> ABB shall Provide the supply & source of supply details

> How the rating of the MCB is selected????

> How the number of batteries are achieved????????


Provide the calculation(Cable drop also shall be
considered).
> Arrangement of batteries in the battery rack shall be
shown.
> ABB has not considered parallel redundant with by pass system.ABB shall consider
the same .
> The provided scheme is like general block diagram.ABB shall provided detail scheme
drawing for review.

ABB shall provide the following for review for 6kVA UPS
> Complete BOM of UPS system including all components
> General arrangement drawing
> Technical Data Sheet
> Operational write up
> Foundation details
> Display details
> Quality Plan