Presentation Massive
Presentation Massive
Jakarta
Mass Foundation
Apartemen 2
Prepared by :
PT.ACSET INDONUSA
APARTMENT 2
Pouring Strip
Matt
Foundation
MATERIAL
- Cellular Foundation
a. Mutu beton fc 40 Mpa = K500
- Matt Foundation
a. Mutu beton fc 35 Mpa = K420
Mix design berdasarkan proposal yang
diajukan pihak PT.Holcim.
Akses Jalan
Concret
e Pump
Batchin
g Plan
Slump
Test
Truck
Mixer
Stock
Yard
Tahapan Pekerjaan
1.
2.
3.
4.
5.
6.
7.
8.
Subgrade Preparation
Lean concrete t = 50 mm
Slab of wall Cellular Foundation t= 700 mm
Wall of Cellular foundation t = 2800 mm
Matt Foundation t = 4000 mm
Girder Beam 350 x 700 mm
Precast slab t = 100 mm
top slab of mass foundation t = 300 mm
1.Preparation Subgrade
Compacted Using
Vibro Roller
Compacted Using
Tamping Rammer
2.Lean Concrete
Lean Concrete
t=50 mm
7. Precast Slab
Precast Slab t = 100 mm
8. Top Slab
Steel Pipe 2
1000 mm
Lean concrete 50 mm
Compacted
`
`
`
`
Detail Formwork
Layout thermocopler
Waktu Pengecoran
Untuk bottom slab Volume = 506 m3 = 13
jam = 1 hari
- Menggunakan 2 CP
Untuk cellular foundation = 526 m3 = 14
jam = 1 hari
- Menggunakan 2 CP
Untuk matt foundation = 2510 m3 = 33 jam
= 2 hari
- Menggunakan 4 CP+1 Stand by
Untuk top slab = 217 m3 = 6 jam = 1 hari
- Menggunakan 2 CP
SISTEM CURING
4000 mmm