You are on page 1of 50

Detailed Project Report 5 MW Solar Power Plant

MGM Minerals Ltd

Detailed Project Report

Contents
1
2

Executive Summary............................................................................................. 4
Introduction.......................................................................................................... 6
2.1 Overview of Indian Power Sector...................................................................8
2.2 Initiatives of the Central Government in Renewable Energy Sector...............8
2.3 Initiatives of Orissa Government in Renewable Energy Sector:.....................9
3 Brief Profile of the Company............................................................................... 10
3.1 Introduction................................................................................................. 10
3.2 Promoters Background................................................................................. 10
4 Project Background............................................................................................ 12
5 Meteorological information................................................................................. 14
5.1 Radiation Climatology of India.....................................................................14
5.2 Radiation Climatology Of Orissa..................................................................21
5.3 Meteorological Data..................................................................................... 21
5.4 Climate Data................................................................................................ 22
6 Site Selection..................................................................................................... 24
5.1 Profile of the District.................................................................................... 24
5.2 District Map.................................................................................................. 25
5.3 Profile of the Land........................................................................................ 25
6 Technical Features.............................................................................................. 26
6.1 Proposed technology....................................................................................26
6.2 Plant Layout................................................................................................. 27
6.3 Plant Specification....................................................................................... 27
6.4 Civil Infrastructure....................................................................................... 31
7 Power Evacuation............................................................................................... 33
8 Project Execution Plan........................................................................................ 34
9 Operational Features.......................................................................................... 36
9.1 Factors Effecting Generation........................................................................36
9.2 Organization of power plant O &M...............................................................37
9.3 Protection of People and Equipment............................................................38
10
Financial Analysis............................................................................................ 39
10.1 Key Assumption........................................................................................... 39
10.2 Project Cost.................................................................................................. 40
10.3 Means of Finance......................................................................................... 40
10.4 Profitability Statement.................................................................................41
10.4.1 Projections of Performance, Profitability and Repayment......................41
10.4.2 Projected Cash Flow...............................................................................43
10.4.3 Projected Balance Sheet........................................................................44
10.4.4 Interest and Repayment Schedule.........................................................46
10.5 Financial Analysis......................................................................................... 47
10.5.1 Debt Service Coverage Ratio:................................................................47
10.5.2 Internal Rate of Return:.........................................................................48
11

Project Contribution to the sustainable development.....................................50

Detailed Project Report

1 Executive Summary
The techno - commercial feasibility report will highlight the technical and financial
aspects of the proposed project activity of 5 MW Grid Connected Solar Power
generation project at Khurda district of Orissa State under Built Own Operate (BOO)
mode. With a strategy to contribute towards sustainable development priorities of
the host country government by investing in renewable energy technology, MGM
Minerals Limited is developing a solar energy project in the state of Orissa.
Technical Aspects:
1
2

Proposed Capacity
Project Site

3
4

Type of system
Type of PV Modules

5
6

Projected Land Required


Power
Conversion
Efficiency of PV Module
Total Modules required
Module capacity
Inverter Capacity
Projected Annual Energy
Production
Capacity Utilization
factor
Grid Evacuation

7
8
9
10
11
12

13
14

Life Time
Power Plant
Composition

5 MW
Village: Patrapada
Tehasil: Tangi
P.S.: Tangi
District: Khurda
State: Orissa
Country: India
Latitude-1958'31"N to 1958'44"N
Longitude-8527'43"E to 8528'7"E
Fixed Structure
A poly crystalline silicon cell is a combination
of more than one silicon cell in the form of
wafer. This system can operate at an efficiency
of 14.6% and is significantly cheaper than
single crystalline cells.
25 Acres
13%
17856
280 Wp
500 kW Inverters (10)
8.322 MU with Degradation factor of 0% per
annum
19%
The Power Generated at 415 V in the plant will
be stepped up to 33/132 kV and connected to
the 33/132 kV substation of GRIDCO which is
available nearby the project site.
20 Years
Solar array, solar modules, power conditioning
system, control room, data logging system,

Detailed Project Report

15

Expected Annual Green


House Gas Emission
Reduction
Expected
Commissioning
Project Promoter

16
17

monitoring system, junction boxes, cables and


other accessories.
6990 tCO2e

September 2010
MGM Minerals limited

Financial Aspects:
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16

Capital Cost
Debt Equity Ratio
Rate of Interest
Term Loan
Loan Tenure
Moratorium
Equity Contribution
Power Sale Price
Pay Back Period With CDM
Pay Back Period Without CDM
DSCR with CDM
DSCR without CDM
IRR with CDM
IRR without CDM
NPV @10% discount with CDM
NPV @10% discount without
CDM

4995 Lakhs INR


01:01
15%
2500 Lakhs INR
10 Years
3 Years
2500 Lakhs INR
Rs 15/Unit
8 Year
9 Year
1.85
1.78
12.79%
11.74%
480.85
303.25

Detailed Project Report

2 Introduction
Energy usage has a dichotomous relationship with the development of the
civilization. With rapid growth in urbanization and industrialization, the pressure is
now on the energy sector to meet up the growing demand so as to sustain the
human energy requirement for day to day activity and support growth. Over use of
fossil fuel on the other hand is result in depletion of the finite fossil fuel reserve and
bringing about environmental degradation. Concern over the sustainability of the
energy supply and the environmental issues due to over use of the finite resources
is forcing the human race to think of a judicious solution of meeting up the energy
requirement without disturbing the ecological balance and raising concern over the
energy security.
In the wake of rising fossil fuel price, bleak projection of the fossil fuel reserve and
increasing concerns over countrys energy security; the government is strategized
towards a radical shift in the power sector plan and favoring the enhancement of
the renewable energy in the power generation mix. With an objective to deepen
institutional reform concerted effort has been made in Indian power sector by the
government with specific focus over the renewable energy sector.
JNSSM Scheme:
With an objective to harness the huge untapped solar energy potential in the
country and promote self energy sufficiency and independency, the Government of
India has launched promotional scheme and incentives to enhance private sector
participation in the field. The project is being conceptualized considering benefits as
mentioned in Jawaharlal Nehru National Solar Mission (JNNSM) for setting up Grid
connected Solar Power Plants. Jawaharlal Nehru National Solar Mission (JNNSM) aims
at development and deployment of solar energy technologies in the country to
achieve parity with grid power tariff by 2022. In the first phase i.e. till 2013 the
mission targets 1100 MW of solar power both thermal and photovoltaic. The mission
has also set up a national level entity i.e. the NTPC Vidyut Vyapar Nigam Limited
(NVVN) who would purchase all the power generated from such solar power plants
at tariff determined by the Central Electricity Regulatory Commission (CERC). At
present the CERC has announced a tariff of Rs 17.91 per unit.
Orissa has been at the forefront in the use of renewable energy and demonstrates
its effective utilization to the nation.
Benefits of Grid Connected Solar Power Systems:
a. The project activity will act as a corner stone towards diversification of national
energy supply and lower dependency on fossil fuel. Such initiative will also
contribute towards bridging up of the demand supply gap which is well reflected

Detailed Project Report


in peak shortage ranges around 14% whereas energy shortage is about 8.8% at
national level.
b. To meet the huge energy requirement in order to sustain the current economic
and industrial growth with diversity and 5% spinning reserve a capacity addition
of 72,000 MW is required during the Eleventh Plan period which accounts for a
considerable amount of capital investment; so such initiative by the project
proponent will obviously promote private sector participation in harmonizing the
growth requirement of the country and will assist in stimulating and accelerating
the commercialization of renewable energy technologies and markets at the grid
level under private ownership.
c. The deployment of project activity would also support governments mission of
achieving of 10% of total planned power generation capacity addition through
renewable.
d. Successful implementation of the project will address the environmental concern
and global warming. Generating power using solar energy will reduce green
house gas emission associated with generation of electrical energy from
combustion of fossil fuel in grid connected power plant that would have
generated otherwise. The project will also result in reducing the pollution load
due to emission of SOx, NOx and TSP which would have emitted otherwise for
generating equivalent quantum of power in the fossil fuel based power plant.
Energy is the backbone of human development and progress. The growing
industrialization, changes in life style is paving towards sharp rise in the energy
demand with an projected rise of more than half of the current demand over the
next twenty five years while the condition of energy supply becoming increasingly
uncertain due to finite availability fossil fuel, enhancing the concern over the energy
security. The increasing demand of energy is slowly depleting and exhausting the
natural resources. If not dealt in sensible and sustainable way will result towards
complete exhaustion of the existing natural resources. Utilizing renewable energy
resources can be considered as an identical solution towards judicious use of the
existing natural resources before it is too late.
Power generation through use of conventional energy sources has always been a
stress full activity in terms of its impact over the environment. These effects are
wide ranging and include perturbation of global climate, threat to endangered
species and towards the biodiversity. Even such impacts also entails towards human
health, destruction of land and production of radioactive and toxic waste. Using of
renewable energy sources and thereby reducing the consumption of fossil fuel can
offer our planet a chance to reduce carbon emissions, clean the air, and put our
civilization on a more sustainable footing. It also offers countries around the world
the chance to improve their energy security and spur economic development.

