Q-4) 10 men can complete a job in 14 days.

How long will it take 4 men to finish the same


job if they work at the same rate?
a) 33 days
b) 35 days
c) 37 days
d) 39 days
Answer:

b) 35 days

Solution:
Men : Days
10

14

__________
We know that Men aur Days main hamesha inverse relation hota hai.
Oper ki snap main diye gaye arrows b usi reverse relation ko zahar kartay hain.
Inko likhnay ka method ye hota hai k pehlay numerator (Batay k oper) tail wali value likhain
phir denominator (Batay k nechay) head wali value likhain.
10/4 = X/14
=>
X = (10/4) x 14 = 35 Days Answer