Professional Documents
Culture Documents
&
SURVEYING
for
Civil Engineering
By
www.thegateacademy.com
Syllabus
Transportation Engineering
Highway Planning: Geometric design of highways, testing and specifications of paving materials,
design of flexible and rigid pavements.
Traffic Engineering:
Traffic characteristics, theory of traffic flow, intersection design, traffic signs and signal design,
highway capacity.
Year
2013
2012
2011
2010
2009
2008
2007
2006
2005
2004
2003
2002
2001
2000
14.00
Overall Percentage
12.00
12.00
11.00
15.00
18.00
16.63
16.63
9.00
13.78%
8.67
8.00
17.00
17.00
18.00
THE GATE ACADEMY PVT.LTD. H.O.: #74, KeshavaKrupa (third Floor), 30th Cross, 10th Main, Jayanagar 4th Block, Bangalore-11
: 080-65700750, info@thegateacademy.com Copyright reserved. Web: www.thegateacademy.com
Syllabus
Surveying
2013
2012
2011
2010
2009
Percentage of marks
14.00
12.00
4
-
2008
2006
2007
2005
2004
2003
Overall Percentage
2.78%
3
-
THE GATE ACADEMY PVT.LTD. H.O.: #74, KeshavaKrupa (third Floor), 30th Cross, 10th Main, Jayanagar 4th Block, Bangalore-11
: 080-65700750, info@thegateacademy.com Copyright reserved. Web: www.thegateacademy.com
Contents
Chapter
#1.
#2.
#3.
#4.
CONTENTS
Transportation Engineering
Page No.
113
14 41
Traffic Characteristics
Traffic Signs
Traffic Signals
Various Methods for Finding out the Cycle
Solved Examples
Assignment
Answer Keys
Explanations
1
23
35
68
8
9
10-11
12
12 13
14
14 16
16 18
18 21
22 24
25 29
30 35
36
36 41
42 64
42
42 43
43 52
53 60
61 62
63
63 64
65 78
65 67
67 69
69 70
71 75
76 77
78
78
THE GATE ACADEMY PVT.LTD. H.O.: #74, Keshava Krupa (third Floor), 30th Cross, 10th Main, Jayanagar 4th Block, Bangalore-11
: 080-65700750, info@thegateacademy.com Copyright reserved. Web: www.thegateacademy.com
Page I
Contents
#5.
#6.
#7.
Intersection Design
79 91
92 117
Introduction
Classification of Intersection
Assignment
Answer Keys
Explanations
Subgrade Soil
Stone Aggregates
Bituminous Material
Solved Examples
Assignment
Answer Keys
Explanations
Surveying
79
79 86
87 90
91
91
92 98
98 100
100 107
108 112
113 115
116
116 117
118 - 148
118
118 122
123 132
133 144
145 146
147
147 148
#8.
Introduction
Glossary
Classification Based on Nature of Survey
Choice of Scale of Map
Assignment
Answer Keys
Explanations
149 - 156
149 150
150 151
151 152
153 154
155
155 - 156
#9.
157 - 175
157 162
162 166
167
168 - 171
172 - 173
174
174 - 175
THE GATE ACADEMY PVT.LTD. H.O.: #74, Keshava Krupa (third Floor), 30th Cross, 10th Main, Jayanagar 4th Block, Bangalore-11
: 080-65700750, info@thegateacademy.com Copyright reserved. Web: www.thegateacademy.com
Page II
Contents
#10.
#11.
#12.
176 - 189
176
176 - 177
177
178
178 182
183 - 185
186 - 187
188
188 189
205 - 213
205
205 207
207 - 208
208 211
212
213
213
Leveling
Glossary
Method of Leveling
Leveling Instruments
Special Methods of Sprit Leveling
Recording & Reduction of Levels
Characteristics of Contours
Solved Examples
Assignment
Answer Keys
Explanations
Test Questions
Answer Keys
Explanations
Test Questions
Answer Keys
Explanations
Reference Books
190 204
190 191
191 192
192
192 194
194 197
197 198
199 - 202
203
204
204
214 226
214 220
221
221 - 226
227 - 235
227 232
233
233 - 235
236
THE GATE ACADEMY PVT.LTD. H.O.: #74, Keshava Krupa (third Floor), 30th Cross, 10th Main, Jayanagar 4th Block, Bangalore-11
: 080-65700750, info@thegateacademy.com Copyright reserved. Web: www.thegateacademy.com
Page III
Chapter 1
Transportation Engineering
CHAPTER 1
1. ROMAN ROADS
Roman started 1st time construction of roads in large scale In 312 BC they constructed
Appian Way length over 580 km.
Main Features of Roman roads are:
(i) They are straight regardless of gradients.
(ii) Total thickness was as high as 0.75 to 1.2 meters.
