Professional Documents
Culture Documents
Final Rate Analysis
Final Rate Analysis
of spread sheets
Worksheet- 1 : CHAPTER-1 CARRIAGE OF MATERIALS
Worksheet- 2 : CHAPTER-2 SITE CLEARANCE
Worksheet- 3 : CHAPTER-3 EARTH WORK, EROSION CONTROL AND DRAINAGE
Worksheet- 4 : CHAPTER-4 SUB-BASES, BASES (NON- BITUMINOUS) AND
SHOULDERS
Worksheet- 5 : CHAPTER-5 BASES AND SURFACE COURSES (BITUMINOUS)
Worksheet- 6 : CHAPTER-6 CEMENT CONCRETE PAVEMENTS
Worksheet- 7 : CHAPTER-7 GEOSYNTHETICS AND REINFORCED EARTH
Worksheet- 8 : CHAPTER-8 TRAFFIC SIGNS, MARKINGS & OTHER ROAD
APPURTENANCES
Worksheet- 9 : CHAPTER-9 PIPE CULVERTS
Worksheet- 10 : CHAPTER-10 MAINTENANCE OF ROADS
Worksheet- 11 : CHAPTER-11 HORTICULTURE
Worksheet- 12 : CHAPTER-12 FOUNDATIONS
Worksheet- 13 : CHAPTER-13 SUB-STRUCTURE
Worksheet- 14 : CHAPTER-14 SUPER-STRUCTURE
Worksheet- 15 : CHAPTER-15 RIVER TRAINING AND PROTECTION WORKS
Worksheet- 16 : CHAPTER-16 REPAIR AND REHABILITATION
LEAD
STATEMENT
Lead in kms
Cost of
Carriage
Basic cost
Royalty
Local
5.00
85.00
45.00
10.00
140.00
26.00
190.00
45.00
10.00
245.00
GSB Material
Total
Bargaon/Adhamunda
9.00
105.00
148.00
36.00
289.00
Bargaon/Adhamunda
9.00
105.00
148.00
36.00
289.00
Tel river
10.00
110.00
25.00
10.00
145.00
Tel river
10.00
110.00
29.00
10.00
149.00
Cement. 43 grade
Bhawanipatna
35.00
240.00
4160.00
4400.00
Steel
Bhawanipatna
35.00
240.00
29662.00
29902.00
Emulision (SS-1)
Vizag
491.00
2079.00
13166.00
15245.00
Vizag
491.00
2079.00
18449.00
20528.00
CRMB-55
Vizag
491.00
2079.00
18907.00
20986.00
Emulision (RS-1)
Vizag
491.00
2079.00
13312.00
15391.00
Bhawanipatna
35.00
99.67
576.43
676.10
Bhawanipatna
35.00
99.67
724.22
823.89
Bhawanipatna
35.00
99.67
1026.99
1126.66
Bhawanipatna
35.00
149.50
1515.54
1665.04
Bhawanipatna
35.00
149.50
2032.61
2182.11
Bhawanipatna
35.00
299.00
2505.09
2804.09
Bhawanipatna
35.00
299.00
3434.71
3733.71
Local
5.00
291.50
1568.00
1859.50
Enamel Paint
Bhawanipatna
35.00
0.24
132.00
132.24
Angle Rod
Bhawanipatna
35.00
0.17
30.64
30.81
Drainage pipe
Bhawanipatna
35.00
240.00
350
Granite Spall
Bargaon/Adhamunda
9.00
105.00
148
Bricks(WBCB)(25x12x8cm)
590.00
36.00
289.00
Description of Machine
Activity
Output of
Machine
Output
Unit
Rate
P&M-001
Air Compressor
General Purpose
capacity in cum
170/250
hour
206
P&M-002
Concrete Mixing
cum/hour
20
hour
1440
P&M-003
Concrete Mixing
cum/hour
13
hour
1200
P&M-004
sqm/hour
1750
hour
692
P&M-005
Bitumen Spraying
capacity in litre
1500
hour
128
P&M-006
cum / hour
20
hour
1850
P&M-007
Pumping of concrete
cum / hour
33 / 22
hour
165
P&M-008
Concrete Bucket
capacity in cum
hour
10
P&M-009
Concrete Mixing
cum/hour
2.5
hour
161
P&M-010
Concrete Mixing
cum/hour
7.5
hour
161
P&M-011
Lifting Purpose
hour
825
P&M-012
Lifting Purpose
hour
550
P&M-013
Lifting Purpose
hour
230
P&M-014
Dozer D - 80 - A 12
cum/hour
300/ 150/250
hour
2190
P&M-015
Dozer D - 50 - A 15
cum/hour
200/ 100/150
hour
1592
P&M-016
sqm/hour
1750
hour
516
P&M-017
cum/hour
60 /25
hour
520
P&M-018
KVA
100
hour
450
P&M-019
KVA
50
hour
240
P&M-020
Producing GSB
cum/hour
40
hour
670
P&M-021
DBM/BM/SDC/ Premix
cum/hour
40
hour
15100
P&M-022
DBM/BM/SDC/ Premix
cum/hour
30
hour
11167
P&M-023
DBM/BM/SDC/ Premix
cum/hour
25
hour
8930
P&M-024
DBM/BM/SDC/ Premix
cum/hour
17
hour
7150
P&M-025
Surface Dressing
sqm/hour
1500
hour
1700
P&M-026
cum/hour
60 /60 /60
hour
840
P&M-027
Crushing of Spalls
TPH
100
hour
5590
P&M-028
Crushing of Spalls
11760
P&M-029
Kerb Making
P&M-030
Mastic Cooker
P&M-031
Surface Cleaning
sqm/hour
1250
hour
230
P&M-032
cum/hour
200/200/50/50
hour
1545
P&M-033
sqm/hour
2700
hour
650
P&M-034
cum/hour
40
hour
1725
P&M-035
cum/hour
40/30
hour
739
P&M-036
Rm/hour
2 to 3
hour
3525
P&M-037
cum/hour
25
hour
802
P&M-038
cum/hour
1.5 to 2.00
hour
2690
P&M-039
Repair of potholes
cum/hour
hour
585
P&M-040
hour
83
P&M-041
Ripper
Scarifying
cum/hour
60
hour
18
P&M-042
Rotavator
Scarifying
cum/hour
25
hour
11
P&M-043
Road marking
Sqm/hour
100
hour
60
P&M-044
cum/hour
70/25
hour
269
TPH
200
hour
Rm/hour
80
hour
200
capacity in tonne
hour
1442
P&M-045
cum/hour
30
hour
738
Capacity in cum
5.5
km
24
Capacity in cum
5.5
tonne.km
Capacity in cum
5.5
hour
506
P&M-046
Tipper - 5 cum
P&M-047
Tipper - 5 cum
P&M-048
Tipper - 5 cum
P&M-049
cum/hour
4.5
hour
600
P&M-050
cum/hour
4.5
tonne.km
1.62
P&M-051
cum/hour
hour
550
P&M-052
cum/hour
tonne.km
1.46
P&M-053
Tractor
Pulling
capacity in HP
50
hour
231
P&M-054
hour
242
P&M-055
hour
249
P&M-056
Material Transport
capacity/cum
4.5
km
20
P&M-057
Material Transport
capacity/cum
4.5
hour
506
P&M-058
Material Transport
capacity/cum
4.5
tonne.km
P&M-059
cum/hour
100/60/60
hour
994
P&M-060
Water Tanker
Water Transport
capacity in KL
hour
506
P&M-061
Water Tanker
Water Transport
capacity in KL
km
15.6
P&M-062
Wet Mix
cum/hour
25
hour
777
Sl. No.
Description of Machine
Unit
Rate
P&M-063
Air compressor with pneumatic chisel attachment for cutting hard clay.
hour
206
P&M-064
Batch type cold mixing plant 100-120 TPH capacity producing an average output of 75 tonne per hour
hour
input
P&M-065
hour
input
P&M-066
hour
input
P&M-067
Cement concrete batch mix plant @ 175 cum per hour (effective output)
hour
5160
P&M-068
hour
2760
P&M-070
hour
230
P&M-075
hour
550
P&M-076
hour
500
P&M-078
hour
500
P&M-079
Generator 33 KVA
hour
240
P&M-080
hour
450
P&M-081
hour
1125
P&M-083
hour
300
P&M-085
Piling rig Including double acting pile driving hammer (Hydraulic rig)
hrs
3525
P&M-086
Plate compactor
hour
100
P&M-088
hour
250
P&M-094
P&M-095
hour
16188
1036
Paving of concrete surface
cum / hour
175
(B) Labour
Sl. No.
Description of Labour
Unit
Rate
L-01
day
90
L-02
day
100
L-03
day
100
L-04
Carpenter I Class
day
100
L-05
day
100
L-06
Driller (Jumper)
day
100
L-07
Diver
day
185
L-08
Fitter
day
90
L-09
Mali
day
90
L-10
day
90
L-11
day
100
L-12
Mate / Supervisor
day
80
L-13
Mazdoor
day
70
L-14
day
90
L-15
Mazdoor/Dresser/Sinker (Skilled)
day
100
L-18
Painter I class
day
100
Unit
Rate
(C) Materials
Sl. No.
Description
M-001
cum
289.00
M-003
cum
289.00
M-004
cum
149.00
M-005
cum
149.00
M-006
cum
145.00
M-007
Moorum at Site
cum
140.00
M-008
Cum
289.00
M-009
Cum
140.00
M-012
Cum
609.00
Description
Unit
Rate at Plant
(HMP/Batchi
ng)
Rate at Site
M-013
cum
561.50
561.50
M-014
cum
561.50
561.50
M-015
cum
587.50
587.50
M-016
cum
768.50
768.50
M-017
cum
768.50
768.50
M-018
cum
512.50
512.50
M-019
cum
512.50
512.50
M-020
cum
512.50
512.50
M-021
Stone crusher dust finer than 3mm with not more than 10% passing 0.075 sieve.
cum
395.85
395.85
M-022
cum
395.85
395.85
M-023
cum
input
401.94
M-024
cum
input
401.94
M-025
cum
609.00
609.00
M-026
cum
517.65
517.65
M-027
cum
input
517.65
M-028
cum
input
438.48
M-029
cum
414.12
414.12
M-030
cum
401.94
401.94
M-031
cum
517.65
517.65
M-032
cum
517.65
517.65
M-033
Aggregates 45 mm to 2.8 mm
cum
438.48
438.48
M-034
Aggregates 45 mm to 22.4 mm
cum
438.48
438.48
M-035
Aggregates 53 mm to 2.8 mm
cum
414.12
414.12
M-036
Aggregates 53 mm to 22.4 mm
cum
414.12
414.12
M-037
Aggregates 63 mm to 2.8 mm
cum
408.03
408.03
M-038
Aggregates 63 mm to 45 mm
cum
408.03
408.03
M-039
Aggregates 90 mm to 45 mm
cum
input
395.85
M-040
Aggregates 10 mm to 5 mm
cum
468.93
468.93
M-041
cum
609.00
609.00
M-042
cum
609.00
609.00
M-043
cum
609.00
609.00
M-044
Aggregates 13.2 mm to 10 mm
cum
609.00
609.00
M-045
Aggregates 20 mm to 10 mm
cum
517.65
517.65
M-046
Aggregates 25 mm to 10 mm
cum
517.65
517.65
M-047
Aggregates 19 mm to 6 mm
cum
input
517.65
M-048
Aggregates 37.5 mm to 19 mm
cum
input
438.48
M-049
Aggregates 37.5 mm to 25 mm
cum
438.48
438.48
M-050
cum
468.93
468.93
M-051
cum
609.00
609.00
M-052
cum
609.00
609.00
M-053
cum
517.65
517.65
M-054
cum
517.65
517.65
M-055
cum
438.48
438.48
Description
Sl. No.
Unit
Rate
M-056
metre
60
M-058
Alluminium Paint
litre
204
M-059
sqm
200
M-060
tonne
29902.00
sqm
6000
nos
23000
M-061
M-066
Aluminium sheeting fixed with encapsulated lens type reflective sheeting including 2% towards lettering, cost of angle iron, cost of
drilling holes, nuts, bolts etc.and signs as applicable
Bearing (Elastomeric bearing assembly consisting of 7 internal layers of elastomer bonded to 6 nos. internal reinforcing steel
laminates by the process of vulcanisation,)
M-068
Bearing (Pot type bearing assembly consisting of a metal piston supported by a disc, PTFE pads providing sliding surfaces against
stainless steel mating together with cast steel assemblies/fabricated structural steel assemblies duly painted with all components
nos
120000
M-069
nos
30000
M-071
Bentonite
kg
2.06
M-072
Binding wire
kg
39
M-074
tonne
20528.00
M-075
CRMB-55
tonne
20986.00
M-076
tonne
15245.00
M-077
Bitumen (emulsion-RS1)
tonne
15391.00
M-078
tonne
20986.00
M-079
Brick(23X11X8Cm)
each
1.86
M-080
kg
80
M-081
Cement
tonne
4400.00
M-082
tonne
29902.00
M-083
nos
1000
M-084
sqm
60
M-087
tonne
29902.00
M-089
cum
148
M-090
Curing compound
liter
20
M-091
Delineators from ISI certified firm as per the standard drawing given in IRC - 79
each
600
M-092
cum
10
M-094
Electric Detonators @ 1 detonator for 1/2 gelatin stick of 125 gms each
100 nos
1400
M-095
kg
200
M-097
kg
30
M-101
nos
10
M-103
kg
30.81
M-104
Gelatin 80%
kg
100
M-110
GI bolt 10 mm Dia
nos
1.5
M-111
hour
230
M-118
M-119
HTS strand
M-120
M-123
litre
172
tonne
35000
kg
50
M.S. Clamps
nos
M-124
M.S. Clamps
kg
38
M-126
tonne
29902.00
M-130
kg
49
M-131
Paint
litre
132.24
M-132
litre
132.24
M-137
metre
590.00
M-138
sqm
90
M-141
sqm
80.00
M-142
cum
4000.00
M-144
sqm
60.00
M-145
kg
200
M-147
kg
160
M-148
cum
289.00
M-149
metre
2804.09
M-150
metre
3733.71
metre
676.10
kg
200
M-151
M-152
M-159
nos
5.00
M-163
Selected earth
cum
140.00
M-164
sqm
M-165
Sheathing duct
metre
60
M-167
Sludge / Farm yard manure @ 0.18 cum per 100 sqm at site of work for turfing
cum
50
M-169
cum
289.00
M-173
Steel helmet and cushion block on top of pile head during driving.
M-174
M-175
M-176
M-177
kg
input
M-178
metre
8600
M-179
Structural Steel
tonne
30640.00
M-180
M-181
kg
120
IS:1239
metre
input
IS:1239
metre
600
kg
input
kg
40
Synthetic Geogrids as per clause 3102.8 and approved design and specifications.
sqm
46
M-182
each
100
M-187
Tube anchorage set complete with bearing plate, permanent wedges etc
nos
322
M-188
Unstaked lime
tonne
11000
M-189
Water
KL
10
M-190
litre
29
M-192
kg
52
8%
10%
20%
30 %
Type symble of apostrope(') then input value then one space then
symble of percentage (%) for example '08 %
10%
17
km
5.00
km
input
km
Items No.
Summary of Rates calculated and used for analysis of rates of other items
Unit
Rate
per cm height
per letter
sqm
32.00
Item 8.3
Printing new letter and figures of any shade (ii) English Roman
Item 8.8
Item 8.9
sqm
27.50
cum
3,162.00
cum
2,467.00
cum
1,512.00
Item 12.7 (A )
cum
2,698.80
cum
2,300.00
cum
2,715.70
PCC Grade M15 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer
cum
1,979.00
PCC Grade M20 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer
cum
2,303.00
RCC Grade M20 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer
cum
2,362.50
RCC Grade M20 including OH & CP for Open Foundation by Batching Plant
cum
3,266.60
RCC Grade M20 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by
Batching Plant
cum
2,379.60
PCC Grade M25 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer
cum
2,546.30
PCC Grade M25 including OH & CP for Open Foundation by Batching Plant
cum
3,513.00
PCC Grade M25 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by
Batching Plant
cum
2,565.30
RCC Grade M25 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer
cum
2,608.90
RCC Grade M25 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by
Batching Plant
cum
2,626.00
PCC Grade M30 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer
cum
2,572.70
PCC Grade M30 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by
Batching Plant
cum
2,589.10
RCC Grade M30 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer
cum
2,623.50
RCC Grade M30 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by
Batching Plant
cum
2,641.40
RCC Grade M35 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer
cum
2,691.00
RCC Grade M35 including OH & CP for Open Foundation by Batching Plant
cum
2,859.60
RCC Grade M35 excluding OH & CP for Open Foundation by Batching Plant
cum
3,774.70
RCC Grade M35 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by
Batching Plant
PCC Grade M20 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material &
Mechinery by Mixer
PCC Grade M20 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material &
Mechinery by Batching Plant
PCC Grade M25 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material &
Mechinery by Mixer
PCC Grade M25 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material &
Mechinery by Batching Plant
PCC Grade M30 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material &
Mechinery by Mixer
PCC Grade M30 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material &
Mechinery by Batching Plant
PCC Grade M35 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material &
Mechinery by Mixer
cum
2,776.40
cum
2,559.10
cum
2,529.70
cum
2,696.10
cum
2,665.30
cum
2,722.50
cum
2,693.10
cum
2,784.10
PCC Grade M35 including OH & CP for Well Foundation (Bottom Plug) by Batching Plant
cum
3,798.00
PCC Grade M35 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material &
Mechinery by Batching Plant
cum
2,753.30
PCC Grade M35 including OH & CP for Well Foundation (Well Cap) by Batching Plant
cum
3,682.90
cum
69.60
0.20
cum
Item 14.1(A)
cum
Item 14.1(B)
cum
Item 14.1(E)
cum
Item 14.1(C)
RCC Grade M30 for super-structure including formwork and excluding OH & CP by Batching Plant
cum
Item 14.1(C)
RCC Grade M30 for super-structure excluding formwork and excluding OH & CP by Batching Plant
cum
Item 14.2 A
Supplying ,fitting and placing HYSD bar reinforcement in super-structure exncluding OH & CP
tonne
32,604.30
Item 13.6
tonne
29,902.00
Item 5.17
Fog Seal
sqm
16.70
sqm
27.50
sqm
18.90
sqm
12.10
sqm
41.90
sqm
35.60
22.30
3,726.20
4,134.90
4,383.76
3,170.80
2,642.30
Sr No
Ref. to
MoRTH
Spec.
1.1
Description
Loading and unloading of stone boulder / stone
aggregates / sand / kanker / moorum.
Placing tipper at loading point, loading with front end loader,
dumping, turning for return trip, excluding time for haulage
and return trip
Unit : cum
Taking output = 5.5 cum
Time required for
i) Positioning of tipper at loading point
ii) Loading by front end loader 1 cum bucket capacity @
25 cum per hour
iii) Maneuvering, reversing, dumping and turning for
return
iv) Waiting time, unforeseen contingencies etc
Total
a) Machinery
Tipper 5.5 tonnes capacity
Front end-loader 1 cum bucket capacity @ 25 cum/hour
Note
1.4
Unit
Quantity
Rate Rs
Cost Rs
Remarks/
Input ref.
1 Min
13 Min
2 Min
4 Min
20 Min
hour
hour
0.330
0.330
b) Overheads @ 8% on (a)
c) Contractors profit @ 10% on (a+b)
Cost for 5.5 cum = a+b+c
Rate per cum = (a+b+c)/ 5.5
Unloading will be by tipping.
Cost of Haulage Excluding Loading and Unloading
506.00
520.00
166.98
171.60
P&M-048
P&M-017
27.09
36.57
402.23
73.13
73.10
say
Case I
Surfaced Road
Speed with load : 25 km / hour.
Speed while Returning empty : 35 km / hour.
a) Machinery.
i) Tipper 10 tonne capacity
Time taken for onward haulage with load
Time taken for empty return trip.
b) Overheads @ 8% on (a)
c) Contractors profit @ 10% on (a+b)
cost for 100 t km = a+b+c
Rate per t.km = (a+b+c)/100
hour
hour
0.400
0.290
506.00
506.00
202.40
146.74
27.93
37.71
414.78
4.15
4.10
P&M-048
P&M-048
506.00
506.00
253.00
166.98
33.60
45.36
498.94
4.99
5.00
P&M-048
P&M-048
say
1.4(II)
Case II
hour
hour
0.500
0.330
say
1.4(III)
Case III
hour
hour
1.000
0.670
506.00
506.00
say
1.5
506.00
339.02
67.60
91.26
1003.88
10.04
10.00
P&M-048
P&M-048
b)
Labour
Mate
day
0.060
80.00
4.80
L-12
Mazdoor
day
1.500
70.00
105.00
L-13
cum
1.100 input
#VALUE!
M-002
Material
Supply of quarried stone 150 - 200 mm size
c)
Overheads @ 8% on (a+b)
#VALUE!
d)
#VALUE!
#VALUE!
say
1.6
#VALUE!
day
day
day
0.760
2.000
17.000
80.00
90.00
70.00
60.80
180.00
1190.00
cum
800.000
289.00
231200.00
M-001
Hour
6.000
11760.00
70560.00
P&M-028
Hour
Hour
20.000
20.000
520.00
506.00
10400.00
10120.00
25896.86
34960.77
365340.01
578.46
578.50
P&M-017
P&M-048
say
Note
L-12
L-14
L-13
day
day
day
0.760
2.000
17.000
80.00
90.00
70.00
60.80
180.00
1190.00
cum
800.000
289.00
231200.00
M-001
Hour
6.000
11760.00
70560.00
P&M-028
Hour
Hour
20.000
20.000
520.00
506.00
10400.00
10120.00
25896.86
34960.77
346111.59
464.93
464.90
P&M-017
P&M-048
say
Note
1.8
L-12
L-14
L-13
day
day
day
0.760
2.000
17.000
80.00
90.00
70.00
60.80
180.00
1190.00
L-12
L-14
L-13
cum
800.000
289.00
231200.00
M-001
Hour
6.000
11760.00
70560.00
P&M-028
Hour
Hour
20.000
20.000
520.00
506.00
10400.00
10120.00
25896.86
P&M-017
P&M-048
34960.77
326883.17
435.84
435.80
say
Note
5.9
510
b)
c)
Mate
day
0.440
80.00
35.20
L-12
Mazdoor
day
9.000
70.00
630.00
L-13
Mazdoor skilled
day
2.000
100.00
200.00
L-15
hour
7.200
230.00
1656.00
P&M-031
hour
7.200
206.00
1483.20
P&M-001
hour
6.000
1700.00
10200.00
P&M-025
hour
6.000
506.00
3036.00
P&M-048
hour
6.000
520.00
3120.00
P&M-017
hour
6.000
692.00
4152.00
P&M-004
hour
6.000
269.00
1614.00
P&M-044
tonne
10.800
20528.00
221702.40
M-074
cum
135.000
517.65
69882.75
M-053
Machinery
Material
Bitumen@ 1.20 kg per sqm
25416.92
34312.85
377441.32
41.94
say
41.90
b)
Mate
day
0.440
80.00
35.20
L-12
Mazdoor
day
9.000
70.00
630.00
L-13
Mazdoor skilled
day
2.000
100.00
200.00
L-15
hour
7.200
230.00
1656.00
P&M-031
hour
7.200
206.00
1483.20
P&M-001
hour
6.000
1700.00
10200.00
P&M-025
Machinery
c)
hour
6.000
506.00
3036.00
P&M-048
hour
6.000
520.00
3120.00
P&M-017
hour
6.000
692.00
4152.00
P&M-004
hour
6.000
994.00
5964.00
P&M-059
tonne
9.000
20528.00
184752.00
M-074
cum
90.000
609.00
54810.00
M-052
Material
Bitumen@ 1.00 kg per sqm
21603.07
29164.15
320805.62
35.65
say
Note
5.15
516
Case I
35.60
Unit = sqm
Taking output = 16000 sqm (80 cum)
Taking density of 2.2 tonnes per cum, weight of mix =
264 tonnes
weight of mix = 176 tonnes
a) Labour
b)
Mate
day
0.240
80.00
19.20
L-12
Mazdoor
day
6.000
70.00
420.00
L-13
hour
6.000
230.00
1380.00
P&M-031
Machinery
Mechanical broom
c)
hour
6.000
206.00
1236.00
P&M-001
hour
6.000
650.00
3900.00
P&M-033
hour
6.000
520.00
3120.00
P&M-017
hour
6.000
506.00
3036.00
P&M-048
hour
6.000
802.00
4812.00
P&M-037
hour
2.000
506.00
1012.00
P&M-060
tonne
19.360
15391.00
297969.76
M-077
cum
102.080
149.00
15209.92
M-005
tonne
3.520
11000.00
38720.00
M-188
KL
12.000
10.00
120.00
M-189
Material
Residual Binder @ 11 % of mix 80 x 2.2 x 0.11
Fine aggregate 4.75 mm and below 87 % of total mix,80
x 2.2 x 0.87 = 153.12 tonnes. Taking density1.5,=
153.12/1.5 = 102.08 cum
Filler @ 2 % of total mix = 80 x 2.2 x 0.02
Cost of water
d)
Overheads @ 8% on (a+b+c)
29676.39
e)
40063.13
440694.40
27.54
say
Case II
27.50
3 mm thickness
Unit = sqm
Taking output = 20000 sqm (60 cum)
a) Labour
b)
c)
Mate
day
0.200
80.00
16.00
L-12
Mazdoor
day
5.000
70.00
350.00
L-13
Mechanical broom
hour
6.000
230.00
1380.00
P&M-031
hour
6.000
206.00
1236.00
P&M-001
hour
6.000
650.00
3900.00
P&M-033
hour
6.000
520.00
3120.00
P&M-017
hour
6.000
506.00
3036.00
P&M-048
hour
2.000
506.00
1012.00
P&M-060
tonne
17.160
15391.00
264109.56
M-077
cum
74.800
149.00
11145.20
M-005
tonne
2.640
11000.00
29040.00
M-188
KL
12.000
10.00
120.00
M-189
Machinery
Material
Residual Binder @ 13 % of mix = 60 x 2.2 x 0.13
Fine aggregate 3 mm and below 85 % of total mix, 60x
2.2 x 0.85 = 112.2 tonnes. Taking density 1.5,
Filler @ 2 % of total mix =60x 2.2 x 0.02
Cost of water
d)
Overheads @ 8% on (a+b+c)
e)
25477.18
34394.19
378336.13
18.92
say
Case III
18.90
1.5 mm thickness
Unit = sqm
Taking output = 24000 sqm (36 cum)
a) Labour
b)
c)
Mate
day
0.200
80.00
16.00
L-12
Mazdoor
day
5.000
70.00
350.00
L-13
Mechanical broom
hour
6.000
230.00
1380.00
P&M-031
hour
6.000
206.00
1236.00
P&M-001
hour
6.000
650.00
3900.00
P&M-033
hour
6.000
520.00
3120.00
P&M-017
hour
6.000
506.00
3036.00
P&M-048
hour
2.000
506.00
1012.00
P&M-060
tonne
12.670
15391.00
195003.97
M-077
cum
43.300
395.85
17140.31
M-022
tonne
1.580
11000.00
17380.00
M-188
KL
12.000
10.00
120.00
M-189
Machinery
Material
Residual Binder @ 16 % of mix, 36 x 2.2 x 0.16
Fine aggregate 2.36 mm and below,82 % of total
mix,36x 2.2 x 0.82 = 64.94 tonnes. Taking density 1.5
Filler @ 2 % of total mix = 36x 2.2 x 0.02
Cost of water
d)
Overheads @ 8% on (a+b+c)
e)
19495.54
26318.98
289508.80
12.06
say
5.17
Note
518
Fog Spray
12.10
b)
Mate
day
0.120
80.00
9.60
L-12
Mazdoor
day
3.000
70.00
210.00
L-13
hour
6.000
230.00
1380.00
P&M-031
hour
6.000
206.00
1236.00
P&M-001
tonne
6.000
692.00
4152.00
P&M-004
tonne
7.880
15391.00
121281.08
Machinery
Overheads @ 8% on (a+b+c)
e)
M-077
10261.49
13853.02
152383.19
14.51
say
14.50
c)
Mate
day
0.160
80.00
12.80
L-12
day
4.000
70.00
280.00
L-13
cum
26.250
401.94
10550.93
M-024
tonne
0.790
15391.00
12158.89
M-077
Material
Crushed stone grit 3 mm size @ 3.75 kg per sqm
Bitumenemulsion for precoating grit @ 2 % of grit,39.38
x 0.02
23002.62
2.19
say
5.21
522
Case - I
2.20
Unit = sqm
Taking output = 10500 sqm
a) Labour
b)
c)
Mate
day
0.240
80.00
19.20
L-12
Mazdoor
day
6.000
70.00
420.00
L-13
hour
6.000
230.00
1380.00
P&M-031
hour
6.000
206.00
1236.00
P&M-001
hour
6.000
692.00
4152.00
P&M-004
Machinery
hour
6.000
1700.00
10200.00
P&M-025
hour
6.000
269.00
1614.00
P&M-044
tonne
9.450
20986.00
198317.70
M-078
cum
105.000
468.93
49237.65
M-050
Material
Modified binder
Crushed stone aggregates 5.6 mm size
d)
Overheads @ 8% on (a+b+c)
e)
21326.12
28790.27
316692.94
30.16
say
Case - II
30.00
b)
Mate
day
0.240
80.00
19.20
L-12
Mazdoor
day
6.000
70.00
420.00
L-13
hour
6.000
230.00
1380.00
P&M-031
Machinery
Mechanical broom @ 1250 sqm per hour
c)
hour
6.000
206.00
1236.00
P&M-001
hour
6.000
692.00
4152.00
P&M-004
hour
6.000
1700.00
10200.00
P&M-025
hour
6.000
269.00
1614.00
P&M-044
tonne
11.550
20986.00
242388.30
M-078
cum
105.000
609.00
63945.00
M-051
Material
Modified binder
Crushed stone chipping 11.2 mm size
d)
Overheads @ 8% on (a+b+c)
e)
26028.36
35138.29
386521.15
36.81
say
Case III
37.00
b)
c)
Mate
day
0.240
80.00
19.20
L-12
Mazdoor
day
6.000
70.00
420.00
L-13
Mazdoor skilled
day
2.000
100.00
200.00
L-15
hour
6.000
230.00
1380.00
P&M-031
hour
6.000
206.00
1236.00
P&M-001
hour
6.000
692.00
4152.00
P&M-004
Machinery
hour
6.000
1700.00
10200.00
P&M-025
hour
6.000
269.00
1614.00
P&M-044
tonne
15.750
20986.00
330529.50
M-078
cum
126.000
609.00
76734.00
M-051
Material
Modified binder
Crushed stone aggregates 11.2 mm size
d)
Overheads @ 8% on (a+b+c)
e)
34118.78
46060.35
506663.82
48.25
say
48.00
b)
Mate
day
0.560
80.00
44.80
L-12
Mazdoor
day
12.000
70.00
840.00
L-13
Mazdoor skilled
day
2.000
100.00
200.00
L-15
hour
2.800
230.00
644.00
P&M-031
hour
2.800
206.00
576.80
P&M-001
tonne
2.000
692.00
1384.00
P&M-004
hour
2.000
802.00
1604.00
P&M-037
tonne
3.680
20986.00
77228.48
M-075
#VALUE!
M-108
Machinery
Material
Paving grade bitumen of 80 - 100 penetration @ 1.05 kg
per sqm
Geotextile including 10 % for overlaps
d)
Overheads @ 8% on (a+b+c)
#VALUE!
e)
#VALUE!
#VALUE!
#VALUE!
say
8.3
NOTE
801
#VALUE!
day
0.07
80
5.60
125.00
day
1.25
100
Mazdoor
day
0.50
70
35.00
Litre
0.50
132.24
66.12
b) Material
Paint
c) Overheads @ 8% on (a+b)
18.54
25.03
275.28
0.17
say
8.8
803
0.20
day
0.12
80
9.60
200.00
Painter
day
2.00
100
Mazdoor
day
1.00
70
70.00
Litre
6.00
132.24
793.44
b) Material
Paint conforming to requirement of clause 803.3.
Add for scaffolding @ 1% of labour cost where required
2.80
c) Overheads @ 8% on (a+b)
86.07
116.19
1278.09
31.95
say
8.9
803
32.00
a) Labour
Mate
day
0.03
80
2.40
Painter
day
0.45
100
45.00
Mazdoor
day
0.25
70
17.50
Litre
1.25
132.24
165.30
b) Material
Paint ready mixed approved brand.