Detailed Project Report

2.1

Overview of Indian Power Sector

Energy is the sine qua non of development. India with over a billion people, today
only produces 728962 MU against the annual energy requirement of 799578 MU of
electricity leaving over 600 million Indians, a population equal to the combined
population of USA and EU, without access to electricity. This constrained energy
access is reflected, in the relatively low Human Development Index of India. With an
economic growth slightly above 8% and projected growth rate of over the same the
country is proceeding towards serious dearth of power. The Central Electricity
Authority (CEA) has projected concern over serious power shortage in the coming
fiscal. Indian Power sector is highly fossil fuel dominated one owing to the
comparatively lower cost of power generation from the same. Fossil fuel comprises
of 63.3% of the total installed capacity rest being catered by large hydro power
project 24.87%, nuclear 2.81% leaving 9.02% from renewable. However, with the
improvement in technology and declaration of the incentives from the government
in terms of tariff support and tax break on renewable products is expected to be
commercialized the sector in the near future. The sector is expected to grow
outward from the vibrant domestic capital market, increased activities in the area of
project financing, and private equity investment.
With an installed capacity of 146752.81 MW, which is highly fossil fuel dominated
the country is facing the serious problem of energy shortage in the range of 10.5%
and peak deficit in the range of 13.5%. The power shortage is prevailing and
steadily dominating in spite of consistent sectoral growth in terms of enhancement
of installed capacity. Such demand supply viability gap has occurred in the back
drop of high economic growth, rapid industrialization and abrupt change in life style
leading enhancement of per capita energy consumption. In order the match the
pace of growth and fulfilling the deficit the sector is expanding its capacity leading
towards depletion of the fossil fuel reserve, concern of enhanced environmental
pollution and energy security. The high capital cost of installation, lack of
commercialized technology, lower Capacity Utilization Factor and inconsistency in
supplying of power owing to its high dependency on the nature has hindered the
prioritization and development of the renewable energy sector.

2.2

Initiatives of the Central Government in Renewable


Energy Sector

The ever growing concern over the energy security of the nation had initiated the
thought process of attaining energy self sufficiency for the nation. The very idea of
Energy Self sufficiency was identified as a major driver for promoting renewable

Detailed Project Report


energy technology. The prior experience of oil shock in 70s, increasing crude price
in the global market and uncertainties associated with its supply had paved way
towards formulation of strategy under Commission for Additional Sources of Energy
in the Department of Science & Technology in March 1981. The Commission was
charged with the responsibility of formulating policies and their implementation,
programmes for development of new and renewable energy apart from coordinating
and intensifying R&D in the sector. In 1982, a new department, i.e., Department of
Non-conventional Energy Sources (DNES), that incorporated CASE, was created in
the then Ministry of Energy. In 1992, DNES became the Ministry of Non-conventional
Energy Sources which was re-christened as the Ministry of New and Renewable
Energy in October 2006. Meanwhile the main course power sector has undergone a
massive transition and reform from monopolistic SEB era to a separate generation,
transmission and distribution utilities, regulatory bodies and participation from
private and foreign players promoting a competitive approach to bridge up the
future challenge of the increasing demand, energy security and global
environmental concern. Initiatives of the government to promote participation in
Renewable Energy Sector are as follows:
1. Out of the overall target of 70,000 MW power generation installed capacity
addition during the 11th Plan period, 14,500 MW (about 20%) capacity additions
is proposed from renewable.
2. A provision of Rs. 3925 crore is proposed as subsidy for grid-interactive and
distributed renewable power, including captive power which would save
conventional power.
3. Provision of Rs. 200 crore has been kept for subsidy for solar power (gridinteractive and distributed/ decentralized).
4. Proposal for Rs. 220 crore of financial outlay on research, design and
development of solar photovoltaic under 11th Plan.
5. Planned capacity addition of 30,000 MW is envisaged for the 12 th and 13th Plan
Period.
6. Accelerated depreciation benefit for tax purpose in the first year of installation.
7. Relieve of exercise duty on manufacture of most of the finished product.
8. Low import tariff for capital equipment and most of the material and
component.
9. Soft loan to manufacturers and user of renewable energy technologies.
10.Five year tax holiday for tax generation project.
11.Remunerative price under alternative power purchase policy by the state
government for the power generated through renewable energy technology fed
to the grid by private party.
12.Facility for banking and wheeling of power.
2.3

Initiatives of Orissa Government in Renewable Energy


Sector:

Detailed Project Report


The state of Orissa has been at the forefront of adopting renewable energy
technologies. The State Government under the aegis of Dept. of Science and
Technology, constituted Orissa Renewable Energy Development Agency (OREDA) as
a nodal agency in 1984 with a view to popularize the exploitation and use of
renewable energy resources in the state. Since, its inception, OREDA has provided
renewable energy solutions to more than 2.00 Lakhs households in the state by
providing solar photovoltaic power plants, solar home light systems, solar street
light systems, biomass gasifier and biogas plants. The National Biogas & Manure
Management Program (NBMMP) has been one of the major programs of OREDA right
from its inception. Orissa is one of the leading states in the country as far as the
biogas programme is concerned. OREDA has bagged two gold shields during 1995 96 & 1999 - 2000 for best overall performance at the national level.
OREDAs vision is to make 10% of all new power capacity addition for the period up
to 2012 from renewable energy. Orissa is the first State in the Country to take up
Power Sector Reform to ensure stable and quality power at a reasonable cost. The
Energy Department has three public Sector Undertakings viz. Grid Corporation of
Orissa Limited (GRIDCO), Orissa Hydro Power Corporation Limited (OHPC) and
Orissa Power Generation Corporation Limited (OPGC) under its Administrative
control. The Orissa Electricity Regulatory Commission (OERC), which is a quasi
judicial independent body, ensures a transparent regulatory regime in the power
sector of the state.

3 Brief Profile of the Company


3.1

Introduction

MGM Minerals Limited is a part of 100 Crore MGM Group and is into mining and
exporting iron ore, having its own mines in Sundargarh district of Orissa.
The Group is setting up an integrated steel plant of 0.25 MT per annum capacity
including power plant of 16 MW Capacity through WHRB process. The first phase of
the above plant will be commissioned in 4-5 months time. The plant is being set up
in Dhenkanal district of Orissa. The plant includes sponge iron plant, waste heat
recovery power plant and steel billets manufacturing facilities.
The Group is also diversifying into Horticulture for which land has already been
acquired in different districts in Orissa.

3.2

Promoters Background

Detailed Project Report


The promoters of MGM Minerals Limited are Mr. Rajib Lochan Mohanty and Mr.
Pankaj Lochan Mohanty and Mrs. Meenoti Mohanty.

Rajib Lochan Mohanty


Mr. Rajib Lochan Mohanty is the son of Late Mana Govinda Mohanty, aged about
59 years (D.O.B 05-09-1950), Marine Engineer, is a resident of 2A, Forest Park,
Bhubaneswar. He has 10 years experience in shipping and 25 years experience in
mining business. He is a Director Sun Alloys & Minerals Ltd. & MGM Minerals Ltd. His
net worth is about Rs. 17.46 Crores.

