AMR Blueprint for New Buildings

Version 1.1
28th September 2009.

AMR Pre-Installation Requests

Page 2/47

1.

INTRODUCTION ............... 3

2.

HIGH RISE BUILDINGS ......... 4

3.

LOW RISE BUILDINGS (G+ 4)... 14


3.1.

BUILDINGS WITH ALL WATER METERS ON THE ROOF ... 14

3.2.

BUILDINGS WITH ELECTRICITY AND WATER METERS ON EACH FLOOR ..... 23

4.

VILLAS..... 32

5.

COMMERCIAL VILLAS .. 34

6.

COMPOUNDS.......... 37

7.

BULK AND OPERATIONAL EL. & W. METERS ..... 39

8.

MATERIAL......... 41
8.1.

CABLES ...........

42

8.1.1 A-BUS ..

42

8.1.2 METER DATA CABLE .............

44

8.1.3 POWER CABLE ............. 46


8.2.

PVC POOL BOX AND PIPE.

47

P.O.Box 36423|Abu Dhabi| UAE - phone: +971 2 666 7783|fax: +971-2-666 7784| www.amplex-emirates.ae

AMR Pre-Installation Requests

1.

Page 3/47

INTRODUCTION
In order to make it easier to complete AMR installations in new buildings and to ensure
that all client installation requirements (ADWEA) are met, Contractors should pre-install
the cables-pipes for the AMR equipment in the new buildings.
This chapter describes the AMR pre-installation requisites for the following types of
buildings:

High-rise buildings

Low-rise buildings

Commercial Villas

Villas

Compounds

High-rise building is building with own substation! Low-rise building is building with
power supply from substation which one is feeding 2 or more than 2 buildings!
The main pre-installation requisites that should be observed in future new buildings are:

PVC conduit with data cable should be installed between electrical rooms and
water meter rooms or water meter cabinets. If distance between electrical room
and the water meter room is more than 20 meters or pipe is more than 3 bends,
pull box must be installed on each floor.

PVC conduit with 3-core power cable should be installed between sub main
distribution board (SMDB) and meter board on each floor.

AMR 3 phase spare breaker in each sub main distribution board (SMDB)

On Electrical meter board in electrical room to be enough space for AMR box

In Floor Water Meter Cabinet to be enough space for AMR box

In buildings, where the water meters are installed on the roof, PVC conduit with
4-core data cable should be installed between the nearest Electrical room
(SMDB-with 3 phase power supply) and Amplex Module box which is located in
a room on the roof.

For bulk or operational water meters PVC conduit with 3 core data cable should
be installed between water meter and Main Electrical Room

Main Electrical Room installation should be finished with 3 phase spare breakers
inside MDB for AMR installation with power supply taken directly from Bus
bar!

P.O.Box 36423|Abu Dhabi| UAE - phone: +971 2 666 7783|fax: +971-2-666 7784| www.amplex-emirates.ae

AMR Pre-Installation Requests

2.

Page 4/47

Villa Water meters to be installed near Electrical room ( max 5 m) with PVC
conduit installed between water meter end Electrical Room for each water meter
or group of water meters

Villa Compound installation should be finished with electricity and water meters
grouped in separate rooms

HIGH -RISE BUILDINGS


In high-rise buildings, all water meters are installed in water meter rooms or in water
meter cabinets on each floor
In the following sections, we describe pre-installation requisites for:

2.1

Floor Electrical Meter Room Requests

Floor Water Meter Room Requests

Main Electrical Room Requests

Ground Floor Requests(Shop Meters)

Floor Electrical Meter Room Requests


For floor electrical room AMR pre-installation we have 3 requests:
1. To have 3 phase spare breaker for AMR installation inside SMDB -(Figure1)
2.