(iii) The wearing course consists dressed large stone blocks set in lime mortar.
2. Tresaguet Construction
Pierre tresaguet development roads in France during 1764 A.D.
Main Features are:
(i) Thickness was of the order of 30cm
(ii) Consideration was given to subgrade moisture and drainage of surface water.
(iii) The top wearing surface was made up of smaller slope having a cross slope of 1 in
45 to the surface to provide surface drainage.
3. Metcalf Construction (1717 1810)
John Metcalfe was working in England and he followed the instruction of Robert Phillip.
4. Telford Construction:
His work started in early 19th century.
Main features are:
(i) He provided level subgrade of width 9 meters.
(ii) A binding layer of wearing course 4 cm thick was provided with cross slope of 1 in
45.
(iii) Thickness of foundation stone varied from 17cm at edge to 22cm at the centre.
5. Macadam Construction:
1815 onward he started in England but his new concept came in 1827. This was the 1st
method based on scientific thinking.
Main features are:
(i) Macadam was first person who suggested that heavy foundation stones are not at all
required to be placed at the bottom layer. He provided stones of size less than 5mm
to a uniform thickness of 10cm.
(ii) The importance to subgrade drainage and compaction was given so the subgrade
drainage and compaction was given so the subgrade was compacted and prepared
and prepared with cross slope of 1 in 36.
(iii) The pavement surface was also given the cross slope in 1 in 36.
(iv)Total thickness was kept uniform from edge to centre to a minimum value of 25 cm.
6. Water bound Macadam (W.B.M)
In this method the broken stones of the base course and surface course are bound by the
stone dust in the presence of moisture.
THE GATE ACADEMY PVT.LTD. H.O.: #74, KeshavaKrupa (third Floor), 30th Cross, 10th Main, Jayanagar 4th Block, Bangalore-11
Page 1
: 080-65700750, info@thegateacademy.com Copyright reserved. Web: www.thegateacademy.com
Chapter 1
Transportation Engineering
British government passed a resolution in 1927 in response to which jaykar committee was
constituted in 1927
Jay kar committee proposed that an extra tax should be levied on petrol
Recommendation made by Jayakar Committee
1. The road development in the country should be considered as a national interest as this
has become beyond the capacity of provincial governments and local bodies.
2. An extra tax should be levied on petrol from the road users to develop a road
development fund called central Road fund.
3. A semi-official technical body should be formed to pool technical knowhow from various
parts of the country and to act as an advisory body on various aspects of the roads.
4. A research organization should be instituted to carry out research and development
work.
Most of the recommendation made by jaykar committee was accepted and following
steps were taken.
1. The central Road fund was formed in 1929
2. A semi official technical body known as Indian road congress (IRC) was formed.
3. In 1939 Motor vehicle Act was started 2 in 1950 CRRI (Central Road Research Institute)
was started.
Other Measures Taken Are
4. National Highway Act was brought in 1956.
5. Highway Research Board was setup in 1973.
6. National Transport policy committee in 1978.
7. IRC has played important role in the formulation of the last three 20years road
development plane in India.
THE GATE ACADEMY PVT.LTD. H.O.: #74, KeshavaKrupa (third Floor), 30th Cross, 10th Main, Jayanagar 4th Block, Bangalore-11
Page 2
: 080-65700750, info@thegateacademy.com Copyright reserved. Web: www.thegateacademy.com
Chapter 1
Transportation Engineering
(v) Length of railway track is considered independent of the road system and hence it is
not subtracted to get the road length.
(vi)A development factor of 5% is provided for future development.
Result
The total achievement was higher that targeted but NH and SH were constructed
lesser than targeted.
It should be noted than allowance for development of agriculture and industry
during the next 20 years was made in Nagpur.
12.5
(b) Length of MDR in Km = 90 x no. of towns in state.
Classification of Roads
THE GATE ACADEMY PVT.LTD. H.O.: #74, KeshavaKrupa (third Floor), 30th Cross, 10th Main, Jayanagar 4th Block, Bangalore-11
Page 3
: 080-65700750, info@thegateacademy.com Copyright reserved. Web: www.thegateacademy.com
Chapter 1
Transportation Engineering
4. VR
Modified classification is proposed by third plan as discussed
Road Patterns
a. Rectangular or block pattern
b. Radial or star and block pattern
c. Radial or star and circular pattern
d. Radial or star and guide
e. Heragonal pattern
f. Minimum travel pattern.
THE GATE ACADEMY PVT.LTD. H.O.: #74, KeshavaKrupa (third Floor), 30th Cross, 10th Main, Jayanagar 4th Block, Bangalore-11
Page 4
: 080-65700750, info@thegateacademy.com Copyright reserved. Web: www.thegateacademy.com