Pankaj Lochan Mohanty


Mr. Pankaj Lochan Mohanty is son of Late Mana Govinda Mohanty, aged about
49 years (D.O.B 13-02-1961), is a resident of 2A, Forest Park, Bhubaneswar. He is a
Director of Sun Alloys & Minerals Ltd., MGM Minerals Ltd., and Blue Lagoon Farms
Pvt. Ltd. He has 25 years experience in mining business. His net worth is about
17.38 Crores.

Meenoti Mohanty
Mrs. Meenoti Mohanty is wife of Mr. Rajib Lochan Mohanty aged about 55 years
(D.O.B. 15-06-55) is a resident of 2A, Forest Park, Bhubaneswar. She has 15 years
experience in mining business. He is a Director in Aeon Minerals (P) Ltd & MGM
Minerals Ltd. Her net worth is about 0.50 Crore.

Detailed Project Report

4 Project Background
MGM Minerals Limited proposes to set up a 5 MW grid connected Solar Power plant
at Khurda District in the state of Orissa with the objective of renewable power
generation and supplying clean electricity to grid on BOO (Build, Own & Operate)
basis. The main objective of the project promoter is to be in tune with the
sustainable development priorities of the country and contribute towards climate
change mitigation initiative envisaged by the host country government. Successful
operation of the project activity will act as a cornerstone towards promotion of the
technology. With an age long relationship in the domain the promoter is intended to
set the project activity and demonstrates feasibility of grid interactive solar power in
supplying of reliable clean energy to the grid and support electrical demand in the
country, which is blessed with more than 320 days of sunshine.
The solar power plant shall operate on the principle of direct conversion of sunlight
to electrical energy by employing photovoltaic technology and supply it directly to
the grid.
The plant location is chosen as MGM Minerals Limited is having 15 acres of open
land available in that region, which is well suited for solar PV installations and hence
will reduce the leveling cost, shadow losses and cost for cabling as well due to its
proximity to grid. MGM Minerals Limited is also in the process of acquiring 10 acres
of land adjacent to the current 15 acres of land. 33 KV line of adequate capacity is
available nearby at Jankia, Khurda district about 5 Km from the proposed site and
connectivity to the proposed plant can be nade by drawing 5 Km of 33 KV line for
power synchronization with state grid through CESUs 33 KV system.
The promoter will ensure installation of the proposed solar plant and related
infrastructure will meet international standards for the industry. The power plant will
be scheduled for commissioning within one year from the date of possession of land
through the Orissa Government.
The power plant shall consist of:
Solar Array capacity (5 MW - rated high efficiency modules)

Detailed Project Report


Solar Modules Mounting Structure (may be with a combination of stationary

and tracking systems)


Power Conditioning Unit 10 nos. of 500 kVA main inverters.
Data Logging System
Monitoring Equipments
Junction Boxes
Cables & Earthling materials
Distribution Panels
Control Room

Detailed Project Report

5 Meteorological information
5.1 Radiation Climatology of India
The solar radiant energy, in its passage through the atmosphere undergoes
depletion due to absorption and scattering by the various constituents of the
atmosphere at different levels. While most of absorptions are due to radiatively
active gases, chief of which are carbon dioxide, ozone and water vapour, the
scattering takes place due to all constituents of the atmosphere including
suspended particulate matter. The singlemost modifier of the radiation field is the
cloud, both due to absorption and scattering processes. Both the absorption and
scattering processes take place selectively, i.e. specific gases absorb or scatter at
specific wavelengths/wavelength bands. The absorption can be weak or strong and
partial or total. The scattering occurs both in the forward and backward directions.
The back scattering process can be termed as reflected radiant energy at the
appropriate levels. Ultimately, the radiant energy that reaches the earths surface is
made of the direct beam solar irradiation, the scattered (diffuse) solar irradiation
and the downward terrestriant radiant energy from the atmosphere. This heats up
the earths surface and causes evaporation of moisture in the soil and over water
surfaces.
The earths surface and the constituents of the atmosphere including clouds and
particulate matter emit radiant energy in the infra-red region at their own
temperatures. This energy is absorbed by different atmospheric layers at different
wavelengths, resulting in higher energy level content. But these absorbing layers
also emit their heat resulting in the lowering of the heat energy content. However,
since the temperatures of the different layers decrease as the height increases in
the tropospheric region, the downward radiant energy from the higher layers is
generally lower than those emitted upward by the lower layers.
This results in a net loss of the radiant energy in the infra-red wavelengths
(terrestrial radiant
energy). It is in this terrestrial radiant energy regime that all living organisms
including humans are immersed fully and thrive. It is also this energy field which
causes the changes in the temperature of the air layer close to it and hence the
density of air, leading a chain of interactions to affect the atmospheric temperature
and humidity and then the atmospheric pressure and the wind field. This ultimately
causes the weather patterns and the changes in them.
The amount of radiant energy from the sun over a place is not the same on each
day. The varying distance between the sun and the earth contributes to a small
percentage in the radiation field. Because of the tilt of the axis of rotation of the
earth about itself, the length of the day and night over a place changes everyday.
Also because of the tilt and the rotational movement of the earth, various parts of

Detailed Project Report


the earth are irradiated differently leading to differential heating of any part on the
earths surface. Superposed over this is the varying topography of the earths
terrain, the relative distances from the oceans and the latitudinal distance from the
equator. Thus the amount of solar radiant energy at a place varies depending on the
time of the day and the season. The amount is quite low at the time of sunrise or
sunset as the radiant energy has to traverse a longer pathlength than what it will
be when the sun is at its zenith position. Besides, the radiant energy is vastly
affected by the different types and amounts of clouds. Naturally occurring events
like volcanoes, storms and forest fires and the pollutants released into the
atmosphere by the human and animal activities do reduce the amount of radiant
energy reaching the earths surface due to increased absorption and scattering
effects. Thus the radiation regimes are quite likely to be different even between two
adjoining regions and hence their monitoring is highly desirable and beneficial.
Global Solar Radiation
January

Detailed Project Report

February

March

Detailed Project Report

April

May

Detailed Project Report

June

July

Detailed Project Report

August

Detailed Project Report


September

October

November

Detailed Project Report

December

Detailed Project Report

5.2 Radiation Climatology of Orissa


Month
Jan Fe
Ma Ap Ma
b
r
r
y
4.6 5.3 6.0 6.5 6.4
Insolation
5
2
1
4
(kWh /m2/ day) 5

Jun

Jul

4.7
0

3.9
1

Au
g
3.9
3

Se
p
4.3
0

Oc
t
4.8
3

No
v
4.5
5

De
c
4.3
4

Orissa is blessed with ample solar radiation throughout the year and is ideal for
solar power project. Based on the average insolation data the proposed Solar Plant
is estimated to generate 8.322 million units of electrical energy annually.
Source: NASA

5.3 Meteorological Data


Southern Latitude:
Northern Latitude
Western Longitude
Eastern Longitude
Mid Latitude
Mid Longitude
Insolation
Incident

On

Horizontal

Surface

19 0 28 N
20 0 17 N
84 0 29 N
86 0 25 N
190 53 N
85 0 56 N
4.96

[kWh/m /day]:
Insolation Clearness Index

0.53

Mont
h

Monthly
Average
Insolation
[kWh/m2/d
ay

Monthly
Average
Clearne
ss Index
K

Monthl
y
Averag
e
Dayligh
t
Hours

Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov

4.71
5.46
6.12
6.49
6.30
4.51
4.00
4.01
4.34
4.63
4.48

0.61
0.63
0.62
0.61
0.57
0.41
0.36
0.37
0.43
0.51
0.57

11.0
11.5
12.0
12.6
13.0
13.3
13.2
12.8
12.2
11.7
11.2

Monthl
y
Averag
e
Dayligh
t
Cloud
Amoun
t (%)
26.8
28.3
32.5
41.5
51.9
76.1
82.5
82.9
71.1
51.2
38.5

