Indicative Timetable for Jatiluhur-Jakarta Pipeline Project

NOVEMBER 2014

DECEMBER 2014

JANUARY 2015

FEBRUARY 2015

MARCH 2015

APRIL 2015

TT Meeting & Budget Approval


Mobilization

Water Quality Analysis


Detailed Demand Analysis
Detailed Supply Analysis
Identification of pipeline transmissions
Assessment of WTP, Pipeline Route and Pumps Stations Options
Investigating PPP Options & Cost Estimates
Undertaking Risk Assessment

Prepare RFT & draft contract PSC