You are on page 1of 14

QUT Research Week 2005

Conference Proceedings
Edited by A. C. Sidwell
45 July 2005, Brisbane, Australia

A COLLABORATION OF:

COBRA
the Construction Research Conference of the RICS
Foundation
AUBEA
the Australasian Universities' Building Educators
Association Conference
3rd CIB Student Chapters International Symposium
CIB W89
Building Education and Research
CIB TG53
Postgraduate Research Training in Building and
Construction

Australasian
Universities
Building
Educators
Association

The Queensland University of Technology


Research Week International Conference
4-8 July 2005
Brisbane, Australia

Conference Proceedings

Editor: A. C. Sidwell
July 2005

Published by:
Queensland University of Technology
Australia

ISBN 1-74107-101-1

COST VALUE RECONCILIATION (CVR) IN THE UK


CONSTRUCTION INDUSTRY
Paul Stephenson and Matthew Steven Hill
Faculty of Development and Society, Sheffield Hallam University, Sheffield, UK

ABSTRACT
The application of cost value reconciliation (CVR) in the construction industry is
considered an important part of cost management for the financial control of
construction projects. However, it is often assumed that CVR is not widely utilised
by contracting organisations operating in the UK construction sector. This is
purported to be due to the associated resource requirements and technical skills
necessary to accurately incorporate the technique into an organisations processes.
Clearly, this is especially the case with regard to smaller contractors with less
financial capabilities, and a requirement to keep overhead costs to a minimum. This
assumption has formulated the basis of this research.
The review of literature indicated that the field of CVR is not a widely covered topic.
This paper therefore considers the application of CVR in the UK construction
industry. This includes how CVRs are produced and the information output, in
addition to a measure of its utilisation within industry. Additionally, areas are
identified that may be adapted in order to increase its application. From the research
theoretical CVR models are developed aimed at enhancing CVR as a management
tool. The proposed models are devised to widen the application of CVR amongst
contractors with less financial capabilities or for those that operate mostly on shortterm contracts. Additionally, the proposed models will provide the opportunity to
enhance the benefits to those who regularly apply the technique in practice.
Keywords: budget monitoring, cost and value forecasts, project cost accounts.

INTRODUCTION
There are many aspects of construction work which impinge on the process of
bringing a project to a successful conclusion (Pilcher, 1994). Almost every project
undertaken within the construction industry is to some extent unique and will contain
some elements of uncertainty. Therefore, losses and possible ultimate financial failure
are an ever present problem, and even the most sophisticated contractors may operate
on a very low percentage profit turnover (Upson, 1987). With clients demanding
more complex and sophisticated buildings, to be constructed with increasingly tight
budgets, cost control and financial management is of paramount importance.
Therefore, for all construction projects, costs must be monitored and controlled,
whether from the point of view of the client or owner, or the designer or builder.
It is suggested that many contractors only compare cost and value when the final
account has been agreed. However, it is essential that such reconciliations are
completed during intermediate stages of individual contracts, primarily to establish the
respective profitability but also to identify any financial difficulties.

Stephenson and Hill

Financial control through a CVR can provide detailed information to identify the need
for reserves, downturns in cash flow, and information to make decisions to stem future
losses (Perceval, 1997).

OVERVIEW OF COST VALUE RECONCILIATION


Cost Value Reconciliation (CVR) brings together the established totals for cost and
value to illustrate the profitability of a company. Its intention is to ensure that the
profits shown in company accounts are accurate and realistically display the current
financial position. In this respect, the purpose of CVR is twofold. Firstly, there is the
requirement to provide statutory accounts, which is a legal obligation to provide
certain financial information (Perceval, 1997), in addition to the Standard Statement
of Accounting Practice number 9 (SSAP9), (ICAEW, 1998) which set out accounting
recommendations and requirements for the construction industry. Secondly, and
perhaps more importantly, is the provision of information which can have a direct
bearing on the management of the operations within a company, at all levels
(Perceval, 1997). This is of course dependent upon the information being properly
and accurately provided and interpreted. Therefore, the information must be in a
format that will enable management decisions to be made, taking influence from the
figures displayed.