Monthly
Average
Relative
Humidity
at 10 m
(%)

Monthl
y
Averag
e clear
sky
days

Monthly
average
day time
cloud
amount
(%)

56.6
63.4
65.6
71.6
77.1
80.8
82.1
82.1
81.5
75.3
60.9

13
12
8
4
2
0
0
0
1
5
10

26.8
28.3
32.5
41.5
51.9
79.5
82.5
82.9
71.1
51.2
38.5

Detailed Project Report


Mont
h

Monthly
Average
Insolation
[kWh/m2/d
ay

Monthly
Average
Clearne
ss Index
K

Monthl
y
Averag
e
Dayligh
t
Hours

Dec

4.51

0.62

10.9

Monthl
y
Averag
e
Dayligh
t
Cloud
Amoun
t (%)
24.5

Monthly
Average
Relative
Humidity
at 10 m
(%)

Monthl
y
Averag
e clear
sky
days

Monthly
average
day time
cloud
amount
(%)

52.3

17

24.5

5.4 Climate Data


Month

Temperature (0C)
Maximum

Minimum

Average Day

Normal

Temperature

Rainfall

(0C)
January
February
March
April
May
June
July
August
Septembe

29
36
36
39
38
36
34
31
33

14
16
21
27
27
23
22
20
22

21.5
26.0
28.5
33.0
32.5
29.5
28.0
25.5
27.5

(in mm.)
12.6
27.1
24.3
27.2
52.9
225.1
347.7
357.5
217.5

r
October
November
December

33
31
30

20
18
17

26.5
24.5
23.5

86.3
20.4
3.3

Detailed Project Report

6 Site Selection
1

Profile of the District


State
District

Orissa
District Background: The District KHURDA came into being on 1
st April, 1993 by dividing it off its erstwhile Puri District which
after division became Puri, Khurda and Nayagarh. Later on in the
year 2000 the District name is changed as KHORDHA.
Basic

Information of the District :


Sub-division - 02
Tehasil - 10
Blocks - 10
Notified Area Council (NAC) - 02
Municipality - 02
Municipal Corporation - 01
Parliamentary Constituency - 2
Assembly Constituency - 08

The district is bounded by Cuttack, Nayagarh, Puri and Ganjam


districts.
Location:
Latitude Longitude -

1940' N to 2027 N
8456' E to 8605 E

Detailed Project Report


2

District Map

Proposed Site

Profile of the Land

The proposed project is in:


Village
Tehasil
Police Station
Area of the land

Patrapada
Tangi
Tangi Police Station
25 acres

Satellite view of the proposed land:

Detailed Project Report

7 Technical Features
4

Proposed technology

Poly crystalline technology based modules will be used in the proposed power plant.
These modules are made with high efficiency multi crystalline solar cells (i.e. 13% to
17%). Polycrystalline solar cells are made by a casting process in which molten
silicon is poured into a mould and allowed to cool, then sliced into wafers. This
process results in cells that are significantly cheaper to produce than single crystal
cells, but whose efficiency is limited to less than 20% due to internal resistance at
the boundaries of the silicon crystals.
These polycrystalline solar cells are
best
candidates
for
large-scale
application of photovoltaic energy
conversion because they have shown
efficiencies in excess of 15%.
These cells are encapsulated between
a low iron content high transitivity
tempered glass and premium quality
back
sheet to
provide
efficient
protection from the environmental
conditions. The laminates are framed
with strong, robust and anodized
aluminum profile with multiple holes
for ease of installation. The modules
are fitted with 4 -terminal Tyco junction box with 16A, 40V schottky bypass diodes (3
diodes) and plug in connectors.

Detailed Project Report


5

Plant Layout

The Photovoltaic (PV) Grid connected power plant comprises of mainly of 3


components: The PV array, Module Mounting Structure and the Inverters.
The PV array converts the light energy to direct current (DC) power. The Module
mounting structure is used to hold the module in position. The DC power is
converted to alternating current (AC) power by the PCU, which is connected to the
utility power grid.

As part of the land requirement for the 5 MW p Solar plant, MGM Minerals has
estimated 25 acres for the project activity based on the panel size. Based on the
system design developed for this potential project, a 5 MW p PV array would require
approximately 25 acres of land.
6

Plant Specification

Electrical Specification

Standard Test Conditions


(STC)

Specification
Module Name
Rated Power
Voltage at Maximum Power
Current at Maximum Power
Open Circuit Voltage
Short Circuit Current
Maximum system Voltage
Temp. coefficient of Pmax
Normal Operating Cell
Temp.
Standard Test Conditions
(STC)

Unit
Pmax (W)
Vmp (V)

37
17.0

ELDORA 40
40
17.1

2.25
2.35
21.8
21.9
2.40
4.45
1000 V
2.5 W
Normal
Operating
Temperature
1000 W / m2, 25 C, AM 1.5

Imp (A)
Voc (V)
Isc (A)
Vsys (V) IEC/UL
Tk (Pmax)
45 C 2 C

Cell

Detailed Project Report

Mechanical Specification
Length
Width
Weight
Thickness

(including

J-

box)
Module Area
Module type
Frame material
Glass Type
Encapsulation
Output Cable/Connectors

cm
cm
kg
cm

55.2
66.6
4
3.4

cm2
15.6 * 5.2
Poly - crystalline solar cells
High torsion & anodized aluminum frame provides
structural strength and protection from corrosion.
Tempered low iron content 3.2 mm front glass for
efficient sunlight absorption.
Low iron content high transitivity tempered glass and
premium quality back sheet
4-terminal Tyco junction box with 16A, 40V schottky
by pass diodes (3 diodes).
Modules are designed to meet IEC 61215, IEC 61730
& UL 1703 certification standard.

Inverter:
An inverter is an electrical or electro-mechanical device that converts direct current
(DC) to alternating current (AC); the resulting AC can be at any required voltage and
frequency with the use of appropriate transformers, switching, and control circuits.
Inverters are commonly used to supply AC power. In present case of solar electricity
generation, this is the device that takes the dc power from the PV array and
converts it into standard ac power evacuated to the Grid.
The power conditioning unit will be chosen from either of the following types:

Option I:
10 numbers of 500 kVA current-controlled grid-connect inverters will be used for
interface with grid. The system will have full protection as per international
standard, such as IEEE 929-2000 & UL 1741, for protection against grid over voltage
/ frequency, islanding and all other fault conditions.
Suitable lighting protection and earthling system will be installed for safety of
personnel and protection of the equipment. An integrated data logging system for
performance measurement and visual display of the important parameters, such as
daily/ monthly and cumulative energy generated w. r. t. solar intensity, wind
velocity, ambient temp, module temperature etc. will also be installed.

Detailed Project Report

Option- II:
High efficient inverter modules will be ground mounted in series and parallel strings.
834 numbers of 6 kW or 625 numbers of 8 kW string inverters will be used for
interface with grid. The system will have full protection as per international
standard, such as IEEE 929-2000 & UL 1741, for protection against grid over voltage
/frequency, islanding and all other fault conditions.
Suitable lighting protection and earthling system will be installed for safety of
personnel and protection of the equipment. An integrated data logging system for
performance measurement and visual display of the important parameters, such as
daily / monthly and cumulatively energy generated w. r. t solar intensity, wind
velocity, ambient temp, module temperature etc. also be installed.

