Professional Documents
Culture Documents
Construction Claims Management Towards An Agent Based Approach
Construction Claims Management Towards An Agent Based Approach
INTRODUCTION
Over the past three decades, the construction industry
has experienced an increase in claims, liability exposures and disputes, along with an increasing difficulty
in reaching reasonable settlements in an effective,
economical and timely manner (Barrie & Paulson,
1992). The unique, dynamic and complex nature of the
industry inevitably leads to a situation where conflicts
are bound to arise, and claims are inevitable. In fact,
claims are now considered as a way of life for the
construction industry (Bradley & Langford, 1987), as
shown by the following:
Onyango (1993) found that 52% of all UK construction projects ended up with a claim of some
type;
Keane (1994) reported that 1.2 billion could be the
subject of construction claims or disputes at any one
time and that more than 83% of contractors claimed
for one or more time extensions during 1992-94 in
the UK;
Semple et al. (1994) identified that more than half of
claims constituted an additional cost of at least 30%
of the original contract value based on their survey of
construction projects in Canada. In addition, about a
third of claims amounted to at least 60% of the
original contract value. In some cases, the claim
values were almost as high as the original contract
value.
185
2001 Blackwell Science Ltd
186
Ren, Z. et al.
2001 Blackwell Science Ltd, Engineering, Construction and Architectural Management 8 | 3, 185-197
(e) pricing;
(f) negotiation;
(g) dispute resolution and settlement.
The current industry practice shows that the main
challenge of claims management is not from the overall
management process, but from the ineffectiveness of
management activity at each stage. The key aspects
include how to justify a proposed claim, how to
quantify and present it with full and detailed documentation, and how to negotiate successfully with
the client and his agent (Levin, 1998). For example,
identification of causes of claims and proper documentation have been recognized as the two most important
and difficult factors to justify a claim. The complex
causes and effects of construction claims make it
difficult to clearly address the claim events and liabilities, which is one of the major barriers for the
resolution of claims, and the major reasons for disputes.
Meanwhile, documentation is extremely important
for the justification of claims as well as the whole
claims management process although it is time-consuming, and is rarely directly rewarded (Wilson, 1982).
Proper records are crucial for justifying the identified
claims, analysing the project scope change and addressing the cost of the identified claim.
Following the justification of a claim, the next task
is to quantify the claim, which includes both the direct
costs or delays caused by the unanticipated events,
and the cumulative impacts of such events. However,
arguments are often generated about the rates of
compensation, quantity of the impacts, and especially
the composition of the cumulative effects of the claim
event, such as loss of productivity, disruption and
indirect costs. These items, by nature, are ambiguous
and sensitive. Some of them are impossible to quantify
with precision even with the best information available.
Therefore, it is very difficult to reach a satisfactory
solution between project participants. Part A of Table 1
shows that the numbers of claims for indirect cost items
are higher than for direct cost items. Part B indicates
that claims for such items are more probably to be
disputed. In most cases, negotiations are the main
approaches to resolve such conflicts before they finally
become disputes.
Negotiations go on throughout the whole claims
management process from the justification to the
settlement of a claim. Although standard contracts
like ICE do not suppose that claims will be settled
by negotiation, in practice, and wisely so, many claims
especially those with greater uncertainty such as
material pricing, cost of disruption, and indirect costs
are settled through negotiation between the contractor
2001 Blackwell Science Ltd, Engineering, Construction and Architectural Management 8 | 3, 185-197
187
1 8 8
Ren, Z. et al.
2001 Blackwell Science Ltd, Engineering, Construction and Architectural Management 8 | 3, 185-197
Part B
Claim items
Ranking
Site overhead
Loss of productivity
Loss of revenue
Financing costs
Equipment costs
1
2
3
4
5
1
2
3
4
5
Premium time
Wrong calculation
Poor presentation
Engineer
Willingness to protect himself against any harm
Discouraging any claim caused by the
failure of act of the engineer
Client
Willingness to pay less for more work
Discouraging claims
2001 Blackwell Science Ltd, Engineering, Construction and Architectural Management 8 | 3, 185-197
189
190
Ren, Z. et al.
