Professional Documents
Culture Documents
Design Criteria: The Formal Basis of Design
Design Criteria: The Formal Basis of Design
JOHN W. SCOTT
INTRODUCTION
The design criteria for a particular
concentration and dewatering project
will provide t h e formal basis for design
of t h e process, equipment and facilities.
These criteria will specify t h e required
capacities and operating schedules for
t h e equipment, a s well a s t h e quantity
and quality of t h e feed t o be processed
and products obtained. The general
climatic and geographical conditions a t
t h e site, specific information on soil o r
rock conditions; and applicable design
standards and codes will also be
included.
The design criteria will generally be
based on an interpretation of testwork
carried out on the particular ore and
site, and will thus parallel in detail and
completeness this testwork. As the
project moves from t h e early conceptual
phases through t o final detailed design,
t h e design criteria will be developed and
become more detailed as information is
generated and made available f o r use.
The design criteria a r e critical t o t h e
design e f f o r t a s t h e formal specification
to t h e designer of what and how much is
t o be processed, what and how much is
t o b e produced, and where and under
what conditions.
representative
bulk
samples,
providing a valid design basis.
thus
Engineering
and
Detailed
1. GENERAL CRITERIA
2. METALLURGICAL BALANCE
3. OPERATING
SCHEDULE
THROUGHPUT
4. PROCESS CRITERIA
5. ASSUMPTIONS
6. RECOMMENDED TESTWORK
SECTION I
1.- INTRODUCTION
2.3.-
AND
FEASIBILITY STUDY
OUTLINE OF DESIGN
CRITERIA
4.-
GENERAL CRITERIA
OPERATING
SCHEDULE
AND
CAPACITY
METALLURGICAL
BALANCE
PROCESS
DESCRIPTION
EQUIPMENT
DESCRIPTION
FLOTATION /
MAGNETICSEPN/
ETC.
THICKENING AND
FILTERING
DRYING
AND
SECTION I1
.
.
PACKING
3.- FACILITIES
DESCRIPTION
BUILDINGS
SERVICES
SITE AND ACCESS
REQUIRED
TESTWORK
.
4.-
.
.
TABLE 3.
I.-General Criteria
1.0 Introduction
2.0 Scope o f Work
3.0Criteria Summary
4.0 Mechanical Design Criteria
4.1
4.2.
4.3
4.4
4.5
4.6
4.7.
Conveyors
Chutes
Fabricated Items
Process Pumps
Piping
Linings
Codes and Standards
General
Codes and Standards
5.3
PowerSupplySystem
5.4
Main Substation
5.5
System Voltages
5.6
Emergency Power
5.7
Metering
5.8
Distribution Switchgear
5.9
600 Volt Power
5.10
Motors
5.11 Power Factor Correction
5.12
Motor Controllers
5.13
Controls and Pilot Devices
5.14
Lightning
and
Surge
Protection
5.15 Grounding
5.16
Overhead Transmission
Line
5.17
Lightning and Receptacles
5.18
Wiring Methods
5.17
Wire and Cable
5.20
Conduit
5.21 Enclosures
5.22
Cable Tray
5.23
Special Equipment
5.24
Communications
6.0 Structural Design Criteria
5.2
6.1
6.2
6.3
6.4
6.5
General
Design Loads
Unit Stresses andLimiting
Deflections
Load Factors
Load Combinations
7.0
8.0
9.0
General
Washrooms
Change Rooms
Lunch Rooms
Offices and Labs
Building Enclosures
Purpose
References
General
Instruments
Control Panels
11.1 General
11.2 Schedules and capacity
12.0 Process Metallurgy
12.1 Ore Characteristics
12.2 Metallurgical balance
12.3 Material balance
44.0 Water Supply
44.1 Operating Criteria
44.2 Process Description
44.3 Equipment
47.0 Tailing Disposal
47.1 Operating Criteria
47.2 Process Description
47.3 Equipment
51.0
Ancillary Buildings
51.1
51.2
51.3
51.4
Offices
Change House
Laboratory
Shop & Warehouse
function
of
the
maintenance
requirements of each individual piece of
equipment and also t h e operating
strategy of t h e plant. For instance, a
weekly maintenance shift may be
planned f o r certain areas due t o required
preventive maintenance on certain
critical items of equipment. These items
in t h e design criteria a r e normally
tabulated in a format a s shown in Table
4.