APPLICATION OF CVR
A CVR at a specific data is relatively meaningless unless it is accompanied by an
analysis of the final position of the contract (Capon, 1990). Without additional data;
such as a cost to complete analysis, or means of being certain of a profit at the final
position of the contract, there can be no justification of taking profit. However, the
detailed preparation of the reconciliation together with the associated forecasts to
completion, provide management with a very powerful tool for the identification of
potential problems or critical elements of the contract. In this respect, if
reconciliations identify that a project is making a loss, the process has relatively
limited value without being able to identify the reasons for the losses occurring and
thus providing vital information to prevent a repetition of the loss (Harrison, 1993).
An effective CVR form should generally contain: the initial tender figures and
expected profit, forecast figures at completion for value and profit, the current
payment applications by the contractor, the current certified value, an account of any
adjustments or provisions to the certified valuation, the cost to date at the accounting
period in question, and the cash received to date including the retention deducted and
certified sums unpaid (Barrett, 1992).
Such information will facilitate a
comprehensive CVR assessment to be completed, which will allow the current
financial position of the project to be determined. This will also better indicate the
final position of a contract.
The responsibility for cost value reconciliations will vary from company to company.
However, it is essential that those responsible are aware of all of the implications and
requirements of SSAP9 (Upson, 1987). Those performing such financial management
techniques should be prudent to ensure that they are accurate and realistic to prevent a
company claiming that they are more profitable than they actually are.
There is no defined frequency at which CVRs should take place and there is no timing
criteria set in SSAP9. However, good management practice denotes that to effectively
control project finances such reports should be carried out on a reliable and regular

CVR in the UK construction industry

basis, and should ideally coincide with either the availability of cost figures or current
valuations, and preferably both (Upson, 1987).

DATA COLLECTION AND ANALYSIS


To ascertain the current status of CVR in the UK postal questionnaires were obtained
based on one hundred contractors operating in the construction sector, throughout
England, Scotland and Wales. The selected contractors were identified by turnover,
as being medium or large companies. Also, such organisations will have the most
experience and knowledge of the production and application of CVR, and therefore,
will be in a more suitable position to provide rich and consequential data, especially
regarding how CVR can be standardised. A sample of the findings is presented here.
Contractors were specifically asked if they utilised CVR techniques to control project
costs. From the response received 84% utilise CVR and the remaining 16% used
other techniques. Attention was also focused on how are CVRs were produced within
organisations to establish if there was a common trend in the production of cost value
reconciliations. This provided an insight into what aspect of the CVR process, either
cost or value, could best be adapted. From the respondents, 81% indicated that they
produced CVRs by amending the interim valuations for the work completed, and the
remaining 19% made adjustments to their cost accounts. By adjusting the interim
valuations, the production of CVRs was considered to become far more complicated
and requires greater resources expenditure, regarding cost, time, and technical skills.
This is one aspect that is of particular significance as considerable developments could
be made to the way in which the production of CVRs is approached, especially by
smaller companies.
Additionally assessment was made of the awareness of information output of CVRs,
either during the CVR process or once the reconciliation has been completed. Such
data relates to both individual projects and the operations and provisions of a
company. Again this question was subdivided to determine not only the awareness of
the information output of CVRs, but also the perceived usefulness of such data. Table
1 illustrates the responses received. Here, the respondents were more aware of the
potential to derive information from CVRs regarding individual projects rather than
that relating to the management of the company. This was particularly so where
additional information was provided, which generally related to statements of cost
accruals and claims recovery.
Table 1: Analysis of the information output from CVRs
Information output from CVRs

Awareness of the
information:
Yes

Accurate statement of the present profit/loss on


individual projects
Accurate statement of the current profit/loss for
the present accounting period
Accurate statement of the current profit/loss for
the present financial year
Current cash position of company