DEFICIENCIES IN C L A I M S M A N A G E M E N T
PRACTICE
Despite the extensive studies on claims management
theories and practices, the increasing incidence of
claims and disputes imply that the current claims
management principles and process are ineffective in
meeting industry requirements. Because of the volatile
nature of construction projects, it is also unrealistic
to expect that claims can be avoided or resolved by a
single principle or method. The improvement of
2001 Blackwell Science Ltd, Engineering, Construction and Architectural Management 8 | 3, 185-197
win/lose strategy;
stubborn negotiation style;
making concessions for the sake of a relationship;
bargaining vs. negotiation;
establishing fixed objective vs. a range;
failing to choose right negotiation team members;
failing to plan negotiation;
unclear authority;
failing to document negotiation.
Low client
involvement
2001 Blackwell Science Ltd, Engineering, Construction and Architectural Management 8 | 3, 185-197
191
192
Ren,
Z. et al.
2001 Blackwell Science Ltd, Engineering, Construction and Architectural Management 8 | 3, 185-197
Example
This case involves a seven-town water supply project.
According to the design, the intake structures in G, P
and A towns were the same. The walls of the intake
chamber were based on driven concrete piles. The
length of pile was 8 m with 7.5 m to be driven into the
riverbed. The contractor's quotation for the piling work
was $90 000. According to the contractor's schedule,
the piling work would be made sequentially in G, P and
A towns. After starting the work, the contractor found
that piles could only be driven 3.5 m into riverbed. The
engineer thought the problem was caused by the contractor's old piling machine and reminded the contractor that it was the contractor's responsibility to drive the
piles to the designed level. As a result, the contractor
2001 Blackwell Science Ltd, Engineering, Construction and Architectural Management 8 | 3, 185-197
193
194
Ren,
Z. et al.
2001 Blackwell Science Ltd, Engineering, Construction and Architectural Management 8 | 3, 185-197
S U M M A R Y AND C O N C L U S I O N S
Despite the extensive studies of claims avoidance and
claims management at both pre-construction phase and
construction phase, the continuing escalation in construction claims and disputes show that the solutions
offered by these approaches are inadequate. This paper
has reviewed developments in construction claims
management and highlighted the major deficiencies in
current procedures. One of these is inefficiency in
claims negotiations. T h e paper proposes the use of
intelligent agent technology (particularly MAS) to
overcome these deficiencies. Multiagent systems offer
the potential to improve the efficiency of the claims
negotiation by automating aspects of the negotiation
process such that distributed construction team
2001 Blackwell Science Ltd, Engineering, Construction and Architectural Management 8 | 3, 185-197
195
196
Ren, Z. et al.
ACKNOWLEDGEMENTS
T h e work described in this p a p e r is funded b y the
Engineering a n d Physical Sciences Research Council,
E P S R C u n d e r its Innovative M a n u f a c t u r i n g Initiative
(IMI).
REFERENCES
Adams, K.K. (1988) The development of an expert system for the
analysis of construction contract claims. MS Thesis, University
of Illinois, Urbana-Champaign, IL.
Alkass, S., Mazerolle, M., Tribaldos, E. & Harris, F. (1995)
Computer aided construction delay analysis and claims
preparation. Construction Management and Economics, 13,
335-352.
Badger, W.W. & Gay, S.W. (1996) The top ten lessons
learned in construction contracting. Cost Engineering, 38,
20-24.
Barrie, D.S. & Paulson, B.C. (1992) Professional Construction
Management: Including CM, Design-Construct and General
Contracting, 3rd edn. McGraw-Hill, Inc., New York.
Bradley, S. & Langford, D.A. (1987) Contractor's claims.
Building Technology and Management, June/July, 20-23.
Bramble, B.B. & Callahan, M.T. (1992) Construction Delay
Claims, 2nd edn. Wiley, New York.
Cottam, G. & Hawker, G. (1992) The Institution of Civil
Engineers' Conditions of Contract for Minor Works: A User's
Guide and Commentary. Thomas Telford, London.
Cox, R.K. (1997) Managing change orders and claims. Journal
of Management in Engineering, 13, 24-31.
Cross, J.G. (1977) Negotiation as a learning process. In: The
Negotiation Process: Theories and Application (ed. I.W. Zartman), pp. 29-54. Sage Publications, London.
2001 Blackwell Science Ltd, Engineering, Construction and Architectural Management 8 | 3, 185-197
2001 Blackwell Science Ltd, Engineering, Construction and Architectural Management 8 | 3, 185-197
197