The above mentioned details are for probable system planned to be installed at
the proposed Solar Park.
Option III:
Sunny Boy Grid-Connect inverters (SB- 1100 Sunny Boy 1100 W String Inverter)
will be used with one series string of between 40 photovoltaic modules per inverter.
333 Inverter Units can be linked in parallel allowing extreme system design

Detailed Project Report


flexibility with the possibility of low cost system expansion and maximum system
efficiency. This makes the inverter ideal for use alone or as part of a large PV plant.
This make installation is safer and easier, special polarized plug -in Multi Contact
cable connectors are used for DC input and an AC connector for the grid connection.
The inverters can be located as close to the PV string as desired (even on the roof,
IP65 protection), eliminating long DC wire runs and allowing low DC currents.
Inverters automatically shut down in the event of: High/Low grid AC-voltage;
High/Low grid frequency; Grid failure; or Inverter Malfunction. These inverters
automatically adjust PV array loading to provide maximum efficiency of solar panels
by means of a maximal power point tracker (MPPT).
Technical Specification (SB - 1100 Sunny Boy 1100 W String
Inverter)
Number of panels required
Output Voltage Range
Output Frequency Range
Power consumption in operation
Power consumption at night

333
207 -264Vac
47.0 - 50.5 Hz
~ 4W
0.1W.

(standby)
Max. efficiency
Certification

>93%
G83

Solar module mounting structure:


Ground mounted solar arrays require fairly precise foundation setup, are more
susceptible to theft/vandalism.
Control Room:
A control room facility that will house the centre's communications and control
systems will be there at the plant site. The control room building will house all the
electronic equipment like MCB, Central Inverters, Low Voltage Panels, Transformer
and high voltage panel.
Junction Boxes:
An electrical junction box is a container for electrical junctions, usually intended to
conceal them from sight and to some extent to eliminate tampering. Junction boxes
form an integral part of a circuit protection system.
Monitoring equipments:
Monitoring equipment enables a system owner to track system production and to
benchmark power generation against installer projections to ensure that systems
are operating properly. Monitoring systems can also be used to automate the
recording of kilowatt-hour generation.

Detailed Project Report


Cables and connectors:
Solar cables are extremely robust and resist high mechanical load and abrasion.
High temperature resistance and excellent water proofing characteristics provide a
long service life to the cables used in large scale projects. The connectors with high
current capacity and easy mode of assembly are to be used for the connections of
the power plant cables.

Civil Infrastructure

Leveling:
Preliminary leveling shall be required for the land to have the PV filed in the same
plane. However, in this case, it is not entirely possible. Hence the structures are
designed to maintain the horizontal plane.
Trenches:
All the conduits between the various connection points will be subterranean and
routed in trenches.
Construction Roads:
A network of interconnected tracks provides accessibility to the different places in
the plant. There are two different types of tracks:

Main track: This runs and along the perimeter


Secondary tracks: These connect the main tracks along the rows of
structures.

Final Roads:
Main roads inside the plant as well as the access tracks to the plant will be
conditioned to permit the traffic of all kind of vehicles during normal operation
including visiting.
Fencing:
A fence shall be installed along the perimeter of the plant.
Building:
There will be a building to house the inverters and the switchgears. An option to
have outdoor inverters is also considered and in this case they could be placed
outside of the building.

Detailed Project Report

13 Power Evacuation
The electricity generated from Solar Park can be fed to either 33 kV line by putting a
sub-station. Alternatively the electricity can be fed to the nearest sub-station by
laying a HT transmission line.

Detailed Project Report

14 Project Execution Plan


The project is planned to be implemented at the earliest. The most essential aspect
regarding the implementation of the project is to ensure that the project is
completed within the scheduled. The project zero date starts once the clearance is
being obtained. It is envisaged that the project will have the following phases of
activity.

Phase
Phase
Phase
Phase

I Project Development
II- Finalization of equipment and contracts
III- Procure & Construction
IV- Plant Commissioning

Project Development:
In a power project development of the project plays an important role. Almost 50%
of the work is done if one achieves the power purchase agreement from the
respective state utilities. The project development start with visits to the region,
understanding about the regional conditions, socio economic conditions,
transportation facilities and infrastructure facilities available in the region. Apart
from the above the tasks listed below will be under project development;

Preparation of Detailed Project Report (DPR)


Submission of DPR
Power Purchase Agreement
Clearance from State Level Technical Committee and Land acquisition (Govt.
land preferred)

During this phase, a project team will be formed for the execution of the project.
The engineers from this group will be involved from early stages of execution of
project. These personnel should evolved critical team of installation of
commissioning. After the plant is commissioned these engineers and technicians
should occupy key position in the organization structure for the operation and
maintenance of the plant.
The responsibilities of the project team shall be

Planning & Programming of all resources required for project completion


Inspection of major fabrication items
Organize the construction and commissioning of the plant
Monitoring and controlling the project process

Detailed Project Report

Execute the project within the planned budget

Finalization of equipment and contracts:


In the power plant modules and junction boxes are lead items and the planning
schedule for the project implementation should provide adequate time period for
the acquisition and installation of these equipments. The specification for major
equipment shall be drawn up at an early stage of the project. Programme of design
information, from the equipment suppliers, that satisfied the overall project
schedule shall be drawn up.
Since the project execution calls for closer coordination among the contractors,
consultants, and the company, proper contract coordination and monitoring
procedures shall be made to plan and monitor the project progress.
Procurement & Construction:
The procurement is an important function of the implementation of the project.
Once the purchase order is place, the project team follows up regularly to ensure
smooth and timely execution of the contract and for obtaining technical information
for the inter packing engineering.
When the contracts for the equipment are awarded, detailed programme in the form
of network are tied up with the supplier to clearly indicate the owners obligations
and the suppliers responsibilities. Upon placement of the purchase order, the
project team shall follow up regularly to ensure smooth and timely execution of the
contract and or obtaining technically information for the inter package engineering.
The procurement activity includes review of review of drawings, expediting, stage
and final pre delivery inspection, supervision of installation and commissioning.
During construction the erection and commissioning phase of the contract should
proceed simultaneously. Adequate power and water shall be made available at site
for the construction. Construction manager takes the overall responsibility of the
site.
Plant Commissioning:
The commissioning phase in a project is one were design, manufacturing, erection
and quality assurance expertise are put to test. The commissioning team will be
from manufacturer of the equipment, consultant and the company as discussed in
the earlier section, staff identified to operate the plant will be involved in the
commissioning phase is completed, a checklist shall designed to ensure that the
plant has been properly installed with appropriate safety measures. The
commissioning team will follow the internal operating instructions. The plant shall
be subjected to a performance test.

Detailed Project Report

15 Operational Features
8

Factors Effecting Generation

Standard Test Conditions:


Solar modules produce dc electricity. The dc output of solar modules is rated by
manufacturers under Standard Test Conditions (STC). These conditions are easily
recreated in a factory, and allow for consistent comparisons of products, but need to
be modified to estimate output under common outdoor operating conditions. STC
conditions are: solar cell temperature = 25 0C; solar irradiance (intensity) = 1000
W/m2 (often referred to as peak sunlight intensity, comparable to clear summer
noon time intensity); and solar spectrum as filtered by passing through 1.5
thickness of atmosphere (ASTM Standard Spectrum). A manufacturer may rate a
particular solar module output at 100 Watts of power under STC, and call the
product a 40-watt solar module. This module will often have a production
tolerance of +/-5% of the rating, which means that the module can produce 37
Watts and still be called a 40-watt module. To be conservative, it is best to use the
low end of the power output spectrum as a starting point (37 Watts for a 40-watt
module).
Temperature:
This is defined by percentage drop in power output for every degree of temperature
increase. It is the effect of temperature variation.

Dirt and dust:


Dirt and dust can accumulate on the solar module surface, blocking some of the
sunlight and reducing output. A typical annual dust reduction factor to use is 93% or

Detailed Project Report


0.93. So the 40- watt module, operating with some accumulated dust may
operate on average at about 79 Watts (37 Watts x 0.93 = 34 Watts).
Mismatch and wiring losses:
The maximum power output of the total PV array is always less than the sum of the
maximum output of the individual modules. This difference is a result of slight
inconsistencies in performance from one module to the next and is called module
mismatch and amounts to at least a 2% loss in system power. Power is also lost to
resistance in the system wiring. These losses should be kept to a minimum but it is
difficult to keep these losses below 3% for the system. A reasonable reduction factor
for these losses is 95% or 0.95.
DC to AC conversion losses:
The dc power generated by the solar module must be converted into common
household ac power using an inverter. Some power is lost in the conversion process,
and there are additional losses in the wires from the rooftop array down to the
inverter and out to the house panel. Modern inverters commonly used in residential
PV power systems have peak efficiencies of 92 -94% indicated by their
manufacturers, but these again are measured under well-controlled factory
conditions. Actual field conditions usually result in overall dc-to-ac conversion
efficiencies of about 88-92%, with 90% or 0.90 a reasonable compromise. So, the
40-watt module output, reduced by production tolerance, heat, dust, wiring, ac
conversion, and other losses will translate into about 68 Watts of AC power
delivered to the house panel during the middle of a clear day (40 Watts x 0.95 x
0.89 x 0.93 x 0.95 x 0.90 = 28 Watts).

