You are on page 1of 6

Zadatak 1.

Izrauje se dimnjak kontinuiranog krunog poprenog presjeka. Podaci potrebni za proraun su slijedei:

Polumjer otvora.................................................................................................................. 4m
Debljina stjenke dimnjaka ............................................................................................... 0,4m
irina vanjske platforme ..................................................................................................... 2m
Visina dimnjaka ................................................................................................................ 40m
Visina klizne oplate .......................................................................................................... 1,2m
Trenje oplate i betona .............................................................................................. 1,8kN/m2
Nosivost jedne dizalice (praktina) ................................................................................. 40kN
Stalno optereenje platforme .................................................................................. 7,5kN/m2
Pokretno optereenje platforme ................................................................................ 2kN/m2
Hod dizalice klizne oplate .................................................................................. 20mm/impuls
Brzina podizanja klizne oplate ........................................................................ 7,5 impulsa/sat

Potrebno izraunati:
1. Broj dizalica za podizanje klizne oplate
2. Ukupno vrijeme klizanja oplate cijelom visinom dimnjaka
3. Koliinu betona koja se ugrauje u jednom satu

Rjeenje:
Tlocrt (skica):

R3=6,4m
R2=4,4m

R1=4m

UNUTARNJA
PLATFORMA

VANJSKA
PLATFORMA

1. Potrebno proraunati povrinu oplate PO (na slici rafirano mreasto)i povrinu platformi Pp
(vanjska + unutarnja - na slici rafirano sivo).
Povrina oplate
PO = ( 2 x R1 x +2 x R2 x ) x 1,2m = (2 x 4 x 3,14 + 2 x 4,4 x 3,14) x 1,2 = 52,75 x 1,2 = 63,30m2
Povrina platformi (unutarnje i vanjske)
PP = R12 + R32 R22 = 42 x 3,14 + 6,42 x 3,14 4,42 x 3,14 = 50,24 + 128,61 60,79 = 118,06m2
2. Potrebno proraunati silu koja djeluje na oplatu (N1) (od trenja koje se javlja izmeu oplate i
svjeeg betona) i silu koja djeluje na platformu (N2)( od vlastite teine, tj. stalnog optereenja i
pokretnog optereenja).
N1 = PO x trenje oplate i betona = 63,30m2 x 1,8kN/m2 = 113,94kN
N2 = PP x (stalno + pokretno optereenje platforme) =
= 118,06m2 x (7,5kN/m2 + 2kN/m2) = 118,06m2 x 9,5kN/m2 = 1121,57kN

3. Potrebno izraunati ukupnu vertikalnu silu NUK, te proraunati broj potrebnih dizalica (nDIZALICA).
NUK = N1 + N2 = 113,94kN + 1121,57kN = 1235,51kN
nDIZALICA = NUK / Nosivost jedne dizalice (praktina) = 1235,51kN / 40kN = 30,89
ODABRANO - 31 DIZALICA (uvijek se zaokruuje na PRVI VEI CIJELI BROJ)
4. Potrebno proraunati ukupno vrijeme klizanja TUK
TUK = visina stupa / brzina klizanja oplate
Brzina klizanja oplate se proraunava na slijedei nain. S obzirom da se oplata pomie u impulsima
kojih ima 7,5 u jednom satu, a s obzirom da je hod dizalice u jednom impulsu 20mm, to znai da se
u 1 satu oplata pomakne 7,5 x 20 = 150mm odnosno 15cm, odnosno 0,15m (tj. brzina klizanja
oplate je 0,15m/h).
TUK = 40m / 0,15m/h = 266,67h (nije potrebno preraunavati u dane)
5. Potrebno proraunati koliinu betona koja se ugrauje u jednom satu
Quk = ( R22 R12 ) x 0,15m/h = (4,42 x 3,14 42 x 3,14) x 0,15m/h = 1,58m3/h

Zadatak
Izrauje se stup kontinuiranog pravokutnog poprenog presjeka vanjskih dimenzija 6m x 3m. Podaci
potrebni za proraun su slijedei:

Debljina stjenke stupa ..................................................................................................... 0,5m


irina vanjske platforme ..................................................................................................... 2m
Visina stupa ...................................................................................................................... 50m
Visina klizne oplate .......................................................................................................... 1,2m
Trenje oplate i betona .............................................................................................. 1,8kN/m2
Nosivost jedne dizalice (praktina) ................................................................................. 50kN
Stalno optereenje platforme ................................................................................... 10kN/m2
Pokretno optereenje platforme ............................................................................. 2,2kN/m2
Hod dizalice klizne oplate .................................................................................. 25mm/impuls
Brzina podizanja klizne oplate ........................................................................ svakih 6 minuta

Potrebno izraunati:
1. Broj dizalica za podizanje klizne oplate
2. Ukupno vrijeme klizanja oplate cijelom visinom stupa
3. Koliinu betona koja se ugrauje u jednom satu

Rjeenje:
Tlocrt (skica):

0.5

0.5

UNUTARNJA
PLATFORMA

STJENKA STUPA

VANJSKA PLATFORMA

1. Potrebno proraunati povrinu oplate PO (na slici rafirano mreasto)i povrinu platformi Pp
(vanjska + unutarnja - na slici rafirano sivo).
Povrina oplate
PO = (6m + 6m + 3m + 3m) x 1,2m + (5m + 5m + 2m + 2m) x 1,2m = 38,4m2
Povrina platformi (unutarnje i vanjske)
PP = (5m x 2m) + (10m x 2m + 10m x 2m + 3m x 2m + 3m x 2m) = 10m2 + 52m2 = 62m2
2. Potrebno proraunati silu koja djeluje na oplatu (N1) (od trenja koje se javlja izmeu oplate i
svjeeg betona) i silu koja djeluje na platformu (N2)( od vlastite teine, tj. stalnog optereenja i
pokretnog optereenja).
N1 = PO x trenje oplate i betona = 38.4m2 x 1,8kN/m2 = 69,12kN
N2 = PP x (stalno + pokretno optereenje platforme) =
= 62m2 x (10kN/m2 + 2,2kN/m2) = 62m2 x 12,2kN/m2 = 756,4kN

3. Potrebno izraunati ukupnu vertikalnu silu NUK, te proraunati broj potrebnih dizalica (nDIZALICA).
NUK = N1 + N2 = 69,12kN + 756,4kN = 825,52kN
nDIZALICA = NUK / Nosivost jedne dizalice (praktina) = 825,52kN / 50kN = 16,51
ODABRANO - 17 DIZALICA (uvijek se zaokruuje na PRVI VEI CIJELI BROJ)
4. Potrebno proraunati ukupno vrijeme klizanja TUK
TUK = visina stupa / brzina klizanja oplate
Brzina klizanja oplate se proraunava na slijedei nain. S obzirom da se oplata pomie u impulsima
koji se deavaju svakih 6 minuta, u 1 satu oplata se pomakne 10 puta (60 / 6).
S obzirom da je hod dizalice u jednom impulsu 25mm, to znai da se u 1 satu oplata pomakne
250mm odnosno 25cm, odnosno 0,25m (tj. brzina klizanja oplate je 0,25m/h).
TUK = 50m / 0,25m/h = 200h (nije potrebno preraunavati u dane)
5. Potrebno proraunati koliinu betona koja se ugrauje u jednom satu
Quk = ( 6 x 3 5 x 2 ) x 0,25m/h = (18 10) x 0,25m/h = 8 x 0,25 = 2m3/h