Add @ 1% on cost of material for scaffolding
1.65
c) Overheads @ 8% on (a+b)
18.55
25.04
275.44
12.7
(A)
Unit = cum
Taking output = 5 cum
Square Rubble Coursed Rubble Masonry (first sort)
a)
Material
27.54
say
27.50
MT
cum
0.51
1.05
4400.00
149.00
2244.00
156.45
day
day
0.04
0.90
80.00
70.00
3.20
63.00
2467.00
MT
cum
0.67
0.93
4400.00
149.00
2956.80
139.07
day
day
0.04
0.90
80.00
70.00
3.20
63.00
3162.00
MT
cum
0.29
1.20
4400.00
149.00
1267.20
178.80
day
day
0.04
0.90
80.00
70.00
3.20
63.00
1512.00
Stone
Through and bond stone
(35no.x0.24mx0.24mx0.39m = 0.79 cu.m)
Cement mortar 1:3 (Rate as in Item 12.6 A sub-analysis)
Labour
Mate
Mason
Mazdoor
c) Overhead charges @ 20% on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Cost for 5 cum = a+b+c+d
Rate per cum (a+b+c+d)/5
cum
each
5.50
35.00
289.00
100.00
1589.50
3500.00
M-169
M-182
cum
1.50
2467.00
3700.50
Item 12.6
(A)
day
day
day
0.66
7.50
9.00
80.00
100.00
70.00
L-12
L-11
L-13
say
52.80
750.00
630.00
2044.56
1226.74
13494.10
2698.82
2698.80
b)
1405.3
12.7 (Add)
1400
1405.3
Unit = cum
Taking output = 5 cum
B) Random Rubble Masonry
( coursed/uncoursed )
Unit = cum
Taking output = 5 cum
a) Material
Stone
Through and bond stone
(35nos.x0.24mx0.24mx0.39m = 0.79 cu.m)
Cement mortar 1:3 (Rate as in item 13.6 D)
b) Labour
Mate
Mason
Mazdoor
c) Overheads @ 20% on (a+b)
d) Contractors profit @ 0.1 on (a+b+c)
Cost for 5 cum = a+b+c+d
Rate per cum (a+b+c+d)/5
cum
Nos
5.50
35.00
289.00
100.00
1589.50
3500.00
cum
1.55
2467.00
3823.85
day
day
day
0.62
6.00
9.00
80.00
100.00
70.00
say
49.60
600.00
630.00
2038.59
1223.15
13454.69
2690.94
2690.90
cum
Nos
5.50
35.00
289.00
100.00
1589.50
3500.00
cum
1.55
1512.00
2343.60
day
day
day
0.62
6.00
9.00
80.00
100.00
70.00
49.60
600.00
630.00
1742.54
1045.52
11500.76
2300.15
2300.00
say
@
12.8
MT
cum
cum
cum
cum
4.13
6.75
8.10
4.05
1.35
4400.00
149.00
438.48
517.65
609.00
18172.00
1005.75
3551.69
2096.48
822.15
day
day
day
0.86
1.50
20.00
80.00
100.00
70.00
68.80
150.00
1400.00
hour
hour
6.00
6.00
1,979.00
161.00
240.00
966.00
1440.00
1186.91
say
6171.96
3703.17
40734.92
2715.66
2715.70
Note
12.8
12.8
MT
cum
cum
cum
cum
5.16
6.75
5.40
5.40
2.70
4400.00
149.00
438.48
517.65
609.00
22704.00
1005.75
2367.79
2795.31
1644.30
day
day
day
0.86
1.50
20.00
80.00
100.00
70.00
68.80
150.00
1400.00
hour
hour
6.00
6.00
2,303.00
161.00
240.00
966.00
1440.00
MT
cum
cum
cum
5.21
6.75
8.10
5.40
4400.00
149.00
517.65
609.00
22924.00
1005.75
4192.97
3288.60
day
day
day
0.86
1.50
20.00
80.00
100.00
70.00
68.80
150.00
1400.00
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum)
Generator 33 KVA
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c)
Case II With Batching Plant, Transit Mixer and Conrete Pump
Unit : cum
Taking Output = 120 cum
a) Material
Cement
Coarse Sand
20 mm Aggregate
10 mm Aggregate
b) Labour
Mate
Mason
Mazdoor
c) Machinery
Batching Plant @ 20 cum/hour
Generator 100 KVA
Loader 1 cum capacity
Transit Mixer 4 cum capacity for lead upto 1 km.
Lead beyond 1 km, L-lead in km
Concrete Pump
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c)
d) Formwork @ 4% on cost of concrete i.e.cost of material,
labour and machinery
e) Overheads @ 20% on (a+b+c+d)
f) Contractors profit @ 0.1 on (a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f
Rate per cum = ( a+b+c+d+e+f )/120
12.8
hour
hour
6.00
6.00
2,362.50
161.00
240.00
966.00
1440.00
MT
cum
cum
cum
41.66
54.00
64.80
43.20
4400.00
149.00
517.65
609.00
183304.00
8046.00
33543.72
26308.80
day
day
day
0.84
3.00
18.00
80.00
100.00
70.00
67.20
300.00
1260.00
hour
hour
hour
hour
T-km
hour
6.00
6.00
6.00
15.00
300L
6
2,379.60
1440.00
450.00
520.00
600.00
1.62
165.00
8640.00
2700.00
3120.00
9000.00
8262.00 L= 17
990.00
11421.67
say
59392.68
35635.61
391991.67
3266.60
3266.60
Unit : cum
Taking Output = 120 cum
a) Material
Cement
Coarse sand
40 mm Aggregate
20 mm Aggregate
10 mm Aggregate
b) Labour
MT
cum
cum
cum
cum
5.99
6.75
5.40
5.40
2.70
4400.00
149.00
438.48
517.65
609.00
26356.00
1005.75
2367.79
2795.31
1644.30
day
day
day
0.86
1.50
20.00
80.00
100.00
70.00
68.80
150.00
1400.00
hour
hour
6.00
6.00
2,546.30
161.00
240.00
966.00
1440.00
MT
cum
cum
cum
cum
47.95
54.00
43.20
43.20
21.60
4400.00
149.00
438.48
517.65
609.00
210980.00
8046.00
18942.34
22362.48
13154.40
Mate
Mason
Mazdoor
c) Machinery
Batching Plant @ 20 cum/hour
Generator 100 KVA
Loader 1 cum capacity
Transit Mixer 4 cum capacity for lead upto 1 km.
Transit Mixer 4 cum capacity lead beyond
1 Km, L - lead in Kilometer
Concrete Pump
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c)
d) Formwork @ 3.75% of cost of concrete i.e.cost of material,
labour and machinery
e) Overheads @ 20% on (a+b+c+d)
f) Contractors profit @ 0.1 on (a+b+c+d+e)
cost of 120 cum = a+b+c+d+e+f
Rate per cum (a+b+c+d+e+f)/120
12.8
12.8
day
day
day
0.84
3.00
18.00
80.00
100.00
70.00
hour
hour
hour
hour
T-Km
6.00
6.00
6.00
15.00
300L
1440.00
450.00
520.00
600.00
1.62
hour
6
2,565.30
165.00
67.20
300.00
1260.00
8640.00
2700.00
3120.00
9000.00
8262.00 L= 17
990.00
11543.42
say
63873.57
38324.14
421565.54
3513.05
3513.00
Unit : cum
Taking Output = 120 cum
a) Material
Cement
Coarse sand
20 mm Aggregate
10 mm Aggregate
Admixer
b) Labour
Mate
Mason
Mazdoor
c) Machinery
Batching Plant @ 20 cum/hour
Generator 100 KVA
Loader 1 cum capacity 1 cum
Transit Mixer 4 cum capacity for lead upto 1 km.
Transit Mixer 4 cum capacity lead beyond
1 Km, L - lead in Kilometer
Concrete Pump
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c)
F
PCC Grade M30
Unit = cum
MT
cum
cum
cum
6.05
6.75
8.10
5.40
4400.00
149.00
517.65
609.00
26620.00
1005.75
4192.97
3288.60
day
day
day
0.86
1.50
20.00
80.00
100.00
70.00
68.80
150.00
1400.00
hour
hour
6.00
6.00
2,608.90
161.00
240.00
966.00
1440.00
MT
cum
cum
cum
Kg
48.38
54.00
64.80
43.20
193.52
4400.00
149.00
517.65
609.00
40.00
212872.00
8046.00
33543.72
26308.80
0.00
day
day
day
0.84
3.00
18.00
80.00
100.00
70.00
67.20
300.00
1260.00
hour
hour
hour
hour
T-Km
6.00
6.00
6.00
15.00
300L
1440.00
450.00
520.00
600.00
1.62
hour
6.00
2,626.00
165.00
8640.00
2700.00
3120.00
9000.00
8262.00 L= 17
990.00
Case I
12.8
Unit : cum
Taking Output = 120 cum
a) Material
Cement
Coarse sand
40 mm Aggregate
20 mm Aggregate
10 mm Aggregate
b) Labour
Mate
Mason
Mazdoor
c) Machinery
Batching Plant @ 20 cum/hour
Generator 100 KVA
Loader 1 cum capacity
Transit Mixer 4 cum capacity for lead upto 1 km.
Transit Mixer 4 cum capacity lead beyond
1 Km, L - lead in Kilometer
Concrete Pump
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c)
G
RCC Grade M30
Case I Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement
Coarse sand
20 mm Aggregate
10 mm Aggregate
b) Labour
Mate
Mason
Mazdoor
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum)
Generator 33 KVA
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c)
Case II Using Batching Plant, Transit Mixer and Conrete Pump
Unit = cum
Taking output = 120 cum
a) Material
MT
cum
cum
cum
cum
6.08
6.75
5.40
5.40
2.70
4400.00
149.00
438.48
517.65
609.00
26752.00
1005.75
2367.79
2795.31
1644.30
day
day
day
0.86
1.50
20.00
80.00
100.00
70.00
68.80
150.00
1400.00
hour
hour
6.00
6.00
2,572.70
161.00
240.00
966.00
1440.00
MT
cum
cum
cum
cum
48.60
54.00
43.20
43.20
21.60
4400.00
149.00
438.48
517.65
609.00
213840.00
8046.00
18942.34
22362.48
13154.40
day
day
day
0.84
3.00
18.00
80.00
100.00
70.00
67.20
300.00
1260.00
hour
hour
hour
hour
T-Km
6.00
6.00
6.00
15.00
300L
1440.00
450.00
520.00
600.00
1.62
hour
6.00
2,589.10
165.00
990.00
MT
cum
cum
cum
6.10
6.75
8.10
5.40
4400.00
149.00
517.65
609.00
26840.00
1005.75
4192.97
3288.60
day
day
day
0.86
1.50
20.00
80.00
100.00
70.00
68.80
150.00
1400.00
hour
hour
6.00
6.00
2,623.50
161.00
240.00
966.00
1440.00
8640.00
2700.00
3120.00
9000.00
8262.00 L= 17
12.8
Cement
Coarse sand
20 mm Aggregate
10 mm Aggregate
b) Labour
Mate
Mason
Mazdoor
c) Machinery
Batching Plant @ 20 cum/hour
Generator 100 KVA
Loader 1 cum capacity
Transit Mixer 4 cum capacity for lead upto 1 km.
Transit Mixer 4 cum capacity lead beyond
1 Km, L - lead in Kilometer
Concrete Pump
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c)
H
RCC Grade M35
Case I Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement
Coarse sand
20 mm Aggregate
10 mm Aggregate
b) Labour
Mate
Mason
Mazdoor
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum)
Generator 33 KVA
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c)
Case II Using Batching Plant, Transit Mixer and Conrete Pump
Unit ; cum
Taking Output = 120 cum
a) Material
Cement
Coarse sand
20 mm Aggregate
10 mm Aggregate
Admixer
b) Labour
Mate
Mason
Mazdoor
c) Machinery
Batching Plant @ 20 cum/hour
Generator 100 KVA
Loader 1 cum capacity
Transit Mixer 4 cum capacity for lead upto 1 km.
Transit Mixer 4 cum capacity lead beyond
1 Km, L - lead in Kilometer
Concrete Pump
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c)
d) Formwork @ 3% on cost of concrete i.e.cost of material,
labour and machinery
e) Overheads @ 20% on (a+b+c+d)
f) Contractors profit @ 0.1 on (a+b+c+d+e)
MT
cum
cum
cum
48.80
54.00
64.80
43.20
4400.00
149.00
517.65
609.00
214720.00
8046.00
33543.72
26308.80
day
day
day
0.84
3.00
18.00
80.00
100.00
70.00
67.20
300.00
1260.00
hour
hour
hour
hour
T-Km
6.00
6.00
6.00
15.00
300L
1440.00
450.00
520.00
600.00
1.62
hour
6.00
2,641.40
165.00
990.00
MT
cum
cum
cum
6.33
6.75
8.10
5.40
4400.00
149.00
517.65
609.00
27852.00
1005.75
4192.97
3288.60
day
day
day
0.86
1.50
20.00
80.00
100.00
70.00
68.80
150.00
1400.00
hour
hour
6.00
6.00
2,691.00
161.00
240.00
966.00
1440.00
MT
cum
cum
cum
Kg
50.64
54.00
64.80
43.20
202.56
4400.00
149.00
517.65
609.00
40.00
222816.00
8046.00
33543.72
26308.80
8102.40
day
day
day
0.84
3.00
18.00
80.00
100.00
70.00
67.20
300.00
1260.00
hour
hour
hour
hour
T-Km
6.00
6.00
6.00
15.00
300L
1440.00
450.00
520.00
600.00
1.62
hour
6.00
2,776.40
165.00
8640.00
2700.00
3120.00
9000.00
8262.00 L= 17
8640.00
2700.00
3120.00
9000.00
8262.00 L= 17
990.00
9994.68
68630.16
41178.10
12.11
452959.06
3774.66
3774.70
2859.60
C
Case I
(i)
Bottom Plug
Concrete to be placed using tremie pipe
Using Concrete Mixer
PCC Grade M20
Unit = cum
Taking output = 15 cum
a) Material
Cement
Coarse sand
40 mm Aggregate
20 mm Aggregate
10 mm Aggregate
Admixer
b) Labour
Mate
Mason
Mazdoor
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum)
Generator 33 KVA
Light Crane 3 tonnes capacity for handling tremie pipe
MT
cum
cum
cum
cum
Kg
5.55
6.75
5.40
5.40
2.70
18.60
4400.00
149.00
438.48
517.65
609.00
40.00
24420.00
1005.75
2367.79
2795.31
1644.30
744.00
day
day
day
0.90
1.50
20.00
80.00
100.00
70.00
72.00
150.00
1400.00
hour
hour
hour
6.00
6.00
6.00
161.00
240.00
230.00
966.00
1440.00
1380.00
2559.10
MT
cum
cum
cum
Kg
44.40
54.00
64.80
43.20
148.80
4400.00
149.00
517.65
609.00
40.00
195360.00
8046.00
33543.72
26308.80
5952.00
day
day
day
0.88
3.00
18.00
80.00
100.00
70.00
70.40
300.00
1260.00
hour
hour
hour
hour
T-Km
6.00
6.00
6.00
15.00
300L
1440.00
450.00
520.00
600.00
1.62
hour
6.00
2529.70
165.00
8640.00
2700.00
3120.00
9000.00
8262.00 L= 17
990.00
(ii)
Case I
MT
cum
cum
cum
cum
Kg
5.99
6.75
5.40
5.40
2.70
21.60
4400.00
149.00
438.48
517.65
609.00
40.00
26356.00
1005.75
2367.79
2795.31
1644.30
864.00
day
day
day
0.90
1.50
20.00
80.00
100.00
70.00
72.00
150.00
1400.00
hour
hour
hour
6.00
6.00
6.00
161.00
240.00
230.00
966.00
1440.00
1380.00
2696.10
MT
cum
cum
cum
Kg
47.88
54.00
64.80
43.20
172.80
4400.00
149.00
517.65
609.00
40.00
210672.00
8046.00
33543.72
26308.80
6912.00
day
day
day
0.88
3.00
18.00
80.00
100.00
70.00
70.40
300.00
1260.00
hour
hour
hour
hour
T-Km
6.00
6.00
6.00
15.00
300L
1440.00
450.00
520.00
600.00
1.62
hour
6.00
2665.30
165.00
990.00
MT
cum
cum
cum
cum
Kg
6.08
6.75
5.40
5.40
2.70
21.60
4400.00
149.00
438.48
517.65
609.00
40.00
26752.00
1005.75
2367.79
2795.31
1644.30
864.00
day
day
0.90
1.50
80.00
100.00
72.00
150.00
8640.00
2700.00
3120.00
9000.00
8262.00 L= 17
Mazdoor
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum)
Generator 33 KVA
Light Crane of 3 tonnes capacity for handling tremie pipe
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c)
Case II Using Batching Plant, Transit Mixer and Crane/concrete
pump
Unit = cum
Taking output = 120 cum
a) Material
Cement
Coarse sand
20 mm Aggregate
10 mm Aggregate
Admixer
b) Labour
Mate
Mason
Mazdoor
c) Machinery
Batching Plant @ 20 cum/hour
Generator 100 KVA
Loader 1 cum capacity
Transit Mixer 4 cum capacity for lead upto 1 km.
Transit Mixer 4 cum capacity, lead beyond 1 Km, L lead in Kilometer
Concrete Pump
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c)
(iv)
PCC Grade M35
Case I
day
20.00
70.00
1400.00
hour
hour
hour
6.00
6.00
6.00
161.00
240.00
230.00
966.00
1440.00
1380.00
2722.50
MT
cum
cum
cum
Kg
48.64
54.00
64.80
43.20
172.80
4400.00
149.00
517.65
609.00
40.00
214016.00
8046.00
33543.72
26308.80
6912.00
day
day
day
0.88
3.00
18.00
80.00
100.00
70.00
70.40
300.00
1260.00
hour
hour
hour
hour
T-Km
6.00
6.00
6.00
15.00
300L
1440.00
450.00
520.00
600.00
1.62
hour
6.00
2693.10
165.00
990.00
MT
cum
cum
cum
cum
Kg
6.29
6.75
5.40
5.40
2.70
21.60
4400.00
149.00
438.48
517.65
609.00
40.00
27676.00
1005.75
2367.79
2795.31
1644.30
864.00
day
day
day
0.90
1.50
20.00
80.00
100.00
70.00
72.00
150.00
1400.00
hour
hour
hour
6.00
6.00
6.00
161.00
240.00
230.00
966.00
1440.00
1380.00
4400.00
149.00
517.65
609.00
221232.00
8046.00
33543.72
26308.80
8640.00
2700.00
3120.00
9000.00
8262.00 L= 17
2784.10
MT
cum
cum
cum
50.28
54.00
64.80
43.20
Admixer
b) Labour
Mate
Mason
Mazdoor
c) Machinery
Batching Plant @ 20 cum/hour
Generator 100 KVA
Loader 1 cum capacity
Transit Mixer 4 cum capacity for lead upto 1 km.
Transit Mixer 4 cum capacity, lead beyond 1 Km, L lead in Kilometer
Concrete Pump
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c)
Add 5% of cost of material and labour towards cost of
forming sump, protective bunds, chiselling and making
arrangements for under water concreteing with tremie pipe..
Kg
172.80
40.00
6912.00
day
day
day
0.88
3.00
18.00
80.00
100.00
70.00
70.40
300.00
1260.00
hour
hour
hour
hour
T-Km
6.00
6.00
6.00
15.00
300L
1440.00
450.00
520.00
600.00
1.62
hour
6.00
2753.30
165.00
Say
69053.71
41432.23
455754.51
3797.95
3798.00
Well cap
RCC Grade M35
Using Batching Plant, Transit Mixer and Conrete Pump
Unit = cum
Taking output = 120 cum
a) Material
Cement
Coarse sand
20 mm Aggregate
10 mm Aggregate
b) Labour
Mate
Mason
Mazdoor
c) Machinery
Batching Plant @ 20 cum/hour
Generator 100 KVA
Loader(capacity 1 cum)
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity for lead upto 1 km.
Lead beyond 1 Km, L - lead in Kilometer
Concrete Pump
Formwork @ 3% of (a+b+c)
d) Overheads @ 20% on (a+b+c)
e) Contractors profit @ 0.1 on (a+b+c+d)
cost of 120 cum = a+b+c+d+e
Rate per cum (a+b+c+d+e)/120
MT
cum
cum
cum
50.64
54.00
64.80
43.20
4400.00
149.00
517.65
609.00
222816.00
8046.00
33543.72
26308.80
day
day
day
0.84
3.00
18.00
80.00
100.00
70.00
67.20
300.00
1260.00
hour
hour
hour
6.00
6.00
6.00
1440.00
450.00
520.00
8640.00
2700.00
3120.00
hour
T-Km
hour
15.00
300L
6.00
600.00
1.62
165.00
Say
3.13
990.00
14883.65
8640.00
2700.00
3120.00
9000.00
8262.00 L= 17
Note
304
9000.00
8262.00 L= 17
990.00
9751.61
66961.07
40176.64
441943.04
3682.86
3682.90
Manual Means
(i) Depth upto 3 m
a) Labour
Mate
day
0.320
80.00
25.60
L-12
Mazdoor
day
8.000
70.00
560.00
L-13
b) Overheads @ 8% on (a)
46.85
63.24
695.69
69.57
say
Note
69.60
day
0.32
80
25.60
Mazdoor
day
8.00
70
560.00
hour
6.00
840
5040.00
b) Machinery
Hydraulic excavator 1.0 cum bucket capacity
c) Overheads @ 8% on (a+b)
450.05
607.56
6683.21
13.6
22.28
say
22.30
MT
kg
1.05
6.00
29902.00
39.00
31397.10
234.00
day
day
day
0.34
2.00
6.50
80.00
100.00
70.00
27.20
200.00
455.00
6462.66
1500
&1600
1700
A
Case II
Unit = cum
Taking output = 120 cum
a) Material
Cement
Coarse sand
20 mm Aggregate
10 mm Aggregate
b) Labour
Mate
Mason
Mazdoor
c) Machinery
Batching Plant @ 20 cum/hour
Generator 100 KVA
Loader
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto 1 Km
Lead beyond 1 Km, L - lead in Kilometer
Concrete Pump
Basic Cost of Labour, Material & Mechinery (a+b+c) for 120 cum
(i)
(p)
B
Case II
say
3877.60
42653.56
42653.60
MT
cum
cum
cum
40.92
54.00
64.80
43.20
4400.00
149.00
517.65
609.00
180048.00
8046.00
33543.72
26308.80
day
day
day
0.84
3.00
18.00
80.00
100.00
70.00
67.20
300.00
1260.00
hour
hour
hour
6.00
6.00
6.00
1440.00
450.00
520.00
8640.00
2700.00
3120.00
hour
T-Km
hour
15.00
300L
6.00
282285.80
600.00
1.62
165.00
9000.00
8262.00 L= 17
990.00
282285.80
20.00
say
56457.16
67748.59
40649.16
447140.71
3726.17
3726.20
MT
cum
cum
cum
47.95
54.20
64.80
43.20
4400.00
149.00
517.65
609.00
210980.00
8075.80
33543.72
26308.80
day
day
day
0.84
3.00
18.00
80.00
100.00
70.00
67.20
300.00
1260.00
hour
hour
hour
6.00
6.00
6.00
1440.00
450.00
520.00
8640.00
2700.00
3120.00
hour
15.00
600.00
9000.00
(p)
Height upto 5m
Basic Cost of Labour, Material & Mechinery (a+b+c)
120 cum
d) Formwork and staging 20 % of (a+b+c)
e)
f)
T-Km
hour
300L
6.00
313247.60
1.62
165.00
for
313247.60
20.00
62649.52
75179.42
45107.65
496184.20
C
Case II
4134.87
say
4134.90
RCC Grade M 30
Using Batching Plant, Transit Mixer and Concrete Pump.
Unit = cum
Taking output = 120 cum
a) Material
Cement
Coarse sand
20 mm Aggregate
10 mm Aggregate
b) Labour
Mate
Mason
Mazdoor
c) Machinery
Batching Plant @ 20 cum/hour
Generator 100 KVA
Loader
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto 1 Km
Lead beyond 1 Km, L - lead in Kilometer
Concrete Pump
Basic Cost of Labour, Material & Mechinery (a+b+c) for 120 cum
For formwork and staging add the following:
(i)
(p)
MT
cum
cum
cum
48.79
54.60
64.80
43.20
4400.00
149.00
517.65
609.00
214676.00
8135.40
33543.72
26308.80
day
day
day
0.88
3.00
19.00
80.00
100.00
70.00
70.40
300.00
1330.00
hour
hour
hour
6.00
6.00
6.00
1440.00
450.00
520.00
8640.00
2700.00
3120.00
hour
T-Km
hour
15.00
300L
6.00
317076.40
600.00
1.62
165.00
9000.00
8262.00 L= 17
990.00
317076.40
20.00
say
Rate per cum (a+b+c+d)/120 ( including formwork and excluding OH & CP)
Rate per cum (a+b+c+d)/120 ( excluding formwork and Excluding OH & CP)
E
Case 1
8262.00 L= 17
990.00
63415.28
76098.34
45659.00
502249.02
4185.41
4185.40
3170.80
2642.30
MT
cum
cum
cum
kg
6.45
6.75
8.10
5.40
25.80
4400.00
149.00
517.65
609.00
40.00
28380.00
1005.75
4192.97
3288.60
1032.00
day
day
day
0.96
2.00
22.00
80.00
100.00
70.00
76.80
200.00
1540.00
hour
hour
6.00
6.00
42122.20
161.00
240.00
966.00
1440.00
MT
cum
cum
cum
kg
51.60
54.00
64.80
43.20
206.40
4400.00
149.00
517.65
609.00
40.00
227040.00
8046.00
33543.72
26308.80
8256.00
day
day
day
0.94
3.50
20.00
80.00
100.00
70.00
75.20
350.00
1400.00
hour
hour
hour
6.00
6.00
6.00
1440.00
450.00
520.00
8640.00
2700.00
3120.00
hour
T-Km
hour
15.00
300L
6.00
337731.80
600.00
1.62
165.00
Unit = cum
Taking output = 120 cum
a) Material
Cement
Coarse sand
20 mm Aggregate
10 mm Aggregate
Admixture @ 0.4% of cement
b) Labour
Mate
Mason
Mazdoor
c) Machinery
Batching Plant @ 20 cum/hour
Generator 100 KVA
Loader
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto 1 Km
Lead beyond 1 Km, L - lead in Kilometer
Concrete Pump
Basic Cost of Labour, Material & Mechinery (a+b+c) for 120 cum
For formwork and staging add the following:
(i)
(p)
Height upto 5m
Basic Cost of Labour, Material & Mechinery (a+b+c)
120 cum
d) Formwork and staging 18 % of (a+b+c)
for
337731.80
18.00
60791.72
e)
79704.70
f)
47822.82
526051.05
4383.76
say
Note
9000.00
8262.00 L= 17
990.00
4383.80
14.2
1600
Mate
Blacksmith
Mazdoor
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c)
MT
Kg
1.05
8.00
29902.00
39.00
31397.10
312.00
day
day
day
0.44
3.00
8.00
32604.30
80.00
100.00
70.00
35.20
300.00
560.00
Sr No
Ref. to
MoRTH
Spec.
1.1
Description
Loading and unloading of stone boulder / stone
aggregates / sand / kanker / moorum.
Placing tipper at loading point, loading with front end loader,
dumping, turning for return trip, excluding time for haulage
and return trip
Unit : cum
Taking output = 5.5 cum
Time required for
i) Positioning of tipper at loading point
ii) Loading by front end loader 1 cum bucket capacity @
25 cum per hour
iii) Maneuvering, reversing, dumping and turning for
return
iv) Waiting time, unforeseen contingencies etc
Total
a) Machinery
Tipper 5.5 tonnes capacity
Front end-loader 1 cum bucket capacity @ 25 cum/hour
Note
1.4
Unit
Quantity
Rate Rs
Cost Rs
Remarks/
Input ref.
1 Min
13 Min
2 Min
4 Min
20 Min
hour
hour
0.330
0.330
b) Overheads @ 8% on (a)
c) Contractors profit @ 10% on (a+b)
Cost for 5.5 cum = a+b+c
Rate per cum = (a+b+c)/ 5.5
Unloading will be by tipping.
Cost of Haulage Excluding Loading and Unloading
506.00
520.00
166.98
171.60
P&M-048
P&M-017
27.09
36.57
402.23
73.13
73.10
say
Case I
Surfaced Road
Speed with load : 25 km / hour.
Speed while Returning empty : 35 km / hour.
a) Machinery.
i) Tipper 10 tonne capacity
Time taken for onward haulage with load
Time taken for empty return trip.
b) Overheads @ 8% on (a)
c) Contractors profit @ 10% on (a+b)
cost for 100 t km = a+b+c
Rate per t.km = (a+b+c)/100
hour
hour
0.400
0.290
506.00
506.00
202.40
146.74
27.93
37.71
414.78
4.15
4.10
P&M-048
P&M-048
506.00
506.00
253.00
166.98
33.60
45.36
498.94
4.99
5.00
P&M-048
P&M-048
say
1.4(II)
Case II
hour
hour
0.500
0.330
say
1.4(III)
Case III
hour
hour
1.000
0.670
506.00
506.00
say
1.5
506.00
339.02
67.60
91.26
1003.88
10.04
10.00
P&M-048
P&M-048
b)
Labour
Mate
day
0.060
80.00
4.80
L-12
Mazdoor
day
1.500
70.00
105.00
L-13
cum
1.100 input
#VALUE!
M-002
Material
Supply of quarried stone 150 - 200 mm size
c)
Overheads @ 8% on (a+b)
#VALUE!
d)
#VALUE!