9
Organization of power plant O &M
The organization proposed ensures that the power plant will be headed by a plant
engineer holding the full charge of the power plant operations. The plant engineer
should have experience in solar power technology. Two more technicians will be
required for regular monitoring and a few casuals can be engaged for regular
cleaning of the solar modules.
During commissioning of the plant training will be imparted to the engineers and
supervisors.
The operational training shall cover the following:
The nature, purpose and limitations of all plant and equipments.
The detailed operating instructions of each sanctions and equipment of the
plant.
The emergency procedures and all related HAC issues according the
standard.

Detailed Project Report

The basis for the training shall be the plants operations and maintenance
manual, contract documents and drawing provided by the manufacturer

Sl. No.

Particulars

1
2
3
4
5
6
7

Plant Manager
Degree Engineer
Diploma Engineer
ITI - Technician
ITI - Supervisor
Accounts & Administration
Security & Service (Outsource)
Total

Number
1
1
2
3
3
1
1
12

Protection of People and Equipment

10

The plant will work autonomously with a small amount of preventive


maintenance. A monitoring system will advise if any corrective maintenance
is needed.
Residues produced during construction will be disposed of in recycling
centres. No toxic waste is produced. Sanitary container cabinets are foreseen.
During plant operation, no residues will be produced, except occasional
breakdown of equipment, which will be recycled by the manufacturer or
disposed of as during construction phase.
During the construction phase noise sources in all cases will be far from
residential areas. In exploitation phase, the PV modules work completely
noiseless. Each inverter will produce a noise level below 72dB.
Personnel protection is guaranteed by electrical separation between the grid
and the PV generator via a grid transformer along with insulation monitoring
of PV generator.

Further personnel protection is ensured with the overloading, over voltage and
Reverse current protections in built in the central inverter.

Detailed Project Report

16 Financial Analysis
11

Key Assumption

Sl. No.
1
2
3

Particulars
Project Size
Project Life
Debt : Equity

Project Cost

Term Loan

6
7

12
13
14
15
16
17
18
19
20
21
22
23

Rate of Interest on Term Loan


Rate of Interest on Working
Capital
Loan Tenure
Moratorium
Tax Rate
Tax Holidays (Sec 80IA
Deduction)
MAT Tax Rate
Operation & Maintenance Cost
Escalation in O & M cost
Insurance on WDV of Assets
Inflation rate
Power Sale Price
Capacity Utilization Factor
Number of Working days
Working Hours
1 MW Hour
Degradation Factor
Grid Emission factor

24
25
26
27

CER Price in EURO


1 EURO
Expenditure on CDM
Annual Admin Expenses

8
9
10
11

Data
5
25
2
.33
7,705
.44
5,368
.37
13.39%
12.89%
10
0
33.99%
0
16.995%
8.50
5.72%
0.00%
5.72%
17.91
19%
365
24
1000
0.00%
0.84
12
65
10%
4

Unit
MW
Years

Rs. in Lakhs
Rs. in Lakhs
Per annum
Per annum
Years
Years
Years

Rs. In Lakhs /MW


Per annum
Per annum
Per annum
Rs. per kWh
Days per annum
Per day
kWh
Per annum
tCO2 / MWh
Per CER
INR
of revenue
Rs. in Lakhs

Detailed Project Report

12

Sl.
No.
1

Project Cost
Description

Rs. in Lakhs
Amount
Total
Amount

Land & Land Development


60.00

a)

Land

b)

Land Development

45.00
15.00
2

Office Building
40.00
a)

Building and Civil Construction


40.00

Plant & Machinery


7,500.00
a)

Solar Modules (with junction box;


w/o brackets)

7,500.00

Other Fixed Assets


40.00
a)

Furniture & Fixture

b)

Other Office Equipment

a)

Preliminary & Pre-Operative


Expenses
Company Incorporation

20.00
20.00
5

40.00
15.00

b)

Pre-Operative Expenses
25.00

Contingency

Working Capital

750.00
25.44
a)

(3 Months Operating Expenses)


25.44
Total Project Cost
7,705.44

13

Means of Finance

Sl. No.

Particulars

Total Cost of Project

Rs. In
Lakhs

Detailed Project Report


7,705.44
2

Debt : Equity Ratio

Promoters Contribution

2.33
2,311.63
4

Total Loan Fund


5,393.80
a)

Working Capital
25.44

b)

Term Loan
5,368.37
Total
7,705.44

14

Profitability Statement

16.1.1

Projections of Performance, Profitability and Repayment

Power Revenue
Units Generated (MWh)
Selling price per unit (Rs.)
Sales Income without CDM
CDM Revenue
CER Generated (tCO2)
CER Price in EURO
CDM Revenue
Total Revenue with CDM
Without CDM
Annual Cost
Operation and Maintenance
Administrative Expenses
Salary
Interest on Loan
Depreciation
Total Expenditure (without
CDM)
Profit Before Tax Without
CDM
Taxable Profit without CDM
Income Tax
Profit After Tax without
CDM
With CDM
Expenditure on CDM
Total Expenditure (with
CDM)
Profit Before Tax With CDM

Rs

Construction
Period
Y0

Operational Period
Y1

Y2

Y3

Y4

Y5

Y6

Y7

0
0.00
-

8322
18
1490

8322
18
1490

8322
18
1490

8322
18
1490

8322
18
1490

8322
18
1490

832
18
149

0
0
-

6990
12
55
1545

6990
12
55
1545

6990
12
55
1545

6990
12
55
1545

6990
12
55
1545

6990
12
55
1545

699
12
55
154

43

45

48

50

53

56

59

4
52
706
530
1,335

4
55
667
530
1,301

4
58
622
530
1,262

4
62
571
530
1,217

4
65
513
530
1,165

4
69
446
530
1,105

4
73
370
530
1,03

156

190

229

274

326

386

455

-5,321

-486

513

750

841

909

980

156

190

229

274

326

386

455

5
1,340

5
1,306

5
1,267

5
1,222

5
1,170

5
1,110

5
1,0

205

239

278

323

375

435

504

Add : Depreciation
Less : Depreciation Income
Tax
Taxable Profit with CDM

530
6,007

530
1,206

530
246

530
53

530
14

530
6

530
5

-5,272

-437

562

799

890

958

1,02

Income Tax
Profit After Tax with CDM

205

239

278

323

375

435

504

Detailed Project Report

Operational Period
Y11

Y12

Y13

Y14

Y15

Y16

Y17

Y18

Y19

Y20

Power Revenue
Units Generated (MWh)
Selling price per unit (Rs.)
Sales Income without CDM

8322
18
1490

8322
18
1490

8322
18
1490

8322
18
1490

8322
18
1490

8322
18
1490

8322
18
1490

8322
18
1490

8322
18
1490

8322
18
1490

CDM Revenue
CER Generated (tCO2)
CER Price in EURO
CDM Revenue
Total Revenue with CDM

1490

1490

1490

1490

1490

1490

1490

1490

1490

1490

Without CDM
Annual Cost
Operation and Maintenance

74

78

83

88

93

98

103

109

116

122

Administrative Expenses
Salary
Interest on Loan
Depreciation
Total Expenditure
(without CDM)
Profit Before Tax Without
CDM
Taxable Profit without CDM