TABLE 4
SCHEDULE
TYPICAL
OPERATING
PLANT AREA
PERIOD
FLOTATION
Availability (%I)
94
Process Metallurgy
Operating Schedule and Capacity
The heart of any design is t h e
required
plant
capacity
and t h e
operating schedule. These define t h e s i z e
of t h e equipment and t h e operating duty.
The operating schedule is normally
twenty-four hours per day, t h r e e shifts
per day, 365 days per year for a typical
concentrator. In some cases t h e plant
may b e designed to operate fewer days
per week but continuous twenty-four
hour operation is usual. In some
dewatering sections filters may be
operated on a single shift basis, this will
be clearly set out in t h e design criteria
for t h e area. In addition t o t h e operatinqand
throughput,
some
schedule
estimation of t h e availability of t h e
plant is used f o r setting t h e actual
hourly throughput. This availability is a
Thickening:
Unit a r e a requirements
(Laboratory o r pilot plant)
Flocculant
mixing
requirements
Flocculant r a t e s
Underflow densities
Overflow clarities
Slurry
rheology
(if
underflow
is
non
newtonian)
Filtering:
Unit a r e a requirements
Cloth permeability
Vacuum requirements
Form t i m e
Dry t i m e
Cake thickness
Slurry rheology
Filter Aid requirements
Cloth
washing
requirements
Air blow requirements
Altitude e f f e c t s
Ore mineralogy
Metallurgical balance
Material balance
Feed r a t e (and variations)
Particle Size Distributions (Feed and
Products)
Specific gravity (Feed and Products)
Supplementary Criteria
Froth
Flotation:
Gravity
Separation:
Magnetic
Separation:
Flotation r a t e d a t a
Air requirements
Conditioning time
Reagent additions
Heavy liquid separation
t e s t results
Laboratory and/or pilot
plant results for:
Jigging, Tabling, Spirals
or Cones.
Extended
Mineralogical
Analysis.
Classification
characteristics
Magnetic susceptibilities
Laboratory t e s t results
Magnetic field strength
required
Electrostatic
Separation:
Electrical properties
Laboratory t e s t results
Field strength
Dryness and temperature
requirements
Architectural.
The
architectural
criteria generally reflect t h e style of
building exterior and interior finishes
desired for t h e plant. In addition, t h e
provision of specific criteria for heavy
use areas, particular chemical resistance
requirements,
and
climatic
considerations a r e
important.
The
development of criteria for offices,
washrooms,
drys
and
laboratories
requires a detailed description of t h e
proposed work force and operating
schedules for t h e various areas.
Instrumentation. The instrumentation
desiqn criteria a r e normally developed in
c o n j k c t i o n with the -process. and
mechanical engineering groups, and in
accordance with t h e proposed operating
criteria. The specific instruments chosen
for each application will reflect an
overall control philosophy for t h e plant
whether i t is computer based, distributed
control o r simply local start-stop
switches for simple circuits.
The
particular
design
criteria
referred t o in Appendix I refer t o a
tungsten concentrator incorporating both
flotation and gravity concentration. The
criteria developed for a large base
metals flotation concentrator or an iron
ore concentrator utilizing spirals or
magnetic separation would be similar in
nature but reflect t h e specific ore and
process under consideration.
Plant/Process Area
For each a r e a of the plant and stand
alone unit processes, such a s flotation,
the design criteria will specify the
operating criteria, a process description
and a detailed equipment description.
Onceagain,spacelimitationsprevent
including a complete design criteria for
all process a r e a s of
a typical
concentrator, however excerpts from a
s e t of process a r e a criteria developed
for a tungsten concentrator a r e given in
Appendix 11. The areas covered a r e
generally
applicable
to
most
concentration/dewatering plants but
naturally would be augmented and
modified specifically for t h e plant and
process being designed.
The equipment descriptions in this
particular design criteria are not
specific a s t o supplier, a s t h e equipment
has not yet been purchased. In a fully
detailed design criteria for a project in
detailed
engineering,
the
major
equipment would be committed t o and
would be described specifically. As this
equipment is purchased, t h e design
criteria document will be updated t o
reflect the particular machine t o be
installed.