#VALUE!
say
1.6
#VALUE!
day
day
day
0.760
2.000
17.000
80.00
90.00
70.00
60.80
180.00
1190.00
cum
800.000
289.00
231200.00
M-001
Hour
6.000
11760.00
70560.00
P&M-028
Hour
Hour
20.000
20.000
520.00
506.00
10400.00
10120.00
25896.86
34960.77
365340.01
578.46
578.50
P&M-017
P&M-048
say
Note
L-12
L-14
L-13
day
day
day
0.760
2.000
17.000
80.00
90.00
70.00
60.80
180.00
1190.00
cum
800.000
289.00
231200.00
M-001
Hour
6.000
11760.00
70560.00
P&M-028
Hour
Hour
20.000
20.000
520.00
506.00
10400.00
10120.00
25896.86
34960.77
346111.59
464.93
464.90
P&M-017
P&M-048
say
Note
1.8
L-12
L-14
L-13
day
day
day
0.760
2.000
17.000
80.00
90.00
70.00
60.80
180.00
1190.00
L-12
L-14
L-13
cum
800.000
289.00
231200.00
M-001
Hour
6.000
11760.00
70560.00
P&M-028
Hour
Hour
20.000
20.000
520.00
506.00
10400.00
10120.00
25896.86
P&M-017
P&M-048
34960.77
326883.17
435.84
435.80
say
Note
5.9
510
b)
c)
Mate
day
0.440
80.00
35.20
L-12
Mazdoor
day
9.000
70.00
630.00
L-13
Mazdoor skilled
day
2.000
100.00
200.00
L-15
hour
7.200
230.00
1656.00
P&M-031
hour
7.200
206.00
1483.20
P&M-001
hour
6.000
1700.00
10200.00
P&M-025
hour
6.000
506.00
3036.00
P&M-048
hour
6.000
520.00
3120.00
P&M-017
hour
6.000
692.00
4152.00
P&M-004
hour
6.000
269.00
1614.00
P&M-044
tonne
10.800
20528.00
221702.40
M-074
cum
135.000
517.65
69882.75
M-053
Machinery
Material
Bitumen@ 1.20 kg per sqm
25416.92
34312.85
377441.32
41.94
say
41.90
b)
Mate
day
0.440
80.00
35.20
L-12
Mazdoor
day
9.000
70.00
630.00
L-13
Mazdoor skilled
day
2.000
100.00
200.00
L-15
hour
7.200
230.00
1656.00
P&M-031
hour
7.200
206.00
1483.20
P&M-001
hour
6.000
1700.00
10200.00
P&M-025
Machinery
c)
hour
6.000
506.00
3036.00
P&M-048
hour
6.000
520.00
3120.00
P&M-017
hour
6.000
692.00
4152.00
P&M-004
hour
6.000
994.00
5964.00
P&M-059
tonne
9.000
20528.00
184752.00
M-074
cum
90.000
609.00
54810.00
M-052
Material
Bitumen@ 1.00 kg per sqm
21603.07
29164.15
320805.62
35.65
say
Note
5.15
516
Case I
35.60
Unit = sqm
Taking output = 16000 sqm (80 cum)
Taking density of 2.2 tonnes per cum, weight of mix =
264 tonnes
weight of mix = 176 tonnes
a) Labour
b)
Mate
day
0.240
80.00
19.20
L-12
Mazdoor
day
6.000
70.00
420.00
L-13
hour
6.000
230.00
1380.00
P&M-031
Machinery
Mechanical broom
c)
hour
6.000
206.00
1236.00
P&M-001
hour
6.000
650.00
3900.00
P&M-033
hour
6.000
520.00
3120.00
P&M-017
hour
6.000
506.00
3036.00
P&M-048
hour
6.000
802.00
4812.00
P&M-037
hour
2.000
506.00
1012.00
P&M-060
tonne
19.360
15391.00
297969.76
M-077
cum
102.080
149.00
15209.92
M-005
tonne
3.520
11000.00
38720.00
M-188
KL
12.000
10.00
120.00
M-189
Material
Residual Binder @ 11 % of mix 80 x 2.2 x 0.11
Fine aggregate 4.75 mm and below 87 % of total mix,80
x 2.2 x 0.87 = 153.12 tonnes. Taking density1.5,=
153.12/1.5 = 102.08 cum
Filler @ 2 % of total mix = 80 x 2.2 x 0.02
Cost of water
d)
Overheads @ 8% on (a+b+c)
29676.39
e)
40063.13
440694.40
27.54
say
Case II
27.50
3 mm thickness
Unit = sqm
Taking output = 20000 sqm (60 cum)
a) Labour
b)
c)
Mate
day
0.200
80.00
16.00
L-12
Mazdoor
day
5.000
70.00
350.00
L-13
Mechanical broom
hour
6.000
230.00
1380.00
P&M-031
hour
6.000
206.00
1236.00
P&M-001
hour
6.000
650.00
3900.00
P&M-033
hour
6.000
520.00
3120.00
P&M-017
hour
6.000
506.00
3036.00
P&M-048
hour
2.000
506.00
1012.00
P&M-060
tonne
17.160
15391.00
264109.56
M-077
cum
74.800
149.00
11145.20
M-005
tonne
2.640
11000.00
29040.00
M-188
KL
12.000
10.00
120.00
M-189
Machinery
Material
Residual Binder @ 13 % of mix = 60 x 2.2 x 0.13
Fine aggregate 3 mm and below 85 % of total mix, 60x
2.2 x 0.85 = 112.2 tonnes. Taking density 1.5,
Filler @ 2 % of total mix =60x 2.2 x 0.02
Cost of water
d)
Overheads @ 8% on (a+b+c)
e)
25477.18
34394.19
378336.13
18.92
say
Case III
18.90
1.5 mm thickness
Unit = sqm
Taking output = 24000 sqm (36 cum)
a) Labour
b)
c)
Mate
day
0.200
80.00
16.00
L-12
Mazdoor
day
5.000
70.00
350.00
L-13
Mechanical broom
hour
6.000
230.00
1380.00
P&M-031
hour
6.000
206.00
1236.00
P&M-001
hour
6.000
650.00
3900.00
P&M-033
hour
6.000
520.00
3120.00
P&M-017
hour
6.000
506.00
3036.00
P&M-048
hour
2.000
506.00
1012.00
P&M-060
tonne
12.670
15391.00
195003.97
M-077
cum
43.300
395.85
17140.31
M-022
tonne
1.580
11000.00
17380.00
M-188
KL
12.000
10.00
120.00
M-189
Machinery
Material
Residual Binder @ 16 % of mix, 36 x 2.2 x 0.16
Fine aggregate 2.36 mm and below,82 % of total
mix,36x 2.2 x 0.82 = 64.94 tonnes. Taking density 1.5
Filler @ 2 % of total mix = 36x 2.2 x 0.02
Cost of water
d)
Overheads @ 8% on (a+b+c)
e)
19495.54
26318.98
289508.80
12.06
say
5.17
Note
518
Fog Spray
12.10
b)
Mate
day
0.120
80.00
9.60
L-12
Mazdoor
day
3.000
70.00
210.00
L-13
hour
6.000
230.00
1380.00
P&M-031
hour
6.000
206.00
1236.00
P&M-001
tonne
6.000
692.00
4152.00
P&M-004
tonne
7.880
15391.00
121281.08
Machinery
Overheads @ 8% on (a+b+c)
e)
M-077
10261.49
13853.02
152383.19
14.51
say
14.50
c)
Mate
day
0.160
80.00
12.80
L-12
day
4.000
70.00
280.00
L-13
cum
26.250
401.94
10550.93
M-024
tonne
0.790
15391.00
12158.89
M-077
Material
Crushed stone grit 3 mm size @ 3.75 kg per sqm
Bitumenemulsion for precoating grit @ 2 % of grit,39.38
x 0.02
23002.62
2.19
say
5.21
522
Case - I
2.20
Unit = sqm
Taking output = 10500 sqm
a) Labour
b)
c)
Mate
day
0.240
80.00
19.20
L-12
Mazdoor
day
6.000
70.00
420.00
L-13
hour
6.000
230.00
1380.00
P&M-031
hour
6.000
206.00
1236.00
P&M-001
hour
6.000
692.00
4152.00
P&M-004
Machinery
hour
6.000
1700.00
10200.00
P&M-025
hour
6.000
269.00
1614.00
P&M-044
tonne
9.450
20986.00
198317.70
M-078
cum
105.000
468.93
49237.65
M-050
Material
Modified binder
Crushed stone aggregates 5.6 mm size
d)
Overheads @ 8% on (a+b+c)
e)
21326.12
28790.27
316692.94
30.16
say
Case - II
30.00
b)
Mate
day
0.240
80.00
19.20
L-12
Mazdoor
day
6.000
70.00
420.00
L-13
hour
6.000
230.00
1380.00
P&M-031
Machinery
Mechanical broom @ 1250 sqm per hour
c)
hour
6.000
206.00
1236.00
P&M-001
hour
6.000
692.00
4152.00
P&M-004
hour
6.000
1700.00
10200.00
P&M-025
hour
6.000
269.00
1614.00
P&M-044
tonne
11.550
20986.00
242388.30
M-078
cum
105.000
609.00
63945.00
M-051
Material
Modified binder
Crushed stone chipping 11.2 mm size
d)
Overheads @ 8% on (a+b+c)
e)
26028.36
35138.29
386521.15
36.81
say
Case III
37.00
b)
c)
Mate
day
0.240
80.00
19.20
L-12
Mazdoor
day
6.000
70.00
420.00
L-13
Mazdoor skilled
day
2.000
100.00
200.00
L-15
hour
6.000
230.00
1380.00
P&M-031
hour
6.000
206.00
1236.00
P&M-001
hour
6.000
692.00
4152.00
P&M-004
Machinery
hour
6.000
1700.00
10200.00
P&M-025
hour
6.000
269.00
1614.00
P&M-044
tonne
15.750
20986.00
330529.50
M-078
cum
126.000
609.00
76734.00
M-051
Material
Modified binder
Crushed stone aggregates 11.2 mm size
d)
Overheads @ 8% on (a+b+c)
e)
34118.78
46060.35
506663.82
48.25
say
48.00
b)
Mate
day
0.560
80.00
44.80
L-12
Mazdoor
day
12.000
70.00
840.00
L-13
Mazdoor skilled
day
2.000
100.00
200.00
L-15
hour
2.800
230.00
644.00
P&M-031
hour
2.800
206.00
576.80
P&M-001
tonne
2.000
692.00
1384.00
P&M-004
hour
2.000
802.00
1604.00
P&M-037
tonne
3.680
20986.00
77228.48
M-075
#VALUE!
M-108
Machinery
Material
Paving grade bitumen of 80 - 100 penetration @ 1.05 kg
per sqm
Geotextile including 10 % for overlaps
d)
Overheads @ 8% on (a+b+c)
#VALUE!
e)
#VALUE!
#VALUE!
#VALUE!
say
8.3
NOTE
801
#VALUE!
day
0.07
80
5.60
125.00
day
1.25
100
Mazdoor
day
0.50
70
35.00
Litre
0.50
132.24
66.12
b) Material
Paint
c) Overheads @ 8% on (a+b)
18.54
25.03
275.28
0.17
say
8.8
803
0.20
day
0.12
80
9.60
200.00
Painter
day
2.00
100
Mazdoor
day
1.00
70
70.00
Litre
6.00
132.24
793.44
b) Material
Paint conforming to requirement of clause 803.3.
Add for scaffolding @ 1% of labour cost where required
2.80
c) Overheads @ 8% on (a+b)
86.07
116.19
1278.09
31.95
say
8.9
803
32.00
a) Labour
Mate
day
0.03
80
2.40
Painter
day
0.45
100
45.00
Mazdoor
day
0.25
70
17.50
Litre
1.25
132.24
165.30
b) Material
Paint ready mixed approved brand.
Add @ 1% on cost of material for scaffolding
1.65
c) Overheads @ 8% on (a+b)
18.55
25.04
275.44
12.7
(A)
Unit = cum
Taking output = 5 cum
Square Rubble Coursed Rubble Masonry (first sort)
a)
Material
27.54
say
27.50
MT
cum
0.51
1.05
4400.00
149.00
2244.00
156.45
day
day
0.04
0.90
80.00
70.00
3.20
63.00
2467.00
MT
cum
0.67
0.93
4400.00
149.00
2956.80
139.07
day
day
0.04
0.90
80.00
70.00
3.20
63.00
3162.00
MT
cum
0.29
1.20
4400.00
149.00
1267.20
178.80
day
day
0.04
0.90
80.00
70.00
3.20
63.00
1512.00
Stone
Through and bond stone
(35no.x0.24mx0.24mx0.39m = 0.79 cu.m)
Cement mortar 1:3 (Rate as in Item 12.6 A sub-analysis)
Labour
Mate
Mason
Mazdoor
c) Overhead charges @ 20% on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Cost for 5 cum = a+b+c+d
Rate per cum (a+b+c+d)/5
cum
each
5.50
35.00
289.00
100.00
1589.50
3500.00
M-169
M-182
cum
1.50
2467.00
3700.50
Item 12.6
(A)
day
day
day
0.66
7.50
9.00
80.00
100.00
70.00
L-12
L-11
L-13
say
52.80
750.00
630.00
2044.56
1226.74
13494.10
2698.82
2698.80
b)
1405.3
12.7 (Add)
1400
1405.3
Unit = cum
Taking output = 5 cum
B) Random Rubble Masonry
( coursed/uncoursed )
Unit = cum
Taking output = 5 cum
a) Material
Stone
Through and bond stone
(35nos.x0.24mx0.24mx0.39m = 0.79 cu.m)
Cement mortar 1:3 (Rate as in item 13.6 D)
b) Labour
Mate
Mason
Mazdoor
c) Overheads @ 20% on (a+b)
d) Contractors profit @ 0.1 on (a+b+c)
Cost for 5 cum = a+b+c+d
Rate per cum (a+b+c+d)/5
cum
Nos
5.50
35.00
289.00
100.00
1589.50
3500.00
cum
1.55
2467.00
3823.85
day
day
day
0.62
6.00
9.00
80.00
100.00
70.00
say
49.60
600.00
630.00
2038.59
1223.15
13454.69
2690.94
2690.90
cum
Nos
5.50
35.00
289.00
100.00
1589.50
3500.00
cum
1.55
1512.00
2343.60
day
day
day
0.62
6.00
9.00
80.00
100.00
70.00
49.60
600.00
630.00
1742.54
1045.52
11500.76
2300.15
2300.00
say
@
12.8
MT
cum
cum
cum
cum
4.13
6.75
8.10
4.05
1.35
4400.00
149.00
438.48
517.65
609.00
18172.00
1005.75
3551.69
2096.48
822.15
day
day
day
0.86
1.50
20.00
80.00
100.00
70.00
68.80
150.00
1400.00
hour
hour
6.00
6.00
1,979.00
161.00
240.00
966.00
1440.00
1186.91
say
6171.96
3703.17
40734.92
2715.66
2715.70
Note
12.8
12.8
MT
cum
cum
cum
cum
5.16
6.75
5.40
5.40
2.70
4400.00
149.00
438.48
517.65
609.00
22704.00
1005.75
2367.79
2795.31
1644.30
day
day
day
0.86
1.50
20.00
80.00
100.00
70.00
68.80
150.00
1400.00
hour
hour
6.00
6.00
2,303.00
161.00
240.00
966.00
1440.00
MT
cum
cum
cum
5.21
6.75
8.10
5.40
4400.00
149.00
517.65
609.00
22924.00
1005.75
4192.97
3288.60
day
day
day
0.86
1.50
20.00
80.00
100.00
70.00
68.80
150.00
1400.00
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum)
Generator 33 KVA
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c)
Case II With Batching Plant, Transit Mixer and Conrete Pump
Unit : cum
Taking Output = 120 cum
a) Material
Cement
Coarse Sand
20 mm Aggregate
10 mm Aggregate
b) Labour
Mate
Mason
Mazdoor
c) Machinery
Batching Plant @ 20 cum/hour
Generator 100 KVA
Loader 1 cum capacity
Transit Mixer 4 cum capacity for lead upto 1 km.
Lead beyond 1 km, L-lead in km
Concrete Pump
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c)
d) Formwork @ 4% on cost of concrete i.e.cost of material,
labour and machinery
e) Overheads @ 20% on (a+b+c+d)
f) Contractors profit @ 0.1 on (a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f
Rate per cum = ( a+b+c+d+e+f )/120
12.8
hour
hour
6.00
6.00
2,362.50
161.00
240.00
966.00
1440.00
MT
cum
cum
cum
41.66
54.00
64.80
43.20
4400.00
149.00
517.65
609.00
183304.00
8046.00
33543.72
26308.80
day
day
day
0.84
3.00
18.00
80.00
100.00
70.00
67.20
300.00
1260.00
hour
hour
hour
hour
T-km
hour
6.00
6.00
6.00
15.00
300L
6
2,379.60
1440.00
450.00
520.00
600.00
1.62
165.00
8640.00
2700.00
3120.00
9000.00
8262.00 L= 17
990.00
11421.67
say
59392.68
35635.61
391991.67
3266.60
3266.60
Unit : cum
Taking Output = 120 cum
a) Material
Cement
Coarse sand
40 mm Aggregate
20 mm Aggregate
10 mm Aggregate
b) Labour
MT
cum
cum
cum
cum
5.99
6.75
5.40
5.40
2.70
4400.00
149.00
438.48
517.65
609.00
26356.00
1005.75
2367.79
2795.31
1644.30
day
day
day
0.86
1.50
20.00
80.00
100.00
70.00
68.80
150.00
1400.00
hour
hour
6.00
6.00
2,546.30
161.00
240.00
966.00
1440.00
MT
cum
cum
cum
cum
47.95
54.00
43.20
43.20
21.60
4400.00
149.00
438.48
517.65
609.00
210980.00
8046.00
18942.34
22362.48
13154.40
Mate
Mason
Mazdoor
c) Machinery
Batching Plant @ 20 cum/hour
Generator 100 KVA
Loader 1 cum capacity
Transit Mixer 4 cum capacity for lead upto 1 km.
Transit Mixer 4 cum capacity lead beyond
1 Km, L - lead in Kilometer
Concrete Pump
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c)
d) Formwork @ 3.75% of cost of concrete i.e.cost of material,
labour and machinery
e) Overheads @ 20% on (a+b+c+d)
f) Contractors profit @ 0.1 on (a+b+c+d+e)
cost of 120 cum = a+b+c+d+e+f
Rate per cum (a+b+c+d+e+f)/120
12.8
12.8
day
day
day
0.84
3.00
18.00
80.00
100.00
70.00
hour
hour
hour
hour
T-Km
6.00
6.00
6.00
15.00
300L
1440.00
450.00
520.00
600.00
1.62
hour
6
2,565.30
165.00
67.20
300.00
1260.00
8640.00
2700.00
3120.00
9000.00
8262.00 L= 17
990.00
11543.42
say
63873.57
38324.14
421565.54
3513.05
3513.00
Unit : cum
Taking Output = 120 cum
a) Material
Cement
Coarse sand
20 mm Aggregate
10 mm Aggregate
Admixer
b) Labour
Mate
Mason
Mazdoor
c) Machinery
Batching Plant @ 20 cum/hour
Generator 100 KVA
Loader 1 cum capacity 1 cum
Transit Mixer 4 cum capacity for lead upto 1 km.
Transit Mixer 4 cum capacity lead beyond
1 Km, L - lead in Kilometer
Concrete Pump
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c)
F
PCC Grade M30
Unit = cum
MT
cum
cum
cum
6.05
6.75
8.10
5.40
4400.00
149.00
517.65
609.00
26620.00
1005.75
4192.97
3288.60
day
day
day
0.86
1.50
20.00
80.00
100.00
70.00
68.80
150.00
1400.00
hour
hour
6.00
6.00
2,608.90
161.00
240.00
966.00
1440.00
MT
cum
cum
cum
Kg
48.38
54.00
64.80
43.20
193.52
4400.00
149.00
517.65
609.00
40.00
212872.00
8046.00
33543.72
26308.80
0.00
day
day
day
0.84
3.00
18.00
80.00
100.00
70.00
67.20
300.00
1260.00
hour
hour
hour
hour
T-Km
6.00
6.00
6.00
15.00
300L
1440.00
450.00
520.00
600.00
1.62
hour
6.00
2,626.00
165.00
8640.00
2700.00
3120.00
9000.00
8262.00 L= 17
990.00
Case I
12.8
Unit : cum
Taking Output = 120 cum
a) Material
Cement
Coarse sand
40 mm Aggregate
20 mm Aggregate
10 mm Aggregate
b) Labour
Mate
Mason
Mazdoor
c) Machinery
Batching Plant @ 20 cum/hour
Generator 100 KVA
Loader 1 cum capacity
Transit Mixer 4 cum capacity for lead upto 1 km.
Transit Mixer 4 cum capacity lead beyond
1 Km, L - lead in Kilometer
Concrete Pump
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c)
G
RCC Grade M30
Case I Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement
Coarse sand
20 mm Aggregate
10 mm Aggregate
b) Labour
Mate
Mason
Mazdoor
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum)
Generator 33 KVA
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c)
Case II Using Batching Plant, Transit Mixer and Conrete Pump
Unit = cum
Taking output = 120 cum
a) Material
MT
cum
cum
cum
cum
6.08
6.75
5.40
5.40
2.70
4400.00
149.00
438.48
517.65
609.00
26752.00
1005.75
2367.79
2795.31
1644.30
day
day
day
0.86
1.50
20.00
80.00
100.00
70.00
68.80
150.00
1400.00
hour
hour
6.00
6.00
2,572.70
161.00
240.00
966.00
1440.00
MT
cum
cum
cum
cum
48.60
54.00
43.20
43.20
21.60
4400.00
149.00
438.48
517.65
609.00
213840.00
8046.00
18942.34
22362.48
13154.40
day
day
day
0.84
3.00
18.00
80.00
100.00
70.00
67.20
300.00
1260.00
hour
hour
hour
hour
T-Km
6.00
6.00
6.00
15.00
300L
1440.00
450.00
520.00
600.00
1.62
hour
6.00
2,589.10
165.00
990.00
MT
cum
cum
cum
6.10
6.75
8.10
5.40
4400.00
149.00
517.65
609.00
26840.00
1005.75
4192.97
3288.60
day
day
day
0.86
1.50
20.00
80.00
100.00
70.00
68.80
150.00
1400.00
hour
hour
6.00
6.00
2,623.50
161.00
240.00
966.00
1440.00
8640.00
2700.00
3120.00
9000.00
8262.00 L= 17
12.8
Cement
Coarse sand
20 mm Aggregate
10 mm Aggregate
b) Labour
Mate
Mason
Mazdoor
c) Machinery
Batching Plant @ 20 cum/hour
Generator 100 KVA
Loader 1 cum capacity
Transit Mixer 4 cum capacity for lead upto 1 km.
Transit Mixer 4 cum capacity lead beyond
1 Km, L - lead in Kilometer
Concrete Pump
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c)
H
RCC Grade M35
Case I Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement
Coarse sand
20 mm Aggregate
10 mm Aggregate
b) Labour
Mate
Mason
Mazdoor
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum)
Generator 33 KVA
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c)
Case II Using Batching Plant, Transit Mixer and Conrete Pump
Unit ; cum
Taking Output = 120 cum
a) Material
Cement
Coarse sand
20 mm Aggregate
10 mm Aggregate
Admixer
b) Labour
Mate
Mason
Mazdoor
c) Machinery
Batching Plant @ 20 cum/hour
Generator 100 KVA
Loader 1 cum capacity
Transit Mixer 4 cum capacity for lead upto 1 km.
Transit Mixer 4 cum capacity lead beyond
1 Km, L - lead in Kilometer
Concrete Pump
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c)
d) Formwork @ 3% on cost of concrete i.e.cost of material,
labour and machinery
e) Overheads @ 20% on (a+b+c+d)
f) Contractors profit @ 0.1 on (a+b+c+d+e)
MT
cum
cum
cum
48.80
54.00
64.80
43.20
4400.00
149.00
517.65
609.00
214720.00
8046.00
33543.72
26308.80
day
day
day
0.84
3.00
18.00
80.00
100.00
70.00
67.20
300.00
1260.00
hour
hour
hour
hour
T-Km
6.00
6.00
6.00
15.00
300L
1440.00
450.00
520.00
600.00
1.62
hour
6.00
2,641.40
165.00
990.00
MT
cum
cum
cum
6.33
6.75
8.10
5.40
4400.00
149.00
517.65
609.00
27852.00
1005.75
4192.97
3288.60
day
day
day
0.86
1.50
20.00
80.00
100.00
70.00
68.80
150.00
1400.00
hour
hour
6.00
6.00
2,691.00
161.00
240.00
966.00
1440.00
MT
cum
cum
cum
Kg
50.64
54.00
64.80
43.20
202.56
4400.00
149.00
517.65
609.00
40.00
222816.00
8046.00
33543.72
26308.80
8102.40
day
day
day
0.84
3.00
18.00
80.00
100.00
70.00
67.20
300.00
1260.00
hour
hour
hour
hour
T-Km
6.00
6.00
6.00
15.00
300L
1440.00
450.00
520.00
600.00
1.62
hour
6.00
2,776.40
165.00
8640.00
2700.00
3120.00
9000.00
8262.00 L= 17
8640.00
2700.00
3120.00
9000.00
8262.00 L= 17
990.00
9994.68
68630.16
41178.10
12.11
452959.06
3774.66
3774.70
2859.60
C
Case I
(i)
Bottom Plug
Concrete to be placed using tremie pipe
Using Concrete Mixer
PCC Grade M20
Unit = cum
Taking output = 15 cum
a) Material
Cement
Coarse sand
40 mm Aggregate
20 mm Aggregate
10 mm Aggregate
Admixer
b) Labour
Mate
Mason
Mazdoor
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum)
Generator 33 KVA
Light Crane 3 tonnes capacity for handling tremie pipe
MT
cum
cum
cum
cum
Kg
5.55
6.75
5.40
5.40
2.70
18.60
4400.00
149.00
438.48
517.65
609.00
40.00
24420.00
1005.75
2367.79
2795.31
1644.30
744.00
day
day
day
0.90
1.50
20.00
80.00
100.00
70.00
72.00
150.00
1400.00
hour
hour
hour
6.00
6.00
6.00
161.00
240.00
230.00
966.00
1440.00
1380.00
2559.10
MT
cum
cum
cum
Kg
44.40
54.00
64.80
43.20
148.80
4400.00
149.00
517.65
609.00
40.00
195360.00
8046.00
33543.72
26308.80
5952.00
day
day
day
0.88
3.00
18.00
80.00
100.00
70.00
70.40
300.00
1260.00
hour
hour
hour
hour
T-Km
6.00
6.00
6.00
15.00
300L
1440.00
450.00
520.00
600.00
1.62
hour
6.00
2529.70
165.00
8640.00
2700.00
3120.00
9000.00
8262.00 L= 17
990.00
(ii)
Case I
MT
cum
cum
cum
cum
Kg
5.99
6.75
5.40
5.40
2.70
21.60
4400.00
149.00
438.48
517.65
609.00
40.00
26356.00
1005.75
2367.79
2795.31
1644.30
864.00
day
day
day
0.90
1.50
20.00
80.00
100.00
70.00
72.00
150.00
1400.00
hour
hour
hour
6.00
6.00
6.00
161.00
240.00
230.00
966.00
1440.00
1380.00
2696.10
MT
cum
cum
cum
Kg
47.88
54.00
64.80
43.20
172.80
4400.00
149.00
517.65
609.00
40.00
210672.00
8046.00
33543.72
26308.80
6912.00
day
day
day
0.88
3.00
18.00
80.00
100.00
70.00
70.40
300.00
1260.00
hour
hour
hour
hour
T-Km
6.00
6.00
6.00
15.00
300L
1440.00
450.00
520.00
600.00
1.62
hour
6.00
2665.30
165.00
990.00
MT
cum
cum
cum
cum
Kg
6.08
6.75
5.40
5.40
2.70
21.60
4400.00
149.00
438.48
517.65
609.00
40.00
26752.00
1005.75
2367.79
2795.31
1644.30
864.00
day
day
0.90
1.50
80.00
100.00
72.00
150.00
8640.00
2700.00
3120.00
9000.00
8262.00 L= 17
Mazdoor
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum)
Generator 33 KVA
Light Crane of 3 tonnes capacity for handling tremie pipe
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c)
Case II Using Batching Plant, Transit Mixer and Crane/concrete
pump
Unit = cum
Taking output = 120 cum
a) Material
Cement
Coarse sand
20 mm Aggregate
10 mm Aggregate
Admixer
b) Labour
Mate
Mason
Mazdoor
c) Machinery
Batching Plant @ 20 cum/hour
Generator 100 KVA
Loader 1 cum capacity
Transit Mixer 4 cum capacity for lead upto 1 km.
Transit Mixer 4 cum capacity, lead beyond 1 Km, L lead in Kilometer
Concrete Pump
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c)
(iv)
PCC Grade M35
Case I
day
20.00
70.00
1400.00
hour
hour
hour
6.00
6.00
6.00
161.00
240.00
230.00
966.00
1440.00
1380.00
2722.50
MT
cum
cum
cum
Kg
48.64
54.00
64.80
43.20
172.80
4400.00
149.00
517.65
609.00
40.00
214016.00
8046.00
33543.72
26308.80
6912.00
day
day
day
0.88
3.00
18.00
80.00
100.00
70.00
70.40
300.00
1260.00
hour
hour
hour
hour
T-Km
6.00
6.00
6.00
15.00
300L
1440.00
450.00
520.00
600.00
1.62
hour
6.00
2693.10
165.00
990.00
MT
cum
cum
cum
cum
Kg
6.29
6.75
5.40
5.40
2.70
21.60
4400.00
149.00
438.48
517.65
609.00
40.00
27676.00
1005.75
2367.79
2795.31
1644.30
864.00
day
day
day
0.90
1.50
20.00
80.00
100.00
70.00
72.00
150.00
1400.00
hour
hour
hour
6.00
6.00
6.00
161.00
240.00
230.00
966.00
1440.00
1380.00
4400.00
149.00
517.65
609.00
221232.00
8046.00
33543.72
26308.80
8640.00
2700.00
3120.00
9000.00
8262.00 L= 17
2784.10
MT
cum
cum
cum
50.28
54.00
64.80
43.20
Admixer
b) Labour
Mate
Mason
Mazdoor
c) Machinery
Batching Plant @ 20 cum/hour
Generator 100 KVA
Loader 1 cum capacity
Transit Mixer 4 cum capacity for lead upto 1 km.
Transit Mixer 4 cum capacity, lead beyond 1 Km, L lead in Kilometer
Concrete Pump
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c)
Add 5% of cost of material and labour towards cost of
forming sump, protective bunds, chiselling and making
arrangements for under water concreteing with tremie pipe..
Kg
172.80
40.00
6912.00
day
day
day
0.88
3.00
18.00
80.00
100.00
70.00
70.40
300.00
1260.00
hour
hour
hour
hour
T-Km
6.00
6.00
6.00
15.00
300L
1440.00
450.00
520.00
600.00
1.62
hour
6.00
2753.30
165.00
Say
69053.71
41432.23
455754.51
3797.95
3798.00
Well cap
RCC Grade M35
Using Batching Plant, Transit Mixer and Conrete Pump
Unit = cum
Taking output = 120 cum
a) Material
Cement
Coarse sand
20 mm Aggregate
10 mm Aggregate
b) Labour
Mate
Mason
Mazdoor
c) Machinery
Batching Plant @ 20 cum/hour
Generator 100 KVA
Loader(capacity 1 cum)
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity for lead upto 1 km.
Lead beyond 1 Km, L - lead in Kilometer
Concrete Pump
Formwork @ 3% of (a+b+c)
d) Overheads @ 20% on (a+b+c)
e) Contractors profit @ 0.1 on (a+b+c+d)
cost of 120 cum = a+b+c+d+e
Rate per cum (a+b+c+d+e)/120
MT
cum
cum
cum
50.64
54.00
64.80
43.20
4400.00
149.00
517.65
609.00
222816.00
8046.00
33543.72
26308.80
day
day
day
0.84
3.00
18.00
80.00
100.00
70.00
67.20
300.00
1260.00
hour
hour
hour
6.00
6.00
6.00
1440.00
450.00
520.00
8640.00
2700.00
3120.00
hour
T-Km
hour
15.00
300L
6.00
600.00
1.62
165.00
Say
3.13
990.00
14883.65
8640.00
2700.00
3120.00
9000.00
8262.00 L= 17
Note
304
9000.00
8262.00 L= 17
990.00
9751.61
66961.07
40176.64
441943.04
3682.86
3682.90
Manual Means
(i) Depth upto 3 m
a) Labour
Mate
day
0.320
80.00
25.60
L-12
Mazdoor
day
8.000
70.00
560.00
L-13
b) Overheads @ 8% on (a)
46.85
63.24
695.69
69.57
say
Note
69.60
day
0.32
80
25.60
Mazdoor
day
8.00
70
560.00
hour
6.00
840
5040.00
b) Machinery
Hydraulic excavator 1.0 cum bucket capacity
c) Overheads @ 8% on (a+b)
450.05
607.56
6683.21
13.6
22.28
say
22.30
MT
kg
1.05
6.00
29902.00
39.00
31397.10
234.00
day
day
day
0.34
2.00
6.50
80.00
100.00
70.00
27.20
200.00
455.00
6462.66
1500
&1600
1700
A
Case II
Unit = cum
Taking output = 120 cum
a) Material
Cement
Coarse sand
20 mm Aggregate
10 mm Aggregate
b) Labour
Mate
Mason
Mazdoor
c) Machinery
Batching Plant @ 20 cum/hour
Generator 100 KVA
Loader
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto 1 Km
Lead beyond 1 Km, L - lead in Kilometer
Concrete Pump
Basic Cost of Labour, Material & Mechinery (a+b+c) for 120 cum
(i)
(p)
B
Case II
say
3877.60
42653.56
42653.60
MT
cum
cum
cum
40.92
54.00
64.80
43.20
4400.00
149.00
517.65
609.00
180048.00
8046.00
33543.72
26308.80
day
day
day
0.84
3.00
18.00
80.00
100.00
70.00
67.20
300.00
1260.00
hour
hour
hour
6.00
6.00
6.00
1440.00
450.00
520.00
8640.00
2700.00
3120.00
hour
T-Km
hour
15.00
300L
6.00
282285.80
600.00
1.62
165.00
9000.00
8262.00 L= 17
990.00
282285.80
20.00
say
56457.16
67748.59
40649.16
447140.71
3726.17
3726.20
MT
cum
cum
cum
47.95
54.20
64.80
43.20
4400.00
149.00
517.65
609.00
210980.00
8075.80
33543.72
26308.80
day
day
day
0.84
3.00
18.00
80.00
100.00
70.00
67.20
300.00
1260.00
hour
hour
hour
6.00
6.00
6.00
1440.00
450.00
520.00
8640.00
2700.00
3120.00
hour
15.00
600.00
9000.00
(p)
Height upto 5m
Basic Cost of Labour, Material & Mechinery (a+b+c)
120 cum
d) Formwork and staging 20 % of (a+b+c)
e)
f)
T-Km
hour
300L
6.00
313247.60
1.62
165.00
for
313247.60
20.00
62649.52
75179.42
45107.65
496184.20
C
Case II
4134.87
say
4134.90
RCC Grade M 30
Using Batching Plant, Transit Mixer and Concrete Pump.
Unit = cum
Taking output = 120 cum
a) Material
Cement
Coarse sand
20 mm Aggregate
10 mm Aggregate
b) Labour
Mate
Mason
Mazdoor
c) Machinery
Batching Plant @ 20 cum/hour
Generator 100 KVA
Loader
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto 1 Km
Lead beyond 1 Km, L - lead in Kilometer
Concrete Pump
Basic Cost of Labour, Material & Mechinery (a+b+c) for 120 cum
For formwork and staging add the following:
(i)
(p)
MT
cum
cum
cum
48.79
54.60
64.80
43.20
4400.00
149.00
517.65
609.00
214676.00
8135.40
33543.72
26308.80
day
day
day
0.88
3.00
19.00
80.00
100.00
70.00
70.40
300.00
1330.00
hour
hour
hour
6.00
6.00
6.00
1440.00
450.00
520.00
8640.00
2700.00
3120.00
hour
T-Km
hour
15.00
300L
6.00
317076.40
600.00
1.62
165.00
9000.00
8262.00 L= 17
990.00
317076.40
20.00
say
Rate per cum (a+b+c+d)/120 ( including formwork and excluding OH & CP)
Rate per cum (a+b+c+d)/120 ( excluding formwork and Excluding OH & CP)
E
Case 1
8262.00 L= 17
990.00
63415.28
76098.34
45659.00
502249.02
4185.41
4185.40
3170.80
2642.30
MT
cum
cum
cum
kg
6.45
6.75
8.10
5.40
25.80
4400.00
149.00
517.65
609.00
40.00
28380.00
1005.75
4192.97
3288.60
1032.00
day
day
day
0.96
2.00
22.00
80.00
100.00
70.00
76.80
200.00
1540.00
hour
hour
6.00
6.00
42122.20
161.00
240.00
966.00
1440.00
MT
cum
cum
cum
kg
51.60
54.00
64.80
43.20
206.40
4400.00
149.00
517.65
609.00
40.00
227040.00
8046.00
33543.72
26308.80
8256.00
day
day
day
0.94
3.50
20.00
80.00
100.00
70.00
75.20
350.00
1400.00
hour
hour
hour
6.00
6.00
6.00
1440.00
450.00
520.00
8640.00
2700.00
3120.00
hour
T-Km
hour
15.00
300L
6.00
337731.80
600.00
1.62
165.00
Unit = cum
Taking output = 120 cum
a) Material
Cement
Coarse sand
20 mm Aggregate
10 mm Aggregate
Admixture @ 0.4% of cement
b) Labour
Mate
Mason
Mazdoor
c) Machinery
Batching Plant @ 20 cum/hour
Generator 100 KVA
Loader
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto 1 Km
Lead beyond 1 Km, L - lead in Kilometer
Concrete Pump
Basic Cost of Labour, Material & Mechinery (a+b+c) for 120 cum
For formwork and staging add the following:
(i)
(p)
Height upto 5m
Basic Cost of Labour, Material & Mechinery (a+b+c)
120 cum
d) Formwork and staging 18 % of (a+b+c)
for
337731.80
18.00
60791.72
e)
79704.70
f)
47822.82
526051.05
4383.76
say
Note
9000.00
8262.00 L= 17
990.00
4383.80
14.2
1600
Mate
Blacksmith
Mazdoor
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c)
MT
Kg
1.05
8.00
29902.00
39.00
31397.10
312.00
day
day
day
0.44
3.00
8.00
32604.30
80.00
100.00
70.00
35.20
300.00
560.00
Item
No.