4
91
3
102
275

4
96
3
102
284

4
102
3
102
294

4
108
3
102
304

4
114
3
102
315

4
120
3
102
327

4
127
3
102
340

4
134
3
102
353

4
142
3
102
367

4
150
3
102
382

1,216

1,207

1,197

1,186

1,175

1,163

1,151

1,138

1,124

1,109

1,315

1,306

1,296

1,286

1,275

1,263

1,251

1,238

1,224

1,209

Income Tax
Profit After Tax without
CDM
With CDM
Expenditure on CDM
Total Expenditure (with
CDM)
Profit Before Tax With
CDM
Add : Depreciation
Less : Depreciation
Income Tax
Taxable Profit with CDM

447
769

444
763

441
756

437
749

433
742

429
734

425
726

421
717

416
708

411
698

275

284

294

304

315

327

340

353

367

382

1,216

1,207

1,197

1,186

1,175

1,163

1,151

1,138

1,124

1,109

102
3

102
3

102
3

102
2

102
2

102
2

102
2

102
2

102
2

102
2

1,315

1,306

1,296

1,286

1,275

1,263

1,251

1,238

1,224

1,209

Income Tax
Profit After Tax with CDM

447
769

444
763

441
756

437
749

433
742

429
734

425
726

421
717

416
708

411
698

16.1.2

Projected Cash Flow

Inflow

Y
0

Equity
Capital

2,
3
12
5,
3
94

Loan Fund
Operational

Y
1

Y
2

Y
3

Y
4

Y
5

85

Rs. In Lakhs
Y
Y
Y
6
7
8

1,

1,

Y
9

Y
1
0

1,

1,

Detailed Project Report


Income
Total Cash
Inflow
Outflow
Purchase of
Assets
Preoperative
Expenses
Repayment
of Term Loan
Total Cash
Outflow

7,
7
0
5

Net Inflow/
(Outflow)
Cumulative
Balance

2
5

Equity
Capital
Loan Fund
Operational
Income
Total Cash
Inflow
Outflow
Purchase of
Assets
Preoperativ
e Expenses
Repayment
of Term
Loan
Total Cash
Outflow
Net Inflow/
(Outflow)

6
9
7
6
9

08

05

64

03
3
1,
0
3
3

1
13
1,
1
1
3

20
4
1,
2
0
4

30
9
1,
3
0
9

8
0
8

8
5
3

9
0
5

9
6
4

2
7
4
2
7
4

3
1
3
3
1
3

3
58

40
9

4
67

5
34

61
0

6
97

79
6

90
9

3
5
8

4
0
9

4
6
7

5
3
4

6
1
0

6
9
7

7
9
6

9
0
9

4
6
1
4
8
6

4
5
5
9
4
2

4
5
0
1,
3
9
1

4
4
4
1,
8
3
5

4
3
7
2,
2
7
2

4
3
0
2,
7
0
3

4
2
3
3,
1
2
6

4
1
6
3,
5
4
2

4
0
8
3,
9
4
9

3
9
9
4,
3
4
9

7,
6
40
40

7,
6
8
0
2
5

Inflow

3
5
7
3
5

Rs. In
Lakhs
Y2 Y
4
2
5

Y
1
1

Y
1
2

Y
1
3

Y
1
4

Y
1
5

Y
1
6

Y
1
7

Y
1
8

Y
1
9

Y
2
0

Y
2
1

Y
2
2

Y
2
3

8
71

8
5
8
8
5
8

8
5
1
8
5
1

8
4
4
8
4
4

8
3
6
8
3
6

8
2
7
8
2
7

8
1
9
8
1
9

8
0
9
8
0
9

8
0
0
8
0
0

7
8
9
7
8
9

7
7
8
7
7
8

7
6
7
7
6
7

75
5

8
7
1

8
6
5
8
6
5

8
7

8
6

8
5

8
5

8
4

8
3

8
2

8
1

8
0

8
0

7
8

7
7

7
6

75
5

7
4

75
5

7
4
2
7
4
2

Detailed Project Report


Cumulativ
e Balance

1
5,
2
2
0

5
6
,
0
8
5

8
6
,
9
4
3

1
7
,
7
9
4

4
8,
6
3
7

6
9,
4
7
3

7
1
0,
3
0
1

9
1
1,
1
1
9

9
1
1,
9
2
9

0
1
2,
7
2
9

9
1
3,
5
1
8

8
1
4,
2
9
6

7
1
5,
0
6
3

15
,8
18

2
1
6,
5
6
0

Detailed Project Report

16.1.3

Projected Balance Sheet

Liabilities
Capital
Equity Capital

Y0

Y
1

Y2

Y3

Y4

Y5

Y6

Y7

Y8

Y9

Y1
0

2,31
2

2,
31
2
20
5

2,3
12

2,3
12

2,3
12

2,3
12

2,3
12

2,3
12

2,3
12

2,3
12

2,3
12

44
4

72
1

1,0
44

1,4
19

1,8
54

2,3
57

2,9
40

3,6
15

4,3
94

5,
09
4
25
7,
6
3
6

4,7
81

4,4
23

4,0
13

3,5
46

3,0
12

2,4
02

1,7
05

909

25
7,5
61

25
7,4
81

25
7,3
95

25
7,3
02

25
7,2
03

25
7,0
97

25
6,9
83

25
6,8
61

25
6,7
31

7,
64
0
53
0
7,
11
0
-

7,6
40

7,6
40

7,6
40

7,6
40

7,6
40

7,6
40

7,6
40

7,6
40

7,6
40

1,0
60
6,5
80

1,5
90
6,0
50

2,1
20
5,5
20

2,6
50
4,9
90

3,1
80
4,4
60

3,7
09
3,9
31

4,2
39
3,4
01

4,7
68
2,8
72

5,2
98
2,3
42

48
6
40

94
2
40

1,3
91
40

1,8
35
40

2,2
72
40

2,7
03
40

3,1
26
40

3,5
42
40

3,9
49
40

4,3
49
40

7,
6
3
6

7,5
61

7,4
81

7,3
95

7,3
02

7,2
03

7,0
97

6,9
83

6,8
61

6,7
31

Reserve &
Surplus
Loan Fund
Term Loan

WC Loan
Other Liability
Total

25
7,70
5

5,36
8

Assets
Fixed Assets
Gross Block

7,64
0

Depreciation

Net Block

7,64
0

Investment
Current Assets
Cash & Bank
Balance
Other Current
Assets
Total

25
40
7,70
5

Rs. In
Lakhs
Y1 Y12 Y13 Y14 Y15 Y16 Y17 Y18 Y19 Y20 Y21 Y22 Y23 Y24
1

Y25

Liabilities
Capital
Equity Capital

2,3 2,31 2,31 2,31 2,3122,3122,3122,312 2,312 2,312 2,3122,312 2,312 2,312
12 2
2
2

2,312

Detailed Project Report


Reserve &
Surplus
Loan Fund

5,1 5,92 6,68 7,43 8,1738,9079,63210,34 11,05 11,75 12,44 13,12 13,78 14,442
63 6
2
1
9
7
5
3
1
8

15,08
3

Term Loan

WC Loan

25 25

25

25

25

25

25

25

25

25

25

25

25

25

25

Other Liability

Total

7, 8,26 9,01 9,76 10,5 11,2 11,9 12,6 13,3 14,0 14,7 15,4 16,1 16,779
50 3
9
8
10
44
69
86
94
92
81
58
25
0

17,4
20

7,6 7,64
40 0
5,4 5,50
00 2
2,2 2,13
40 8
- -

7,6407,6407,6407,640 7,640 7,640 7,6407,640 7,640 7,640

7,640

5,8085,9106,0116,113 6,215 6,317 6,4176,518 6,619 6,720

6,820

1,8321,7301,6291,527 1,425 1,323 1,2231,122 1,021 920

820

Assets
Fixed Assets
Gross Block
Depreciation
Net Block
Investment

7,64
0
5,60
4
2,03
6
-

7,64
0
5,70
6
1,93
4
-

Current Assets
Cash & Bank
Balance
Other Current
Assets
Total

5,2 6,08 6,94 7,79 8,6379,47310,30 11,11 11,92 12,72 13,51 14,29 15,06 15,818
20 5
3
4
1
9
9
9
8
6
3
40 40 40 40 40
40
40
40
40
40
40
40
40
40

