T1
3

Procesul de executie
Nr.crt.

Denumirea

Ti, ti

Sapatura generala mecanizata

T1=3

Sapatura manuala la fundatii

t2=4

Turnare beton in talpi de fundatie

t3=2

Executie cuzineti

t4=3

Executie elevatie

t5=4

Umpluturi

T6=3

Montare cofraje si armaturi in planseu cota -0.05

t7=5

10

Turnare beton in planseu

T8=1

Decofrare planseu

T9=2

3
0

10
24
23
22
21
20
19
18
17
16
15
14
13
12
11
10
9
8
7
6
5
4
3
2
1
0

t2
4

t2

t2

t3

t4
2

t5

Martie
6

Aprilie

9 10 11 12 13 16 17 18 19 20 23 24 25 26 27 30 31

9
3
3

9 10

Mihoc Paul

Organizare

Grupa 3401-B

5-6

T6

t7

D = T+t+tt+ = 146sch
ANUL 2015
Aprilie
13 14 15 16 17 20 21 22 23 25 28 29 30 30

Mai
1

8 11 12 13 14 15 18

10

Mmed = AG/D =24*9+3*28+9*12+15*4+6*24+10*30+3*12/146 = 948/146

Organizarea lucrarilor
desuccesiva
executie A executia ciclurilor pe sectoare
Metoda

t7
5

t7

t7

t7
5

t7
5

T8

Tt=7

+t+tt+ = 146sch

NUL 2015
Mai

Iunie
19 20 21 22 25 26 27 28 29

9 10 11 12 15 16 17 18 19 22 23 24 25

+3*12/146 = 948/146= 6,49 muncitori

Tt=7

Iulie
26 29 30

9 10 13 14 15 16 17 20

Mmed