Unit
Rate
CHAPTER-1
CARRIAGE OF MATERIALS
1.1
1.2
1.3
1.4
(i)
(ii)
(iii)
1.5
Loading and unloading of stone boulder / stone aggregates / sand / kanker / moorum. (Placing tipper at loading point,
loading with front end loader, dumping, turning for return trip, excluding time for haulage and return trip)
Loading and Unloading of Boulders by Manual Means
Loading and Unloading of Cement or Steel by Manual Means and stacking.
Cost of Haulage Excluding Loading and Unloading
Surfaced Road
Unsurfaced Gravelled Road
Katcha Track and Track in river bed / nallah bed and choe bed.
Hand Broken Stone Aggregates 63 mm nominal size (Supply of quarried stone, hand breaking into coarse aggregate 63 mm
nominal size (passing 80 mm and retained on 50 mm sieve) and stacking as directed)
cum
73.00
cum
tonne
95.00
138.00
tonne.km
tonne.km
tonne.km
4.10
5.00
10.00
cum
#VALUE!
1.6
Crushing of stone aggregates 13.2 mm nominal size. (Crushing of stone boulders of 150 mm size in an integrated stone
crushing unit of 200 tonnes per hour capacity comprising of primary and secondary crushing units, belt conveyor and vibrating
screens to obtain stone aggregates of 13 mm nominal size.)
cum
609.00
1.7
Crushing of stone aggregates 20 mm nominal size (Crushing of stone boulders of 150 mm size in an integrated stone
crushing unit of 200 tonnes per hour capacity comprising of primary and secondary crushing units, belt conveyor and vibrating
screens to obtain stone aggregates of 20 mm nominal size.)
cum
517.00
1.8
Crushing of stone aggregates 40 mm nominal size (Crushing of stone boulders of 150 mm size in an integrated stone
crushing unit of 200 tonnes per hour capacity comprising of primary and secondary crushing units, belt conveyor and vibrating
screens to obtain stone aggregates of 40 mm nominal size.)
cum
436.00
each
each
each
each
hectare
79.20
161.00
283.70
512.50
4348.00
hectare
hectare
13319.00
17941.00
hectare
hectare
26639.50
32154.00
CHAPTER-2
SITE CLEARANCE
Cutting of Trees, including Cutting of Trunks, Branches and Removal (Cutting of trees, including cutting of trunks, branches
and removal of stumps, roots, stacking of serviceable material with all lifts and up to a lead of 1000 mtrs and earth filling in the
depression/pit.)
2.1
(i)
(ii)
(iii)
(iv)
2.2
2.3
(i)
A
B
(ii)
A
B
2.4
(i)
I
A
B
C
II
Page 1 of 36
cum
cum
cum
129.00
146.00
327.00
Item
No.
A
B
(ii)
A
B
C
D
(iii)
A
B
C
D
E
F
(iv)
(v)
A
B
C
(vi)
A
B
(vii)
A
B
(viii)
(ix)
A
B
C
2.5
I
A
B
II
A
2.6
Unit
Rate
cum
cum
230.00
355.70
cum
cum
cum
cum
94.00
111.50
87.00
84.00
cum
cum
cum
cum
cum
cum
cum
101.00
111.50
94.00
91.00
87.10
94.00
178.00
tonne
tonne
tonne
395.00
299.00
3.00
1000
numbers
304.00
1000
numbers
109.00
cum
cum
122.00
26.00
sqm
4.00
metre
metre
metre
45.10
61.10
104.50
cum
cum
235.00
178.00
cum
135.20
cum
809.00
2.7
Dismantling Guard Rails (Dismantling guard rails by manual means and disposal of dismantled material with all lifts and up to a
lead of 1000 metres, stacking serviceable materials and unserviceable materials separately.)
metre
26.80
2.8
Dismantling Kerb Stone (Dismantling kerb stone by manual means and disposal of dismantled material with all lifts and up to a
lead of 1000 metre)
metre
6.80
2.9
Dismantling Kerb Stone channel (Dismantling kerb stone channel by manual means and disposal of dismantled material with
all lifts and up to a lead of 1000 metre)
metre
10.00
Page 2 of 36
Item
No.
2.10
A
B
C
2.11
Unit
Dismantling Kilometre Stone (Dismantling of kilometre stone including cutting of earth, foundation and disposal of dismantled
material with all lifts and lead upto 1000 m and back filling of pit.)
5th KM stone
Ordinary KM Stone
Hectometre Stone
Dismantling of Fencing (Dismantling of barbed wire fencing/ wire mesh fencing including posts, foundation concrete, back filling
of pit by manual means including disposal of dismantled material with all lifts and up to a lead of 1000 metres, stacking serviceable
material and unserviceable material separately. )
Rate
each
each
each
116.00
70.90
14.00
metre
13.00
2.12
Dismantling of CI Water Pipe Line (Dismantling of CI water pipe line 600 mm dia including disposal with all lifts and lead upto
1000 metres and stacking of serviceable material and unserviceable material separately under supervision of concerned
department)
metre
49.00
2.13
Removal of Cement Concrete Pipe of Sewer Gutter (Removal of cement concrete pipe of sewer gutter 1500 mm dia under the
supervision of concerned department including disposal with all lifts and up to a lead of 1000 metres and stacking of serviceable
and unserviceable material separately but excluding earth excavation and dismantling of masonry works.)
metre
90.00
2.14
Removal of Telephone / Electric Poles and Lines (Removal of telephone / Electric poles including excavation and dismantling
of foundation concrete and lines under the supervision of concerned department, disposal with all lifts and up to a lead of 1000
metres and stacking the serviceable and unserviceable material separately)
each
51.00
CHAPTER-3
EARTH WORK, EROSION CONTROL AND DRAINAGE
3.1
Excavation in Soil by Manual Means. (Excavation for roadway in soil using manual means including loading in truck for carrying
of cut earth to embankment site with all lifts and lead upto1000 metres.)
cum
83.00
3.2
Excavation in ordinary rock by manual means (Excavation in ordinary rock using manual means including loading in a truck
and carrying of excavated material to embankment site with in all lifts and leads upto 1000 metres )
cum
101.00
3.3
Excavation in Soil with Dozer with lead upto 100 metres ( Excavation for road way in soil by mechanical means including
cutting and pushing the earth to site of embankment upto a distance of 100 metres (average lead50 metres), including trimming
bottom and side slopes in accordance with requirements of lines, grades and cross sections.)
cum
88.00
cum
147.00
Excavation in Ordinary Rock with Dozer with lead upto 100 metres (Excavation for roadway in ordinary rock by deploying a
dozer, 80 HP including cutting and pushing the cut earth to site of embankment upto a distance of 100 metres ( average lead 50
metres ), trimming bottom and side slopes in accordance with the requirements of lines, grades and cross sections.)
3.4
3.5
Excavation in Hard Rock (requiring blasting) with disposal upto 1000 metres (Excavation for roadway in hard rock
(requiring blasting) by drilling, blasting and breaking, trimming of bottom and side slopes in accordance with requirements of
lines, grades and cross sections, loading and disposal of cut road with in all lifts and leads upto 1000 metres )
cum
133.00
3.6
Excavation in Soil using Hydraulic Excavator CK 90 and Tippers with disposal upto 1000 metres. (Excavation for
roadwork in soil with hydraulic excavator of0.9 cum bucket capacity including cutting and loading in tippers, trimming bottom and
side slopes, in accordance with requirements of lines, grades and cross sections, and transporting to the embankment location
within all lifts and lead upto 1000m)
cum
43.80
3.7
Excavation in Ordinary Rockusing Hydraulic ExcavatorCK-90 and Tippers with disposal upto 1000 metres. (Excavation
for roadway in ordinary rock with hydraulic excavator of 0.9 cum bucket capacity including cutting and loading in tippers,
transporting to embankment site within all lifts and lead upto 1000 m, trimming bottom and side slopes in accordance with
requirements of lines, grades and cross sections.)
cum
53.20
3.8
Excavation in Hard Rock (blasting prohibited) (Excavation for roadway in hard rock (blasting prohibited) with rock breakers
including breaking rock, loading in tippers and disposal within all lifts and lead upto 1000 metres, trimming bottom and side slopes
in accordance with requirements of lines, grades and cross sections.)
cum
cum
211.00
300.00
cum
207.00
cum
48.00
A
B
3.9
3.10
Mechanised
Manual Method
Excavation in Hard Rock (controlled blasting) with disposal upto 1000 metres (Excavation for roadway in hard rock with
controlled blasting by drilling, blasting and breaking, trimming of bottom and side slopes in accordance with requirements of lines,
grades and cross sections, loading and disposal of cut road with in all lifts and leads upto 1000 metres )
Excavation in Marshy Soil (Excavation for roadway in marshy soil with hydraulic excavator 0.9 cum bucket capacity including
cutting and loading in tippers and disposal with in all lifts and lead upto 1000 metres, trimming of bottom and side slopes in
accordance with requirements of lines, grades and cross sections.)
Page 3 of 36
Item
No.
Unit
Removal of Unserviceable Soil with Disposal upto 1000 metres (Removal of unserviceable soil including excavation, loading
and disposal upto 1000 metres lead but excluding replacement by suitable soil which shall be paid separately as per clause 305.)
3.11
3.12
Pre-splitting of Rock Excavation Slopes (Carrying out excavation in hard rock to achieve a specified slope of the rock face by
controlled use of explosives and blasting accessories in properly aligned and spaced drill holes, collection of the excavated rock by
a 80 HP dozer, loading in tipper by a front end loader and disposing of the material with all lifts and lead upto 1000 m, all as
specified in clause No. 303)
3.13
Excavation for Structures (Earth work in excavation of foundation of structures as per drawing and technical specification,
including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and
bottom, backfilling the excavation earth to the extent required and utilising the remaining earth locally for road work.)
(i)
A
B
(ii)
A
B
(iii)
A
(iv)
A
(v)
A
B
3.14
Ordinary soil
Manual Means (Depth upto 3 m)
Mechanical Means (Depth upto 3 m)
Ordinary rock (not requiring blasting)
Manual Means (Depth upto 3 m)
Mechanical Means
Hard rock ( requiring blasting )
Manual Means
Hard rock ( blasting prohibited )
Mechanical Means
Marshy soil
Manual means ( upto 3 m depth)
Mechanical Means
Scarifying Existing Granular Surface to a Depth of 50 mm by Manual Means (Scarifying the existing granular road surface to
a depth of 50 mm and disposal of scarified material within all lifts and leads upto 1000 metres. )
Rate
cum
44.00
sqm
96.00
cum
cum
70.00
22.00
cum
cum
87.00
30.00
cum
201.00
cum
288.00
cum
cum
243.00
145.00
sqm
9.00
3.15
Scarifying existing bituminous surface to a depth of 50 mm by mechanical means (Scarifying the existing bituminous road
surface to a depth of 50 mm and disposal of scarified material with in all lifts and lead upto 1000 metres.)
sqm
3.10
3.16
Embankment Construction with Material Obtained from Borrow Pits (Construction of embankment with approved material
obtained from borrow pits with all lifts and leads, transporting to site, spreading, grading to required slope and compacting to meet
requirement of table 300-2)
cum
120.40
3.17
Construction of Embankment with Material Deposited from Roadway Cutting (Construction of embankment with approved
materials deposited at site from roadway cutting and excavation from drain and foundation of other structures graded and
compacted to meet requirement of table 300-2)
cum
70.50
3.18
Construction of Subgrade and Earthen Shoulders (Construction of subgrade and earthen shoulders with approved material
obtained from borrow pits with all lifts & leads, transporting to site, spreading, grading to required slope and compacted to meet
requirement of table No. 300-2)
cum
143.70
cum
42.50
cum
22.00
cum
69.00
cum
53.00
sqm
18.90
3.19
Case-I
Case-II
3.20
3.21
3.22
3.23
Page 4 of 36
sqm
#VALUE!
Item
No.
Unit
Rate
Surface Drains in Soil (Construction of unlined surface drains of average cross sectional area 0.40 sqm in soil to specified lines,
grades, levels and dimensions to the requirement of clause 301 and 309. Excavated material to be used in embankment within a
lead of50 metres (average lead 25 metres))
3.24
A
B
Mechanical means
Manual Means
Surface Drains in Ordinary Rock (Construction of unlined surface drain of average cross sectional area 0.4 sqm in ordinary
rock to specified lines, grades, levels and dimensions as per approved design and to the requirement of clause 301 to 309.
Excavated material to be used in embankment at site.)
metre
metre
55.00
17.00
A
B
Mechanical Means
Manual Means
Surface Drains in Hard Rock (Rate per metre may be worked out based on quantity of hard rock as per design.)
Sub Surface Drains with Perforated Pipe (Construction of subsurface drain with perforated pipe of 100 mm internal diameter of
metal/ asbestos cement/ cement concrete/PVC, closely jointed, perforations ranging from 3 mm to 6 mm depending upon size of
material surrounding the pipe, with 150 mm bedding below the pipe and 300 mm cushion above the pipe, cross section of
excavation 450 x 550 mm. Excavated material to be utilised in roadway at site )
metre
metre
metre
71.00
26.00
3.25
3.26
3.27
#VALUE!
3.28
Aggregate Sub- Surface Drains (Construction of aggregate sub surface drain 300 mm x 450 mm with aggregates conforming to
table 300-4, excavated material to be utilised in roadway )
metre
110.00
3.29
Underground Drain at Edge of Pavement (Construction of an underground drain 1 m x 1 m (inside dimensions) lined with RCC20 cm thick and covered with RCC slab10 cm in thickness on urban roads)
metre
1650.00
3.30
Preparation and Surface Treatment of formation. (Preparation and surface treatment of formation by removing mud and
slurry, watering to the extent needed to maintain the desired moisture content, trimming to the required line, grade, profile and
rolling with 8-10 tonne smooth wheeled roller, complete as per clause 310.)
sqm
1.00
3.31
Construction of Rock fill Embankment (Construction of rock fill embankment with broken hard rock fragments of size not
exceeding 300 mm laid in layers not exceeding 500 mm thick including filling of surface voids with stone spalls, blinding top layer
with granular material, rolled with vibratory road roller, all complete as per clause 313)
cum
40.00
3.32
Excavation in Hill Area in Soil by Mechanical Means (Excavation in soil in hilly area by mechanical means including cutting
and trimming of side slopes and disposing of excavated earth with all lifts and lead upto 1000 metres)
cum
104.00
3.33
Excavation in Hilly Area in Ordinary Rock by Mechanical Means not Requiring Blasting. (Excavation in hilly area in
ordinary rock not requiring ballasting by mechanical means including cutting and trimming of slopes and disposal of cut material
with all lift and lead upto 1000 metres )
cum
146.00
3.34
Excavation in Hilly Areas in Hard Rock Requiring Blasting (Excavation in hilly areas in hard rock requiring blasting, by
mechanical means including trimming of slopes and disposal of cut material with all lifts and lead upto 1000 metres.)
cum
194.00
Work in Urban Roads (The cost of earth work in urban roads inhabited area will be comparatively higher due to following
reasons:)
Embankment Construction with Fly ash/Pond ash available from coal or lignite burning Thermal Plants as waste
material. (Construction of embankment with fly ash conforming to table 1 of IRC: SP: 58 - 2001 obtained from coal or lignite
burning thermal power stations as waste material, spread and compacted in layer of 200mm thickness each at OMC, all as
specified in IRC: SP: 58-2001 and as per approved plans.)
3.35
3.36
cum
#VALUE!
cum
cum
cum
#REF!
#REF!
#REF!
CHAPTER-4
SUB-BASES, BASES ( NON- BITUMINOUS) AND SHOULDERS
Granular Sub-base with Close Graded Material (Table:- 400-1)
Plant Mix Method (Construction of granular sub-base by providing close graded Material, mixing in a mechanical mix plant at
OMC, carriage of mixed Material to work site, spreading in uniform layers with motor grader on prepared surface and compacting
with vibratory power roller to achieve the desired density, complete as per clause 401 )
4.1
A
(i)
(ii)
(iii)
B
(i)
(ii)
cum
cum
Page 5 of 36
974.00
999.00
Descriptions
Unit
cum
998.00
cum
cum
cum
412.30
923.00
799.00
By Mechanical Means
By Manual Means
Lime Treated Soil for Sub- Base (Providing, laying and spreading soil on a prepared sub grade, pulverising, mixing the spread
soil in place with rotavator with 3 % slaked lime with minimum content of 70% of CaO, grading with motor grader and compacting
with the road roller at OMC to achieve at least 98%of the max dry density to form a layer of sub base.)
cum
cum
779.60
764.60
cum
831.00
cum
511.00
cum
cum
1366.00
1161.00
4.5
Cement Treated Soil Sub Base/ Base (Providing, laying and spreading soil on a prepared sub grade, pulverising, adding the
designed quantity of cement to the spread soil, mixing in place with rotavator, grading with the motor grader and compacting with
the road roller at OMC to achieve the desired unconfined compressive strength and to form a layer of sub-base/base.)
4.6
Cement Treated Crushed Rock or combination as per clause 403.2 and table 400.4in Sub base/ Base (Providing, laying
and spreading Material on a prepared sub grade, adding the designed quantity of cement to the spread Material, mixing in place
with rotavator, grading with the motor grader and compacting with the road roller at OMC to achieve the desired unconfined
compressive strength and to form a layer of sub-base/base.)
(i)
(ii)
Rate
4.7
Making 50 mm x 50 mm Furrows (Making 50 mm x 50 mm furrows, 25mm deep, 450 to the center line of the road and at one
metre interval in the existing thin bituminous wearing coarse including sweeping and disposal of excavated material within 1000
metres lead)
sqm
219.00
4.8
Inverted Choke (Construction of inverted choke by providing, laying, spreading and compacting screening B type/ coarse sand of
specified grade in uniform layer on a prepared surface with motor grader and compacting with power roller etc)
cum
266.00
4.9
Water Bound Macadam (Providing, laying, spreading and compacting stone aggregates of specific sizes to water bound
macadam specification including spreading in uniform thickness, hand packing, rolling with vibratory roller 8-10 tonnes in stages to
proper grade and camber, applying and brooming requisite type of screening/ binding Materials to fill up the interstices of coarse
aggregate, watering and compacting to the required density.)
cum
cum
745.00
903.25
cum
cum
cum
761.00
841.00
899.00
cum
cum
770.00
908.00
cum
cum
724.00
883.20
cum
cum
741.00
821.00
A
(i)
(a)
(b)
(ii)
(a)
(b)
(c)
(iii)
(a)
(b)
B
(i)
(a)
(b)
(ii)
(a)
(b)
By Manual Means
Grading- I (Using Screening Crushable type such as Moorum or Gravel)
Using Screening Crushable type such as Moorum or Gravel
Using Screening Type-A (13.2mm Agg.)
Grading- II (Using Screening Crushable type such as Moorum or Gravel)
Using Screening Crushable type such as Moorum or Gravel
Using Screening Type-A (13.2mm Agg.)
Using Screening Type-B (11.2mm Agg.)
Grading- III (Using Screening Crushable type such as Moorum or Gravel)
Using Screening Crushable type such as Moorum or Gravel
Using Screening Type-B (11.2mm Agg.)
By Mechanical Means:
Grading- I (Using Screening Crushable type such as Moorum or Gravel)
Using Screening Crushable type such as Moorum or Gravel
Using Screening Type-A (13.2mm Agg.)
Grading- II (Using Screening Crushable type such as Moorum or Gravel)
Using Screening Crushable type such as Moorum or Gravel
Using Screening Type-A (13.2mm Agg.)
Page 6 of 36
Item
No.
(c)
(iii)
(a)
(b)
4.10
Unit
Rate
cum
879.00
cum
cum
750.00
888.00
cum
197.00
4.11
Penetration Coat Over Top Layer of Crushed Cement Concrete Base (Spraying of bitumen over cleaned dry surface of
crushed cement concrete base at the rate of 25 kg per 10 sqm by a bitumen pressure distributor, spreading of key aggregates at
the rate of 0.13 cum per 10 sqm by a mechanical gritter and rolling the surface as per clause 506.3.8)
sqm
14.00
4.12
Wet Mix Macadam (Providing, laying, spreading and compacting graded stone aggregate to wet mix macadam specification
including premixing the Material with water at OMC in mechanical mix plant carriage of mixed Material by tipper to site, laying in
uniform layers with paver in sub- base / base course on well prepared surface and compacting with vibratory roller to achieve the
desired density.)
cum
939.60
4.13
Construction of Median and Island with Soil Taken from Roadway Cutting (Construction of Median and Island above road
level with approved material deposited at site from roadway cutting and excavation for drain and foundation of other structures,
spread, graded and compacted as per clause 407)
cum
91.00
4.14
Construction of Median and Island with Soil Taken from Borrow Areas (Construction of median and Island above road level
with approved material brought from borrow pits, spread, sloped and compacted as per clause 407)
cum
139.00
4.15
4.16
sqm
#REF!
Crusher Run Macadam Base (Providing crushed stone aggregate, depositing on a prepared surface by hauling vehicles,
spreading and mixing with a motor grader, watering and compacting with a vibratory roller to clause 410 to form a layer of subbase/Base)
4.17
A
(i)
(ii)
(i)
(ii)
cum
cum
By Mixing Plant :
4.18
765.00
798.00
cum
cum
#REF!
#REF!
cum
#VALUE!
CHAPTER-5
BASES AND SURFACE COURSES (BITUMINOUS)
Prime coat (Providing and applying primer coat with bitumen emulsion on prepared surface of granular Base including clearing of
road surface and spraying primer at the rate of 0.60 kg/sqm using mechanical means.)
Tack coat
Providing and applying tack coat with bitumen emulsion using emulsion pressure distributor at the rate of 0.20 kg
per sqm on the prepared bituminous/granular surface cleaned with mechanical broom.
5.1
5.2
sqm
12.00
sqm
4.60
cum
cum
3368.00
3365.00
Bituminous Macadam (Providing and laying bituminous macadam with 100-120 TPH hot mix plant producing an average output
of 75 tonnes per hour using crushed aggregates of specified grading premixed with bituminous binder, transported to site, laid
over a previously prepared surface with paver finisher to the required grade, level and alignment and rolled as per clauses 501.6
and 501.7 to achieve the desired compaction)
5.3
(i)
(ii)
Page 7 of 36
Item
No.
Unit
Rate
Bituminous Penetration Macadam (Construction of penetration macadam over prepared Base by providing a layer of
compacted crushed coarse aggregate using chips spreader with alternate applications of bituminous binder and key aggregates
and rolling with a smooth wheeled steel roller 8-10 tonne capacity to achieve the desired degree of compaction)
5.4
A
B
5.5
50 mm thick
75 mm thick
Built-Up-Spray Grout (Providing, laying and rolling of built-up-spray grout layer over prepared base consisting of a two layer
composite construction of compacted crushed coarse aggregates using motor grader for aggregates. key stone chips spreader
may be used with application of bituminous binder after each layer, and with key aggregates placed on top of the second layer to
serve as a Base conforming to the line, grades and cross-section specified, the compacted layer thickness being 75 mm)
sqm
sqm
169.00
228.00
sqm
141.00
Dense Graded Bituminous Macadam (Providing and laying dense bituminous macadam with 100-120 TPH batch type HMP
producing an average output of 75 tonnes per hour using crushed aggregates of specified grading, premixed with bituminous
binder @ 4.0 to 4.5% by weight of total mix of mix and filler, transporting the hot mix to work site, laying with a hydrostatic paver
finisher with sensor control to the required grade, level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to
achieve the desired compaction as per MoRTH specification clause No. 507 complete in all respects.)
5.6
(i)
(ii)
cum
cum
3849.80
3880.60
(i)
(ii)
cum
cum
4606.00
4834.00
(i)
(ii)
cum
cum
4454.30
5071.00
sqm
sqm
41.90
36.00
sqm
71.00
5.7
5.8
5.9
Case -1
Case - II
5.10
(i)
(ii)
5.11
5.12
(i)
(ii)
Case - I: Mechanical method using Penetration grade Bitumen and HMP of appropriate capacity not less than 75
tonnes/hour .
Case - II: Open-Graded Premix Surfacing using cationic Bitumen Emulsion
Close Graded Premix Surfacing/Mixed Seal Surfacing (Mechanical means using HMP of appropriate capacity not less
than 75 tonnes/hour. Providing, laying and rolling of close-graded premix surfacing material of 20 mm thickness
composed of 11.2 mm to 0.09 mm (Type-a) or 13.2 mm to 0.09 mm (Type-b) aggregates using penetration grade
bitumen to the required line, grade and level to serve as wearing course on a previously prepared base, including
mixing in a suitable plant, laying and rolling with a Smooth wheeled roller 8-10 tonne capacity, and finishing to required
level and grade. )
Seal Coat (Providing and laying seal coat sealing the voids in a bituminous surface laid to the specified levels, grade and cross
fall using Type A and B seal coats)
Case - I : Type A
Case - II : Type B (Providing and laying of premix sand seal coat with HMP of appropriate capacity not less than 75 tonnes/
hours using crushed stone chipping 6.7 mm size and penetration bitumen of suitable grade.)
Page 8 of 36
sqm
#VALUE!
sqm
84.00
sqm
32.00
sqm
25.00
Item
No.
Unit
Rate
5.13
Supply of Stone Aggregates for Pavement Courses (Supply of stone aggregates from approved sources confirming to the
physical requirement, specified in the respective specified clauses, including royalties, fees rents, collection, transportation,
stacking and testing and measured in cum as per clause 514.5 Competitive market rates to be ascertained. Alternatively, rates for
stone crushing given in chapter 1may be adopted, if found economical. In case for supply of aggregates at site are not available,
nearest crusher site may be ascertained. Loading and un-loading charges and cost of carriage may be added to these rates to
arrive at the cost at site.)
cum
5.14
Mastic Asphalt (Providing and laying 25 mm thick mastic asphalt wearing course with paving grade bitumen meeting the
requirements given in table 500-29, prepared by using mastic cooker and laid to required level and slope after cleaning the
surface, including providing antiskid surface with bitumen precoated fine-grained hard stone chipping of 13.2 mm nominal size at
the rate of 0.005cum per 10 sqm and at an approximate spacing of 10 cm center to center in both directions, pressed into surface
when the temperature of surfaces not less than 1000C, protruding 1 mm to 4 mm over mastic surface, all complete as per clause
515.)
sqm
653.00
5.15
Slurry Seal Providing and laying slurry seal consisting of a mixture of fine aggregates, portland cement filler, bituminous emulsion
and water on a road surface including cleaning of surface, mixing of slurry seal in a suitable mobile plant, laying and compacting to
provide even riding surface)
5 mm thickness
3 mm thickness
1.5 mm thickness
Recycling of Bituminous Pavement with Central Recycling Plant (Recycling pavement by cold milling of exiting bituminous
layers, planning the surface after cold milling, reclaiming excavated material to the extent of 30 % of the required quantity, hauling
and stock piling the reclaimed material near the central recycling plant after carrying out necessary checks and evaluation, adding
fresh material including rejuvenators as required, mixing in a hot mix plant, transporting and laying at site and compacting to the
required grade, level and thickness, all as specified in clause 517.)
sqm
sqm
sqm
29.00
20.00
12.00
Fog Spray
1.In case it is decided by the engineer to blind the fog spray, the following may be added
Bituminous Cold Mix ( Including Gravel Emulsion) (Providing, laying and rolling of bituminous cold mix on prepared base
consisting of a mixture of unheated mineral aggregate and emulsified or cutback bitumen, including mixing in a plant of suitable
type and capacity, transporting, laying, compacting and finishing to specified grades and levels.)
sqm
sqm
cum
cum
cum
cum
(i)
(ii)
(iii)
5.16
5.17
added
5.18
(i)
(ii)
(iii)
(iv)
5.19
Modified Binder (Supply of modified binder produced by mixing bitumen with modifier such as natural rubber or crumb rubber or
any other polymer found compatible with bitumen and which allows properties given in clause 521.3 and IRC: SP: 53 blending of
modifier with bitumen to be done either at the refinery or at the site plant capable of producing the modified binder to be delivered
in drums which shall be agitated in melted condition using suitable device before use to ensure uniform dispersion.)
5.20
5.21
(i)
(ii)
Page 9 of 36
cum
cum
#VALUE!
15.00
2.00
#VALUE!
#VALUE!
#VALUE!
#VALUE!
4080.00
tonne
sqm
30.00
sqm
37.00
Descriptions
Unit
Rate
(iii)
Stress Absorbing Membrane (SAM) crack width above 9 mm and cracked area above 50 % (Providing and laying a
single coat of a stress absorbing membrane over a cracked road surface, with crack width above 9 mm and cracked area above
50 % after cleaning with a mechanical broom, using modified binder complying with clause 521, sprayed at the rate of 15 kg per
10 sqm and spreading 11.2 mm crushed stone aggregates @ 0.12 cum per 10 sqm, sweeping the surface for uniform spread of
aggregates and surface finished to conform to clause 902.)
sqm
(iv)
Case - IV : Bitumen Impregnated Geotextile (Providing and laying a bitumen impregnated geotextile layer after cleaning the
road surface, geotextile conforming to requirements of clause 704.3, laid over a tack coat with 1.05 kg per sqm of paving grade
bitumen 80 - 100 penetration and constructed to the requirement of clause 704.4.5)
sqm
#VALUE!
cum
cum
cum
#VALUE!
#VALUE!
#VALUE!
5.22
(i)
(ii)
(iii)
48.00
Recipe Cold Mix (Providing and laying of premix of crushed stone aggregates and emulsion binder, mixed in a batch type cold
mixing plant, laid over prepared surface, by paver finisher, rolled with a pneumatic tyred roller initially and finished with a smooth
steel wheel roller, all as per clause 519.3)
75 mm thickness
40 mm thickness
25 mm thickness
CHAPTER-6
CEMENT CONCRETE PAVEMENTS
6.1
Dry Lean Cement Concrete Sub- base (Construction of dry lean cement concrete Sub- base over a prepared sub-grade with
coarse and fine aggregate conforming to IS: 383, the size of coarse aggregate not exceeding 25 mm, aggregate cement ratio not
to exceed 15:1, aggregate gradation after blending to be as per table 600-1, cement content not to be less than 150 kg/ cum,
optimum moisture content to be determined during trial length construction, concrete strength not to be less than 10 Mpa at 7
days, mixed in a batching plant, transported to site, laid with a paver with electronic sensor, compacting with 8-10 tonnes vibratory
roller, finishing and curing.)
cum
1688.90
6.2
Cement Concrete Pavement (Construction of un-reinforced, dowel jointed, plain cement concrete pavement over a prepared
sub base with 43 grade cement @ 400 kg per cum, coarse and fine aggregate conforming to IS 383, maximum size of coarse
aggregate not exceeding 25 mm, mixed in a batching and mixing plant as per approved mix design, transported to site, laid with a
fixed form or slip form paver, spread, compacted and finished in a continuous operation including provision of contraction,
expansion, construction and longitudinal joints, joint filler, separation membrane, sealant primer, joint sealant, debonding strip,
dowel bar, tie rod, admixtures as approved, curing compound, finishing to lines and grades as per drawing )
cum
3644.10
6.3
Rolled Cement Concrete Base (Construction of rolled cement concrete base course with coarse and fine aggregate conforming
to IS:383, the size of coarse aggregate not exceeding 25 mm with minimum, aggregate cement ratio15:1 and minimum cement
content of 200 kg/cum, aggregate gradation to be as per table 600-4 after blending, mixing in batching plant at optimum moisture
content, transporting to site, laying with a paver with electronic sensor, compacting with 8-10 tonnes smooth wheeled vibratory
roller to achieve, the designed flexural strength, finishing and curing.)
cum
1951.00
6.4
Transition section between rigid and flexible pavement (Due to change in the properties of materials and type of
construction, a gradual changeover from rigid pavement to flexible pavement is desirable to avoid any damage at the butting joint.