No

100%

Usefulness of the
information:
Very

Not very

100%

97%

3%

100%

94%

6%

94%

6%

78%

22%

91%

9%

56%

44%

84%

16%

53%

47%

75%

25%

Summary of the companys provisions


Details of overhead recovery on individual
projects

Stephenson and Hill

Data were also collected in relation to CVR and other cost control techniques. This
provided for identification of where CVR was under performing or where other
techniques were performing better than CVR. From such data, ideas can be generated
relating to standardisation of the application of CVR that could also be validated by
hard evidence. The majority of organisations used a budget monitor system followed
by those using a cost coding system. These were the main two techniques used
though others such as, earned value management, and network analysis methods were
also applied to control project costs. The main features of the cost control systems in
the survey were also reflective of the perceived usefulness of the techniques. Budget
monitoring systems illustrated close assessment of identified budgets with actual
expenditure for monitoring purposes. Cost coding systems identified the features of
identifiable costs which could be coded and related to cost centres and sections of
work, some being integrated into company accounting systems. Earned value
management, while being less popular than the previous two, provides the opportunity
for project assessment in terms of cost and time. Data can be established, and also
presented graphically, for budgeted cost of work performed (BCWP), actual cost of
work performed (ACWP) and budgeted cost of work performed (BCWP) i.e. earned
value. This provides a powerful tool for use in project cost control and is starting to
gain more widespread use within UK construction. Network analysis, however, did
not feature strongly in the survey, although its use in cost control can be directly
related to programmed activities of construction work. The responses from companies
using these techniques are shown in figure 1.

40

Number of respondents

35

34

30
23

25
20
15

10
5
1
0
Budget monitor
system

Network analysis

Cost coding
system

Earned value
management

Cost control techniques

Figure 1: Additional cost control techniques utilised

Furthermore, the reasons for the selection of the cost control techniques utilised,
including CVR, were examined to identify what the determining factors are. The
responses received are demonstrated in figure 2.
It was identified that company polices and best practice procedures were the most
dominant selection factors. With regards to CVR, best practice procedures tend to
relate to SSAP9 and the production of management of company accounts. This also

CVR in the UK construction industry

30
27
25

Number of respondents

25

20
15
15

10
7

6
4

0
Company policy

Best practice
procedures

Legislation/audit
trails

Cost/time
constraints

Contractual
obligations

Contract length

Selection factors

Figure 2: How the techniques utilised are determined

relates to compliance of company policy, although only 18% of the respondents


regard audit trails as determining selection factors.
Additionally, cost and time constraints were a predominant selection factor, as it was
highlighted by 39% of the responding contractors. In relation to CVR, as highlighted
previously, the time and cost to complete is a particular drawback of the technique and
is one of the main factors that discourages contractors from utilising the process.
In terms of specific advantages of CVR over these techniques, respondents identified
that the specific aspects of CVR that stand out from other cost control techniques
relate to the accuracy of the information produced. Though, it was stated that this
information is subjective to judgment and is only as accurate as that used in its
production. Despite these factors, it was stated:
That close control over project cost, company provisions and overheads,
and value earned are vital to the success of a construction company, and
that CVR provides such control the most accurately.
Furthermore, it was also recognised that greater control outside the boundaries of an
individual project is received from CVR above other techniques. These responses
validate the utilisation of CVR as a primary measure to be used in the construction
sector, though through its current use, its application amongst smaller contractors in
many cases remains unjustifiable.
The disadvantages of CVR over these techniques focused on skill requirements of the
individuals producing the CVRs, and that they are based on the judgment of a specific
individual. In this respect, this should not be a factor to discourage the application of
CVR as it must be considered that such factors are not the cause of the technique but
rather the individuals involved and that prudence is an essential factor in CVR
accuracy and success.

Stephenson and Hill

CVR MODEL
From the knowledge gained on the application of CVR and the information extracted
from the research, a theoretical model was developed in order to standardise the
application of CVR and enhance the benefits. This is shown in Figure 3.

