msproj11
Page 2
msproj11