After provision of an expansion joint in the cement concrete slab, the thickness of slab should be tapered to 10 cm over a length of
3 m towards the flexible pavement. The deficiency of thickness caused due to tapering of the slab should be made up by the
asphaltic layers.)
6.5
Construction of Base/Sub-base of pavement with lean concrete - fly ash. (Construction of Base/sub-base using cement,
sand, fly ash and coarse aggregates proportioned as per table 4 of IRC: 74/1979 and with water content ratio, slump and
compressive strength as defined in the said table, mix prepared in a batching and mixing plant and compacted with a vibratory
roller 8-10 tonnes capacity within the time limit laid down vide clause 7.6.3 of IRC: 74-1979, construction joints properly formed at
the end of day's work, cured for 14 days, all as specified in IRC: 74-1979 and as per approved plans.)
cum
#VALUE!
6.6
Cement - Fly ash concrete pavement. (Construction reinforced-reinforced, dowel jointed, plain cement concrete pavement over
a prepared sub base with 43 grade cement, coarse and fine aggregate conforming to IS 383, maximum size of coarse aggregate
not exceeding 25 mm, replacing cement by fly ash to the extent of 15% and sand by 10%, mixed in a batching and mixing plant as
per approved mix design, transported to site, laid with a fixed form or slip form paver, spread, compacted and finished in a
continuous operation including provision of contraction, expansion, construction and longitudinal joints, joint filler, separation
membrane, sealant primer, joint sealant, debonding strip, dowel bar, tie rod, admixtures as approved, curing compound, finishing
to lines and grades as per drawing )
cum
#VALUE!
CHAPTER-7
Page 10 of 36
Item
No.
Unit
Rate
7.1
Sub- Surface Drain with Geotextiles (Construction of sub surface drain 200 mm dia using geotextiles treated with carbon black
with physical properties as given in clause 702.2.3 formed in to a stable network and a planar geocomposite structure, joints
wrapped with geotextile to prevent ingress of soil, all as per clause 702 and approved drawings including excavation and
backfilling)
metre
#VALUE!
7.2
Narrow Filter Sub- Surface Drain (Construction of a narrow filter sub- surface drain consisting of porous or perforated pipe laid
in narrow trench surrounded by a geotextile filter fabric, with a minimum of 450 mm overlap of fabric and installed as per clause
702.3 and 309.3.5 including excavation and backfilling)
metre
#VALUE!
7.3
Laying Paving Fabric Beneath a Pavement Overlay (Providing and laying paving fabric with physical requirements as per table
704-2 over a tack coat of paving grade Bitumen 80-100 penetration, laid at the rate of 1 kg per sqm over thoroughly cleaned and
repaired surface to provide a water resistant membrane and crack retarding layer. Paving fabric to be free of wrinkling and folding
and to be laid before cooling of tack coat, brooming and rolling of surface with pneumatic roller to maximise paving fabric contact
with pavement surface)
sqm
#VALUE!
7.4
Laying Boulder Apron in Crates of Synthetic Geogrids (Providing, preparing and laying of geogrid crated apron 1 m x 5 m,
600 mm thick including excavation and backfilling with baffles at 1 metre interval, made with geogrids having characteristics as per
clause 704.2, joining sides with connectors/ring staples, top corners to be tie tensioned, placing of suitable cross interval ties in
layers of 300 mm connecting opposite side with lateral braces and tied with polymer braids to avoid bulging, constructed as per
clause 704.3. filled with stone with minimum size of 200 mm and specific gravity not less than 2.65, packed with stone spalls,
keyed to the foundation recess in case of sloping ground and laid over a layer of geotextile to prevent migration of fines, all as per
clause 704 and laid as per clause 2503.3 and approved design.)
cum
#VALUE!
7.5
Reinforced Earth Retaining Wall (Reinforced earth retaining walls have four main components as under: a) Excavation for
foundation, foundation concrete and cement concrete grooved seating in the foundation for facing elements (facia material). b)
Facia material and its placement. c) Assembling, joining with facing elements and laying of the reinforcing elements. d) Earthfill
with granular material which is to be retained by the wall.)
(i)
(ii)
A
Type 1
Type 2
Type 3
Type 4
Type 5
B
sqm
707.00
metre
metre
metre
metre
metre
sqm
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
63.00
CHAPTER-8
TRAFFIC SIGNS, MARKINGS & OTHER ROAD APPURTENANCES
Cast in Situ Cement Concrete M20 kerb (Construction of cement concrete kerb with top and bottom width 115 and 165 mm
respectively, 250 mm high in M 20 grade PCC on M-10 grade foundation 150 mm thick, foundation having 50 mm projection
beyond kerb stone, kerb stone laid with kerb laying machine, foundation concrete laid manually, all complete as per clause 408)
8.1
A
B
metre
metre
150.00
155.80
A
B
metre
metre
277.00
287.00
8.2
8.3
(i)
Hindi ( Matras commas and the like not to be measured and paid for Half letter shall be counted as half )
Page 11 of 36
cm height
per letter
0.30
Item
No.
(ii)
Unit
cm height
per letter
Rate
0.20
Retro- reflectorised Traffic signs (Providing and fixing of retro- reflectorised cautionary, mandatory and informatory sign as per
IRC :67 made of encapsulated lens type reflective sheeting vide clause 801.3, fixed over aluminium sheeting, 1.5 mm thick
supported on a mild steel angle iron post 75 mm x 75 mm x 6 mm firmly fixed to the ground by means of properly designed
foundation with M15 grade cement concrete 45 cm x 45 cm x 60 cm, 60 cm below ground level as per approved drawing)
8.4
(i)
( ii )
( iii )
( iv )
(v)
(vi )
( vii )
8.5
90 cm equilateral triangle
60 cm equilateral triangle
60 cm circular
80 mm x 60 mm rectangular
60 cm x 45 cm rectangular
60 cm x 60 cm square
90 cm high octagon
Direction and Place Identification signs upto 0.9 sqm size board. (Providing and erecting direction and place identification
retro-reflectorised sign asper IRC:67 made of encapsulated lens type reflective sheeting vide clause 801.3, fixed over aluminium
sheeting, 2 mm thick with area not exceeding 0.9 sqm supported on a mild steel single angle iron post 75 x 75 x 6 mm firmly fixed
to the ground by means of properly designed foundation with M15 grade cement concrete 45 x 45 x 60 cm, 60 cm below ground
level as per approved drawing)
8.6
Direction and Place Identification signs with size more than 0.9 sqm size board. (Providing and erecting direction and place
identification retro- reflectorised sign asper IRC :67 made of encapsulated lens type reflective sheeting vide clause 801.3, fixed
over aluminium sheeting, 2 mm thick with area exceeding 0.9 sqm supported on a mild steel angle iron post 75 mm x 75 mm x 6
mm, 2 Nos. firmly fixed to the ground by means of properly designed foundation with M 15 grade cement concrete45 cm x 45 cm x
60 cm, 60 cm below ground level as per approved drawing)
8.7
Overhead Signs (Providing and erecting overhead signs with a corrosion resistant aluminium alloy sheet reflectorised with high
intensity retro-reflective sheeting of encapsulated lense type with vertical and lateral clearance given in clause 802.2 and 802.3
and installed as per clause 802.7 over a designed support system of aluminium alloy or galvanised steel trestles and trusses of
sections and type as per structural design requirements and approved plans)
A
B
8.8
each
each
each
each
each
each
each
3563.60
2180.80
3086.10
4490.30
2993.40
3634.90
5858.80
sqm
8472.00
sqm
8702.30
tonne
tonne
44981.00
264.10
sqm
31.90
8.9
Painting on Steel Surfaces (Providing and applying two coats of ready mix paint of approved brand on steel surface after
through cleaning of surface to give an even shade)
sqm
27.50
8.10
Painting on Wood Surfaces (Providing and applying two coats of ready mix paint of approved brand on wood surface after
through cleaning of surface to give an even shade)
sqm
31.70
8.11
Painting Lines, Dashes, Arrows etc on Roads in Two Coats on New Work (Painting lines, dashes, arrows etc on roads in
two coats on new work with ready mixed road marking paint conforming to IS:164 on bituminous surface, including cleaning the
surface of all dirt, dust and other foreign matter, demarcation at site and traffic control )
(i)
(ii)
Over 10 cm in width
Up to 10 cm in width
Painting Lines, Dashes, Arrows etc on Roads in Two Coats on Old Work (Painting lines, dashes, arrows etc on roads in two
coats on old work with ready mixed road marking paint confirming to IS: 164 on bituminous surface, including cleaning the surface
of all dirt, dust and other foreign matter, demarcation at site and traffic control )
sqm
sqm
43.50
39.30
(i)
(ii)
Over 10 cm in width
Up to 10 cm in width
Road Marking with Hot Applied Thermoplastic Compound with Reflectorising Glass Beads on Bituminous Surface
(Providing and laying of hot applied thermoplastic compound 2.5 mm thick including reflectorising glass beads @ 250 gms per
sqm area, thickness of 2.5 mm is exclusive of surface applied glass beads as per IRC:35 .The finished surface to be level, uniform
and free from streaks and holes.)
sqm
sqm
29.00
30.00
sqm
557.80
each
1679.30
8.12
8.13
8.14
(i)
Kilo Metre Stone (Reinforced cement concrete M15grade kilometre stone of standard design as per IRC:8-1980, fixing in
position including painting and printing etc)
5th kilometre stone (precast)
Page 12 of 36
Item
No.
(ii)
(iii)
8.15
Unit
Rate
each
each
1021.20
274.80
each
787.00
245.20
8.16
Boundary pillar (Reinforced cement concrete M15 grade boundary pillars of standard design as per IRC:25-1967, fixed in
position including finishing and lettering but excluding painting)
each
8.17
G.I Barbed wire Fencing 1.2 metre high (Providing and fixing 1.2 metres high GI barbed wire fencing with 1.8 m angle iron
posts 40 mm x 40 mm x 6 mm placed every 3 metres center to center founded in M15 grade cement concrete, 0.6 metre below
ground level, every 15th post, last but one end post and corner post shall be strutted on both sides and end post on one side only
and provided with 9 horizontal lines and 2 diagonals interwoven with horizontal wires, fixed with GI staples, turn buckles etc
complete as per clause 807 )
metre
#VALUE!
8.18
G.I Barbed wire Fencing 1.8 metre high (Providing and fixing 1.8 metres high GI barbed wire fencing with 2.4 m angle iron
posts 50 mm x 50 mm x 6 mm placed every 3 metres center to center founded in M15 grade cement concrete, 0.6 metre below
ground level, every 15th post, last but one end post and corner post shall be strutted on both sides and end post on one side only
and provided with 12 horizontal lines and 2 diagonals interwoven with horizontal wires, fixed with GI staples, turn buckles etc
complete as per clause 807 )
metre
#VALUE!
8.19
Fencing with welded steel wire Fabric 75 mm x 50 mm (Suggestive) (Providing 1.20 metre high fencing with angle iron posts
50 mm x 50 mm x 6 mm at 3 metre center to center with 0.40 metre embedded in M15 grade cement concrete, corner, end and
every 10th post to be strutted, provided with welded steel wire fabric of 75 mm x 50 mm mesh or 75 mm x 25 mm mesh and fixed
to iron posts by flat iron 50 x 5 mm and bolts etc. complete in all respects.)
metre
#VALUE!
8.20
Tubular Steel Railing on Medium Weight steel channel ( ISMC series) 100 mm x 50 mm (Providing, fixing and erecting 50
mm dia steel pipe railing in 3 rows duly painted on medium weight steel channels (ISMC series) 100 mm x 50 mm, 1.2 metres high
above ground, 2 m centre to centre, complete as per approved drawings)
metre
2753.00
8.21
Tubular Steel Railing on Precast RCC posts, 1.2 m high above ground level (Providing, fencing and erecting 50 mm dia
painted steel pipe railing in 3 rows on precast M20 grade RCC vertical posts1.8 metres high (1.2 m above GL) with 3 holes 50 mm
dia for pipe, fixed 2 metres centre to, complete as per approved drawing)
metre
2466.00
metre
2230.80
metre
1839.00
Reinforced Cement Concrete Crash Barrier (Provision of an Reinforced cement concrete crash barrier at the edges of the
road, approaches to bridge structures and medians, constructed with M-20 grade concrete with HYSD reinforcement conforming
to IRC:21 and dowel bars 25 mm dia, 450 mm long at expansion joints filled with pre-moulded asphalt filler board, keyed to the
structure on which it is built and installed as per design given in the enclosure to MOST circular No. RW/NH - 33022/1/94-DO III
dated 24 June 1994 as per dimensions in the approved drawing and at locations directed by the Engineer, all as specified)
8.22
(i)
8.23
8.24
M 20 grade concrete
Metal Beam Crash Barrier
Type - A, "W" : Metal Beam Crash Barrier (Providing and erecting a "W" metal beam crash barrier comprising of 3 mm thick
corrugated sheet metal beam rail, 70 cm above road/ground level, fixed on ISMC series channel vertical post, 150 x 75 x 5 mm
spaced 2 m centre to centre, 1.8 m high, 1.1 m below ground/road level, all steel parts and fitments to be galvanised by hot dip
process, all fittings to conform to IS:1367 and IS:1364, metal beam rail to be fixed on the vertical post with a spacer of channel
section 150 x 75 x 5 mm, 330 mm long complete as per clause 810)
Type - B, "THRIE" : Metal Beam Crash Barrier (Providing and erecting a "Thrie" metal beam crash barrier comprising of 3
mm thick corrugated sheet metal beam rail, 85 cm above road/ground level, fixed on ISMC series channel vertical post, 150 x
75 x 5 mm spaced 2 m centre to centre, 2 m high with 1.15 m below ground level, all steel parts and fitments to be galvanised
by hot dip process, all fittings to conform to IS:1367 and IS:1364, metal beam rail to be fixed on the vertical post with a space of
channel section 150 x 75 x 5 mm, 546 mm long complete as per clause 810)
Road Traffic Signals electrically operated (Since it is a ready made item commercially produced and erected by specialised
firm in the electrical and electronic field, rate may be taken based on market enquiry from firms specialised in this field and ISI
certified for the approved design and drawing.)
Page 13 of 36
metre
#VALUE!
Item
No.
Unit
Rate
metre
#VALUE!
Anti - Glare Screen with 25 mm steel pipe framework fixed with circular and rectangular vans (Providing and erecting
an anti - glare screen with 25 mm dia vertical pipes fabricated and framed in the form of panels of one metre length and 1.75
mtr height fixed with circular vane 250 mm dia at top and rectangular vane 600 x 300 mm at the middle, made out of steel sheet
of 3 mm thickness, end vertical pipes of the panel made larger for embedding in foundation concrete, applying 2 coats of paint
on all exposed surfaces, all as per approved design and drawings.)
metre
#VALUE!
Anti - Glare Screen with Rectangular Vane of MS sheet (Providing and erecting anti - glare screen with rectangular vanes
of size 750 x 500 mm made from MS sheet, 3 mm thick and fixed on MS angle 50 x 50 x 6 mm at an angle of 450 to the
direction of flow of traffic, 1.5 m center to center, top edge of the screen 1.75 m above ground level, vertical post firmly
embedded in cement concrete foundation 0.60 m below ground level, applying 2 coats of paint on exposed faces, all complete
as per approved design and drawings)
metre
Flexible Crash Barrier, Wire Rope Safety Barrier (Providing and erecting a wire rope safety barrier with vertical posts of
medium weight RS Joist (ISMB series) 100 mm x 75 mm (11.50 kg/m), 1.50 m long 0.85 m above ground and 0.65 m below
ground level, split at the bottom for better grip, embedded in M 15 grade cement concrete 450 x 450 x 450 mm, 1.50 m center to
center and with 4 horizontal steel wire rope 40 mm dia and anchored at terminal posts 15 m apart. Terminal post to be embedded
in M 15 gradecementconcretefoundation2400 x 450 x 900 mm (depth), strengthened by a strut of RS joist 100 x 75 mm, 2 m long
at 450 inclination and a tie 100 x 8 mm, 1.50 m long at the bottom, all embedded in foundation concrete as per approved design
and drawing, rate excluding excavation and cement concrete.)
8.25
8.26
A
539.00
Street Lighting (Providing and erecting street light mounted on a steel circular hollow pole of standard specifications for street
lighting, 9 m high spaced 40 m apart, 1.8 m overhang on both sides if fixed in the median and on one side if fixed on the footpath,
fitted with sodium vapour lamp and fixed firmly in concrete foundation.)
8.27
(i)
(ii)
8.28
each
each
#VALUE!
#VALUE!
each
#VALUE!
Cable Duct Across the Road (Providing and laying of a reinforced cement concrete pipe duct, 300 mm dia, across the road
(new construction), extending from drain to drain in cuts and toe of slope to toe of slope in fills, constructing head walls at both
ends, providing a minimum fill of granular material over top and sides of RCC pipe as per IRC:98-1997, bedded on a 0.3 m thick
layer of granular material free of rock pieces, outer to outer distance of pipe at least half dia of pipe subject to minimum 450 mm in
case of double and triple row ducts, joints to be made leak proof, invert level of duct to be above higher than ground level to
prevent entry of water and dirt, all as per IRC: 98 - 1997 and approved drawings.)
8.29
(i)
(ii)
(iii)
8.30
8.31
8.32
Traffic Control System and Communication system (Providing a traffic control centre and communication system including
telecommunication facilities and related accessories, CCTV, radar, vehicle detection camera, central computer system These are
specialised item of telecommunication system and are the commercial products. The designer is required to contact the
manufacturers to ascertain market prices. In case of civil works required to be executed for these installations, pricing may be
done as per rates in relevant chapters for quantities derived approved design and drawing.)
8.33
Gantry Mounted Variable Message Sign board (Providing and erecting gantry mounted variable message sign board
electronically operated capable of flashing the desired message over a designed support system of aluminium alloy or galvanised
steel, erected as per approved design and drawings and with lateral clearance as per clause 802.3)
(i)
Page 14 of 36
metre
metre
metre
1685.60
3214.00
4748.00
tonne
44165.00
Item
No.
(ii)
8.34
A
Message Display (Message display board 6 sqm electronically operated with complete electronic fitments for flashing the predetermined messages.)
Traffic Impact Attenuators at Abutments and Piers
With Scrap Tyres (Provision and installation of traffic attenuators at abutment/pier of flyovers bridges using scrap tyres of size
100 x 20 retrieved from trucks laid in 2 rows and 4 tiers, one above the other and tied with 20 mm wire rope as per approved
design and drawings.)
Unit
Rate
sqm
#VALUE!
Using Plastic/Steel Barrel, Filled with Sand (Provision and installation of traffic impact attenuator at abutment/pier of flyovers
bridges using plastic/steel barrels 0.60 m dia and 1.0 m in height, filled with sand in three rows and tied with20 mm steel wire
rope as per approved design and drawings)
sqm
#VALUE!
With HI - DRO cell Sandwich (Patented) ((In this patented HI - DRO cell system, water gets discharged from plastic tubes
on impact over a pre-determined time, thus absorbing the energy))
sqm
#VALUE!
8.35
Road Markers/Road Stud with Lense Reflector (Providing and fixing of road stud 100x 100 mm, die cast in aluminium,
resistant to corrosive effect of salt and grit, fitted with lense reflectors, installed in concrete or asphaltic surface by drilling hole 30
mm upto a depth of 60 mm and bedded in a suitable bituminous grout or epoxy mortar, all as per BS 873 part 4:1973)
each
#VALUE!
8.36
Traffic Cone (Provision of red fluorescent with white reflective sleeve traffic cone made of low density polyethylene (LDPE)
material with a square base of 390 x 390 x 35 mm and a height of 770 mm, 4 kg in weight, placed at 1.5 m interval, all as per BS
873)
each
#VALUE!
8.37
A
B
C
8.38
Roadside Amenities
Rest Areas (Providing plainly furnished accommodation for rest rooms, dormitories, restaurants, stalls, shops, petrol pump,
telephone booth, first aid room, traffic aid post, police assistance booth, including electricity, toilet and sewerage system Pricing
may be done based on current plinth area rates approved by PWD/CPWD/MES for a particular zone. Area is required to be
assessed for specific location as per actual site conditions)
Parking areas and Bus Laybyes for Trucks, Buses and Light vehicles (Pricing of parking areas may be done for the
quantities of various items based on the approved dimensions and pavement design for a particular terrain and soil. Rates for
items may be from respective chapters.)
Lawn (Providing a lawn planted with grass and its maintenance )
Rumble Strips (Provision of 15 nos rumble strips covered with premix bituminous carpet, 15-20 mm high at center, 250 mm wide
placed at 1 m center to center at approved locations to control speed, marked with white strips of road marking paint.)
8.39
Policeman Umbrella (Provision of a 2 m high (floor to roof) umbrella for traffic policeman at road crossings, where necessary,
installed on a raised platform, built on a central support of a steel pipe 100 mm dia, roof made of 25 mm dia steel pipe to provide
covered area of 3 sqm, roofed with CGI sheets, all steel parts to be given 2 coats of paint)
8.40
High Mast Pole Lighting at Interchanges and Flyovers (Providing and erecting a high mast pole lighting with 30 m high hot
dip galvanised mast designed to withstand forces exerted with wind speeds of 180 km per hour with 3 seconds gust, as per
IS:875 (Part 3) - 1978, fitted with a base flange, door at the base of mast with heavy duty internal lock, lantern carriage, suitable
winching arrangement for safe working load of 750 kg and high powered electrically driven power tools for raising and lowering of
lantern carriage, flexible 8 core electric cable, lightening conductor, earthing terminal, and fixing 2 nos aviation obstruction lights
on top of the mast, all complete as per approved design and drawings This is a specialised work and is generally done by firms
who specialise in such jobs. The detailed designs and estimates are submitted by the firms alongwith their tender for checks by
the Department. The cost of this work is required to be worked out based on approved design, drawings and estimate of the
lowest tender. A separate contract for this work is concluded as the contractors for road and bridge works generally donot undertake
8.41
Toll Plaza (The construction, operation and maintenance of Toll Plaza can be broken into separate items of work as under based
on the approved design and drawings:-)
8.42
Safety Devices and signs in Construction Zones (Provision and fixing of traffic signs for limited period at suitable locations in
construction zone comprising of warning zone, approach transition zone, working zone and terminal transition zone with a
minimum distance of 60 cm from the edge of the kerb in case of kerbed roads and 2 to 3 m from the edge of the carriageway in
case of un-kerbed roads, the bottom edge of the lowest sign plate to be not less than 2 m above the road level, fixed on 60 mm x
60 mm x 6 mm angle iron post, founded and installed as per approved design and drawings, removed and disposed of after
completion of construction work, all as per IRC:SP:55-2001)
8.43
Portable Barricade in Construction Zone (Installation of a steel portable barricade with horizontal rail 300 mm wide, 2.5 m in
length fitted on a 'A' frame made with 45 x 45 x 5 mm angle iron section, 1.5 m in height, horizontal rail painted (2 coats) with
yellow and white stripes, 150 mm in width at an angle of 450, 'A' frame painted with 2 coats of yellow paint, complete as per
IRC:SP:55-2001 )
Page 15 of 36
sqm
each
each
1675.00
Item
No.
8.44
A
Unit
Rate
each
2707.00
With Wooden Components (Construction of a permanent type barricade made of wooden components, 1.5 m high from
road level, fitted with 3 horizontal planks 200 mm wide and 3.66 m long on 100 x 100mm wooden vertical post, painted with
yellow and white striups, 150 mm in width at an angle of450, complete as per IRC:SP:55-2001 )
each
With Bricks (Construction of a permanent type barricade made with brick work in mud mortar, 1.5 m high, 4 m long, 600
mm thick, plastered with cement mortar 1:6, painted with yellow and white strips)
each
8.45
Drum Delineator in Construction Zone (Provision of metal drum/empty bitumen drum delineator, 300 mm in diameter, 800
mm high, filled with earth for stability, painted in circumferential strips of alternate black and white 100 mm wide fitted with
reflectors 3 Nos of 7.5 cm dia, all as per IRC:SP:55-2001)
each
#VALUE!
8.46
Flagman (Positioning of a smart flagman with a yellow vest and a yellow cap and a red flag 600 x 600 mm securely fastened to a
staff 1 m in length for guiding the traffic)
each
#VALUE!
#VALUE!
4932.00
CHAPTER-9
PIPE CULVERTS
9.1
PCC 1:3:6 in Foundation (Plain cement concrete 1:3:6 mix with crushed stone aggregate 40 mm nominal size mechanically
mixed, placed in foundation and compacted by vibration including curing for 14 days.)
9.2
Laying Reinforced Cement Concrete Pipe NP4/prestrssed concrete pipe on first class bedding in single row . (Laying
Reinforced cement concrete pipe NP4/prestrssed concrete pipe for culverts on first class bedding of granular material in single
row including fixing collar with cement mortar 1:2 but excluding excavation, protection works, backfilling, concrete and masonry
works in head walls and parapets . )
A
B
9.3
A
B
cum
2131.00
1000 mm dia
1200 mm dia
Laying Reinforced Cement Concrete Pipe NP 4 /prestrssed concrete pipe on first class bedding in double row . (Laying
Reinforced cement concrete pipe NP4 /prestrssed concrete pipe for culverts on first class bedding of granular material in double
row including fixing collar with cement mortar 1:2 but excluding excavation, protection works, backfilling, concrete and masonry
works in head walls and parapets . )
metre
metre
3445.80
4584.30
1000 mm dia
1200 mm dia
metre
metre
6938.10
9218.40
CHAPTER-10
MAINTENANCE OF ROADS
10.1
Restoration of Rain Cuts (Restoration of rain cuts with soil, moorum, gravel or a mixture of these, clearing the loose soil,
benching for 300 mm width, laying fresh material in layers not exceeding 250 mm and compacting with plate compactor or power
rammers to restore the original alignment, levels and slopes)
cum
52.00
10.2
Maintenance of Earthen Shoulder (filling with fresh soil) (Making up loss of material/ irregularities on shoulder to the design
level by adding fresh approved soil and compacting it with appropriate equipment.)
sqm
23.80
10.3
Maintenance of Earth Shoulder (stripping excess soil) (Stripping excess soil from the shoulder surface to achieve the
approved level and compacting with plate compactor)
sqm
7.00
10.4
Filling Pot- holes and Patch Repairs with open - graded Premix surfacing, 20mm. (Removal of all failed material, trimming
of completed excavation to provide firm vertical faces, cleaning of surface, painting of tack coat on the sides and base of
excavation as per clause 503, back filling the pot holes with hot bituminous material as per clause 511, compacting, trimming and
finishing the surface to form a smooth continuous surface, all as per clause 3004.2)
sqm
74.00
10.5
Filling Pot- holes and Patch Repairs with - Bituminous concrete, 40mm. ( Removal of all failed material, trimming of
completed excavation to provide firm vertical faces, cleaning of surface, painting of tack coat on the sides and base of excavation
as per clause 503, back filling the pot holes with hot bituminous material as per clause 504, compacting, trimming and finishing
the surface to form a smooth continuous surface, all as per clause 3004.2)
sqm
sqm
175.00
201.00
metre
1.40
(i)
(ii)
10.6
Page 16 of 36
Item
No.
10.7
10.8 A
B
(i)
(ii)
(iii)
(iv)
C
(i)
(ii)
(iii)
D
(i)
(ii)
10.9
10.10
10.11
10.12
Unit
Dusting (Applying crusher dust to areas of road where bleeding of excess bitumen has occurred.)
Fog Seal (ref item 5.17)
Crack Prevention courses. (ref item 5.21)
Stress Absorbing Membrane (SAM) crack width less than 6 mm
Stress Absorbing Membrane (SAM) with crack width 6 mm to 9 mm
Stress Absorbing Membrane (SAM) crack width above 9 mm and cracked area above 50 %
Bitumen Impregnated Geotextile
Slurry Seal (ref item 5.15)
5 mm thickness
3 mm thickness
1.5 mm thickness
Surface Dressing for maintance works. (ref item 5.9)
19 mm nominal chipping size
13 mm nominal size chipping
Repair of joint Grooves with Epoxy Mortar Repair of spalled joint grooves of contraction joints, longitudinal joints and
expansion joints in concrete pavements using epoxy mortar or epoxy concrete)
Repair of old Joints Sealant (Removal of existing sealant and re sealing of contraction, longitudinal or expansion joints in
concrete pavement with fresh sealant material)
Hill Side Drain Clearance (Removal of earth from the choked hill side drain and disposing it on the valley side manually)
Land Slide Clearance in soil (Clearance of land slides in soil and ordinary rock by a bull-dozer D 80 A-12, 180 HP and disposal
of the same on the valley side)
Rate
sqm
0.90
sqm
16.70
sqm
sqm
sqm
sqm
30.00
37.00
48.00
#VALUE!
sqm
sqm
sqm
27.50
18.90
12.10
sqm
sqm
41.90
35.60
metre
258.20
metre
#VALUE!
metre
9.00
cum
44.00
10.13
Land slide Clearance in Hard Rock Requiring Blasting (Clearing of land slide in hard rock requiring blasting for 50% of the
boulders and disposal of the same on the valley side.)
cum
84.00
10.14
Snow Clearance on Roads with Dozer (Snow clearance from road surface by a bull- dozer 165 Hp and disposing it on the
valley side)
cum
3.00
10.15
Snow Clearance on Roads with Snow Blowers (Snow clearance from road surface by a snow blower and disposing on the
valley side.)
cum
#VALUE!
CHAPTER-11
HORTICULTURE
Spreading of Sludge Farm Yard Manure or/and good Earth (Spreading of sludge farm yard manure or/ and good earth in
required thickness (cost of sludge, farm- yard manure or/and good earth to be paid for separately))
11.1
11.2
(i)
(ii)
11.3
Grassing with ' Doobs' Grass (Grassing with 'Doobs' grass including watering and maintenance of the lawn for 30 days or more
till the grass forms a thick lawn free from weeds and fit for moving including supplying good earth if needed)
In rows 15 cm apart in either direction
In rows 7.5 cm apart in either direction
Making Lawns including Ploughing and Dragging with 'Swagha' Breaking of Clod (Making lawns including ploughing and
breaking of clod, removal of rubbish, dressing and supplying doobs grass roots and planting at 15 cm apart, including supplying
and spreading of farm yard manure at rate of 0.18 cum per 100 sqm)
11.4
Maintenance of Lawns or Turfing of Slopes (Maintenance of lawns or Turfing of slopes (rough grassing)
year including watering etc)
11.5
Turfing Lawns with Fine Grassing including Ploughing, Dressing (Turfing lawns with fine grassing including ploughing,
dressing including breaking of clods, removal of rubbish, dressing and supplying doobs grass roots at 10 cm apart, including
supplying and spreading of farm yard manure at rate of0.6 cum per 100 sqm)
Maintenance of Lawns with Fine Grassing for the First Year
a) Planting Permanent Hedges including Digging of Trenches (Planting permanent hedges including digging of trenches,
60 cm wide and 45 cm deep, refilling the excavated earth mixed with farmyard manure, supplied at the rate of 4.65 cum per 100
metres and supplying and planting hedge plants at 30 cm apart)
11.6
11.7
(b)
a)
11.8
(b)
Page 17 of 36
cum
5.80
sqm
sqm
#VALUE!
#VALUE!
sqm
#VALUE!
sqm
sqm
sqm
112.00
#VALUE!
138.00
metre
#VALUE!
metre
km
km
#VALUE!
#VALUE!
#VALUE!
Descriptions
Unit
Rate
#VALUE!
11.9
Planting of Trees and their Maintenance for one Year (Planting of trees by the road side (Avenue trees) in 0.60 m dia holes,
1 m deep dug in the ground, mixing the soil with decayed farm yard/sludge mannure, planting the saplings, backfilling the trench,
watering, fixing the tree guard and maintaining the plants for one year)
each
11.10
Renovation Lawns including, Weeding, Forking the Ground, Top Dressing with Forked Soil (Renovation lawns
including, weeding, forking the ground, top dressing with forked soil, watering and maintenance the lawns, for 30 days or more,
till the grass forms a thick lawn, free from weeds, and fit for moving and disposal of rubbish as directed, including supplying good
earth, if needed but excluding the cost of well decayed farm yard manure)
sqm
11.11
Supply at Site Well Decayed Farm Yard Manure (Supply at site of work well decayed farm yard manure, from any available
source, approved by the engineer in charge including screening and stacking)
cum
11.12
Supply at Site of Work/ Store - Deoiled Neem Cake (Supply at site of work/ store- deoiled neem cake duly packed in used
gunny bags)
quintal
11.13
11.14
6.00
cum
each
608.00
12.00
11.15
Edging with 2nd class Bricks, laid dry lengthwise (Edging with 2nd class bricks, laid dry lengthwise, including
excavation, refilling, consolidation, with a hand packing and spreading nearly surplus earth within a lead of 50
metres)
metre
11.16
Making Tree Guard 53 cm dia and 1.3 m high as per design from empty bitumen drum (Making tree guard 53 cm dia and
1.3 m high as per design from empty bitumen drum, slit suitably to permit sun and air, (supplied by the department at stock issue
rate) including providing and fixing 2 nos MS sheet rings 50 x 0.5 mm with rivets, complete in all respect)
each
#VALUE!