Establish project cost


accounting system for
duration of project

External interim
valuation received from
Cut-off cost accounts to establish
cost to date for work performed
Completion by contractor
Amend external valuation
(to incorporate: claims,
variations, overvaluation,
and undervaluation)

Adjust cost to date figures


(to include cost accruals for
materials, plant, labour and
subcontractors)
Completion by contractor

Completion by contractor

Add provisions for additional


future work not recoverable
under the contract

Reconcile adjusted totals to determine


present project performance and profit

Note: Completion by contractor refers to an


individual with detailed knowledge of the
contract (e.g. a site manager)

Information Output:
profit earned to date,
profit expectations of
project, movement in
company provisions,
present cash position

Figure 3: Flowchart of proposed CVR model

To increase the utilisation of CVR amongst contractors with lower financial


capabilities or who largely participate in contracts of a lesser value, a CVR system
could be set up where each individual project establishes its own cost accounts, which
is on-going for the duration of the project.

CVR in the UK construction industry

By this method, when the interim external valuation is certified by the clients
architect, the project costing account is cut-off to coincide with the date of the
valuation. Here a total for the cost to date can be established, which will cover the
same quantity of work as that certified in the valuation. However, before these totals
can be reconciled, some preliminary adjustments may be required.
From the external valuation received, adjustments may be necessary to incorporate the
anticipated value of any disputed items or variations involved in the contract, or for
items that have been under/over valued. For such adjustments SSAP9 requires a
conservative estimate to be made. Therefore, the completion of this aspect of the
CVR can be performed by an individual with detailed knowledge of the contract, but
without specialist skills in this field; for example, a site manager. By producing the
totals for the valuation side, a large proportion of the required calculations and
assessments will have been transferred to the clients QS. Thus, the process of
establishing the value earned to date is largely shortened whilst the accuracy is
maintained. However, such a process does denote that the value earned may be
determined by the client rather than the contractor if the external valuations are not
closely examine to ensure they represent the work completed. Furthermore, additional
calculations may be necessary to incorporate any provisions required for future costs
not recoverable under the conditions of the contract.
To maintain the accuracy of the reconciliations, the project cost will need to be closely
monitored to ensure that the costs included have actually been incurred and therefore,
that cost matches revenue. If the contractor can make every endeavour to ensure that
the monthly valuations coincide as nearly as possible with the companys accounting
period, then this will quicken the CVR process as it will substantially reduce the
adjustments to be made. However, this is often unlikely, and therefore to ensure that
they represent the same quantity of work, necessary adjustments may be required to
the established actual cost to date totals. The adjustments will be predominantly made
to material, plant and subcontractor costs.
When the interim valuation is prepared materials incorporated into the works or stored
on site will be included in the detailed make-up of the valuation. However, the
relevant invoices for such materials may not necessarily have been raised by the
supplier or indeed received by the contractor, and consequently they will be excluded
from the cost accounts. In such circumstances a schedule of accruals will need to be
prepared in order that cost may be adjusted to match the valuation.
Where plant is hired externally similar problems to those outlined above will also
apply to plant invoices. In fact, it is probably more common for plant invoices to be
delayed as plant hire companies often delay raising invoices until the plant is taken off
hire. Moreover, delivery and collection charges may also distort the true costs at
various stages of the contract, and the contractor may be contra-charged for any losses
or damage to plant. It is therefore essential that provisions for anticipated losses or
damage are made and any adjustments for distortions or late invoices are made to the
cost accounts.
Payments to subcontractors are likely to be inaccurate during the course of an
accounting period for a number of reasons. Primarily, there is likely to be a difference
in the date of the close down of the cost accounts to the date that the subcontractor
submits their application for payment. Such payment applications will cover a
difference quantity of work to that of the cost accounts, and therefore, adjustment will
be necessary to the cost of the subcontracted work to ensure that it covers the same

