PROYECTO
TIPO
PROGRESIVA
:I
: 19+804.0
: 23+112.0
DIMENSIONAMIENTO
SUELO:
Cps= 2.1 kg/cm2
F= 4.10 Tn
Ws/c =
0.931 Tn/m
s = 34
m = 0.35
MURO:
gm = 2.30 T/m3
0.4 m
0.50
1.90
0.30
0.50
Empuje del
Suelo
Volteo :
Ok!
Deslizamiento :
Ok!
Soporte del suelo :
Ok!
ESTABILIDAD
H=
1.90 m
0.20
0.90
ABREVIATURAS UTILIZADAS:
Cps=
s =
m=
=
r =
gr =
gm =
H=
z=
Ws/c=
F=
(Cos 2 Cos 2
Ka Cos * ( )
Cos
(Cos 2 Cos 2
Ka = 0.29
E =
= 0
r = 34
gr = 1.41 T/m3
RESULTADOS:
1.60
0.20
RELLENO:
0.73 T
Eh = 0.73 T
Ev = 0.00 T
.5 T
Esc(h) = 0.50 T
Esc(v) =
0.000 T
0.48 T-m
Mv = 0.94 T-m
Es el peso del muro, la reaccion del puente canal, el peso del relleno y la sobrecarga existente:
F= 4.10 Tn
Ws/c =
0.9306 Tn/m
0.50
0.40
1.60
1.90
3
0.20
0.50
0.90
0.30
o'
0.20
Brazo (m)
1.47
0.18
0.62
0.56
0.28
4.10
-
Momento (Tn/m)
0.59
0.40
0.12
0.63
0.28
0.45
0.44
0.77
0.21
0.75
1.64
0.40
0.90
0.90
Me=SWi*Xi=
3.27 T-m
FSV = Me / Mv =
3.49
>
1.75
Ok!
2.1
>
1.5
Ok!
qmax = 4Fe/(3L-6e)
Hallando L/6 se tiene:L/6=
0.15 m
Como e < L/6, se tiene el caso (a), luego:
qmax =
1.1 kg/cm2
qmin =
0.5 kg/cm2
<
TIPO
PROGRESIVA
: II
: 10+364.0
: 16+160.0
DIMENSIONAMIENTO
SUELO:
Cps= 1.24 kg/cm2
F= 14.79 Tn
Ws/c =
0.931 Tn/m
s = 31.4
m = 0.35
MURO:
gm = 2.30 T/m3
0.5 m
0.50
RESULTADOS:
ESTABILIDAD
1.60
1.90
Volteo :
Deslizamiento :
Soporte del suelo :
0.30
0.50
0.80
H=
1.90 m
0.60
1.90
ABREVIATURAS UTILIZADAS:
Cps=
s =
m=
=
r =
gr =
gm =
H=
z=
Ws/c=
F=
(Cos 2 Cos 2
Ka Cos * ( )
Cos
(Cos 2 Cos 2
Ca = 0.31
E =
0.80 T
Eh = 0.80 T
Ev =
0.50 T-m
0.00 T
RELLENO:
= 0.0
r = 31.4
gr = 1.40 T/m3
.56 T
Esc(h) = 0.56 T
Esc(v) =
0.000 T
0.53 T-m
Mv = 1.03 T-m
Es el peso del muro, la reaccion del puente canal, el peso del relleno y la sobrecarga existente:
F= 14.79 Tn
Ws/c =
0.931 Tn/m
0.50
0.50
1.60
1.90
3
0.50
0.80
1.90
0.30
o'
0.60
Brazo (m)
1.84
0.55
1.31
1.46
0.74
14.79
-
Momento (Tn/m)
1.56
0.85
0.66
1.20
1.25
0.95
2.28
1.57
1.12
1.50
12.57
0.85
1.90
1.90
Me=SWi*Xi=
19.45 T-m
FSV = Me / Mv =
18.82
>
1.75
Ok!
5.4
>
1.5
Ok!
qmax = 4Fe/(3L-6e)
Hallando L/6 se tiene:L/6=
0.32 m
Como e < L/6, se tiene el caso (a), luego:
qmax =
1.208 kg/cm2
qmin =
1.0 kg/cm2
<
TIPO
PROGRESIVA
: III
: 11+076.5
: 13+494.7
: 15+276.7
DIMENSIONAMIENTO
SUELO:
Cps= 1.70 kg/cm2
F= 35.24 Tn
Ws/c =
0.931 Tn/m
s = 30.6
m = 0.35
MURO:
gm = 2.30 T/m3
0.4 m
0.50
RESULTADOS:
ESTABILIDAD
3.00
3.40
Volteo :
Deslizamiento :
Soporte del suelo :
0.40
1.00
0.90
H=
RELLENO:
= 0.0
r = 30.6
gr = 1.42 T/m3
3.40 m
1.50
3.40
ABREVIATURAS UTILIZADAS:
Cps=
s =
m=
=
r =
gr =
gm =
H=
z=
Ws/c=
F=
Cos
(Cos 2 Cos 2
Cos
(Cos Cos
Ka Cos * ( 2 2 )
Ca = 0.33
E =
2.67 T
Eh = 2.67 T
Ev =
3.03 T-m
0.00 T
1.03 T
Esc(h) = 1.03 T
Esc(v) =
0.000 T
1.75 T-m
Mv = 4.78 T-m
Es el peso del muro, la reaccion del puente canal, el peso del relleno y la sobrecarga existente:
F= 35.24 Tn
Ws/c =
0.931 Tn/m
0.50
0.40
3.00
3.40
3
1.00
0.90
3.40
0.40
o'
1.50
Brazo (m)
2.76
1.73
3.13
5.33
1.40
35.24
-
Momento (Tn/m)
4.69
1.70
3.57
2.07
5.32
1.70
14.73
2.77
3.70
2.65
59.91
1.70
3.40
3.40
Me=SWi*Xi=
91.92 T-m
FSV = Me / Mv =
19.24
>
1.75
Ok!
4.7
>
1.5
Ok!
qmax = 4Fe/(3L-6e)
Hallando L/6 se tiene:L/6=
0.57 m
Como e < L/6, se tiene el caso (a), luego:
qmax =
1.697 kg/cm2
qmin =
1.2 kg/cm2
<