11.17
Making Tree Guard 53 cm dia and 2 metres high as per design from empty bitumen drums (Making tree guard 53 cm dia
and 2 metres high as per design from empty bitumen drums, slit suitably to permit sun and air, ( supplied by the department at
stock issue rate) including providing and fixing four legs 40 cm long of 30 x 3 mm MS riveted to tree guard and providing and
fixing 2 nos MS sheet rings 50 x 0.5 mm with rivets complete in all respects)
each
#VALUE!
11.18
Wrought Iron and Mild Steel Welded Work (Wrought iron and mild steel welded work) (using angles, square bars, tees
and channel grills, grating frames, gates and tree guards of any size and design etc. including cost of screens and welding rods
or bolts and nuts complete fixed in position but without the cost of excavation and concrete for fixing which will be paid separately)
quintal
4437.70
11.19
Tree Guard with MS Iron (Providing and fixing MS iron tree guard 60 cm dia and 2 metre high above ground level formed of 4
Nos (25 x 6 mm) and 8 Nos (25 x 3 mm) vertical MS riveted to 3 Nos (25 x 6 mm) iron rings in two halves, bolted together with 8
mm dia and 30 mm long bolts including painting two coats with paint of approved brand over a coat of priming, complete in all
respects.)
each tree
guard
1215.60
11.20
Tree Guard with MS Angle Iron and Steel Wire (Providing and fixing tree guard 0.60 metre square, 2.00 metre high fabricated
each tree
with MS angle iron 30 x 30 x 3 mm, MS iron 25 x 3 mm and steel wire3 mm dia welded and fabricated as per design in two halves
guard
bolted together)
1730.30
11.21
Compensatory Afforestation (Planting trees as compensatory afforestation at the rate of 290 trees per hectare at a spacing of
6 m by grubbing and leveling the ground upto a depth of 150 mm, digging holes 0.9 m dia, 1 m deep, mixing farm yard/sludge
manure with soil, planting of sapling 2 m high with 25 cm dia stem, backfilling the hole and watering)
hectare
#VALUE!
CHAPTER-12
FOUNDATIONS
12.1
I
A
(i)
(ii)
(iii)
B
Excavation for Structures (Earth work in excavation of foundation of structures as per drawing and technical specification,
including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and
bottom and backfilling with approved material.)
Ordinary soil
Manual Means
upto 3 m depth
3 m to 6 m depth
Above 6 m depth
Mechanical Means
cum
cum
cum
Page 18 of 36
34.00
43.00
58.00
Item
No.
(i)
(ii)
(iii)
II
A
(i)
B
III
A
IV
A
V
(i)
A
B
VI
12.2
12.3
12.4
12.5
12.6 A
B
C
D
12.7
(a)
(b)
12.8
A
B
C
Case I
Case II
D
Case I
Case II
E
Case I
Case II
F
Case I
Case II
G
Case I
Case II
H
Case I
Case II
Unit
Depth upto 3 m
Depth 3 m to 6 m
Depth above 6m
Ordinary rock (not requiring blasting)
Manual Means
Depth upto 3 m
Mechanical Means
Hard rock ( requiring blasting )
Manual Means
Hard rock ( blasting prohibited )
Mechanical Means
Marshy soil
upto 3 m depth
Manual means
Mechanical Means
Back Filling in Marshy Foundation Pits
Filling Annular Space Around Footing in Rock (Lean cement concrete 1:3:6 nominal mix. Rate may be taken as per items
13.4.)
Sand Filling in Foundation Trenches as per Drawing & Technical Specification
PCC 1:3:6 in Foundation (Plain cement concrete 1:3:6 nominal mix in foundation with crushed stone aggregate 40 mm nominal
size mechanically mixed, placed in foundation and compacted by vibration including curing for 14 days.)
Brick masonry work in cement mortar 1:3 in foundation complete excluding pointing and plastering, as per drawing
and technical specifications
Cement mortar1:3 (1cement :3 sand)
Cement mortar1:2 (1cement :2 sand)
Cement mortar1:4 (1cement :4 sand)
Cement mortar1:6 (1cement :6 sand)
Stone masonry work in cement mortar 1:3 in foundation complete as drawing and Technical Specification
Square Rubble Coursed rubble masonry( first sort )
Random Rubble Masonry
Plain/Reinforced cement concrete in open foundation complete as per drawing and technical specifications
PCC Grade M15
PCC Grade M20
RCC Grade M20
Using concrete mixer
With Batching Plant, Transit Mixer and Concrete Pump
PCC Grade M25
Using concrete Mixer
With Batching Plant, Transit Mixer and Concrete Pump
RCC Grade M25
Using concrete Mixer
With Batching Plant, Transit Mixer and Concrete Pump
PCC Grade M30
Using Concrete Mixer
Using Batching Plant, Transit Mixer and Concrete Pump
RCC Grade M30
Using Concrete Mixer
Using Batching Plant, Transit Mixer and Concrete Pump
RCC Grade M35
Using Concrete Mixer
Using Batching Plant, Transit Mixer and Concrete Pump
Page 19 of 36
Rate
cum
cum
cum
30.90
35.40
42.30
cum
cum
48.00
40.00
cum
187.00
cum
211.00
cum
cum
cum
178.00
68.00
150.00
cum
258.50
cum
2367.60
cum
2272.00
cum
2467.00
cum
cum
cum
3162.00
2007.00
1533.00
cum
cum
2699.00
2691.00
cum
cum
2715.70
3161.30
cum
cum
3243.00
3266.60
cum
cum
3487.00
3513.00
cum
cum
3573.00
3596.20
cum
cum
3515.00
3537.10
cum
cum
3584.00
3608.60
cum
cum
3659.00
3682.90
Item
No.
12.9
A
B
C
12.10
12.11
A
(i)
Case I
Case II
(ii)
Case I
Case II
(iii)
Case I
Case II
B
(I)
(ii)
(iii)
Case I
Case II
(iv)
Case I
Case II
(v)
Case I
Case II
(vi)
Case I
Case II
(vii)
Case I
Case II
(viii)
Case I
Case II
(ix)
C
(i)
Case I
Case II
(ii)
Case I
Case II
(iii)
Case I
Case II
Unit
Rate
each
each
24577.00
#VALUE!
metre
1524.00
tonne
51906.00
cum
cum
3742.00
3769.00
cum
cum
4132.00
4160.00
cum
cum
4263.00
4398.00
cum
cum
2874.00
3344.00
cum
cum
3430.00
3455.00
cum
cum
3697.00
3725.00
cum
cum
3788.00
3813.00
cum
cum
3736.00
3759.00
cum
cum
3809.00
3835.00
cum
cum
3907.00
4031.00
4084.00
cum
cum
3530.00
3488.00
cum
cum
3720.00
3676.00
cum
cum
3757.00
3715.00
Providing and constructing temporary island 16 m diameter for construction of well foundation for 8m dia. Well.
Assuming depth of water 1.0 m and height of island to be 1.25m.
Assuming depth of water 4.0 m and height of island 4.5 m.
Providing and constructing one span service road to reach island location from one pier location to another pier
location
Providing and laying cutting edge of mild steel weighing 40 kg per metre for well foundation complete as per drawing
and technical specification.
Plain/Reinforced cement concrete, in well foundation complete as per drawing and technical specification
Well curb
RCC M20 Grade
Using concrete mixer
With Batching Plant, Transit Mixer and Concrete Pump
RCC M25 Grade
Using concrete mixer
With Batching Plant, Transit Mixer and Concrete Pump
RCC M35 Grade
Using concrete mixer
With Batching Plant, Transit Mixer and Concrete Pump
Well steining
PCC M15 Grade
PCC M20 Grade
RCC M20 Grade
Using concrete mixer
With Batching Plant, Transit Mixer and Concrete Pump
PCC M25 Grade
Using concrete mixer
With Batching Plant, Transit Mixer and Concrete Pump
RCC M25 Grade
Using concrete mixer
With Batching Plant, Transit Mixer and Concrete Pump
PCC M30 Grade
Using concrete mixer
With Batching Plant, Transit Mixer and Concrete Pump
RCC M30 Grade
Page 20 of 36
Descriptions
PCC Grade M35
Using Concrete Mixer
Using Batching Plant, Transit Mixer and Crane/concrete pump
Intermediate plug
Grade M20 PCC
Using Concrete Mixer
Using Batching Plant, Transit Mixer and Crane/concrete pump
Grade M25 PCC
Using Concrete Mixer
Using Batching Plant, Transit Mixer and Crane/concrete pump
Grade M30 PCC
Using Concrete Mixer
Using Batching Plant, Transit Mixer and Crane/concrete pump
Top plug
Grade M15 PCC
Using Concrete Mixer
Grade M20 PCC
Using Concrete Mixer
Grade M25 PCC
Using Concrete Mixer
Using Batching Plant, Transit Mixer and Crane/concrete pump
Grade M30 PCC
Using Concrete Mixer
Using Batching Plant, Transit Mixer and Crane/concrete pump
Well cap
RCC Grade M20
Using concrete Mixer
Using Batching Plant, Transit Mixer and Concrete Pump
RCC Grade M25
Using concrete Mixer
Using Batching Plant, Transit Mixer and Concrete Pump
RCC Grade M30
Using Concrete Mixer
Using Batching Plant, Transit Mixer and Concrete Pump
RCC Grade M35
Using Concrete Mixer
Using Batching Plant, Transit Mixer and Concrete Pump
RCC M40 Grade
Sinking of 6 m external diameter well ( other than pneumatic method of sinking ) through all types of strata namely sandy
soil, clayey soil and rock as shown against each case, complete as per drawing and technical specifications. Depth of
sinking is reckoned from bed level.
Sandy soil
Depth below bed level upto 3.0 M
Beyond 3m upto 10m depth
Beyond 10m upto 20m
Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter
Beyond 20m upto 30 m
Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter
Add 20% of cost for Kentledge including supports, loading arrangement and Labour .
Beyond 30m upto 40 m
Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter
Add 20% of cost for Kentledge including supports, loading arrangement and Labour .
Page 21 of 36
Unit
Rate
cum
cum
3842.00
3798.00
cum
cum
3378.00
3339.00
cum
cum
3559.00
3518.00
cum
cum
3594.00
3555.00
cum
2612.00
cum
3040.00
cum
cum
3361.00
3386.00
cum
cum
3396.00
3418.00
cum
cum
3207.00
3229.00
cum
cum
3573.00
3597.00
cum
cum
3584.00
3608.00
cum
cum
cum
3659.00
3683.00
3854.00
metre
metre
1979.00
2874.00
metre
3796.00
metre
7119.00
8542.00
metre
metre
16912.00
20295.00
Item
No.
B
(i)
(ii)
(iii)
a
b
(iv)
a
b
c
(v)
a
b
c
C
(i)
D
(i)
12.13
A
(i)
(ii)
(iii)
a
(iv)
a
b
(v)
a
b
B
(I)
(ii)
(iii)
a
b
(iv)
a
b
c
(v)
a
b
c
C
(i)
D
(i)
Page 22 of 36
Unit
Rate
metre
metre
2877.00
6352.00
metre
metre
8390.00
8809.00
metre
metre
metre
15737.00
20655.00
19671.00
metre
metre
metre
37390.00
47112.00
44868.00
metre
7594.00
metre
8699.00
metre
metre
6053.00
4167.00
metre
5503.00
metre
metre
10322.00
12386.00
metre
metre
24525.00
29430.00
metre
metre
4167.00
6037.00
metre
metre
7973.00
8372.00
metre
metre
metre
14956.00
19630.00
18695.00
metre
metre
35534.00
44773.00
42641.00
metre
6988.00
metre
10070.00
Item
No.
Unit
Rate
metre
metre
3768.00
4666.00
metre
6163.00
metre
metre
11561.00
13873.00
metre
metre
4064.00
4876.00
metre
metre
5095.00
6737.00
metre
metre
8897.00
9342.00
metre
metre
metre
16689.00
21905.00
20861.00
metre
metre
metre
39651.00
49961.00
47581.00
metre
7753.00
metre
9999.00
metre
metre
3799.00
5127.00
metre
6772.00
metre
metre
12703.00
15244.00
metre
metre
30179.00
36215.00
metre
metre
5360.00
7272.00
metre
metre
9605.00
10085.00
Sinking of 8 m external diameter well ( other than pneumatic method of sinking ) through all types of strata namely sandy
soil, clayey soil and rock as shown against each case, complete as per drawing and technical specifications. Depth of
sinking is reckoned from bed level.
12.14
A
(i)
(ii)
(iii)
a
(iv)
a
b
(v)
a
b
B
(i)
(ii)
(iii)
a
b
(iv)
a
b
c
(v)
a
b
c
C
(i)
D
(i)
12.15
A
(i)
(ii)
(iii)
a
(iv)
a
b
(v)
a
b
B
(i)
(ii)
(iii)
a
b
Sandy soil
Depth below bed level upto 3.0 M
Beyond 3m upto 10m depth
Beyond 10m upto 20m
Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter
Beyond 20m upto 30 m
Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter
Add 20% of cost for Kentledge including supports, loading arrangement and Labour .
Beyond 30m upto 40 m
Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter
Add 20% of cost for Kentledge including supports, loading arrangement, and Labour etc.
Clayey soil ( 8m dia. Well )
Depth upto 3.0 M
Beyond 3m upto 10m depth
Beyond 10 m upto 20 m
Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter
Add for dewatering @ 5% of cost, if required.
Beyond 20m upto 30 m
Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter
Add 5% of cost for dewatering on the cost, if required
Add 25% of cost for Kentledge including supports, loading arrangement and Labour ).
Beyond 30m upto 40 m
Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter
Add 5% of cost for dewatering, if required
Add 20% of cost for Kentledge including supports, loading arrangement and Labour).
Soft rock ( 8m dia well )
Depth in soft rock strata upto 3m
Hard rock ( 8m dia well )
Depth in hard rock strata upto 3 m
Sinking of 9 m external diameter well ( other than pneumatic method of sinking ) through all types of strata namely sandy
soil, clayey soil and rock as shown against each case, complete as per drawing and technical specifications. Depth of
sinking is reckoned from bed level.
Sandy soil
Depth below bed level upto 3.0 M
Beyond 3m upto 10m depth
Beyond 10m upto 20m
Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter
Beyond 20m upto 30 m
Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter
Add 20% of cost for Kentledge including supports, loading arrangement and Labour .
Beyond 30m upto 40 m
Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter
Add 20% of cost for Kentledge including supports, loading arrangement, and Labour etc.
Clayey soil ( 9m dia. Well )
Depth below bed level upto 3.0 M
Beyond 3m upto 10m depth
Beyond 10 m upto 20 m
Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter
Add for dewatering @ 5% of cost, if required.
Page 23 of 36
Item
No.
(iv)
a
b
c
(v)
a
b
c
C
(i)
D
(i)
12.16
A
(i)
(ii)
(iii)
a
(iv)
a
b
(v)
a
b
B
(i)
(ii)
(iii)
a
b
(iv)
a
'b
c
(v)
a
b
c
C
(i)
D
(i)
12.17
A
(i)
(ii)
(iii)
a
Unit
Page 24 of 36
Rate
metre
metre
metre
18016.00
23646.00
22520.00
metre
metre
metre
42805.00
53934.00
51366.00
metre
9847.00
metre
11818.00
metre
metre
4628.00
5394.00
metre
7122.00
metre
metre
13358.00
16029.00
metre
metre
31735.00
38082.00
metre
metre
5801.00
7080.00
metre
metre
9350.00
9818.00
metre
metre
metre
17539.00
23021.00
21924.00
metre
metre
41672.00
52506.00
50006.00
metre
10066.00
metre
13829.00
metre
metre
10808.00
8054.00
metre
10636.00
Item
No.
(iv)
a
b
(v)
a
b
B
(i)
(ii)
(iii)
a
b
(iv)
a
b
c
(v)
a
b
c
C
(i)
D
(i)
12.18
A
(i)
(ii)
(iii)
a
(iv)
a
b
(v)
a
b
B
(i)
(ii)
(iii)
a
b
(iv)
a
b
c
(v)
a
b
c
Unit
Page 25 of 36
Rate
metre
metre
19952.00
23942.00
metre
metre
47403.00
56883.00
metre
metre
9651.00
14507.00
metre
metre
19160.00
20118.00
metre
metre
metre
35939.00
47169.00
44923.00
metre
metre
metre
85383.00
107582.00
102459.00
metre
22575.00
metre
31243.00
metre
metre
22084.00
24497.00
metre
32353.00
metre
metre
60685.00
72822.00
metre
metre
144179.00
173014.00
metre
metre
23814.00
37027.00
metre
metre
48901.00
51346.00
metre
metre
metre
91724.00
120388.00
114655.00
metre
metre
metre
217923.00
274583.00
261508.00
Item
No.
C
(i)
D
(i)
12.19
A
(i)
(ii)
(iii)
a
(iv)
a
b
(v)
a
b
B
(i)
(ii)
(iii)
a
b
(iv)
a
b
c
(v)
a
b
c
C
(i)
D
(i)
12.20
12.21
12.22
Unit
Sandy soil
Depth from bed level upto 3.0 M
Beyond 3m upto 10m depth
Beyond 10m upto 20m
Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter
Beyond 20m upto 30 m
Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter
Add 20% of cost for Kentledge including supports, loading arrangement and Labour .
Beyond 30m upto 40 m
Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter
Add 20% of cost for Kentledge including supports, loading arrangement, and Labour etc.
Clayey soil (Twin D Type Well )
Depth below bed level upto 3.0 M
Beyond 3m upto 10m depth
Beyond 10 m upto 20 m
Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter
Add for dewatering @ 5% of cost, if required.
Beyond 20m upto 30 m
Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter
Add 5% of cost for dewatering on the cost, if required
Add 25% of cost for Kentledge including supports, loading arrangement and Labour ).
Beyond 30m upto 40 m
Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter
Add 5% of cost for dewatering, if required
Add 20% of cost for Kentledge including supports, loading arrangement and Labour).
Soft rock (Twin D Type well )
Depth of soft rock strata upto 3m
Hard rock (Twin D Type well )
Depth of hard rock strata upto 3 m
Pneumatic sinking of wells with equipment of approved design, drawing and specifications worked by competent and
trained personnel and comprising of compression and decompression chambers, reducers, two air locks separately
for men and plant & materials, arrangement for supply of fresh air to working chambers, check valves, exhaust
valves, shafts made from steel plates of riveted construction not less than 6 mm thick to withstand an air pressure of
0.50 MPa, controlled blasting of hard rock where required, staircases and 1 m wide landing plate forms with railing,
arrangement for compression and decompression, electric lighting of 50 V maximum, proper rooms for rest and
medical examinations and compliance with safety precautions as per IS:4138, all as per clause1207.6 of MoRTH
Specifications.
Sand filling in wells complete as per drawing and technical specifications
Providing steel liner 10 mm thick for curbs and 6mm thick for steining of wells including fabricating and setting out as
per detailed drawing
Rate
metre
53546.00
metre
73004.00
metre
metre
5024.00
5401.00
metre
7134.00
metre
metre
13381.00
16057.00
metre
metre
31791.00
38150.00
metre
metre
5824.00
7862.00
metre
metre
10383.00
10903.00
metre
metre
metre
19478.00
25565.00
24348.00
metre
metre
metre
46278.00
58311.00
55534.00
metre
11702.00
metre
14878.00
cum
258.00
tonne
47612.00
12.23
Bored cast-in-situ M35 grade R.C.C. pile excluding reinforcement complete as per drawing and technical specifications
and removal of excavated earth with all lifts and lead upto 1000 m. (Pile diameter-750 mm)
metre
3651.50
12.24
Bored cast-in-situ M35 grade R.C.C. pile excluding reinforcement complete as per drawing and technical specifications
and removal of excavated earth with all lifts and lead upto 1000 m. (Pile diameter-1000 mm)
metre
5976.00
Page 26 of 36
Item
No.
Unit
Rate
12.25
Bored cast-in-situ M35 grade R.C.C. pile excluding reinforcement complete as per drawing and technical specifications
and removal of excavated earth with all lifts and lead upto 1000 m. (Pile diameter-1200 mm)
metre
7650.50
12.26
Driven cast-in-place vertical M35 grade R.C.C. pile excluding reinforcement complete as per drawing and & Technical
Specification (Pile diameter - 750 mm)
metre
3094.00
12.27
Driven cast-in-place vertical M35 grade R.C.C. piles excluding reinforcement complete as per drawing and & Technical
Specification (Pile diameter - 1000 mm)
metre
4879.00
12.28
Driven cast-in-place vertical M35 grade R.C.C. piles excluding reinforcement complete as per drawing and & Technical
Specification (Pile diameter - 1200 mm)
metre
7135.00
12.29
Driven precast vertical M35 grade R.C.C. piles excluding reinforcement complete as per drawing and & Technical
Specification (Pile Diameter=500 mm)
metre
#VALUE!
12.30
Driven precast vertical M35 grade R.C.C. piles excluding reinforcement complete as per drawing and & Technical
Specification (Pile Diameter=750 mm)
metre
#VALUE!
12.31
Driven precast vertical M35 grade R.C.C. piles excluding reinforcement complete as per drawing and & Technical
Specification (Pile Diameter=1000 mm)
metre
#VALUE!
12.32
Driven precast vertical M35 grade R.C.C. piles excluding reinforcement complete as per drawing and & Technical
Specification (Size of pile - 300 mm x 300 mm)
metre
#VALUE!
12.33
Driven precast vertical M35 grade R.C.C. piles excluding reinforcement complete as per drawing and & Technical
Specification (Size of pile - 500 mm x 500 mm)
metre
#VALUE!
12.34
Driven precast vertical M35 grade R.C.C. piles excluding reinforcement complete as per drawing and & Technical
Specification (Size of pile - 750 mm x 750 mm)
metre
#VALUE!
12.35
Driven vertical steel piles complete as per drawing and & Technical Specification (Section of the pile - H Section steel
column 400 x 250 mm (ISHB Series) )
metre
#VALUE!
metre
#VALUE!
12.36
12.37
12.38
A
(i)
(ii)
B
(i)
(ii)
C
(i)
(ii)
D
(i)
(ii)
12.39
12.40
Driven vertical steel piles complete as per drawing and & Technical Specification (Section of the pile - H Section steel
column 450 x 250 mm (ISHB Series) )
Pile load test on single vertical pile in accordance with IS:2911(Part-IV)
Cement concrete for reinforced concrete in pile cap complete as per drawing and Technical Specification
RCC Grade M20
Using Concrete Mixer
Using Batching Plant, Transit Mixer and Concrete Pump
RCC Grade M25
Using concrete mixer.
Using Batching Plant, Transit Mixer and Concrete Pump
RCC Grade M30
Using concrete mixer.
Using Batching Plant, Transit Mixer and Concrete Pump
RCC Grade M35
Using concrete mixer.
Using Batching Plant, Transit Mixer and Concrete Pump
Levelling course for Pile cap
Supplying, fitting and placing un-coated HYSD bar reinforcement in foundation complete as per drawing and
technical specifications
Supplying, fitting and placing un-coated Mild steel reinforcement complete in foundation as per drawing and technical
specification
12.41
cum
cum
3212.00
3246.00
cum
cum
3563.00
3597.00
cum
cum
3607.00
3641.00
cum
cum
cum
3699.00
3733.60
2609.90
tonne
42613.70
tonne
42696.00
cum
2304.40
sqm
sqm
21.40
58.50
cum
cum
2792.90
2803.00
CHAPTER-13
SUB-STRUCTURE
Brick masonry work in 1:3 in sub-structure complete excluding pointing and plastering, as per drawing and technical
specifications
13.1
13.2
13.3
13.4
A
B
Pointing with cement mortar (1:3 ) on brick work in substructure as per Technical specifications
Plastering with cement mortar (1:3 ) on brick work in sub-structure as per Technical specifications
Stone masonry work in cement mortar 1:3 for substructure complete as per drawing and Technical Specifications
Random Rubble Masonry
Coursed rubble masonry (first sort )
Page 27 of 36
Item
No.
C
13.5
A
(p)
B
(p)
C
(p)
Case I
Case II
(q)
Case I
Case II
(r)
Case I
Case II
D
(p)
Case I
Case II
(q)
Case I
Case II
(r)
Case I
Case II
E
(p)
Case I
Case II
(q)
Case I
Case II
(r)
Case I
Case II
F
(p)
Case I
Case II
(q)
Case I
Case II
(r)
Case I
Case II
G
(p)
Case I
Case II
(q)
Case I
Page 28 of 36
Unit
Rate
cum
3154.00
cum
2873.50
cum
3344.00
cum
cum
3697.00
3724.80
cum
cum
3832.00
3860.00
cum
cum
4000.00
4030.00
cum
cum
3736.00
3759.40
cum
cum
3871.00
3896.00
cum
cum
4041.00
4067.00
cum
cum
3430.40
3455.20
cum
cum
3555.00
3581.00
cum
cum
3711.00
3738.00
cum
cum
3788.00
3813.00
cum
cum
3912.00
3938.00
cum
cum
4098.00
4125.00
cum
cum
3809.00
3835.00
cum
3917.00
Descriptions
With Batching Plant, Transit Mixer and Concrete Pump
Height above 10m
Using concrete Mixer
With Batching Plant, Transit Mixer and Concrete Pump
RCC Grade M35
Height upto 5m
Using concrete Mixer
With Batching Plant, Transit Mixer and Concrete Pump
Height 5m to 10m
Using concrete Mixer
With Batching Plant, Transit Mixer and Concrete Pump
Height above 10m
Using concrete Mixer
With Batching Plant, Transit Mixer and Concrete Pump
Supplying, fitting and placing HYSD bar reinforcement in sub-structure complete as per drawing and technical
specifications
Unit
Rate
cum
3943.00
cum
cum
4069.00
4097.00
cum
cum
3907.00
4031.30
cum
cum
3993.00
4119.00
cum
cum
4120.00
4251.00
tonne
42653.60
13.7
Supplying, fitting and placing Mild steel reinforcement complete in sub-structure as per drawing and technical
specification
tonne
42489.00
13.8
Providing weep holes in Brick masonry/Plain/Reinforced concrete abutment, wing wall/return wall with 100 mm dia AC
pipe, extending through the full width of the structure with slope of 1V :20H towards drawing foce. Complete as per
drawing and Technical specifications
each
99.60
cum
cum
325.70
334.30
cum
1049.90
13.9
A
B
13.10
Back filling behind abutment, wing wall and return wall complete as per drawing and Technical specification
Granular material
Sandy material
Providing and laying of Filter media with granular materials/stone crushed aggregates satisfying the requirements laid
down in clause 2504.2.2. of MoRTH specifications to a thickness of not less than 600 mm with smaller size towards the
soil and bigger size towards the wall and provided over the entire surface behind abutment, wing wall and return wall
to the full height compacted to a firm condition complete as per drawing and technical specification.
13.11
Supplying, fitting and fixing in position true to line and level cast steel rocker bearing conforming to IRC: 83(Pt.-1)
section IX and clause 2003 of MoRTH specifications complete including all accessories as per drawing and Technical
Specifications.
tonne
capacity
#VALUE!
13.12
Supplying, fitting and fixing in position true to line and level forged steel roller bearing conforming to IRC: 83(Pt.-1)
section IX and clause 2003 of MoRTH specifications complete including all accessories as per drawing and Technical
Specifications.
tonne
capacity
#VALUE!
13.13
Supplying, fitting and fixing in position true to line and level sliding plate bearing with PTFE surface sliding on
stainless steel complete including all accessories as per drawing and Technical Specifications and BS: 5400, section
9.1 & 9.2 (for PTFE) and clause 2004 of MoRTH Specifications.
tonne
capacity
13.14
Supplying, fitting and fixing in position true to line and level elastomeric bearing conforming to IRC: 83 (Part-II) section
IX and clause 2005 of MoRTH specifications complete including all accessories as per drawing and Technical
Specifications.
13.15
Supplying, fitting and fixing in position true to line and level sliding plate bearing with stainless steel plate sliding on
stainless steel plate with mild steel matrix complete including all accessories as per drawing and Technical
Specifications.
13.16
Supplying, fitting and fixing in position true to line and level POT-PTFE bearing consisting of a metal piston supported
by a disc or unreinforced elastomer confined within a metal cylinder, sealing rings, dust seals, PTFE surface sliding
against stainless steel mating surface, completre assembly to be of cast steel/fabricated structural steel, metal and
elastomer elements to be as per IRC: 83 part-I & II respectively and other parts conforming to BS: 5400, section 9.1 &
9.2 and clause 2006 of MoRTH Specifications complete asper drawing and approved technical specifications.
CHAPTER-14
SUPER-STRUCTURE
Page 29 of 36
cubic
centimetre
tonne
capacity
tonne
capacity
502.00
1.60
#VALUE!
102.40
Descriptions
Unit
Rate
cum
cum
cum
3700.00
3855.00
4009.00
cum
cum
cum
3855.00
4009.00
4163.00
cum
cum
cum
3726.20
3881.00
4037.00
cum
cum
cum
3881.40
4036.70
4191.90
cum
cum
cum
4105.00
4276.00
4447.00
cum
cum
cum
4276.00
4447.00
4618.00
cum
cum
cum
4134.90
4307.20
4479.40
cum
cum
cum
4307.00
4479.00
4652.00
Furnishing and Placing Reinforced/Prestressed cement concrete in super-structure as per drawing and Technical
Specification
RCC Grade M20
Using Concrete Mixer
Page 30 of 36
Descriptions
For solid slab super-structure, 20-30% of (a+b+c)
Height upto 5m
Height 5m to 10m
Height above 10m
For T-beam & slab, 25-35% of (a+b+c)
Height upto 5m
Height 5m to 10m
Height above 10m
Using Batching Plant, Transit Mixer and Concrete Pump.
Page 31 of 36
Unit
Rate
cum
cum
cum
4163.00
4337.00
4510.00
cum
cum
cum
4337.00
4510.00
4684.00
cum
cum
cum
4185.40
4359.80
4534.00
cum
cum
cum
4360.00
4534.00
4709.00
cum
cum
cum
4199.00
4377.00
4555.00
cum
cum
cum
4377.00
4555.00
4733.00
cum
cum
cum
4911.00
5267.00
5622.00
cum
cum
cum
4220.00
4399.00
4578.00
cum
cum
cum
4399.00
4578.00
4757.00
cum
cum
cum
4935.00
5293.00
5651.00
Descriptions
Unit
Rate
cum
cum
cum
4448.00
4634.00
4819.00
cum
cum
cum
4634.00
4819.00
5004.00
cum
cum
cum
4383.80
4569.50
4755.00
cum
cum
cum
4570.00
4755.00
4941.00
cum
cum
cum
5127.00
5498.00
5870.00
cum
cum
cum
4554.00
4750.00
4946.00
cum
cum
cum
4750.00
4946.00
5143.00
cum
cum
cum
5339.00
5732.00
6124.00
cum
cum
cum
5503.00
5910.00
6318.00
cum
cum
cum
5821.00
6252.00
6683.53
tonne
43037.70
Page 32 of 36
Item
No.
Unit
Rate
14.3
High tensile steel wires/strands including all accessories for stressing, stressing operations and grouting complete as
per drawing and Technical Specifications
tonne
69481.20
14.4
Providing and laying Cement concrete wearing coat M-30 grade including reinforcement complete as per drawing and
Technical Specifications
cum
6729.50
14.5
Mastic Asphalt (Providing and laying 12 mm thick mastic asphalt wearing course on top of deck slab excluding prime coat with
paving grade bitumen meeting the requirements given in table 500-29, prepared by using mastic cooker and laid to required level
and slope after cleaning the surface, including providing antiskid surface with bitumen precoated fine grained hard stone chipping
of 9.5 mm nominal size at the rate of 0.005cum per 10 sqm and at an approximate spacing of 10 cm center to center in both
directions, pressed into surface when the temperature of surfaces not less than 100 deg. C, protruding 1 mm to 4 mm over
mastic surface, all complete as per clause 515.)
sqm
353.70
14.6
Construction of precast RCC railing of M30 Grade, aggregate size not exceeding 12 mm, true to line and grade,
tolurence of vertical RCC post not to exceed 1 in 500, centre to centre spacing between vertical post not to exceed
2000 mm, leaving adequate space between vertical post for expansion, complete as per approved drawings and
technical specifications.
metre
1142.20
14.7
Construction of RCC railing of M30 Grade in-situ with 20 mm nominal size aggregate, true to line and grade, tolurence
of vertical RCC post not to exceed 1 in 500, centre to centre spacing between vertical post not to exceed 2000 mm,
leaving adequate space between vertical post for expansion, complete as per approved drawings and technical
specifications.
metre
1108.60
metre
each
cum
1974.00
733.80
2612.30
cum
5708.30
14.8
14.9
14.10
14.11
14.12
Providing, fitting and fixing mild steel railing complete as per drawing and Technical Specification
Drainage Spouts complete as per drawing and Technical specification
PCC M15 Grade leveling course below approach slab complete as per drawing and Technical specification
Reinforced cement concrete approach slab including reinforcement and formwork complete as per drawing and
Technical specification
Providing anti-corrosive treatment to HYSD reinforcement with Fusion Bonded Epoxy Coating (FBEC)
per the prevailing market rates.)
