You are on page 1of 1

SHELL MARINA LOBP -GMP PROJECT

CONTROL CIRCUIT FUNCTION TEST REPORT


AREA: . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Page:

SYSTEM :

CONTRACT NO:

CP / 13 - 001 / L

EQUIPMENT NO:

DRAWING NO:

SWITCHBOARD NO:

LOCATION:

DUTY:

COMPARTMENT NO:

REV:

Associated Tests

YES

N/A

NO

YES

N/A

NO

1. Compartment checks completed (area Illumination values Form PLPL.EA. F4036).


Operation of the following has been verified

YES

N/A

NO

2. Stop buttons

13. Vendor package interface.

3. Start buttons.

14. Alarm annunciation.

4. Inch button.

15. Indicator lamps.

5. Reset buttons.

16. Metering.

6. Duty - standby selector.

17. Main contactor.

7. Hand - Off - Auto selector.

18. Control relays.

8. On-Off switches.

19. Auxiliary contacts.

9. Limit switches.

20. Electrical interlocks.

10. Interface relays.

21. Timers.

11. ACMV master trip relay panel interface.

22. Tested tags fitted.

12. Instrument interface.


Operational Verification
23. Circuit operation as per process description and schematic diagram.

Yes

No

Setting and Rating


Motor FLC

Motor Fuse Rating

Overload Setting E/F PU Relay Setting


E/F Relay Timer Setting

Trip and Interlock System

YES

N/A

Control Fuse
Control Fuse Rating
Rating

NO

24. Has the shutdown system been tested.

Remarks :

COMPLETED BY
COMPANY
SIGNATURE
NAME
DATE
PLPL.EA. F4035

If NO Remarks Enter NONE Initial and Date

EXECUTED BY

VERIFIED BY

VERIFIED / REVIEWED BY

You might also like