To have enough space on meter board for AMR box installation (25x35 cm)(Figure1)

3. To install PVC conduit with 3 core (1.5mm2) power cable between SMDB
and Electrical Meter board-(Figure1)

P.O.Box 36423|Abu Dhabi| UAE - phone: +971 2 666 7783|fax: +971-2-666 7784| www.amplex-emirates.ae

AMR Pre-Installation Requests

Page 5/47

Figure 1 ( Floor Electrical Meter Room)

P.O.Box 36423|Abu Dhabi| UAE - phone: +971 2 666 7783|fax: +971-2-666 7784| www.amplex-emirates.ae

AMR Pre-Installation Requests

2.2

Page 6/47

Floor Water Meter Room Requests

For floor water meter AMR pre-installation we have 3 requests:


1. To have enough space in water meter cabinet or in water meter room for AMR
box (25x25cm)-(Figure 2 & 4A & 4B)
2. To install PVC conduit with 4 core (A-BUS) data cable, following rules of pull
box ( after 3 bands and after 20m) -(Figure 3 & Figure 4)
3. Maximum 4 core (A-BUS) data cable distance 50 meters!

P.O.Box 36423|Abu Dhabi| UAE - phone: +971 2 666 7783|fax: +971-2-666 7784| www.amplex-emirates.ae

AMR Pre-Installation Requests

Page 7/47

Figure 2 ( Floor Water Meter Room)

P.O.Box 36423|Abu Dhabi| UAE - phone: +971 2 666 7783|fax: +971-2-666 7784| www.amplex-emirates.ae

AMR Pre-Installation Requests

Page 8/47

Figure 3 ( Pool Box after 20m)

P.O.Box 36423|Abu Dhabi| UAE - phone: +971 2 666 7783|fax: +971-2-666 7784| www.amplex-emirates.ae

AMR Pre-Installation Requests

Page 9/47

Figure 4 ( Pool box after 3 bands)

P.O.Box 36423|Abu Dhabi| UAE - phone: +971 2 666 7783|fax: +971-2-666 7784| www.amplex-emirates.ae

AMR Pre-Installation Requests

Page 10/47

Figure 4A ( Water meter room)

Figure 4B ( Water meter cabinet)

P.O.Box 36423|Abu Dhabi| UAE - phone: +971 2 666 7783|fax: +971-2-666 7784| www.amplex-emirates.ae

AMR Pre-Installation Requests

2.3

Page 11/47

Main Electrical Room Requests

For floor electrical room AMR pre-installation we have 2 requests:


1. All CT Electrical Meters to be installed on wall Electricity Meter board-(Figure 5)
2. 3 phase spare power breaker inside MDB and PVC conduit with 3 core (1.5mm2)
power cable between AMR 3 phase spare barker and Electrical Meter board(Figure 5)

P.O.Box 36423|Abu Dhabi| UAE - phone: +971 2 666 7783|fax: +971-2-666 7784| www.amplex-emirates.ae

AMR Pre-Installation Requests

Page 12/47

Figure 5 ( Main Electrical Room)

P.O.Box 36423|Abu Dhabi| UAE - phone: +971 2 666 7783|fax: +971-2-666 7784| www.amplex-emirates.ae

AMR Pre-Installation Requests

2.4

Page 13/47

Ground Floor Requests (Shop Meters)

Request is to have all shop water meters grouped in ground water meter room and all shop
electricity meters to have in ground electrical room.-(Figure 6)

Figure 6 (Ground Floor-Shops))

P.O.Box 36423|Abu Dhabi| UAE - phone: +971 2 666 7783|fax: +971-2-666 7784| www.amplex-emirates.ae

AMR Pre-Installation Requests

3.

Page 14/47

LOW RISE BUILDINGS (G+ 4)

Low-rise building is building with power supply from substation which one is feeding 2 or more
than 2 buildings! On site we have two types:
1. Low-rise buildings, where all water meters are placed on the roof either in a water meter room
or in water meter cabinet on the wall 3.1!
2. Low-rise buildings with water meter floor installation 3.2. !

