Risk event description and

impact area

Impact Rating

Probability
Rating

Risk
Score

Group member getting ill or


injured.

High

High

Loss of project data and files


due to system errors

High

Low

Group member not participating


in group work.

High

Low

Conflicts between group


members.

Low

High

Resources needed for project


not being provided.

Low

Low

Risk Response
Description
The group member would
need to bring proof that
he/she was ill or injured,
signed sick note by
doctor.
We will have to re-do the
entire work all over again
and this might cause the
group to miss deadline.
Complain to tutor or the
head of the project
explaining the situation.
The other group members
should take a vote on the
situation on who support.
Explain the situation to
the head of strand.

Trigger
Strike rule applied if reason for
absence is not good enough

The new work done will be


backed up by group members,
in case of the same situation
occurring.
Strike rule applied if group
member still isnt doing work
after being reported to the tutor.
Both group members will be
kicked out, if they are still
having a conflict after voting.
Strike rule can be applied
Try and get the resources
needed from the strand leader
early.