(To be taken as
tonne
Precast - pretensioned Girders (Providing, precasting, transportation and placing in position precast pretensioned concrete
girders as per drawing and technical specifications)
Providing and fixing Helical pipes in voided concrete slabs
Crash Barriers (The rate analysis for rigid crash barrier in reinforced cement concrete, semi-rigid crash barrier with metal beam
and flexible crash barrier with wire ropes have been made and included in chapter-8 on Traffic and Transportation.)
cum
#VALUE!
metre
#VALUE!
14.16
Painting on concrete surface (Providing and applying 2 coats of water based cement paint to unplastered concrete surface
after cleaning the surface of dirt, dust, oil, grease, efflorescence and applying paint @ of 1 litre for 2 Sq.m. )
metre
26.00
14.17
Burried Joint (Providing and laying a burried expansion joint, expansion gap being 20 mm, covered with 12 mm thick, 200 mm
wide galvanised wieldable structural steel plate as per IS: 2062, placed symmetrical to centre line of the joint, resting freely over
the top surface of the deck concrete, welding of 8 mm dia. 100 mm long galvanised nails spaced 300 mm c/c along the centre line
of the plate, all as specified in clause 2604.)
metre
794.00
14.13
14.14
14.15
14.18
(i)
Filler joint
Providing & fixing 2 mm thick corrugated copper plate in expansion joint complete as per drawing & Technical
Specification.
metre
#VALUE!
(ii)
Providing & fixing 20 mm thick compressible fibre board in expansion joint complete as per drawing & Technical
Specification.
metre
22.00
(iii)
Providing and fixing in position 20 mm thick premoulded joint filler in expansion joint for fixed ends of simply
supported spans not exceeding 10 m to cater for a horizontal movement upto 20 mm, covered with sealant complete
as per drawing and technical specifications.
metre
34.40
(iv)
Providing and filling joint sealing compound as per drawings and technical specifications with coarse sand and 6%
bitumen by weight
metre
8.00
Asphaltic Plug joint (Providing and laying of asphaltic plug joint to provide for horizontal movement of 25 mm and vertical
movement of 2 mm, depth of joint varying from 75 mm to 100 mm, width varying from 500 mm to 750 mm (in traffic direction),
covered with a closure plate of 200mm x 6mm of wieldable structural steel conforming to IS: 2062, asphaltic plug to consist of
polymer modified bitumen binder, carefully selected single size aggregate of 12.5 mm nominal size and a heat resistant foam
caulking/backer rod, all as per approved drawings and specifications.)
metre
803.00
14.19
Page 33 of 36
Item
No.
Elastomeric Slab Steel Expansion Joint (Providing and laying of an elastomeric slab steel expansion joint, catering to right or
skew (less than 20 deg., moderately curved with maximum horizontal movement upto 50 mm, complete as per approved
drawings and standard specifications to be installed by the manufacturer/supplier or their authorised representative ensuring
compliance to the manufacturer's instructions for installation and clause 2606 of MoRTH specifications for road & bridge works.)
14.20
Unit
Rate
metre
#VALUE!
14.21
Compression Seal Joint (Providing and laying of compression seal joint consisting of steel armoured nosing at two edges of the
joint gap suitably anchored to the deck concrete and a preformed chloroprene elastomer or closed cell foam joint sealer
compressed and fixed into the joint gap with special adhesive binder to cater for a horizontal movement upto 40 mm and vertical
movement of 3 mm.)
metre
6578.00
14.22
Strip Seal Expansion Joint (Providing and laying of a strip seal expansion joint catering to maximum horizontal movement upto
70 mm, complete as per approved drawings and standard specifications to be installed by the manufacturer/supplier or their
authorised representative ensuring compliance to the manufacturer's instructions for installation.)
metre
11931.00
14.23
Modular Strip / Box Seal Joint (Providing and laying of a modular strip Box steel expansion joint including anchorage catering to
a horizontal movement beyond 70 mm and upto 140mm, complete as per approved drawings and standard specifications to be
installed by the manufacturer/supplier or their authorised representative ensuring compliance to the manufacturer's instructions for
installation.)
metre
#VALUE!
14.24
Modular Strip / Box Seal Joint (Providing and laying of a modular strip box seal expansion joint catering to a horizontal
movement beyond 140mm and upto 210mm, complete as per approved drawings and standard specifications to be installed by
the manufacturer/supplier or their authorised representative ensuring compliance to the manufacturer's instructions for
installation.)
metre
#VALUE!
CHAPTER-15
RIVER TRAINING AND PROTECTION WORKS
Providing and laying boulders apron on river bed for protection against scour with stone boulders weighing not less
than 40 kg each complete as per drawing and Technical specification.
15.1
A
15.2
15.3
Cement concrete blocks (size 0.5 x 0.5 x 0.5 m) (Providing and laying of apron with cement concrete blocks of size 0.5x0.5x0.5
m cast in-situ and made with nominal mix of M-15 grade cement concrete with a minimum cement content of 250 kg/cum as per
IRC: 21-2000.)
15.4
Providing and laying Pitching on slopes laid over prepared filter media including boulder apron laid dry in front of toe
of embankment complete as per drawing and Technical specifications
A
B
15.5
Stone/Boulder
Cement Concrete blocks of size 0.3x0.3 x0.3 m cast in cement concrete of Grade M15
Providing and laying Filter material underneath pitching in slopes complete as per drawing and Technical specification
15.6
Geotextile Filter (Laying of a geotextile filter between pitching and embankment slopes on which pitching is laid to prevent
escape of the embankment material through the voids of the stone pitching/cement concrete blocks as well as to allow free
movement of water without creating any uplift head on the pitching.)
15.7
Toe protection (A toe wall for toe protection can either be in dry rubble masonry in case of dry rubble pitching or pitching with
stones in wire crates or it can be in PCC M15 nominal mix if cement concrete block have been used for pitching . Rates for toe
wall can be adopted from respective clauses depending upon approved design. The rate for excavation for foundation, dry rubble
masonry and PCC M15 have been analysed and given in respective chapters.)
15.8
Providing and laying Flooring complete as per drawing and Technical specifications laid over cement concrete
bedding.
A
B
15.9
15.10
A
B
Page 34 of 36
cum
cum
577.50
#VALUE!
cum
2770.00
cum
cum
577.50
2770.00
cum
1095.30
sqm
71.10
cum
cum
cum
2413.20
3648.00
675.10
cum
cum
2699.00
2715.70
Item
No.
Unit
Rate
15.11
Flexible Apron :Construction of flexible apron 1 m thick comprising of loose stone boulders weighing not less than 40
kg beyond curtain wall.
cum
15.12
Gabian Structure for Retaining Earth (Providing and construction of a gabain structure for retaining earth with segments of
wire crates of size 7 m x 3 m x 0.6 m each divided into 1.5 m compartments by cross netting, made from 4 mm galvanised steel
wire @ 32 kg per 10 sqm having minimum tensile strength of 300 Mpa conforming to IS:280 and galvanizing coating conforming to
IS:4826, woven into mesh with double twist, mesh size not exceeding 100 x 100 mm, filled with boulders with least dimension of
200 mm, all loose ends to be tied with 4 mm galvanised steel wire)
cum
#VALUE!
15.13
Gabian Structure for Erosion Control, River Training Works and Protection works (Providing and constructing gabain
structures for erosion control, river training works and protection works with wire crates of size 2 m x 1 m x 0.3 m each divided
into 1m compartments by cross netting, made from 4 mm galvanised steel wire @ 32 kg per 10 sqm having minimum tensile
strength of 300 Mpa conforming to IS:280 and galvanizing coating conforming to IS:4826, woven into mesh with double twist,
mesh size not exceeding 100 mm x 100 mm, filled with boulders with least dimension of 200 mm, all loose ends to be securely
tied with 4 mm galvanised steel wire.)
cum
#VALUE!
594.30
CHAPTER-16
REPAIR AND REHABILITATION
16.1
Removal of existing cement concrete wearing coat including its disposal complete as per Technical specification
without causing any detrimental effect to any part of the bridge structure and removal of dismantled material with all
lifts and lead upto 1000m (Thickness 75 mm)
sqm
56.70
16.2
Removal of existing asphaltic wearing coat comprising of 50 mm thick asphaltic concrete laid over 12 mm thick mastic
asphalt including disposal with all lift and lead upto 1000m.
sqm
43.20
16.3
Guniting concrete surface with cement mortar applied with compressor after cleaning surface and spraying with epoxy
complete as per Technical specification
sqm
588.20
16.4
Providing and inserting nipples with approved fixing compound after drilling holes for grouting as per Technical
specifications including subsequent cutting/removal and sealing of the hole as necessary of nipples after completion
of grouting with Cement/Epoxy
each
16.5
Sealing of cracks/porous concrete by injection process through nipples/Grouting complete as per Technical
specification.
A
B
16.6
16.7
16.8
16.9
16.10
Cement Grout
Cement mortar (1:1) Grouting
Patching of damaged concrete surface with polymer concrete and curing compounds, initiator and promoter,
available in present formulations, to be applied as per instructions of manufacturer and as approved by the Engineer.
Sealing of crack / porous concrete with Epoxy Grout by injection through nipples complete as per clause 2803.1.
Applying epoxy mortar over leached, honey combed and spalled concrete surface and exposed steel reinforcement
complete as per Technical specification
Removal of defective concrete, cleaning the surface thoroughly, applying the shotcrete mixture mechanically with
compressed air under pressure, comprising of cement, sand, coarse aggregates, water and quick setting compound
in the proportion as per clause 2807.1., sand and coarse aggregates conforming to IS: 383 and table 1 of IS: 9012
respectively, water cement ratio ranging from 0.35 to 0.50, density of gunite not less than 2000 kg/cum, strength not
less than 25 Mpa and workmanship conforming to clause 2807.6.
Applying pre-packed cement based polymer mortar of strength 45 Mpa at 28 days for replacement of spalled concrete
kg
kg
#VALUE!
45.40
70.60
sqm
9093.70
kg
419.60
sqm
sqm
#VALUE!
259.70
sqm
#VALUE!
sqm
#VALUE!
16.12
tonne
#VALUE!
16.13
Providing external prestressing with high tensile steel wires/strands including drilling for passage of prestessing steel,
all accessories for stressing and stressing operation and grouting complete as per drawing and Technical specification
tonne
#VALUE!
16.14
Providing external prestressing with high tensile steel wires/strands including drilling for passage of prestessing steel,
all accessories for stressing and stressing operation and grouting complete as per drawing and Technical specification
tonne
#VALUE!
16.11
Page 35 of 36
Descriptions
Unit
Rate
each
each
metre
metre
metre
metre
#VALUE!
#VALUE!
1647.60
85.40
137.70
74.90
metre
105.60
Repair of RCC Railing (Carrying out repair of RCC M30 railing to bring it to the original shape.)
Repair of steel Railing (Repair of steel railing to bring it to the original shape)
metre
metre
76.30
192.00
Page 36 of 36
CHAPTER-1
CARRIAGE OF MATERIALS
Sr No
Ref. to
MoRTH
Spec.
1.1
Note
1.3
Description
Unit
cum
Quantity
Rate Rs
Remarks/
Input ref.
1 Min
13 Min
2 Min
4 Min
20 Min
hour
hour
0.330
0.330
506.00
520.00
166.98
171.60
say
27.09
36.57
402.23
73.13
73.00
P&M-048
P&M-017
day
day
0.080
2.000
80.00
70.00
6.40
140.00
L-12
L-13
hour
2.000
506.00
1012.00
92.67
125.11
1376.18
137.62
138.00
P&M-057
say
1.6
Cost Rs
b)
Mate
day
0.760
80.00
60.80
L-12
Mazdoor Skilled
day
2.000
90.00
180.00
L-14
day
17.000
70.00
1190.00
L-13
cum
800.000
289.00
231200.00
M-001
Material
Stone Boulder of size 150 mm and below
c)
Machinery
Integrated stone crusher of 200 TPH including belt
conveyor and vibrating screens
Front end loader 1 cum bucket capacity
Hour
6.000
11760.00
70560.00
P&M-028
Hour
20.000
520.00
10400.00
P&M-017
Hour
20.000
506.00
10120.00
P&M-048
Sr No
Ref. to
MoRTH
Spec.
Description
d)
e)
Unit
Quantity
Rate Rs
34960.77
384568.43
608.90
say
1.7
Remarks/
Input ref.
25896.86
Note
Cost Rs
609.00
b)
Mate
day
0.760
80.00
60.80
L-12
Mazdoor Skilled
day
2.000
90.00
180.00
L-14
day
17.000
70.00
1190.00
L-13
cum
800.000
289.00
231200.00
M-001
Material
Stone Boulder of size 150 mm and below
c)
Machinery
Integrated stone crusher of 200 TPH including belt
conveyor and vibrating screens
Front end loader 1 cum bucket capacity
Hour
6.000
11760.00
70560.00
P&M-028
Hour
20.000
520.00
10400.00
P&M-017
Hour
20.000
506.00
10120.00
P&M-048
d)
e)
25896.86
34960.77
384568.43
516.58
say
Note
1.8
517.00
day
0.760
80.00
60.80
L-12
Mazdoor Skilled
day
2.000
90.00
180.00
L-14
Sr No
Ref. to
MoRTH
Spec.
Description
Mazdoor
b)
Quantity
Rate Rs
Remarks/
Input ref.
day
17.000
70.00
1190.00
L-13
cum
800.000
289.00
231200.00
M-001
Machinery
Integrated stone crusher of 200 TPH including belt
conveyor and vibrating screens
Front end loader 1 cum bucket capacity
Hour
6.000
11760.00
70560.00
P&M-028
Hour
20.000
520.00
10400.00
P&M-017
Hour
20.000
506.00
10120.00
P&M-048
d)
e)
25896.86
34960.77
326883.17
435.84
say
Note
Cost Rs
Material
Stone Boulder of size 150 mm and below
c)
Unit
436.00
CHAPTER-2
SITE CLEARANCE
Sr No
2.1
Ref. to
MoRTH
Spec.
201
Description
(i)
Unit
Quantity
Rate Rs
Labour
Mate
d)
day
0.020
80.00
1.60
L-12
day
0.600
70.00
42.00
L-13
hour
0.100
231.00
23.10
P&M-053
5.34
7.20
79.24
say
(ii)
d)
day
0.040
80.00
3.20
L-12
day
0.900
70.00
63.00
L-13
hour
0.300
231.00
69.30
P&M-053
10.84
14.63
160.97
say
(iii)
d)
day
0.080
80.00
6.40
L-12
day
2.000
70.00
140.00
L-13
hour
0.400
231.00
92.40
P&M-053
19.10
25.79
161.00
2.1
79.20
2.1
Remarks/
Input ref.
2.1
Cost Rs
283.69
say
283.70
day
day
0.160
4.000
80.00
70.00
12.80
280.00
L-12
L-13
hour
0.600
231.00
138.60
34.51
46.59
512.50
512.50
P&M-053
say
Sr No
2.3
Ref. to
MoRTH
Spec.
201
2.3
Description
(ii)
A
Unit
Quantity
Rate Rs
b)
Labour
Mate
day
0.160
80.00
12.80
L-12
Mazdoor
day
4.000
70.00
280.00
L-13
hour
10.000
2190.00
21900.00
P&M-014
hour
1.000
231.00
231.00
P&M-053
Machinery
Dozer 80 HP with attachment for removal of trees &
stumps
Tractor-trolley
c)
d)
1793.90
2421.77
26639.47
say
202
Remarks/
Input ref.
2.4
Cost Rs
26639.50
Dismantling of Structures
Dismantling of existing structures like culverts, bridges,
retaining walls and other structure comprising of masonry,
cement concrete, wood work, steel work, including T&P and
scaffolding wherever necessary, sorting the dismantled
material, disposal of unserviceable material and stacking the
serviceable material with all lifts and lead of 1000 metres
Unit = cum
Taking output = 1.25 cum
2.4
II
b)
Labour
Mate
day
0.020
80.00
1.60
L-12
day
0.250
70.00
17.50
L-13
day
0.250
90.00
22.50
L-14
hour
0.670
206.00
138.02
P&M-001
hour
0.270
231.00
62.37
P&M-053
Machinery
Air Compressor 250 cfm with 2 leads of pneumatic
breaker @ 1.5 cum per hour
Tractor-trolley
c)
d)
19.36
26.13
287.48
229.99
say
2.4 II
230.00
b)
Mate
day
0.050
80.00
4.00
L-12
day
0.660
90.00
59.40
L-14
Blacksmith
day
0.250
100.00
25.00
L-02
day
0.250
70.00
17.50
L-13
Machinery
Sr No
Ref. to
MoRTH
Spec.
Description
Air Compressor 250 cfm with 2 leads of pneumatic
breaker @ 1.00 cum per hour
Tractor-trolley
c)
d)
Unit
Quantity
Rate Rs
1.000
206.00
206.00
P&M-001
hour
0.270
231.00
62.37
P&M-053
29.94
40.42
444.63
355.71
say
b)
Labour
Mate
day
0.030
80.00
2.40
L-12
day
0.750
70.00
52.50
L-13
hour
0.270
231.00
62.37
P&M-053
Machinery
Tractor-trolley
c)
d)
9.38
12.67
139.32
111.45
say
2.4
(iii)
B
b)
Labour
Mate
day
0.030
80.00
2.40
L-12
day
0.750
70.00
52.50
L-13
hour
0.270
231.00
62.37
P&M-053
Machinery
Tractor-trolley
c)
d)
9.38
12.67
139.32
111.45
say
b)
Labour
Mate
day
0.016
80.00
1.28
L-12
day
0.400
70.00
28.00
L-13
hour
0.270
231.00
62.37
P&M-053
Machinery
Tractor-trolley
c)
d)
7.33
9.90
108.88
87.10
say
(ix)
111.50
2.4
111.50
2.4 (iii)
355.70
In cement mortar
a)
2.4 (iii)
Remarks/
Input ref.
hour
2.4 (ii)
Cost Rs
87.10
Up to 600 mm dia
a)
b)
Labour
Mate
day
0.020
80.00
1.60
L-12
Mazdoor
day
0.520
70.00
36.40
L-13
3.04
Sr No
Ref. to
MoRTH
Spec.
Description
c)
Unit
Quantity
Rate Rs
45.14
say
Labour
Mate
day
0.030
80.00
2.40
L-12
Mazdoor
day
0.700
70.00
49.00
L-13
b)
c)
4.11
5.55
61.06
say
Labour
Mate
day
0.050
80.00
4.00
L-12
Mazdoor
day
1.200
70.00
84.00
L-13
b)
c)
7.04
9.50
104.54
say
2.5
202
61.10
Above 900 mm
a)
Note
45.10
2.4 (ix)
Remarks/
Input ref.
4.10
Cost Rs
104.50
2.5
II
By Mechanical Means
Bituminous course
a)
b)
Labour
Mate
day
0.010
80.00
0.80
L-12
Mazdoor
day
0.300
70.00
21.00
L-13
Machinery
Tractor-trolley
hour
0.380
231.00
87.78
P&M-053
hour
0.017
249.00
4.23
P&M-055
c)
d)
9.11
12.29
135.21
say
2.7
202
135.20
b)
Labour
Mate
day
0.006
80.00
0.48
L-12
day
0.150
70.00
10.50
L-13
hour
0.050
231.00
11.55
P&M-053
Machinery
Tractor-trolley
Sr No
Ref. to
MoRTH
Spec.
Description
c)
d)
Unit
Quantity
Rate Rs
2.43
26.77
say
202
Remarks/
Input ref.
1.80
Cost Rs
26.80
b)
Labour
Mate
day
0.010
80.00
0.80
L-12
day
0.150
70.00
10.50
L-13
hour
0.200
231.00
46.20
P&M-053
Machinery
Tractor-trolley
c)
d)
4.60
6.21
68.31
6.83
say
2.10
202
6.80
Ordinary KM Stone
Quantity of cement concrete = 0.269 cum
a)
b)
Labour
Mate
day
0.020
80.00
1.60
L-12
Mazdoor
day
0.500
70.00
35.00
L-13
hour
0.100
231.00
23.10
P&M-053
Machinery
Tractor-trolley
c)
d)
6.45
70.92
4.78
say
70.90
CHAPTER - 3
EARTH WORK, EROSION CONTROL AND DRAINAGE
Sr No
3.1
Ref. to
MoRTH
Spec.
301
Description
Excavation in Soil by Manual Means .
Excavation for roadway in soil using manual means
including loading in truck for carrying of cut earth to
embankment site with all lifts and lead upto1000 metres.
Unit = cum
Taking output = 120 cum
a) Labour
Mate
Mazdoor
b) Machinery
Truck 5.5 cum capacity
c) Overhead charges @ 8% on (a+b)
d) Contractor's profit @ 10% on (a+b+c)
Cost of 120 cum = a+b+c+d
Rate per cum = (a+b+c+d)/120
Note
3.2
301
3.3
301
Quantity
Rate Rs
Cost Rs
Remarks/
Input ref.
day
day
1.800
45.000
80.00
70.00
144.00
3150.00
L-12
L-13
hour
10.000
506.00
P&M-057
say
5060.00
668.32
902.23
9924.55
82.70
83.00
Note
Unit
day
day
2.800
70.000
80.00
70.00
224.00
4900.00
L-12
L-13
hour
10.000
506.00
P&M-057
say
5060.00
814.72
1099.87
12098.59
100.82
101.00
day
day
0.080
2.000
80.00
70.00
6.40
140.00
hour
6.000
2190.00
13140.00
1062.91
1434.93
15784.24
87.69
88.00
say
L-12
L-13
P&M-014
Sr No
3.4
Ref. to
MoRTH
Spec.
301
Description
Excavation in Ordinary Rock with Dozer with lead upto
100 metres
Excavation for roadway in ordinary rock by deploying a
dozer, 80 HP including cutting and pushing the cut earth to
site of embankment upto a distance of 100 metres ( average
lead 50 metres ), trimming bottom and side slopes in
accordance with the requirements of lines, grades and cross
sections.
Unit = cum
Taking output = 108 cum
a) Labour
Mate
Mazdoor
b) Machinery
Dozer, 80 HP @ 20 cum per hour
c) Overhead charges @ 8% on (a+b)
d) Contractor's profit @ 10% on (a+b+c)
Cost for 108 cum = a+b+c+d
Rate per cum = (a+b+c+d)/108
Unit
Quantity
Rate Rs
day
day
0.120
3.000
80.00
70.00
9.60
210.00
hour
6.000
2190.00
13140.00
1068.77
1442.84
15871.20
146.96
147.00
say
3.5
301
Cost Rs
Remarks/
Input ref.
L-12
L-13
P&M-014
b)
c)
Labour
Mate
day
0.220
80.00
17.60
L-12
Mazdoor
day
3.000
70.00
210.00
L-13
Driller
day
2.000
100.00
200.00
L-06
Blaster
day
0.250
100.00
25.00
L-03
Machinery
Dozer, 80 HP @ 30 cum per hour
hour
6.000
2190.00
13140.00
P&M-014
hour
6.000
206.00
1236.00
P&M-001
hour
6.000
520.00
3120.00
P&M-017
hour
11.250
506.00
5692.50
P&M-048
6300.00
M-104
Materials
Gelatin 80 per cent
kg
63.000
100.00
each
252.000
14.00
cum
90.000
(148.00)
2176.10
23937.13
132.98
say
3.6
301
(13320.00)
1611.93
Note
133.00
M-089
Sr No
Ref. to
MoRTH
Spec.
Description
Unit
Quantity
Rate Rs
Cost Rs
Remarks/
Input ref.
b)
Labour
Mate
day
0.080
80.00
6.40
L-12
Mazdoor
day
2.000
70.00
140.00
L-13
hour
6.000
840.00
5040.00
P&M-026
hour
16.000
506.00
8096.00
P&M-048
Machinery
Hydraulic excavator 0.9 cum bucket capacity @ 60 cum
per hour
Tipper 5.5 cum capacity, 4 trips per hour.
c)
d)
1062.59
1434.50
15779.49
43.83
say
3.7
301
43.80
b)
Labour
Mate
day
0.080
80.00
6.40
L-12
Mazdoor
day
2.000
70.00
140.00
L-13
hour
6.000
840.00
5040.00
P&M-026
hour
11.000
506.00
5566.00
P&M-048
Machinery
Hydraulic Excavator 0.90 cum bucket capacity @ 36
cum per hour
Tipper 5.5 cum capacity, 4 trips per hour.
c)
d)
860.19
1161.26
12773.85
53.22
say
3.8
301
53.20
Labour
Mate
day
0.400
80.00
32.00
L-12
day
10.000
70.00
700.00
L-13
Sr No
Ref. to
MoRTH
Spec.
Description
b)
Quantity
Rate Rs
hour
6.000
840.00
P&M-026
6.500
506.00
3289.00
P&M-048
18.000
(148.00)
(2664.00)
M-089
511.76
690.88
7599.64
211.10
say
5040.00
cum
3.8
Remarks/
Input ref.
hour
Note
Cost Rs
Machinery
Hydraulic excavator with rock breaker attachment @ 6
cum per hour
Tipper 5.5 cum capacity, 1 trip per hour.
d)
Unit
211.00
b)
Labour
Mate
day
1.640
80.00
131.20
L-12
day
16.000
70.00
1120.00
L-13
Chiseller
day
24.000
100.00
2400.00
L-05
Blacksmith
day
1.000
100.00
100.00
L-02
hour
2.900
506.00
1467.40
P&M-048
cum
8.000
(148.00)
(1184.00)
M-089
Machinery
Tipper 5.5 cum capacity, 1 trip per hour.
322.77
435.74
4793.10
299.57
say
Note
3.9
301
300.00
b)
Labour
Mate
day
0.220
80.00
17.60
L-12
Mazdoor
day
3.000
70.00
210.00
L-13
Driller
day
2.000
100.00
200.00
L-06
Blaster
day
0.500
100.00
50.00
L-03
hour
6.000
2190.00
13140.00
Machinery
Dozer 80 HP @ 30 cum per hour
P&M-014
Sr No
Ref. to
MoRTH
Spec.
Description
c)
Quantity
Rate Rs
Cost Rs
Remarks/
Input ref.
hour
6.000
206.00
1236.00
P&M-001
hour
6.000
520.00
3120.00
P&M-017
hour
8.200
506.00
4149.20
P&M-048
6300.00
M-104
Materials
Gelatin 80 per cent
Unit
kg
63.000
100.00
each
1008.000
14.00
cum
90.000
(148.00)
M-089
2126.74
2507.32
3384.89
37233.75
206.85
say
Note
3.10
301
207.00
b)
Labour
Mate
day
0.080
80.00
6.40
L-12
Mazdoor
day
2.000
70.00
140.00
L-13
hour
6.000
840.00
5040.00
P&M-026
hour
13.640
506.00
6901.84
P&M-048
Machinery
Hydraulic excavator 0.90 cum bucket capacity @ 50
cum per hour
Tipper 5.5 cum capacity, 4 trips per hour.
c)
d)
967.06
1305.53
14360.83
47.87
say
3.11
301
48.00
b)
Labour
Mate
day
0.080
80.00
6.40
L-12
Mazdoor
day
2.000
70.00
140.00
L-13
hour
6.000
840.00
5040.00
P&M-026
Machinery
Excavator0.90 cum bucket capacity @ 60 cum per hour
Sr No
Ref. to
MoRTH
Spec.
Description
Tipper 5.5 cum capacity, 4 trips per hour.
c)
d)
Unit
Quantity
hour
16.360
Rate Rs
506.00
1454.17
44.43
say
303
P&M-048
15995.90
3.12
8278.16
Remarks/
Input ref.
1077.16
Note
Cost Rs
44.00
b)
c)
Mate
day
0.600
80.00
48.00
L-12
Mazdoor
day
15.000
70.00
1050.00
L-13
hour
6.000
206.00
1236.00
P&M-001
hour
6.000
2190.00
13140.00
P&M-014
hour
6.000
520.00
3120.00
P&M-017
kg
42.000
100.00
4200.00
M-104
each
672.000
14.00
Machinery
Materials
Gelatin 80 per cent
2576.16
3477.82
38255.98
95.64
say
Note
3.13
304
(i)
96.00
b)
Labour
Mate
day
0.320
80.00
25.60
L-12
Mazdoor
day
8.000
70.00
560.00
L-13
46.85
Sr No
Ref. to
MoRTH
Spec.
Description
c)
Unit
Quantity
Rate Rs
695.69
69.57
say
3.13 (i)
Remarks/
Input ref.
63.24
Note
Cost Rs
70.00
b)
Labour
Mate
day
0.320
80.00
25.60
L-12
Mazdoor
day
8.000
70.00
560.00
L-13
hour
6.000
840.00
5040.00
P&M-026
Machinery
Hydraulic excavator 1.0 cum bucket capacity
c)
d)
450.05
607.56
6683.21
22.28
say
Note
3.13
(ii)
A
22.00
Labour
Mate
day
0.400
80.00
32.00
L-12
Mazdoor
day
10.000
70.00
700.00
L-13
b)
c)
58.56
79.06
869.62
86.96
say
Note
3.13 (ii)
87.00
b)
Labour
Mate
day
0.240
80.00
19.20
L-12
Mazdoor
day
6.000
70.00
420.00
L-13
hour
6.000
840.00
5040.00
P&M-026
Machinery
Hydraulic excavator 1.0 cum bucket capacity
c)
d)
438.34
591.75
6509.29
30.14
say
30.00
Sr No
Ref. to
MoRTH
Spec.
Description
Note
3.13
(iii)
A
Unit
Quantity
Rate Rs
Cost Rs
Remarks/
Input ref.
b)
Labour
i) Mate
day
0.530
80.00
42.40
L-12
ii) Driller
day
0.840
100.00
84.00
L-06
iii) Blaster
day
0.400
100.00
40.00
L-03
iv) Mazdoor
day
12.000
70.00
840.00
L-13
hour
0.667
206.00
137.33
P&M-001
kg
3.500
100.00
350.00
M-104
each
14.000
14.00
Machinery
e)
135.18
182.49
2007.40
200.74
say
Note
3.13
(iv)
201.00
Mechanical Means
a)
b)
Labour
Mate
day
0.200
80.00
16.00
L-12
Mazdoor
day
5.000
70.00
350.00
L-13
hour
10.000
206.00
2060.00
P&M-001
Machinery
194.08
262.01
2882.09
3.13
(v)
288.21
say
288.00
80.00
32.00
Labour
Mate/Supervisor
day
0.400
L-12
Sr No
Ref. to
MoRTH
Spec.
Description
Mazdoor
b)
Quantity
Rate Rs
day
10.000
70.00
700.00
L-13
hour
2.670
231.00
616.77
P&M-053
d)
cum
5.000
140.00
700.00
M-163
e)
163.90
221.27
2433.94
243.39
say
3.13 (v)
b)
Labour
i) Mate
day
0.080
80.00
6.40
L-12
day
2.000
70.00
140.00
L-13
hour
0.170
840.00
142.80
P&M-026
hour
0.450
506.00
227.70
P&M-048
cum
5.000
140.00
700.00
M-163
Machinery
Hydraulic excavator 1.0 cum bucket capacity @ 60 cum
per hour
Tipper 5.5 cum capacity, 4 trips per hour.
c)
Material
Selected earth for refilling
d)
e)
97.35
131.43
1445.68
144.57
say
3.14
305.4.3
243.00
Note
Remarks/
Input ref.
Material
Selected earth for refilling
Note
Cost Rs
Machinery
Tractor-trolley
c)
Unit
145.00
b)
Labour
Mate
day
0.200
80.00
16.00
L-12
day
5.000
70.00
350.00
L-13
hour
1.670
231.00
385.77
P&M-053
Machinery
Tractor-trolley
d)
e)
60.14
81.19
893.10
Sr No
Ref. to
MoRTH
Spec.
Description
Unit
Quantity
Rate Rs
3.15
305.4.3
Remarks/
Input ref.
8.93
say
Note
Cost Rs
9.00
b)
Labour
Mate
day
0.010
80.00
0.80
L-12
Mazdoor
day
0.250
70.00
17.50
L-13
hour
0.080
249.00
19.92
P&M-055
hour
0.200
520.00
104.00
P&M-017
hour
0.230
506.00
116.38
P&M-048
Machinery
c)
d)
20.69
27.93
307.22
3.07
say
3.16
305
3.10
b)
Labour
Mate
day
0.040
80.00
3.20
L-12
Mazdoor
day
1.000
70.00
70.00
L-13
hour
1.670
840.00
1402.80
tonne.km
160 x L
2.00
Machinery
Hydraulic Excavator1 cum bucket capacity @ 60 cum
per hour
Tipper 10 tonne capacity
c)
P&M-026
1600.00 Lead =5 km
& P&M-058
hour
0.500
2190.00
1095.00
P&M-014
hour
1.000
1545.00
1545.00
P&M-032
160.00
hour
4.000
506.00
2024.00
P&M-060
hour
1.000
994.00
994.00
P&M-059
Material
Cost of water
Compensation for earth taken from private land
d)
e)
KL
24.000
10.00
240.00
M-189
cum
100.000
10.00
1000.00
M-092
810.72
1094.47
12039.19
120.39
say
120.40
Sr No
Ref. to
MoRTH
Spec.
Description
Note
3.17
305
Unit
Quantity
Rate Rs
Cost Rs
Remarks/
Input ref.