3.1 Buildings with All Water Meters on the Roof

In the following sections, we describe pre-installation requisites for:

3.1.1

3.1.1. Floor Electrical Meter Room Requests

3.1.2. Roof Water Meter Room Requests

3.1.3. Main Electrical Room Requests

3.1.4. Ground Floor Requests(Shop Meters)

Floor Electrical Meter Room Requests


For floor electrical room AMR pre-installation we have 3 requests:
1. To have 3 phase spare breaker for AMR installation inside SMDB -(Figure7)
2. To have enough space on meter board for AMR box installation (25x35 cm)(Figure7)
3.To install PVC conduit with 3 core (1.5mm2) power cable between SMDB and
Electrical Meter board-(Figure7)

P.O.Box 36423|Abu Dhabi| UAE - phone: +971 2 666 7783|fax: +971-2-666 7784| www.amplex-emirates.ae

AMR Pre-Installation Requests

Page 15/47

Figure 7 ( Floor Electrical Meter Room)

P.O.Box 36423|Abu Dhabi| UAE - phone: +971 2 666 7783|fax: +971-2-666 7784| www.amplex-emirates.ae

AMR Pre-Installation Requests

Page 16/47

3.1.2. Roof Water Meter Room Requests


In buildings, where the water meters are installed on the roof, PVC conduit with 4-core data
cable should be installed between the nearest Electrical room (SMDB-with 3 phase power
supply) and Amplex Module box which is located in a room on the roof.
In low-rise buildings, where all water meters are placed on the roof either in a water meter room
( Figure 10A) or in water meter cabinet on the wall, the following pre-installation work should
be carried out:

PVC conduit with 4 core data (A-BUS cable maximum 30m) cable should be
installed between the nearest Electrical room meter board (SMDB with 3 phase power supply)
and Amplex Module box which is located in a room on the roof. (Figure 8 & 9)

PVC conduit with 4 core data cable (A-BUS cable maximum 30m) should be
installed between each water meter cabinet and Amplex Module box which is located in a room
on the roof. (Figure 10)

P.O.Box 36423|Abu Dhabi| UAE - phone: +971 2 666 7783|fax: +971-2-666 7784| www.amplex-emirates.ae

AMR Pre-Installation Requests

Page 17/47

Figure 8 (Nearest Electrical room)

P.O.Box 36423|Abu Dhabi| UAE - phone: +971 2 666 7783|fax: +971-2-666 7784| www.amplex-emirates.ae

AMR Pre-Installation Requests

Page 18/47

Figure 9 (Roof Water Meter Room)

P.O.Box 36423|Abu Dhabi| UAE - phone: +971 2 666 7783|fax: +971-2-666 7784| www.amplex-emirates.ae

AMR Pre-Installation Requests

Page 19/47

Figure 10 (Water Meter Room)

P.O.Box 36423|Abu Dhabi| UAE - phone: +971 2 666 7783|fax: +971-2-666 7784| www.amplex-emirates.ae

AMR Pre-Installation Requests

Page 20/47

Figure 10A (Roof Water Meter Room)

3.1.3. Main Electrical Room Requests

For floor electrical room AMR pre-installation we have 2 requests:


1. All CT Electrical Meters to be installed on wall Electricity Meter board-(Figure
10B)
2. 3 phase spare power breaker inside MDB and PVC conduit with 3 core (1.5mm2)
power cable between AMR 3 phase spare barker and Electrical Meter board(Figure 10B)

P.O.Box 36423|Abu Dhabi| UAE - phone: +971 2 666 7783|fax: +971-2-666 7784| www.amplex-emirates.ae

AMR Pre-Installation Requests

Page 21/47

Figure 10B (Main Electrical Room in LR)

P.O.Box 36423|Abu Dhabi| UAE - phone: +971 2 666 7783|fax: +971-2-666 7784| www.amplex-emirates.ae

AMR Pre-Installation Requests

3.1.4

Page 22/47

Ground Floor Requests (Shop Meters)

Request is to have all shop water meters grouped in ground water meter room and all shop
electricity meters to have in ground electrical room.-(Figure 11)

Figure 11 (Ground Floor-Shops))

P.O.Box 36423|Abu Dhabi| UAE - phone: +971 2 666 7783|fax: +971-2-666 7784| www.amplex-emirates.ae

AMR Pre-Installation Requests

Page 23/47

3.2 Buildings with Electricity and Water Meters on each floor

In low-rise buildings where both water and electricity meters are located on the
individual floors.
In the following sections, we describe pre-installation requisites for:

3.2.1

3.2.1. Floor Electrical Meter Room Requests

3.2.2. Floor Water Meter Room Requests

3.2.3. Main Electrical Room Requests

3.2.4. Ground Floor Requests(Shop Meters)

Floor Electrical Meter Room Requests


For floor electrical room AMR pre-installation we have 3 requests:
1.To have 3 phase spare breaker for AMR installation inside SMDB -(Figure12)
2. To have enough space on meter board for AMR box installation (25x35 cm)(Figure12)
3.To install PVC conduit with 3 core (1.5mm2) power cable between SMDB and
Electrical Meter board-(Figure12)

P.O.Box 36423|Abu Dhabi| UAE - phone: +971 2 666 7783|fax: +971-2-666 7784| www.amplex-emirates.ae

AMR Pre-Installation Requests

Page 24/47

Figure 12 ( Floor Electrical Meter Room)

P.O.Box 36423|Abu Dhabi| UAE - phone: +971 2 666 7783|fax: +971-2-666 7784| www.amplex-emirates.ae

AMR Pre-Installation Requests

Page 25/47

3.2.1 Floor Water Meter Room Requests

For floor water meter AMR pre-installation we have 3 requests:


4. To have enough space in water meter cabinet or in water meter room for AMR
box (25x25cm)-(Figure 13 & 4A & 4B)
5. To install PVC conduit with 4 core (A-BUS) data cable, following rules of pull
box ( after 3 bands and after 20m) -(Figure 14 & Figure 15)
6. Maximum 4 core (A-BUS) data cable distance 50 meters!

P.O.Box 36423|Abu Dhabi| UAE - phone: +971 2 666 7783|fax: +971-2-666 7784| www.amplex-emirates.ae

AMR Pre-Installation Requests

Page 26/47

Figure 13 ( Floor Water Meter Room)

P.O.Box 36423|Abu Dhabi| UAE - phone: +971 2 666 7783|fax: +971-2-666 7784| www.amplex-emirates.ae

AMR Pre-Installation Requests

Page 27/47

Figure 14 ( Pool Box after 20m)

P.O.Box 36423|Abu Dhabi| UAE - phone: +971 2 666 7783|fax: +971-2-666 7784| www.amplex-emirates.ae

AMR Pre-Installation Requests

Page 28/47

Figure 15 ( Pool box after 3 bands)

P.O.Box 36423|Abu Dhabi| UAE - phone: +971 2 666 7783|fax: +971-2-666 7784| www.amplex-emirates.ae

AMR Pre-Installation Requests

Page 29/47

3.2.3. Main Electrical Room Requests

For floor electrical room AMR pre-installation we have 2 requests:


1. All CT Electrical Meters to be installed on wall Electricity Meter board-(Figure 16)
2. 3 phase spare power breaker inside MDB and PVC conduit with 3 core (1.5mm2)
power cable between AMR 3 phase spare barker and Electrical Meter board(Figure 16)

P.O.Box 36423|Abu Dhabi| UAE - phone: +971 2 666 7783|fax: +971-2-666 7784| www.amplex-emirates.ae

AMR Pre-Installation Requests

Page 30/47

Figure 16 (Main Electrical Room in LR)

P.O.Box 36423|Abu Dhabi| UAE - phone: +971 2 666 7783|fax: +971-2-666 7784| www.amplex-emirates.ae

AMR Pre-Installation Requests

Page 31/47

3.2.4. Ground Floor Requests (Shop Meters)

Request is to have all shop water meters grouped in ground water meter room and all shop
electricity meters to have in ground electrical room.-(Figure 17)

Figure 17 (Ground Floor-Shops))

P.O.Box 36423|Abu Dhabi| UAE - phone: +971 2 666 7783|fax: +971-2-666 7784| www.amplex-emirates.ae

AMR Pre-Installation Requests

4.