16,56
0
40

7, 8,26 9,01 9,76 10,5 11,2 11,9 12,6 13,3 14,0 14,7 15,4 16,1 16,779
50 3
9
8
10
44
69
86
94
92
81
58
25
0

17,4
20

16.1.4

Interest and Repayment Schedule

Term Loan
Int. rate
Opening Balance

Y1

Y2

Y3

Y4

Y5

Y6

Y7

5368

5094

4781

4423

4013

3546

3012

Repayment

274

313

358

409

467

534

610

Closing Balance

5094

4781

4423

4013

3546

3012

2402

702

663

619

568

509

443

367

Loan Obtained

Amount of Interest

5368

13.39%

Detailed Project Report

Interest
on Loan

Y
1

Y
2

Y
3

Y
4

Y
5

Y
6

Y
7

Y
8

Y
9

7
0
6

6
6
7

6
2
2

5
7
1

5
1
3

4
4
6

3
7
0

2
8
3

1
8
4

Y
1
0
7
1

Y
1
1
3

Y
1
2
3

Y
1
3
3

Y
1
4
3

Y
1
5
3

Y
1
6
3

Y
1
7
3

Y
1
8
3

Y
1
9
3

Y
2
0
3

Y
2
1
3

Y
2
2
3

Y
2
3
3

Rs.
In
Lakh
s
Y Y
2 2
4 5
3 3

Detailed Project Report


16.2 Financial Analysis
16.2.1

Debt Service Coverage Ratio:

With CDM Revenue

Y0

Y1

Y2

Y3

Y4

Y5

Y6

Net Profit after Tax


Add : Interest
Add : Depreciation
Cash Accrual
Total Int & Repayment
DSCR

205
706
530
1,441
980
1.47

239
667
530
1,435
980
1.46

278
622
530
1,430
980
1.46

323
571
530
1,424
980
1.45

375
513
530
1,417
980
1.45

435
446
530
1,410
980
1.44

5
3
5
1
9
1

Without CDM Revenue

Y0

Y1

Y2

Y3

Y4

Y5

Y6

Net Profit after Tax


Add : Interest
Add : Depreciation
Cash Accrual
Total Int & Repayment
DSCR

Y0
-

156
706
530
1,392
980
1.42

190
667
530
1,386
980
1.41

229
622
530
1,381
980
1.41

274
571
530
1,375
980
1.40

326
513
530
1,368
980
1.40

386
446
530
1,361
980
1.39

4
3
5
1
9
1

Average DSCR with CDM

Average DSCR without CDM

1.44

1.39

Detailed Project Report


16.2.2

Internal Rate of Return:

With CDM Revenue

Y0

Y1

Y2

Y3

Y4

Y5

Y6

Y7

Y8

Y9

Y10

Cash Inflow

0
461

455

450

444

437

430

423

416

408

399

-2,31
2

-2,31
2

461

455

450

444

437

430

423

416

408

399

-2,31
2

-1,8
51

-1,3
95

-94
6

-50
2

-65

366

789

1,20
5

1,61
2

2,01
2

Cash Outflow
Net Cash Flow
Cumulative Cash Flow

With CDM Revenue

Y11

Y12

Y13

Y14

Y15

Y16

Y17

Y18

Y19

Y20

Y21

Y22

871

865

858

851

844

836

827

819

809

800

789

778

871

865

858

851

844

836

827

819

809

800

789

778

2,88
3

3,74
7

4,60
6

5,45
7

6,30
0

7,13
6

7,96
4

8,78
2

9,59
2

10,3
92

11,1
81

11,9
59

Y4

Y5

Y6

Y7

Y8

Cash Inflow
Cash Outflow
Net Cash Flow
Cumulative Cash Flow
PAY BACK PERIOD with
CDM
IRR with CDM Revenue

Y6
21.3
5%

NPV @ 10% with CDM


2,05
2

Without CDM Revenue

Y0

Cash Inflow

Y1

Y2

Y3

0
412

406

401

395

388

381

374

367

-2,312

-2,312

412

406

401

395

388

381

374

367

-2,312

-1,90
0

-1,49
4

-1,09
3

-698

-310

71

445

812

Cash Outflow
Net Cash Flow
Cumulative Cash Flow

Without CDM
Revenue
Cash Inflow

Y11

Y12

Y13

Y14

Y15

Y16

Y17

Y18

Y19

Y20

Y21

Y22

Detailed Project Report


871

865

858

851

844

836

827

819

809

800

789

778

871

865

858

851

844

836

827

819

809

800

789

778

2,39
2

3,25
7

4,11
5

4,96
6

5,81
0

6,64
5

7,47
3

8,29
2

9,10
1

9,90
1

10,6
90

11,4
69

Cash Outflow
Net Cash Flow
Cumulative Cash Flow
PAY BACK PERIOD w/o
CDM
IRR without CDM
Revenue
NPV @ 10% w/o CDM

Y6
19.7
8%
1,7
78

Detailed Project Report

17 Project Contribution to the sustainable development


Direct Benefits:
Experience & training with Grid Connected PV systems Grid connected PV
systems are becoming increasingly popular worldwide. As the cost of PV systems
are approaching competitiveness with other conventional power, large scale use
of solar PV power plants is envisaged in future. The first hand experience of
engineers would help them to promote large scale use of solar projects in India.
The power generated from the Solar Power Plant will help in meeting the demand
due to expected growth of industry, utilizing existing transmission and distribution
network and saving losses.
Benefits to electricity Department:
Voltage Support- the PV system will boost the voltage of grid electricity and
prevent the voltage drop when large power is consumed by induction loads. The
system will also supply power close to unity power factor thereby improving the
grid quality and increasing its capacity. There will be savings in cost of voltage
stabilization equipment such as shunt capacitors with controlled switches. In rural
remote locations, at the end of the distribution systems where the voltages are
known to be very low due to over loading and under sized grids, the solar power
generating system would provide voltage support to the grid by feeding power
during the day when peak day time loads cause the grid to overload.
Social Benefits:
This project can produce substantial reductions in green house gas emissions,
particularly carbon dioxide. The countrys majority generation capacity is largely
coal based and produces high quantity of carbon dioxide and other harmful
gasses. If the untapped solar energy potential is realized, carbon dioxide and other
toxic gas emissions can be lowered by significant quantity. Therefore, every
kilowatt of solar energy produced has to be seen from this perspective and as a
small but major step towards mitigation of carbon dioxide emission and
subsequently combat climate change.
For a 5 MWp Solar PV power plant in the region of Orissa, it is estimated that there
will be reduction in the emission of green house gases by approx. 6990 tonnes of
CO2 per year. There will also be reduction in NO x, SOx, suspended particles and
other volatile organic compounds. The use of solar energy can prevent damage to
lungs and other serious health problems, reducing SMOG and acid rain.
The evil effects of climate change are briefly examined below to understand the
long term social benefits:

Detailed Project Report


a. Rising levels of green house gases (GHGs predominantly carbon dioxide)
are expected to cause climate change. By absorbing infrared radiation,
these gasescontrol the flow of natural energy through the climate system.
The climate has to adjust to the thickening blanket of GHGs climate models
predict that the global temperature will rise by about 1- 3.5 deg. C by the
year 2100. It may be noted that this projected change is larger than any
climate change experienced in the past.
b. The mean sea level is expected to rise 15- 95 cm by the year 2100, causing
flooding of low lying areas and causing other damages. Forests, deserts and
other unmanaged ecosystems would face new climatic stresses. Human
society will face new risks and pressures. Food security is likely to be
affected and some regions are likely to experience food shortages and
hunger. Water resources will be affected as precipitation and evaporation
pattern change around the world. Sea level rise and extreme weather
events could damage physical infrastructure.
Sulphur emissions from coal and oil fired power stations produce clouds of
microscopic particles that reflect sunlight back into space. This could cause acid
rain.

You might also like