1. Grounding cables.
2. Rack position in Diagram.
3. Dummy slots e.g. WRFU.MRFU
4. Power breakers check Ampere of breakers and power configuration on SAF 63A
5. VSWR test max software 1.30dbm in Huawei.
6. Feeder and jumpers cables installation, looping, weather proofing, grounding. PHYSICAL layout.
7. Roxtec is sealed and fixed well after new cables installation.
8. Indoor outdoor labeling.
REJECTED
1.
2.
CIVIL ISSUES
1. Roxtec.
2. Bus bar.
3. Grounding. Indoor out door
4. Tower Load.
Life load, dead load, wind load, etc
Tubular three leg masts, angular four leg lattice towers, and mobile site with telescopic towers.