Page 32/47

Villas

In Villas, the following pre-installation work should be carried out:


1. To have 3 phase spare breaker for AMR installation inside SMDB -(Figure18)
2. To have enough space on meter board for AMR box installation (25x35 cm)(Figure18)
3. To install PVC conduit with 3 core (1.5mm2) power cable between SMDB
and Electrical Meter board-(Figure18)
4. All electricity meters inside Villa Electrical Room-(Figure18)
5. Villa Water meters to be installed near Electrical room ( max 5m from El.
Room)
6. Between each Water meter or group of water meters and Electrical Room to be
installed PVC conduit with 3 core data cable for each water meter -(Figure18)

P.O.Box 36423|Abu Dhabi| UAE - phone: +971 2 666 7783|fax: +971-2-666 7784| www.amplex-emirates.ae

AMR Pre-Installation Requests

Page 33/47

Figure 18 (Villa Installation)

P.O.Box 36423|Abu Dhabi| UAE - phone: +971 2 666 7783|fax: +971-2-666 7784| www.amplex-emirates.ae

AMR Pre-Installation Requests

5.

Page 34/47

COMMERCIAL VILLAS
In Commercial Villas, all water meters are installed or roof and all electricity meters are
installed in Main Electrical room!
In the following sections, we describe pre-installation requisites for:

Main Electrical Room Requests

Roof Water Meter Requests

Ground Floor Requests(Shop Meters)

5.1. Main Electrical Room Requests

For main electrical room AMR pre-installation we have 3 requests:


1. To have 3 phase spare breaker for AMR installation inside SMDB -(Figure19)
2. To have enough space on meter board for AMR box installation (25x35 cm)(Figure19)
3.To install PVC conduit with 3 core (1.5mm2) power cable between SMDB and
Electrical Meter board-(Figure19)

P.O.Box 36423|Abu Dhabi| UAE - phone: +971 2 666 7783|fax: +971-2-666 7784| www.amplex-emirates.ae

AMR Pre-Installation Requests

Page 35/47

Figure 19 (Commercial Villa El. Room)

P.O.Box 36423|Abu Dhabi| UAE - phone: +971 2 666 7783|fax: +971-2-666 7784| www.amplex-emirates.ae

AMR Pre-Installation Requests

Page 36/47

5.2 Roof Water Meter Requests


AMR pre-installation request for water meter roof installation is that PVC conduit (maximum
30m) should be installed between the nearest sub main distribution board (SMDB) or Service
power Supply (with 3 phase power supply) and roof. (Figure 20)

Figure 20 (Commercial Villa Roof Installation)

P.O.Box 36423|Abu Dhabi| UAE - phone: +971 2 666 7783|fax: +971-2-666 7784| www.amplex-emirates.ae

AMR Pre-Installation Requests

6.

Page 37/47

Villa Compounds

All meters in Villa compounds should be groped in few water meter rooms ( for water meters) and
in few electricity rooms ( for electricity meters)!

For Villa Compound AMR pre-installation we have 2 requests:


1. To group all electricity meters in few Electrical rooms and to group all water meters
in water meter rooms ( Figure 21)
2. To have between each water meter and electricity meter room for same villas
installed PVC pipe with 4 core data cable(maximum distance of A-BUS cable 30m)
( Figure 21)

P.O.Box 36423|Abu Dhabi| UAE - phone: +971 2 666 7783|fax: +971-2-666 7784| www.amplex-emirates.ae

AMR Pre-Installation Requests

Page 38/47

Figure 21 (Villa Compound Installation)


For Compounds with High&Low-rise buildings should follow already described ,in this document,
pre-installation requests for High&Low-rise buildings!

P.O.Box 36423|Abu Dhabi| UAE - phone: +971 2 666 7783|fax: +971-2-666 7784| www.amplex-emirates.ae

AMR Pre-Installation Requests

7.

Page 39/47

Bulk and Operational water meters

Bulk or Operational should be installed in water meter room on ground floor or in some available
room in ground floor. If is Bulk or Operational water meter in ground floor water meter room than
we should follow already described ,in this document, pre-installation requests for High&Low-rise
buildings ( PVC pipe with 4 core data cable between ground water and electricity room)!If is Bulk
or Operational water meter in some available room we should have PVC pipe with 3 core data
cable between this meter and Main Electrical room. (Figure 22)

P.O.Box 36423|Abu Dhabi| UAE - phone: +971 2 666 7783|fax: +971-2-666 7784| www.amplex-emirates.ae

AMR Pre-Installation Requests

Page 40/47

Figure 23 (Bulk or Operational Water meter )

P.O.Box 36423|Abu Dhabi| UAE - phone: +971 2 666 7783|fax: +971-2-666 7784| www.amplex-emirates.ae

AMR Pre-Installation Requests

8.

