Professional Documents
Culture Documents
Pm-Levelling & Monitoring
Pm-Levelling & Monitoring
Project Management
4. What are the resource implications of the schedule for the activities?
5. Because a project never proceeds exactly as planned, how can the project manager
quickly recognize and react to a surprise that might otherwise unfavorably affect the
projects duration?
2
An advertising campaign.
A political campaign.
Performing a complex surgery.
Filming a major motion picture.
PROJECT MANAGEMENT:
THE 3 PHASES AND 10 STEPS
Step 1:
Step 2:
Step 3:
Step 4:
Project Decomposition
Specification of the Precedence Relationships
Estimation of the Activity Durations
Construction of the Project Network
Step 5:
Step 6:
Phase II: Planning & Scheduling
Step 7:
Step 8:
Phase III: Monitoring & Replanning
Code
A
B
C
D
E
F
G
H
I
J
K
L
M
N
Description of Activity
Hiring of Manager of Computer Services Department
Structural Modifications
Enlarging and Resurfacing of Parking Lot
Hiring of Staff of Computer Services Department
Purchasing and Receipt of Computer
Electrical Modifications
Heating and Cooling Modifications
Plumbing Modifications
Exterior Painting and Installation of Exterior Fixtures
Installation of Computer
Sheetrocking of Walls and Ceiling
Training of Staff of Computer Services Department
Interior Painting and Interior Decorating
Landscaping
Estimated
Duration
(days)
10
19
13
8
14
4
1
3
5
4
6
8
9
7
Predecessors
None
None
None
A
A
B
B
B
B
E, F, G
F, G, H
D, J
K
C, I
Responsibility
Special
Requirements
D (8)
A (10)
E (14)
START
L (8)
F (4)
J (4)
G (1)
K (6)
B (19)
M (9)
FINISH
H (3)
I (5)
N (7)
C (13)
An activity's Latest Finish Time (LFT) is the earliest possible time at which the activity can finish without causing the
project to finish after its earliest finish time.
Step 7: Computation of Each Activitys TS and Identification of the Critical Path
An activity's Total Slack (TS) is the maximum possible increase in the activity's duration that will not increase the project's
earliest finish time (assuming that all other durations remain the same).
A critical activity has a Total Slack of 0. The critical path consists of the critical activities. (It is possible to
9
have more than one critical path.)
NOTE: If you need to shorten the project duration by more than one day, then
repeat the above procedure one day at a time.
10
F [3]
K [2]
M [3]
G [4]
H [1]
I [3]
N [3]
C [4]
0
9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38
TIME
11
F [3]
K [2]
M [3]
G [4]
H [1]
I [3]
N [3]
C [4]
0
10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38
TIME
F [3]
K [2]
M [3]
G [4]
H [1]
I [3]
N [3]
C [4]
0
12
10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38
TIME
F [3]
K [2]
M [3]
G [4]
H [1]
I [3]
N [3]
C [4]
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38
TIME
= EST
= LST
= In Between EST & LST
13
F [3]
K [2]
M [3]
G [4]
H [1]
I [3]
N [3]
C [4]
0
10
11
12
13
14
15
16
17
18
19
20
TIME
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
35
36
37
38
35
36
F [3]
K [2]
M [3]
G [4]
H [1]
I [3]
N [3]
C [4]
0
10
11
12
13
14
15
16
17
18
19
20
TIME
21
22
23
24
25
26
27
28
29
30
31
32
33
34
F [3]
K [2]
M [3]
G [4]
H [1]
I [3]
N [3]
C [4]
0
2
= EST
7
= LST
10
11
12
13
14
15
16
17
18
19
20
TIME
21
22
23
24
25
26
27
28
29
30
31
32
33
34
14
37
38
ACTIVITY
REQUIRED SIZE OF
DAILY WORKFORCE
(laborers)
A B C D E F G H
J K L M N
Note: In the preceding Gantt Charts, the above numbers were the [bracketed
numbers] that appeared after the activity codes.
15
F [3]
K [2]
M [3]
G [4]
H [1]
I [3]
N [3]
C [4]
0
10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38
TIME
13
13
LABORERS
12
11
11
10
9
8
7
6
6
5
2
1
0
0
10
11
12
13
14
15
16
17
18
19
20
TIME
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
16
38
F [3]
K [2]
M [3]
G [4]
H [1]
I [3]
N [3]
C [4]
0
10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38
TIME
18
18
17
16
16
15
15
14
13
12
LABORERS
12
11
11
10
10
9
8
7
6
5
4
3
2
1
0
0
10
11
12
13
14
15
16
17
18
19
20
TIME
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
17
38
F [3]
K [2]
M [3]
G [4]
H [1]
I [3]
N [3]
C [4]
0
= EST
10 11
12 13 14 15 16 17 18 19 20
TIME
= In Between EST & LST
= LST
21 22 23 24 25 26 27 28 29
30 31 32 33 34 35 36 37 38
LABORERS
12
11
11
10
9
8
7
6
4
3
2
1
0
0
10
11
12
13
14
15
16
17
18
19
20
TIME
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
18
38
13
13
12
11
11
10
LABORERS
9
8
7
6
6
5
2
1
0
0
10
11
12
13
14
15
16
17
18
19
20
TIME
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
35
36
37
38
37
38
18
18
17
16
16
15
15
14
13
12
LABORERS
12
11
11
10
10
9
8
7
6
5
4
3
2
1
0
0
10
11
12
13
14
15
16
17
18
19
20
TIME
21
22
23
24
25
26
27
28
29
30
31
32
33
34
11
11
10
9
8
LABORERS
7
6
4
3
19
2
1
0
0
10
11
12
13
14
15
16
17
18
19
20
TIME
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
1.
2.
In fact, from among all possible Hybrid Schedules, there is one that has a
peak resource usage of 10 laborers.
What happens when there is more than one resource?
20
2.
Considering the most up-to-date information, the project manager should revise the estimate of all activity durations.
(At the time of revision, there is no uncertainty about the durations of the activities that have already finished.
However, for those activities either in-progress or not-yet-started, the most up-to-date information should lead to
more accurate estimates of the durations.)
Using these revised estimates of the activity durations, the project manager should determine a revised plan by
21
repeating Phase IIs planning and scheduling.
Project Monitoring
Earned Value Analysis (EVA)
23
Monitoring Progress
Compare actual expenditure by week with
planned budget
Compare actual vs budget spent by
milestone
Earned Value Analysis
24
25
27
28
30
20
10
0
1
11
13
15
17
19
21
29