Professional Documents
Culture Documents
كيف تكون بلانر محترفا - أسئلة تساعدك في المقابلات الفنية..
كيف تكون بلانر محترفا - أسئلة تساعدك في المقابلات الفنية..
:
7
10/14/2014
Planning Engineer
7 2013
) - search(
...
) - Follow by Email (
...Email address
Submit
(31) 2014
(2) 2013
)(1
)(1
...
-1 .
-2 .
-3 .
-4 .
-5
.
-6 .
-7 .
:
-1
-2 computer skills
-3
.
-4
-5 benefits
-6
-7
.
-8
:
-1 scope of work (project
) definition phases/sectional milestones
NOA-notice of award, NTP-notice to proceed.
-2 method statement
overlap tentative/ level 2
.
-3 feasibility study design stage (conceptual
) detailed bidding tender stage project life cycle:
start up planning execution &monitoring .close out
-4 ) (WBS work breakdown structure
procurement purchase order delivery .
:
LEVEL 1: PROJECT, LEVEL 2: PHASE, LEVEL 3: WORK TYPE, LEVEL 4: ELEMENT.
-5 %4-2 -5
%10 %75-65
man-hours .cost wise
-6 long lead items overseas
1/6
http://prof-planner.blogspot.com/2013/03/blog-post.html
... :
10/14/2014
stock on shelf .
-7 CPM critical path method
sub-critical paths critical activities
.total float=0
-8 lead driving resource )duration = quantity /
) ((productivity of crew * no of crews comply with .logistics
-9 night shift
intensives .
-10 resource allocation, cost loading )resource
(units=quantity/production rate resource loading
.histograms
-11 start date finish date )(SS, FF, FS, SF
FS: finish to start
SS, FF .
-12 lag, lead FS lag
lead ) (-ve lag ) (buffering time supply
chain management .
-13 flag, milestone activity
.
-14 hammock, level of effort support-type project activity dummy
on-going tasks that depend on other activities SS
FF )
.(prelims
-15 open end activity
.log
-16 total float free float forward pass early dates
backward pass late dates total float Slack free
float driving .
-17 )resource leveling, limits (max/time
max/time
smoothing
resource leveling: technique used to.
.examine unbalanced use of resources over time, and for resolving over-allocations
-18 baseline programme accepted
revised baseline.
-19 who owns the float uncritical activity total float
.first come-first served basis
-20 constrains
mandatory .
-21 update : suspension
exp finish %100
.
Activity % Complete
physical, duration, units
-22
:
progress
:
Duration Percent Complete
.
resource units
original
steps
:
Physical Percent Complete
.
manually
step weight
resource units
:
Units Percent Complete
.
resource driven schedule
-23 Progress Override, Retained Logic progress over-ride
breaks the predecessors out of sequence Continuous duration
. proceed continuously until finish
Retained Logic Interruptible
conservative Min. Relationships
strong logic .loop
-24 line of balance
resource constrained diagrams on a cumulative basis
.housing, pipelines, bridges, roads, rail and tunneling works
-25 )(BCWP, BCWS, ACWP :
BCWP: budget cost of work performed = earned value
BCWS: budget cost of work scheduled = planned value
ACWP: actual cost of work performed = actual cost
-26 EVM ) (earned value management apple to apple
SV, CV, SPI, CPI: ) KPI (key performance indicators :
Schedule variance (Sv)=earned value (ev)planned value (pv),
Schedule performance index (spi)= ev/pv
Cost variance (Cv)= earned value (ev)-actual cost (ac),
2/6
http://prof-planner.blogspot.com/2013/03/blog-post.html
... :
10/14/2014
Cost performance index (cpi)=ev/ac
3/6
http://prof-planner.blogspot.com/2013/03/blog-post.html
10/14/2014
... :
4/6
http://prof-planner.blogspot.com/2013/03/blog-post.html
10/14/2014
... :
mido mido
) - (2
mohamed maged
2014-8-23 ......
ppregister.4shared.com:
https://www.facebook.com/groups/prof.planners/360116230803315
+1
1
:
2
https://www.facebook.com/events/282614868588261
1
mohamed
maged
https://www.linkedin.com/groups/be-Prof-Planner-Planning-Engineer-8141598
+1
2
1
3
mohamed maged
..
mohamed maged
https://www.facebook.com/#!/pages/To-be-Prof-Planner-Planning-Engineer/546274345404002
Google+ -
mohamed maged
+1
2
1
hatem
mohamed maged
MS Word
/https://www.facebook.com/groups/prof.planners
: )(Atom
Share It
...
5/6
http://prof-planner.blogspot.com/2013/03/blog-post.html
10/14/2014
... :
Share this on Facebook
Tweet this
View stats
>> (NEW) Appointment gadget
- lag
94 40
.Ethereal .merrymoonmary .Blogger
6/6
http://prof-planner.blogspot.com/2013/03/blog-post.html