Page 41/47

Material

Materials for pre-installation requisites that should be observed in future new buildings are
(Figure 23A):
1. A-BUS cable ( 4 core data cable)
2. 3 core meter data cable
3. PVC Pool BOX and Pipe

Figure 23A (Material for Installation)

P.O.Box 36423|Abu Dhabi| UAE - phone: +971 2 666 7783|fax: +971-2-666 7784| www.amplex-emirates.ae

AMR Pre-Installation Requests

Page 42/47

8.1 Cables

8.1.1. A-BUS ( 4 Core data Cable)- (Figure 24)

Figure 24 (A-Bus Cable)


Specification:
-

(7/0.30 x 4C) + (D.W) 7/0.30 + AL/MY

Conductor:
-

Material

: Bare annealed copper

Diameter

: 0.30mm

Combination

:7

Stranded diameter

: 0.90mm (reference)

Cross section area

: 0.4948somm (approx.)

P.O.Box 36423|Abu Dhabi| UAE - phone: +971 2 666 7783|fax: +971-2-666 7784| www.amplex-emirates.ae

AMR Pre-Installation Requests

Copper content

Page 43/47

: 23.6kg/km

Insulation:
-

Material

: Polyethylene

Diameter

:1.80+-0.10mm

Nominal thickness

:0.45 mm

Colour

: Blue, Green, Orange, Brown

Drain wire:
-

Material

: Bare annealed copper

Composition

:7/0.30

Wrapper:
-

Material

: AL/MY

Jacket:
-

Material

: Polyvinyl chloride

Diameter

: 6.30+-0,20mm

Nominal thickness

: 0.93mm

Colour

: Grey

P.O.Box 36423|Abu Dhabi| UAE - phone: +971 2 666 7783|fax: +971-2-666 7784| www.amplex-emirates.ae

AMR Pre-Installation Requests

Page 44/47

8.1.2. 3-Core Meter Data Cable- (Figure 25)

Figure 25 (3 core data cable)


Specification:
-

(7/0.30 x 3C) + Talcum powder+ AL/MY

Conductor:
-

Material

: Bare annealed copper

Diameter

: 0.30mm

Combination

:7

Stranded diameter

: 0.90mm (reference)

Cross section area

: 0.4948somm (approx.)

Copper content

: 16.6kg/km

P.O.Box 36423|Abu Dhabi| UAE - phone: +971 2 666 7783|fax: +971-2-666 7784| www.amplex-emirates.ae

AMR Pre-Installation Requests

Page 45/47

Insulation:
-

Material

: Polyethylene

Diameter

:1.80+-0.10mm

Nominal thickness

:0.45 mm

Colour

: Black, Green, Red

Wrapper:
-

Material

: AL/MY

Jacket:
-

Material

: Polyvinyl chloride

Diameter

: 6.30+-0,20mm

Nominal thickness

: 0.93mm

Colour

: Grey

P.O.Box 36423|Abu Dhabi| UAE - phone: +971 2 666 7783|fax: +971-2-666 7784| www.amplex-emirates.ae

AMR Pre-Installation Requests

8.1.3.
-

Page 46/47

Power cable - (Figure 26)

3-Core Cable XV4 3X24A (3XLPE/85)

Figure 26 ( Power Cable)

Heat resistance

: 70 degree Celsius

Sheeting material

: PVC

Core

: 3 core stranded (or with single core) , 1.5 mm, power cable

Colour

: Red, Black, Yellow/Green

P.O.Box 36423|Abu Dhabi| UAE - phone: +971 2 666 7783|fax: +971-2-666 7784| www.amplex-emirates.ae

AMR Pre-Installation Requests

8.2

Page 47/47

PVC Box and Pipe- (Figure 27)

All installation should be finished with PVC Conduit (25mm size) and with PVC bands, clamps and
pool box for conduit pipe 25mm.

Figure 27 (PVC)

P.O.Box 36423|Abu Dhabi| UAE - phone: +971 2 666 7783|fax: +971-2-666 7784| www.amplex-emirates.ae