Stephenson and Hill

volume of work. Such adjustments can easily be made on a pro-rata basis. In this
respect, the valuation of the subcontractors work may also be inaccurate as it may be
considerably under or overvalued. In such circumstances, the contractor will be
required to establish an accurate valuation of the work carried out by the subcontractor
and take the relevant costs of such work into their cost accounts. Additional
difficulties may occur where the subcontractor has claims against the main contractor
which have not been settled. Here, the amount of the claim must be added to the
adjusted cost.
The process of the cost side of the reconciliation, including the adjustments that may
be required, is largely unchanged from that of the traditional CVR process. Though
additional calculations are necessary to primarily establish the cost to date when the
cost account is cut off. However, this does not denote that additionally skills or
resources are required on the individual producing the CVR. Again, any individual
with detailed knowledge of the contract, such as a site manager, can prepare such
calculations, as they are relatively straight forward. This should therefore become
routine practice in a short period of time. Additionally, it is unlikely that any training
would be required to enable such an individual to produce such data.
Once realistic and accurate totals have been calculated for the costs incurred and value
earned, including provisions for future additional costs and foreseeable losses, the
figures can be reconciled. By subtracting the cost from the value, the present
profitability performance of the contract will be determined.
At project level, the information output, accuracy and control received from this CVR
model would be the same as a traditional CVR system; thus enabling management to
make essential decisions regarding the performance of the project. However, the
skills, resources and time required to produce the reconciliation outcomes would be
significantly shorten as a large quantity of the calculations will be produced outside
the organisation. As previously highlighted, this does transfer the establishment of the
contractors value earned to the clients representatives, and therefore, the contractors
must demonstrate caution.
Conversely, at an organisation level, the simplified CVR model is less satisfactory as
accurately transferring the established data to company accounts becomes difficult.
This is because the dates at which the reconciliations will take place will be
determined by the production of the external valuations for each project, rather than a
standard cost cut off date across all projects undertaken by the contractor. Therefore,
annual reporting would require additional reconciliations or the continuation of
techniques already in place. Furthermore, on long-term contracts, the determination
of attributable profits to be taken into a companys accounts would also become
difficult, especially in conformance to the provisions of SSAP9 and general rules of
prudence.
However, it was established that the level of control extracted from CVRs by those
that apply the technique was significantly less than for contracts of a smaller value or
shorter duration. With regards to smaller contractors, it could be assumed that they
would be predominantly involved in such contracts and therefore the level of control
received at project level would be sufficient to justify its application.

CVR AND BUDGET MONITOR SYSTEMS


The CVR model previously proposed does not significantly advance the technique
and is rather an adaptation of the traditional CVR process. From the research

CVR in the UK construction industry

undertaken it was noted that some contractors proposed the application of CVR in
conjunction with a budget monitor system. By combining such techniques, it is
possible to enhance management control of project costing accounts in addition to the
variation of standards of prudence. This should inevitably increase the accuracy of the
information produced from the reconciliations completed. If a budget monitor system
is to be used in conjunction with CVR, it should be set up alongside project cost
accounts, to allow relevant costing information to be transferred across. This is
illustrated in figure 4.

Cost Value Reconciliation


(CVR)

Budget Monitor System


(BMS)

Receive External Valuation


from clients QS

Record and monitor costs


incurred and cost accruals

Calculate cost to date to


for work completed to
valuation date

Completed by contractor

Adjust valuation and costs


totals as necessary to
accurately represent value
earned and costs incurred

Completed by contractor

Assessment of provisions
used to aid calculations

Reconcile established totals


to determine current trading
position of contract

Records of cost accruals


and project progress
against programme, used
to aid calculations

Forecasts of financial
performance of future events
used to aid calculations

Establish cost to complete


and anticipated future
position of contract

Information produced:
Profit/loss summaries,
Provisions summary,
Cash position,
Future position of contract,
Progress assessments,
Performance of work executed

Figure 4: Flowchart of CVR and BMS model used to enhance management control

Cost value reconciliations provide a snap shot of the financial status at a particular
time, without necessarily presenting information regarding the final outcome of a
project. Combined with a budget monitory system, data concerning future resource

