Professional Documents
Culture Documents
Intro To Construction 2
Intro To Construction 2
CIEG 486-010
Construction Management
Contractual arrangement: at-risk or
management services for fee only
or
Act of managing the construction process
Construction Management
Contractual arrangement
Construction management personnel can
represent owner or contractor
CM manages the basic resources of
construction
Basic Resources
workforce
subcontractors
equipment
construction
plant
material
information
time
money
Project Management
Optimize the three attributes of: quality, cost,
and time
Principle objective of a construction manager
is to complete each project on time and within
budget, while maintaining acceptable levels
of safety and risk
Design Phase
Bid
Construction phase
Traditional Design-Bid-Build
Time
Savings
Design Phase
Construction phase
Lighting
West Approach
East Approach
Bridge Deck
Trusses/Framing
Suspended Steel
Main Cables
Towers
West Piers
East Piers
Test Piles
Anchorages
Contract Types
Traditional vs. alternative
Classification by method of award and
method of pricing
Model contracts have been developed
by AIA, AGC, CEC, DBIA, CMAA, and
Engineers Joint Contract Documents
Committee (EJCDC)
Contract Types
Method of Award
1. Competitive bidding
formally advertised public work
selective invitation for private work
awarding of contracts by:
Lowest responsible bid or
Best value i.e.: technical score price or
price + time(ft), and other variations
Contract Types
Method of Award
2. Negotiated contracts
Generally private work
Benefits include flexibility of pricing arrangement
Often used on projects of large size and great
complexity
Owner may value expertise and integrity of a
particular contractor and can award contract without
competition that may otherwise exclude that
contractor from the work
Method of Pricing
Fixed-price
1. Lump sum
Traditional, single fixed price
Predetermined price that includes profit,
overhead, and all other costs
Greatest risk to contractor resulting in a
higher markup (the greater the risk, the
higher required rate of return )
Most common contract form
Method of Pricing
Fixed-price
2. Unit-price contract
Prices of specified units of work are fixed or
predetermined
Actual cost to the owner will vary with actual
quantities placed
Best used when details and general character
of the work are known, but quantities are
subject to variation
Risk of unbalanced bids
Method of Pricing
Cost-plus
Method of Pricing
Cost-plus
Construction Contracts
Prequalification of bidders
Evidence of satisfactory previous experience
Financial stability
Advanced or specialized prequalification may be
required as dictated by the magnitude and nature
of the work
Bid bonds are often required
Payment bond
Contract form or
agreement
General conditions or
provisions
Supplemental and/or
special conditions
Plans
Specifications
Carefully considered
Expressed clearly
Time-tested
Comprehensive
Fair
Balanced
Applicable to the elements of a construction projects
Construction Contracts
bidders are required to:
Construction Contracts
contract documents should:
Include a hierarchy to determine which
documents govern in case of conflict, i.e.:
DelDOTs hierarchy
Not contain ambiguous language
Not contain exculpatory clauses
Inspection of materials
Inspection of field work
Authority of the Engr.
Duties of the inspector
Permits and licenses
Labor considerations
Work done by the owner
Lines and grades
Order and discipline
Performance
Final inspection &
acceptance
Retainage
Bonding and insurance
Guarantee of equipment
Borings
Spare parts
Force majeure
Indemnification
Liens
Labor laws
Differing site conditions
Delays and extension of time
Liquidated damages
Consequential damage
Occupational safety, and
health of workers
Permits, licenses, and
regulations
Termination for default by
contractor
Suspension of work
Warranties and guarantees
Specifications
Standard, supplemental, and special
provisions
two types of specifications:
method specification dictates equipment
and procedures
performance spec specifies only the
desired end result or product
should include hierarchy
Hierarchy
Governing ranking of contract components in
case of a discrepancy (DelDOT)
General Notices
Special Provisions
Plans
Supplemental Specifications
Standard Construction Details
Standard Specifications
Zoning Regulations
imposed by local zoning commissions
Environmental Regulations
imposed by the EPA, State DEP (DNREC), or local
agency
Shop Drawings
structural steel details & erection plan
erection procedures (safety)
PS/PC concrete items
shoring & underpinning details
jacking plans and calculations
scaffolding and falsework
concrete formwork design and details
construction sequencing diagrams
Shop Drawings
cofferdam design & details
dewatering procedure
stream diversions
pipe and ductwork fabrication details
reinforcing steel bending diagrams and bar lists
structural timber elements
ornamental iron or steel
maintenance of traffic plans (alternates)
Change Orders
a written order issued by the owner to the
contractor for a change to the contract within
the scope of work
change orders are written for:
extra work
increasing or decreasing the contract quantities
alterations
Contracts
Liquidated damages
Incentive/Disincentive (bonus/penalty)
Acceleration
Increase crew levels, crew size
Add shifts and/or extend work hours
CPM schedule is an extremely valuable tool in
analyzing delay claims
Types of Claims
delay or disruption claim
extra work claim
acceleration
impossibility-of-performance claim
defective design claim (error or omission)
interference claim
superior knowledge claim
Dispute Resolution
Early settlement between parties
Alternative depute resolution (ADR)
negotiation
arbitration (1 or 3 members)
mediation
neutral advisors
Dispute Review Board (DRB)
3 or more odd number of board members selected
evenly by both sides
Litigation
sometimes unavoidable; usually undesirable; but
sometimes best method
Credits
Credits reimbursement from contractor to
owner for work eliminated (lump sum
contract or item)
Credit may also be given when specified
performance criteria is not met
Claims Avoidance
producing comprehensive, accurate, contract
documents
constructibility review
clear understanding of contract requirements prior to
bidding
having good administrative procedures in place
open and honest communication
timely troubleshooting
Claims Avoidance
Claims avoidance begins in the preconstruction phase
Contract documents need to be clear,
accurate, comprehensive, and fairly
distribute risk
100%
AyI
0%
Concept &
Feasibility
Design and
Engineering
Startup Oper.