LIST OF APPENDICES
APPENDIX I Examplesof General Design
Data
APPENDIX I1Examples of Process Area
Criteria
ACKNOWLEDGEMENT
The assistance o f my colleagues at
Wright Engineers L t d particularly Brian
Montpellier,
Project
Manager
and
management permission to prepare this
paper are gratefully acknowledged.
EXAMPLES OF G E N E R A L E I I C DATA
APPENDIX
5-
hn.
-= -8
m
g%
L
.u5ue'5k Z g
4.4.
.-a .-a .z
g .5
In.-
22.2 ew r. G.- p
ee=A,x
a*
a a s 9 ee
aa.ia,
J=
m 4.
-8
5 % :3
Lb
m m
"l
C
.-em .,5-
*.
.-
8
0,
- 3 ' -
L m
r o B
3;
;
." ..C
$23
35
i;%
,:ad
W U 5
C * .%
9Zk
;%i a&
.%23S
w '3
rn
- .- Y
g=%%
.E5;
gc; yo
W
x n
c w
* Y D
Z Y 8
.I:='W%
6.1.1
Standards
Before structural design or detailing conrences m any
sectian of the woject, reference shall be made to
Kisht Enginems Limited desi.gn and d-afting standards
to ensure that a l l item c m l y with these standards.
6.2
Desiqn Loads
( i i i ) hmv Structures
Buildings and their structural u*bers made of plain and
reinfmed masonry shall c m f a r to CSR Standard
~ - 5 3 0 ( - H 7 8 'ksmry Design and Cmskwtim for
Buildingsn.
7.3 kterials
- latest editim
in Canada
latest edit ion
- The Federal Ministry of Energy, nines and Petroleua
Reswces, ninwal Resarrces 8ranchr invirormental
Reulations - latest edition
- Underuritwls Reconmendations
- The lbtional Fire Code of Canada 1977 - latest edition
Ontario Plumbing Code -latest edition
- Pressure Vessels and Piping Regulations as issued by the
Euvanaent of the N.W.T.
- Canadian Standard Association
kplicable local Codes.
National
Assaiatim Inc. (SMM) Duct Constructim Standards.
7.2
7.5
Guide
P~OCESS
Ventilalion
by Y.C.L.
Heaeon.
x w s
VI
C
L
::
5%
."
W W *
- m c
.
I
U
k$q
C
?P"l
ul
3 C ) C
6%
U 5
g.=z 8
gas'
O
m . 5
*.
LC
w
Y-0
g3.55
m w w
A.
.."
C I
.5-z
0
Y .r.
s9
=2s
2'-%
m
a
.-2 6
"l .Y Y
c
'-
92.2.2
92.0 Sulphide Cmditiminq and Flotation
92.1 Cueratins Criteria
9.1.1
Primary Flotation
- Solids F!ow
- %lids S.6.
- h l p Censity
- Tic2
42.1.1
33 mtph
3.4
322 Solids nlw
5 min.
S~ccindarvF!otation (U~qpqradePlant)
- Eolids Flow
tlbatchi
b l i d s nlw
??.:.I
kcid C~ndltionwTanks
Batch !4.3
- Salids S.G.
- F~lpDensitv
5.4
==QL.
- Tine
IS
ninlstase
92.2.1
Upqrack Flotatim
Primarv Flotation
Trc a:.!
.: 2.11 hi?h riid stcei rthber
line2 conditicrlin~tank receivins slirrry
from the rod nil1 scr'ew. t!uhsnical
asitation is prcvided by a sos~.ntkd
i.wellw nounted on an overhead frane.
The agitators are driven by ar. eleitric
aotm thr~uqha V-belt &ive and rilht
an?le seat. box. Flsw thrwsh i s by
gravity..
The tanks contains vertical b a f f l ~to
ninioize urirling and 0.5 in minim
freeboard to prevent splashing over the
sides. The tanks have X I ovwf low pipe
to channel eergmcy overflor product to
the floor drain and suq.
92.3.2
Reasent Ccnsuwt im
CWPW Sul~hate
Sulphuric k i d
Frothw
Xanthate
Lime
8 % 50 cu f t .
4 x 50 cu ft.
2 r 50 cu ft.
92.4.2
kqlt
kqlt
&It
kq/t
kglt
bppw Sulphate