20 March 2015

Mr. Franck Wicquart


Project Manager
OTV Philippines
Dear Mr. Wicquart:
Greetings!
Below is the timeline of ativities that went through in obtaining necessary permits for the Pasay
STP project.
Preliminary Permits

Date Issued by Pasay City

Barangay Clearance/Resolution
Fencing Permit
Demolition Permit
Excavation Permit
Locational Clearance
Temporary Electrical Permit

August 3, 2014 (by Barangay 168)


January 12, 2015
January 12, 2015
January 12, 2015
December 16, 2014
January 6, 2015

Building Permit
Architectural
Strucural
Electrical
Mechanical
Sanitary and Plumbing
Fire Safety Evacuation Clearance

February 17, 2015


February 17, 2015
February 17, 2015
February 17, 2015
February 17, 2015
February 6, 2015

The application for Locational Clearance was submitted to Pasay City on June 30, 2014.
In the process of application, two (2) public hearing was held dated August 3, 2014 and August
prior for the issuance of Locational Clearance of the project.
Pasay City Government issued the Locational Clearance on December 16, 2014,and reminded
the tax clearance of the property where the project is to built.
The process of securing the permit resumed on January 5, 2015 with constant follow up and
submission of other documents that Pasay City required during the processing of the latter.
I hope this provides useful information for future inquiry of STP Pasay project stakeholder.
Very truly yours,
Michael Allan E. Sicat
President and CEO