Stephenson and Hill

levels, methods of sequence of work, and programme progress, would also be


provided. This would facilitate cost/time assessment and provide a direct relationship
between cost and progress/performance on construction projects.
Financial control through a CVR and BMS would also provide detailed information to
identify the need for reserves, downturns in cash flow and information to make
decisions to stem future losses. Therefore, management should use CVRs in
conjunction a BMS to highlight variances and consider what can or should be done to
improve the current position. Such considerations are mainly concerned with adverse
variances, but opportunities to improve on a favourable variance should not be
overlooked. In this respect, the combination of a CVR and BMS provide management
with relevant information allowing them to make appropriate decisions with regards to
future activities to be undertaken on a project.
The main advantage of utilising a BMS is to add to the accuracy of the information
produced, which will be received through the determination of the future position of
the contract. As work commences more is known about the likely actual costs of
future work. For example, the number of resources required in the performance of
major activities, sub-contracts let at greater or smaller margins than provided in the
tender, and progress against programme. By bringing such data together it will be
possible to set out the expected costs and income from the main activities, which may
reveal that the original targets and profit expectations may no longer be attainable, or
even may be exceeded. For such information the establishment of costs to complete,
foreseeable losses, future provisions or unprofitable future work becomes far simpler
to calculate. Furthermore, it will also indicate the areas of the contract or programme
requiring change or remedial action, in far greater detail than could be established
solely from a CVR.
Using a BMS in conjunction with CVRs would certainly enhance the performance and
accuracy of the information produced, and the extent of management control from a
traditional CVR. However, such a system would require a greater number of
resources, certainly in relation to IT provisions, but would also have cost and time
constraints. Therefore, with regards to the application of such a system amongst
smaller contractors, the additional resources requirements and levels of control may
be too vast to justify its utilisation. This is especially so if the budget is to be used in
conjunction with the CVR model as accurately transferring the information produced
to company accounts would remain difficult.
Such a system would therefore be better suited to a traditional approach to CVR,
where the reconciliations are produced at the close of the companys cost accounts for
all projects undertaken. Here the budget system would certify and enhance the
accuracy of the information produced by control in the standards of prudence, but
would also greatly aid management in their decision making processes. Additionally,
profits taken up on long-term contracts would be further certified, allowing companies
to ensure their accounts are fairly representative of their actual trading position. In
this respect, using the two techniques in conjunction would be better utilised by larger
contractors with the financial capabilities to establish and support the resource
demands.

SUMMARY
From the research and the application of CVR in the UK construction industry it has
been established that, as a whole, the full potential of CVR is being realised by those

CVR in the UK construction industry

that utilise it. It was observed that CVR is mostly applied as a management tool, at
both project level and throughout the financial management of company operations.
The research also identified the essential characteristics of CVR in addition to specific
areas which were comparably underperforming. The theoretical models developed
on the findings of the research demonstrate how CVR could be adapted to increase the
benefits realised by contractors.
Firstly, a model was identified that would increase the application of CVR amongst
contractors with lower financial capabilities, referred to as smaller contractors. Such
companies could not justify the application of a traditional CVR technique as the
value received, with regards to the level of control desired, would be largely
outweighed by the resource input required. Therefore, by simplifying the process of
producing CVRs without reducing the accuracy of the information output at project
level, the introduction of project costing accounts provide a satisfactory alternative.
More conclusively, by utilising CVRs in conjunction with a BMS, the benefits
received are enhanced as a contractor is more able to forecast and control future
activities and is able to base decisions made on reliable information. Additionally, by
combining the techniques the accuracy of the information produced is validated as the
BMS reduces the judgments to be made and restricts variances in standards of
prudence; thus enhancing the benefits received.

REFERENCES
Barrett, F. R. (1992) Cost Value Reconciliation (2nd edition), Berkshire, The Chartered
Institute of Building.
Capon, G. C. C. (1990) Construction Industry: An industry accounting and auditing guide,
London, Chartac Books.
Harrison, R. S. (1993) The transfer of information between estimating and other functions in
a contractors organisation, Construction Papers, Berkshire, The Chartered Institute
of Building.
Perceval, C. S. (1997) Management and Financial Reporting, Construction Papers,
Berkshire, The Chartered Institute of Building.
Pilcher, R. (1994) Project Cost Control in Construction (2nd edition), Oxford, Blackwell
Scientific Publications.
The Institute of Chartered Accountants in England and Wales (ICAEW) (1998) Standard
Statement of Accounting Practice 9 (Revised): Stocks and long-term contracts,
London, The Institute of Chartered Accountants in England and Wales.
Upson, A. (1987) Financial Management for Contractors, Oxford, BSP Profession Books.

You might also like