Professional Documents
Culture Documents
Dobbins PDF
Dobbins PDF
Agenda
Industry Standards
Structure Hardware
Cable Attachment Hardware ADSS
Cable Attachment Hardware OPGW
Installation Apparatus
OPGW Installation Methods
ADSS Installation Methods
Key Installation Issues
Cable Diameter
MRDT and UTS
Cable Construction Type
Cable Diameter
Heliformed deadend
Reinforcing rods
Aluminu
Aluminum
m
or copper
ground
ground
wire
clamp
FiberLign deadend
Hi-Bus Suspension
Hi-Bus Trunion
0 to 20 Line Angle
Slip rating to 20% for UTS
under 25Klbs
Top Mount Style
Superior Vibration Resistance
Hi-Bus Trunnion
Single Suspension
Double Mechanical Suspension
31 to 60 Line Angle
Slip rating to 3000 lbs
Vertical load at 25Klbs
Yoke Plate/Anchor Shackle
Double Suspension
Bonding Clamp
Damper System
Used to control Aeolian Vibration
Engineered to cable diameter,
tension, and span
Software analysis program provides
specific recommendation of number of
dampers and locations
OPGW MFGR provides
recommendations
Stockbridge Damper
Spiral Dampers
Torque-balanced design
Mechanical Deadend
Cable Diameter
MRCL and UTS
Jacket Type
Mechanical Deadened
Tangent/Suspension Choices
Tangent (Trunion)
Suspension
Corona Ring
Vibration Dampers
Aeolian Vibration Control
Distribution Applications
Spiral Vibration Damper
Transmission Applications
Spiral Vibration Dampers
Stockbridge Dampers
Installation Equipment
Reel Stands
Reel stands are designed to be used with
tensioners to supply the necessary hold-back
tension to the cable
Reels are not designed to withstand the
forces developed by braking during high
tension stringing operations
Direct tension stringing from the
reel at cable installation stringing
tensions should not be attempted
Bullwheel Characteristics
Recommended guidelines
Semicircular grooves with depths of 50% or more
than the cable diameter, and with a flare angle of
5 to 15 from the vertical center line reference
The minimum radius at the bottom of the groove
should be at least 35 times the diameter of the
cable
Elastomer lined grooves or other smooth surface
finish
Puller Characteristics
The system should be capable of
maintaining a constant and even tension
Equipped with tension indicating and limiting
devices
Braking system to maintain a constant holdback tension at various pulling speeds
Positive braking systems are required for
pullers and tensioners to maintain cable
tensions when pulling is stopped
Fail safe braking systems are recommended
Travelers/Blocks
Lined Blocks Recommended
Large Diameter for:
First position after payoff
Final position before take-up
Heavy Angles (25 or greater)
Smaller Diameters
Tangent
12 minimum sheave diameter
Running Ground
Safety device for personnel
protection
Protects personnel from induced
voltages and transients
Requited at pay-out and at take-up
locations
Must be tied to a made ground of
multiple grounding rods
flare
vertical
Diameter
(minimum)
Bull Wheel
70 X cable OD
st
1 and Last
Structure Stringing
Block
Angle Structures
(> 20 )
Tangent Structures
(< 20 )
40 X cable OD
Cable
Manufacturers
Recommendation
Typically < 30 X
cable OD
Pull Rope
Torque Balanced
High Dielectric
Low Elongation
High UTS
Abrasion Resistance
Anti-Rotation Device
The use of the ARD depends upon the construction of the cable.
This device is utilized to avoid cable twisting during the pulling
operation.
Tension Hoist
Dynamometer
Utilized for final tensioning process
Must be rated for 2X the maximum
sagging tension
Typical accuracy is 0.5% of full
scale reading of dynamometer
Pre-Pull Checklist
Verify power system outage and key power company contacts for call
outages
Verify fiber integrity by testing reels and comparing to factory readings
Inspect pull location for best setup of payout end verses the pulling end or
the direction
Identify key concern areas such as heavy line angle changes, road
crossings or elevation changes
Verity length of pull verse length of cable. Be sure to plan for extra needed
for payout and pulling set up location. Account for sag requirements.
Frame tower or pole attachment hardware ahead of pull
Set up all travelers on tower structures
Verify communications of payout and pulling technicians
Installation Diagram
Pay-out end.
Take-up end.
4 to 5 wraps on BW.
Reef per mfgr.
Breaking mechanism.
Proper traveler sizes.
ADR if required.
Structures framed
Road crossings prepared
Attach cable to helicopter leader rope
(150) with wire mesh grip and clevis
swivel
Load cable and pull rope, start payout
process with Helicopter
Transfer at last structure to puller and presag to maximum installation tension
Target sag deadend segment to deadend
segment
12-7
Diameter (in.)
Modulus (kpsi)
Weight (lbs/ft)
Maximum Rated Design Tension
(MRDT) (lbs)
Rated Tensile Strength (RTS) (lbs)
Span ranges
Critical spans
SAG-10 Output
46
12-22
What Not to Do
During OPGW Installation
1.
2.
3.
4.
Do not locate the reel of OPGW too far from the tensioner.
5.
Do not allow the OPGW cable to sag down between the reel and
the tensioner.
6.
7.
48
12-22,23
What Not to Do
During OPGW Installation
8.
9.
10.
11.
Do not fail to utilize the correct type and size of cable grips.
12.
13.
49
12-23
What Not to Do
During OPGW Installation
14.
15.
Do not fail to check and/or test the ground resistance at the base
of each tower to ensure that it has a resistance at or below 10 to
15.
16.
Do not fail to check the condition of the existing shield wire if you
are planning to use the existing wire to pull in the cable.
17.
Do not fail to test the fibers immediately before the reels of cable
are installed.
50
Pre-Pull Checklist
Verify power system outage and key power company contacts for call
outages
Verify fiber integrity by testing reels and comparing to factory readings
Inspect pull location for best setup of payout end verses the pulling end or
the direction
Identify key concern areas such as heavy line angle changes, road
crossings or elevation changes
Verity length of pull verse length of cable. Be sure to plan for extra needed
for payout and pulling set up location. Account for sag requirements.
Frame tower or pole attachment hardware ahead of pull
Set up all travelers on tower structures
Verify communications of payout and pulling technicians
11-20
ADSS Installation
Back Pull Method
Pay-out end.
Take-up end.
4 to 5 wraps on BW.
Breaking mechanism.
Proper traveler sizes.
11-21
ADSS Installation
Drive-off Method
54
Structures framed
Road crossings prepared
11-8
57
11-25
What Not to Do
During ADSS Installation
1.
2.
3.
Do not locate the reel of ADSS too far from the tensioner.
4.
Do not allow the ADSS cable to sag down between the reel and
the tensioner when pulling.
5.
6.
58
11-25
What Not to Do
During ADSS Installation
7.
8.
9.
10.
Do not fail to utilize the correct type and size of tensioning grips.
11.
12.
Do not fail to test the fibers immediately before the reels of cable
are installed.
59
Sheath Repair
End of Presentation