Compensation for earth will vary from place to place and will
have to be assessed realistically as per particular ground
situation. In case earth is available from Govt. land,
compensation for earth will not be required. The position is
required to be clearly stated in the cost estimate.
Construction of Embankment with Material Deposited
from Roadway Cutting
Construction of embankment with approved materials
deposited at site from roadway cutting and excavation from
drain and foundation of other structures graded and
compacted to meet requirement of table 300-2.
Unit = cum
Taking output = 100 cum
a)
b)
c)
Labour
Mate
day
0.020
80.00
1.60
L-12
Mazdoor
day
0.500
70.00
35.00
L-13
Machinery
Dozer 80 HP for spreading @ 200 cum per hour
hour
0.500
2190.00
1095.00
P&M-014
hour
1.000
1545.00
1545.00
P&M-032
hour
4.000
506.00
2024.00
P&M-060
hour
1.000
994.00
994.00
P&M-059
KL
24.000
10.00
240.00
M-189
Material
Cost of water
d)
e)
474.77
640.94
7050.30
70.50
say
Note
3.18
305
70.50
b)
Labour
Mate
day
0.040
80.00
3.20
L-12
Mazdoor
day
1.000
70.00
70.00
L-13
hour
1.670
840.00
1402.80
tonne.km
175xL
2.00
Machinery
Hydraulic excavator1 cum bucket capacity @ 60 cum
per hour
Tipper 10 tonne capacity
P&M-026
1750.00 Lead =5 km
& P&M-058
hour
0.500
2190.00
1095.00
P&M-014
hour
2.000
1545.00
3090.00
P&M-032
175.00
hour
4.000
506.00
2024.00
P&M-060
hour
1.250
994.00
1242.50
P&M-059
Sr No
Ref. to
MoRTH
Spec.
Description
c)
Unit
Quantity
Rate Rs
e)
KL
24.000
10.00
240.00
M-189
cum
100.000
10.00
1000.00
M-092
967.40
1305.99
14365.89
143.66
say
305.3.4
Remarks/
Input ref.
Material
Cost of water
3.19
Cost Rs
143.70
b)
c)
Labour
Mate
day
0.120
80.00
9.60
L-12
Mazdoor
day
3.000
70.00
210.00
L-13
hour
9.000
249.00
2241.00
P&M-055
hour
6.000
1545.00
9270.00
P&M-032
hour
4.000
506.00
2024.00
P&M-060
hour
7.500
994.00
7455.00
P&M-059
KL
24.000
10.00
240.00
M-189
Machinery
Material
Cost of water
d)
e)
1715.97
2316.56
25482.12
42.47
say
3.22
307
42.50
b)
c)
Labour
Mate
day
0.120
80.00
9.60
L-12
day
3.000
70.00
210.00
L-13
hour
2.000
506.00
1012.00
P&M-060
Tractor-trolley
hour
1.000
231.00
231.00
P&M-053
cum
0.180
50.00
9.00
M-167
KL
12.000
10.00
120.00
M-189
Machinery
Material
Farm yard manure @ 0.18 cum per 100 sqm at site of
work
Cost of water
d)
e)
127.33
171.89
1890.82
18.91
Sr No
Ref. to
MoRTH
Spec.
Description
Unit
Quantity
Rate Rs
say
Cost Rs
18.90
Remarks/
Input ref.
CHAPTER - 4
SUB-BASES, BASES ( NON- BITUMINOUS) AND SHOULDERS
Sr No
4.2
Ref. to
MoRTH
Spec.
401
Description
Unit
Quantity
Rate Rs
Cost Rs
Remarks/
Input ref.
b)
c)
Labour
Mate
day
0.400
80.00
32.00
L-12
Mazdoor skilled
day
2.000
100.00
200.00
L-15
Mazdoor
day
8.000
70.00
560.00
L-13
hour
6.000
1545.00
9270.00
P&M-032
hour
6.000
994.00
5964.00
P&M-059
hour
3.000
506.00
1518.00
P&M-060
Machinery
Material
cum
134.400
245.00
32928.00
cum
172.800
245.00
42336.00
cum
76.800
145.00
11136.00
M-022
KL
18.000
10.00
180.00
M-189
Cost of water
4.2
(i)
e)
8329.92
11245.39
123699.31
412.33
say
4.2
(ii)
e)
18656.45
25186.20
277048.25
923.49
say
4.2
(iii)
923.00
e)
16136.59
21784.40
239628.39
798.76
say
Average rate
Note
412.30
799.00
711.43
Sr No
4.3
Ref. to
MoRTH
Spec.
402
Description
Unit
Quantity
Rate Rs
Cost Rs
Remarks/
Input ref.
By Mechanical Means
a)
b)
Labour
Mate
day
0.360
80.00
28.80
L-12
day
1.000
100.00
100.00
L-15
day
8.000
70.00
560.00
L-13
hour
12.000
249.00
2988.00
P&M-055
Machinery
Tractor with ripper and rotavator attachments @ 60 cum
per hour for ripping and 25 cum per hour for mixing
c)
hour
6.000
1545.00
9270.00
P&M-032
hour
6.00x0.65*
994.00
3876.60
P&M-059
hour
12.000
506.00
6072.00
P&M-060
tonne
15.750
11000.00
173250.00
M-188
KL
72.000
10.00
720.00
M-189
Material
Lime at site
Cost of water
15749.23
e)
21261.46
233876.10
779.59
say
Note
4.3
779.60
b)
c)
Labour
Mate
day
1.440
80.00
115.20
L-12
Mazdoor skilled
day
1.000
100.00
100.00
L-15
Mazdoor
day
35.000
70.00
2450.00
L-13
hour
2.500
994.00
2485.00
P&M-059
hour
6.000
506.00
3036.00
P&M-060
tonne
8.000
11000.00
88000.00
M-188
KL
36.000
10.00
360.00
M-189
Machinery
Material
Lime at site
Cost of water
d)
e)
7723.70
10426.99
114696.89
764.65
say
764.60
Sr No
4.4
Ref. to
MoRTH
Spec.
402
Description
Unit
Quantity
Rate Rs
Cost Rs
Remarks/
Input ref.
b)
Labour
Mate
day
0.480
80.00
38.40
L-12
Mazdoor skilled
day
2.000
100.00
200.00
L-15
Mazdoor
day
10.000
70.00
700.00
L-13
hour
6.000
840.00
5040.00
P&M-026
tonne.km
525 x L
2.00
Machinery
Excavator 0.90 cum bucket capacity
Tipper for carriage of soil
c)
hour
6.000
1545.00
9270.00
hour
6.000
994.00
5964.00
P&M-059
hour
12.000
242.00
2904.00
P&M-054
hour
12.000
506.00
6072.00
P&M-060
tonne
15.750
11000.00
173250.00
M-188
KL
72.000
10.00
720.00
M-189
525.00
Cost of water
d)
e)
16794.67
22672.81
249400.88
831.34
say
403
P&M-032
Material
Lime at site
4.5
5250.00 Lead =5 km
& P&M-058
831.00
b)
Labour
Mate
day
0.480
80.00
38.40
L-12
Mazdoor skilled
day
2.000
100.00
200.00
L-15
Mazdoor
day
10.000
70.00
700.00
L-13
hour
6.000
840.00
5040.00
P&M-026
tonne.km
525 x L
2.00
Machinery
Excavator 0.90 cum bucket capacity
Tipper for carriage of soil
5250.00 Lead =5 km
& P&M-058
hour
6.000
1545.00
9270.00
P&M-032
hour
6.000
994.00
5964.00
P&M-059
525.00
Sr No
Ref. to
MoRTH
Spec.
Description
c)
Unit
Quantity
Rate Rs
hour
12.000
242.00
2904.00
P&M-054
hour
12.000
506.00
6072.00
P&M-060
tonne
21.000
4400.00
92400.00
M-081
KL
72.000
10.00
720.00
M-189
Material
Cost of water
d)
e)
10326.67
13941.01
153351.08
511.17
say
403
Remarks/
Input ref.
4.6
Cost Rs
511.00
b)
c)
Mate
day
0.480
80.00
38.40
L-12
Mazdoor skilled
day
2.000
100.00
200.00
L-15
Mazdoor
day
10.000
70.00
700.00
L-13
hour
6.000
1545.00
9270.00
P&M-032
hour
6.000
994.00
5964.00
P&M-059
hour
12.000
242.00
2904.00
P&M-054
hour
10.000
506.00
5060.00
P&M-060
tonne
24.000
4400.00
105600.00
cum
211.200
561.50
118588.80
M-014
cum
76.800
609.00
46771.20
M-025
cum
96.000
512.50
49200.00
M-019
KL
60.000
10.00
600.00
M-189
cum
124.800
438.48
54722.30
M-028
cum
19.200
609.00
11692.80
M-025
cum
240.000
401.94
96465.60
M-023
KL
60.000
10.00
600.00
M-189
Machinery
Material
Cost of water
M-081
or
Grading of material for Base course
Cost of water
4.6
(i)
e)
27591.71
37248.81
409736.92
1365.79
say
4.6
(ii)
1366.00
23457.37
e)
31667.45
Sr No
Ref. to
MoRTH
Spec.
Description
Unit
Quantity
Rate Rs
1161.14
say
4.7
404.3.1
Remarks/
Input ref.
348341.92
Cost Rs
1161.00
(i)
b)
Labour
Mate
day
0.080
80.00
6.40
L-12
Mazdoor
day
2.000
70.00
140.00
L-13
hour
0.200
231.00
46.20
P&M-053
Machinery
Tractor-trolley
c)
d)
15.41
20.80
228.81
218.81
say
(ii)
b)
Labour
Mate
day
0.160
80.00
12.80
L-12
Mazdoor
day
4.000
70.00
280.00
L-13
hour
0.400
231.00
92.40
P&M-053
Machinery
Tractor-trolley
c)
d)
30.82
41.60
457.62
447.62
say
4.8
404.3.2
219.00
448.00
Inverted Choke
Construction of inverted choke by providing, laying, spreading
and compacting screening B type/ coarse sand of specified
grade in uniform layer on a prepared surface with motor
grader and compacting with power roller etc
Unit = cum
Taking output = 600 cum
a)
b)
c)
Labour
Mate
day
0.920
80.00
73.60
L-12
Mazdoor skilled
day
2.000
100.00
200.00
L-15
Mazdoor
day
21.000
70.00
1470.00
L-13
Machinery
Motor Grader 110 HP
hour
6.000
1545.00
9270.00
P&M-032
hour
6.000
994.00
5964.00
P&M-059
hour
18.000
506.00
9108.00
P&M-060
cum
720.000
149.00
107280.00
M-004
KL
108.000
10.00
1080.00
M-189
Material
Screening type 'B' or coarse sand
Cost of water
d)
10755.65
Sr No
Ref. to
MoRTH
Spec.
Description
e)
Unit
Quantity
Rate Rs
159721.37
266.20
say
404
Remarks/
Input ref.
14520.12
4.9
Cost Rs
266.00
b)
Labour
Mate
day
10.080
80.00
806.40
L-12
Mazdoor skilled
day
2.000
100.00
200.00
L-15
Mazdoor
day
250.000
70.00
17500.00
L-13
hour
6.000
994.00
5964.00
P&M-059
hour
12.000
hour
24.000
506.00
12144.00
P&M-060
cum
435.600
395.85
172432.26
M-039
cum
97.200
609.00
59194.80 M-052
cum
108.000
140.00
15120.00
M-007
cum
28.800
140.00
4032.00
M-007
KL
144.000
10.00
1440.00
M-189
Machinery
Vibratory roller 8 - 10 tonne @ 60cum per hour
or
4.9A
(i)
4.9A (i)
(a)
e)
18048.53
24365.52
268020.71
744.50
say
745.00
OR
4.9A (i)
(b)
21897.08
e)
29561.05
Sr No
Ref. to
MoRTH
Spec.
Description
Unit
Quantity
Rate Rs
(ii)
Remarks/
Input ref.
325171.59
Cost Rs
903.25
say
903.00
177737.87
Grading-II
Aggregate
cum
435.600
408.03
cum
57.600
609.00
35078.40 M-052
cum
105.590
140.00
14782.60
cum
86.400
609.00
52617.60 M-051
cum
28.800
140.00
4032.00
M-007
KL
144.000
10.00
1440.00
M-189
M-038
Stone Screening
Type A 13.2 mm for grading-II@ 0.12 cum per 10 sqm
OR
M-007
Binding material
Binding Material @ 0.06cum per 10 sqm for grading II
material
Cost of water
4.9A (ii)
(a)
e)
18445.99
24902.09
273922.94
760.90
say
761.00
OR
4.9A (ii)
(b)
e)
20392.21
27529.49
302824.37
841.18
say
4.9A (ii)
(c)
e)
21795.35
29423.72
323660.94
(iii)
841.00
899.06
say
899.00
180390.67
Grading-III
Aggregate
Grading-III 53 mm to 22.4 mm@ 0.91 cum per 10 sqm for
compacted thickness of 75 mm
cum
435.600
414.12
M-036
cum
86.400
609.00
52617.60 M-051
cum
105.590
140.00
14782.60
Stone Screening
Type B 11.2 mm for grading-III @ 0.18 cum per 10 sqm
OR
Crushable type such as Moorum or Gravel for grading II
&III @ 0.22 cum per 10 sqm
M-007
Sr No
Ref. to
MoRTH
Spec.
Description
Unit
Quantity
Rate Rs
Cost Rs
Remarks/
Input ref.
Binding material
Binding Material @ 0.06cum per 10 sqm for grading II
material
Cost of water
4.9A
(iii)
(a)
cum
28.800
140.00
4032.00
M-007
KL
144.000
10.00
1440.00
M-189
e)
18658.21
25188.59
277074.47
769.65
say
770.00
OR
4.9A
(iii)
(b)
e)
22007.57
29710.22
326812.47
907.81
say
4.9
908.00
b)
Labour
Mate
day
0.680
80.00
54.40
L-12
Mazdoor skilled
day
2.000
100.00
200.00
L-15
Mazdoor
day
15.000
70.00
1050.00
L-13
Machinery
Motor grader 110 HP @ 50cum/hr. for spreading
hour
7.200
1545.00
11124.00
P&M-032
hour
6.000
994.00
5964.00
P&M-059
hour
12.000
hour
24.000
506.00
12144.00
P&M-060
cum
435.600
395.85
172432.26
M-039
cum
97.200
609.00
59194.80 M-052
cum
108.000
140.00
15120.00
M-007
cum
28.800
140.00
4032.00
M-007
KL
144.000
10.00
1440.00
M-189
or
4.9B
(i)
4.9B (i)
(a)
17562.29
e)
23709.10
Sr No
Ref. to
MoRTH
Spec.
Description
Unit
Quantity
Rate Rs
Cost Rs
Remarks/
Input ref.
260800.05
724.44
say
724.00
OR
4.9B (i)
(b)
e)
21410.84
28904.63
317950.93
(ii)
883.20
say
883.00
177737.87
Grading-II
Aggregate
cum
435.600
408.03
cum
57.600
609.00
35078.40 M-052
cum
105.590
140.00
14782.60
cum
86.400
609.00
52617.60 M-051
cum
28.800
140.00
4032.00
M-007
KL
144.000
10.00
1440.00
M-189
M-038
Stone Screening
Type A 13.2 mm for grading-II@ 0.12 cum per 10 sqm
OR
M-007
Binding material
Binding Material @ 0.06cum per 10 sqm for grading II
material
Cost of water
4.9B (ii)
(a)
e)
17959.75
24245.66
266702.28
740.84
say
741.00
OR
4.9B (ii)
(b)
e)
19905.97
26873.06
295603.71
821.12
say
4.9B (ii)
(c)
e)
21309.11
28767.30
316440.28
(iii)
821.00
879.00
say
879.00
414.12
180390.67
Grading-III
Aggregate
Grading-III 53 mm to 22.4 mm@ 0.91 cum per 10 sqm for
compacted thickness of 75 mm
cum
435.600
M-036
Sr No
Ref. to
MoRTH
Spec.
Description
Unit
Quantity
Rate Rs
Cost Rs
Remarks/
Input ref.
Stone Screening
Type B11.2 mm for grading-III @ 0.18 cum per 10 sqm
cum
86.400
609.00
52617.60 M-051
cum
105.590
140.00
14782.60
M-007
cum
28.800
140.00
4032.00
M-007
KL
144.000
10.00
1440.00
M-189
OR
Crushable type such as Moorum or Gravel for grading II
&III @ 0.22 cum per 10 sqm
Binding material
Binding Material @ 0.06cum per 10 sqm for grading II
material
Cost of water
4.9B
(iii)
(a)
e)
18171.97
24532.16
269853.81
749.59
say
750.00
OR
4.9B
(iii)
(b)
e)
21521.33
29053.80
319591.81
887.76
say
Note
4.10
405
888.00
Labour
Mate
day
4.160
80.00
332.80
L-12
Mazdoor skilled
day
2.000
100.00
200.00
L-15
day
102.000
70.00
7140.00
L-13
hour
6.000
1545.00
9270.00
P&M-032
hour
6.000
994.00
5964.00
P&M-059
hour
12.000
hour
6.000
520.00
3120.00
P&M-017
tonne.km
720 x L
2.00
24480.00
Lead =17
km & P&M058
or
2448.00
hour
12.000
506.00
6072.00
P&M-060
Sr No
Ref. to
MoRTH
Spec.
Description
c)
Unit
Quantity
Rate Rs
Cost Rs
Remarks/
Input ref.
Material
e)
KL
72.000
10.00
70979.20
197.16
say
4.11
405.2
M-189
6452.65
Note
720.00
4779.74
197.00
b)
c)
Labour
Mate
day
0.560
80.00
44.80
L-12
Mazdoor skilled
day
2.000
100.00
200.00
L-15
Mazdoor
day
12.000
70.00
840.00
L-13
hour
6.000
230.00
1380.00
P&M-031
hour
6.000
1700.00
10200.00
P&M-025
hour
6.000
520.00
3120.00
P&M-017
hour
6.000
506.00
3036.00
P&M-048
hour
6.00x0.65*
994.00
3876.60
P&M-059
hour
4.280
692.00
2961.76
P&M-004
cum
97.500
609.00
59377.50
M-051
tonne
0.250
20528.00
5132.00
M-074
Machinery
Material
Crushed stone aggregate 11.2 mm size
Bitumen (60-70 grade)
d)
e)
7213.49
9738.22
107120.37
14.28
say
Note
4.12
406
14.00
Sr No
Ref. to
MoRTH
Spec.
Description
Unit
Quantity
Rate Rs
Cost Rs
Remarks/
Input ref.
b)
Labour
Mate
day
0.480
80.00
38.40
L-12
Mazdoor skilled
day
2.000
100.00
200.00
L-15
Mazdoor
day
10.000
70.00
700.00
L-13
hour
6.600
1036.00
6837.60
P&M-094
hour
6.000
450.00
2700.00
P&M-018
hour
6.000
520.00
3120.00
P&M-017
Machinery
Paver finisher
hour
6.000
739.00
4434.00
P&M-035
hour
6x0.65
994.00
3876.60
P&M-059
hour
12.000
hour
3.000
506.00
1518.00
P&M-060
tonne.km
495 x L
2.00
16830.00
Lead =17
km & P&M058
or
Tipper
1683.00
cum
89.100
438.48
39068.57
cum
118.800
517.65
61496.82
M-031
cum
89.100
395.85
35270.24
M-022
KL
18.000
10.00
180.00
M-189
Cost of water
d)
e)
14236.26
19218.95
211408.43
939.59
say
Note
4.14
407
M-034
939.60
b)
Labour
Mate
day
0.160
80.00
12.80
L-12
Mazdoor
day
4.000
70.00
280.00
L-13
Machinery
Sr No
Ref. to
MoRTH
Spec.
Description
Unit
Quantity
Rate Rs
hour
1.000
506.00
506.00
P&M-060
hour
6.000
100.00
600.00
P&M-086
hour
0.500
840.00
420.00
P&M-026
tonne.km
52.5 x L
2.00
Cost of water
d)
e)
KL
6.000
10.00
265.28
2918.08
138.96
say
A. Earthen Shoulders
The rate as applicable for sub-grade construction may be
adopted.
B. Hard Shoulders
Rate as applicable for sub-base and or base may be adopted
as per approved design.
C. Paved shoulders
The rate may be adopted as applicable for different layers of
pavement depending upon approved design of paved
shoulders.
60.00
196.50
525.00 Lead =5 km
& P&M-058
52.50
4.15
Remarks/
Input ref.
Note
Cost Rs
139.00
M-189
CHAPTER - 5
BASES AND SURFACE COURSES (BITUMINOUS)
Sr No
5.1
Ref. to
MoRTH
Spec.
502
Description
Quantity
Rate Rs
Cost Rs
Remarks/
Input ref.
day
day
0.080
2.000
80.00
70.00
6.40
140.00
L-12
L-13
hour
hour
hour
hour
2.800
2.800
2.000
1.000
230.00
206.00
692.00
506.00
644.00
576.80
1384.00
506.00
P&M-031
P&M-001
P&M-004
P&M-060
tonne
KL
2.100
6.000
15245.00
10.00
M-076
M-189
say
32014.50
60.00
2826.54
3815.82
41974.06
11.99
12.00
Prime Coat
Providing and applying primer coat with bitumen
emulsion on prepared surface of granular Base
including clearing of road surface and spraying primer
at the rate of 0.60 kg/sqm using mechanical means.
Unit = sqm
Taking output = 3500 sqm
a) Labour
Mate
Mazdoor
b) Machinery
Mechanical broom @ 1250 sqm per hour
Air compressor 250 cfm
Bitumen pressure distributor @ 1750 sqm per hour
Water tanker 6 KL capacity @ 1 trip per hour
c) Material
Bitumen emulsion @ 0.6 kg per sqm (SS1)
Cost of water
d) Overhead charges @ 8% on (a+b+c)
e) Contractor's profit @ 10% on (a+b+c+d)
Cost for 3500 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/3500
Note
5.2
Unit
503
day
day
0.080
2.000
80.00
70.00
6.40
140.00
L-12
L-13
hour
hour
hour
2.800
2.800
2.000
230.00
206.00
692.00
644.00
576.80
1384.00
P&M-031
P&M-001
P&M-004
tonne
0.700
15391.00
10773.70
1081.99
1460.69
16067.58
4.59
4.60
M-077
say
Note
5.6
507
Sr No
Ref. to
MoRTH
Spec.
Description
Unit
Quantity
Rate Rs
Cost Rs
Remarks/
Input ref.
b)
Mate
day
0.840
80.00
67.20
L-12
day
16.000
70.00
1120.00
L-13
day
5.000
100.00
500.00
L-15
hour
6.000
11167.00
67002.00
P&M-022
hour
6.000
1725.00
10350.00
P&M-034
hour
6.000
1125.00
6750.00
P&M-081
hour
6.000
520.00
3120.00
P&M-017
tonne.km
450 x L
2.00
15300.00
Lead =17
km & P&M058
Machinery
1530.00
hour
6.00x0.65*
269.00
1049.10
P&M-044
hour
6.00x0.65*
994.00
3876.60
P&M-059
hour
6.00x0.65*
738.00
2878.20
P&M-045
tonne
19.130
20528.00
392700.64
M-074
cum
63.190
438.48
27707.55
M-049
25 - 10 mm 13 per cent
cum
37.340
517.65
19329.05
M-046
cum
54.580
468.93
25594.20
M-040
cum
126.390
401.94
50801.20
M-030
cum
5.630
395.85
2228.64
M-021
25 - 10 mm 30 per cent
cum
86.160
517.65
44600.72
M-046
10 - 5 mm 28 per cent
cum
80.430
468.93
37716.04
M-040
cum
114.900
401.94
46182.91
M-030
cum
5.630
395.85
2228.56
M-021
or
Grading - II19 mm (Nominal Size)
Sr No
Ref. to
MoRTH
Spec.
Description
(i)
Unit
Quantity
Rate Rs
d)
e)
50552.35
68245.67
750702.40
3849.76
say
3849.80
e)
50957.76
68792.97
756722.70
Remarks/
Input ref.
(ii)
Cost Rs
3880.63
say
3880.60
80.00
67.20
*1. Although the roller are required only for 3 hours as per
norms of output, but the same have to be available at site for
six hours as the hot mix plant and paver will take six hours
for mixing and paving the output of 450 tonnes considered in
this analysis. To cater for the idle period of these rollers,
their usage rates have been multiplied by a factor of 0.65.
2.Quantity of Bitumen has been taken for analysis purpose.
The actual quantity will depend upon job mix formula.
3. Labour for traffic control, watch and ward and other
miscellaneous duties at site including sundries have been
included in administrative overheads of the contractor.
4. In case DBM is laid over freshly laid tack coat, provision
of mechanical broom and 2 mazdoors shall be deleted as
the same has been included in the cost of tack coat.
5. The individual density for each size of aggregates to be
used for construction I.e. 37.5-25 mm, 25-10 mm etc. should
be found in the laboratory and accordingly the quantities
should be ammended for use in field. The average density of
1.5 tonne/cum is only a reference density in this Data Book.
5.8
509
day
0.840
L-12
Sr No
Ref. to
MoRTH
Spec.
Unit
Quantity
Rate Rs
Cost Rs
Remarks/
Input ref.
day
16.000
70.00
1120.00
L-13
day
5.000
100.00
500.00
L-15
hour
6.000
11167.00
67002.00
P&M-022
hour
6.000
1725.00
10350.00
P&M-034
hour
6.000
1125.00
6750.00
P&M-081
hour
6.000
520.00
3120.00
P&M-017
tonne.km
450 x L
2.00
15300.00
Lead =17
km & P&M058
Description
Mazdoor working with HMP, mechanical broom, paver,
roller, asphalt cutter and assistance for setting out lines,
levels and layout of construction
Skilled mazdoor for checking line & levels
b)
Machinery
1530.00
hour
6.00x0.65*
269.00
1049.10
P&M-044
hour
6.00x0.65*
994.00
3876.60
P&M-059
hour
6.00x0.65*
738.00
2878.20
P&M-045
tonne
22.500
20986.00
472185.00
M-074
20 - 10 mm 35 per cent
cum
99.750
517.65
51635.59
M-045
10 - 5 mm 23 per cent
cum
65.550
468.93
30738.36
M-040
cum
114.000
401.94
45821.16
M-030
cum
5.59
395.85
2211.22
M-021
(i)
e)
57290.75
77342.52
850767.70
4454.28
say
Note
*1. Although the rollers are required only for 3 hours as per
norms of output, but the same have to be available at site for
six hours as the hot mix plant and paver will take six hours
for mixing and paving the output of 450 tonnes considered in
this analysis. To cater for the idle period of these rollers,
their usage rates have been multiplied by a factor of 0.65
2.Quantity of Bitumen has been taken for analysis purpose.
The actual quantity will depend upon job mix formula.
3. Labour for traffic control, watch and ward and other
miscellaneous duties at site including sundries have been
included in administrative overheads of the contractor.
4. In case BC is laid over freshly laid tack coat, provision of
mechanical broom and 2 mazdoors shall be deleted as the
same has been included in the cost of tack coat.
4454.30
Sr No
Ref. to
MoRTH
Spec.
Description
Unit
Quantity
Rate Rs
Cost Rs
Remarks/
Input ref.
5.9
510
b)
c)
Mate
day
0.440
80.00
35.20
L-12
Mazdoor
day
9.000
70.00
630.00
L-13
Mazdoor skilled
day
2.000
100.00
200.00
L-15
hour
7.200
230.00
1656.00
P&M-031
hour
7.200
206.00
1483.20
P&M-001
hour
6.000
1700.00
10200.00
P&M-025
hour
6.000
506.00
3036.00
P&M-048
hour
6.000
520.00
3120.00
P&M-017
hour
6.000
692.00
4152.00
P&M-004
hour
6.000
269.00
1614.00
P&M-044
tonne
10.800
20528.00
221702.40
M-074
cum
135.000
517.65
69882.75
M-053
Machinery
Material
Bitumen@ 1.20 kg per sqm
25416.92
34312.85
377441.32
41.94
say
Note
5.10
511
41.90
Sr No
Ref. to
MoRTH
Spec.
Description
Unit
Quantity
Rate Rs
Cost Rs
Remarks/
Input ref.
b)
Mate
day
0.840
80.00
67.20
L-12
day
16.000
70.00
1120.00
L-13
day
5.000
100.00
500.00
L-15
hour
6.000
15100.00
90600.00
P&M-021
hour
6.000
1125.00
6750.00
P&M-081
hour
6.000
520.00
3120.00
P&M-017
tonne.km
450 x L
2.00
15300.00
Lead =17
km & P&M058
Machinery
hour
6.000
1725.00
10350.00
P&M-034
hour
6.000
738.00
4428.00
P&M-045
tonne
14.970
20528.00
307304.16
M-074
cum
276.750
609.00
168540.75
M-043
c)
Material
Bitumen@ 14.60 kg per 10 sqm
1530.00
48768.81
65837.89
724216.81
70.66
say
5.10
Note
(ii)
71.00
b)
c)
Mate
day
0.800
80.00
64.00
L-12
Mazdoor
day
18.000
70.00
1260.00
L-13
Mazdoor skilled
day
2.000
100.00
200.00
L-15
hour
6.000
161.00
966.00
P&M-009
hour
6.000
269.00
1614.00
P&M-044
tonne
1.940
input
#VALUE!
M-073
Machinery
Material
Cationic Bitumen Emulsion @ 21.50 kg per 10 sqm
Sr No
Ref. to
MoRTH
Spec.
Description
Crushed stone aggregates 13.2 mm to 5.6 mm @ 0.27
cum per 10 sqm
d) Overhead charges @ 8% on (a+b+c)
e)
Unit
Quantity
Rate Rs
Cost Rs
Remarks/
Input ref.
cum
24.300
609.00
14798.70
M-043
#VALUE!
#VALUE!
#VALUE!
#VALUE!
say
5.11
512
#VALUE!
b)
Mate
day
0.840
80.00
67.20
L-12
day
16.000
70.00
1120.00
L-13
day
5.000
100.00
500.00
L-15
hour
6.000
8930.00
53580.00
P&M-023
hour
6.000
1125.00
6750.00
P&M-081
hour
6.000
520.00
3120.00
P&M-017
tonne.km
450 x L
2.00
15300.00
Lead =17
km & P&M058
Machinery
1530.00
hour
6.000
1725.00
10350.00
P&M-034
hour
6.000
269.00
1614.00
P&M-044
tonne
22.500
20528.00
461880.00
M-074
cum
276.750
609.00
168540.75
M-041
Material
Type - A
* Bitumen@ 22 kg per 10 sqm
Stone crushed aggregates 11.2 mm to 0.09 @ 0.27 cum
per 10 sqm
d) Overhead charges @ 8% on (a+b+c)
e)
57948.16
78230.01
860530.12
83.95
say
84.00
CHAPTER- 6
CEMENT CONCRETE PAVEMENTS
Sr No
6.1
Ref. to
MoRTH Spec.
Description
601
Quantity
Rate Rs
Cost Rs
Remarks/
Input ref.
6.2
Unit
Page 1 of 2
day
day
day
1.120
6.000
22.000
80.00
100.00
70.00
89.60
600.00
1540.00
L-12
L-15
L-13
hour
hour
hour
hour
hour
hour
tonne.km
6.000
6.000
6.000
6.000
8.000
8.000
990 x L
520.00
2760.00
450.00
1725.00
994.00
506.00
2.00
3120.00
16560.00
2700.00
10350.00
7952.00
4048.00
33660.00
P&M-017
P&M-068
P&M-080
P&M-034
P&M-059
P&M-060
Lead =17
km & P&M058
3366.00
cum
405.000
563.00
cum
203.000
149.00
30247.00
M-004
tonne
KL
67.500
48.000
4400.00
10.00
M-081
M-189
say
297000.00
480.00
51178.21
69090.58
759996.39
1688.88
1688.90
day
day
day
2.000
15.000
35.000
80.00
100.00
70.00
160.00
1500.00
2450.00
L-12
L-15
L-13
hour
hour
2.800
18.000
230.00
520.00
644.00
9360.00
P&M-031
P&M-017
Sr No
Ref. to
MoRTH Spec.
Description
Cement concrete batch mix plant @ 175 cum per hour
(effective output)
Electric generator 250 KVA
Slip form paver with electronic sensor
Water tanker6 KL capacity
Transit truck agitator 5 cum capacity.
Unit
Quantity
Rate Rs
6.000
5160.00
30960.00
P&M-067
hour
hour
hour
tonne.km
6.000
6.000
36.000
2415xL
1125.00
16188.00
506.00
2.00
6750.00
97128.00
18216.00
82110.00
P&M-081
P&M-095
P&M-060
Lead =17
km & P&M058
8211.00
hour
hour
12.000
12.000
300.00
250.00
cum
945.000
563.00
cum
473.000
149.00
70477.00
M-004
tonne
tonne
tonne
sqm
414.000
9.450
1.170
3675.000
4400.00
29902.00
29902.00
3.00
1821600.00
282573.90
34985.34
11025.00
M-081
M-126
M-082
M-164
sqm
16.330
80.00
1306.40
M-141
kg
kg
sqm
liter
kg
875.000
116.670
46.670
1850.000
2070.000
50.00
30.00
90.00
20.00
40.00
43750.00
3500.10
4200.30
37000.00
82800.00
M-120
M-097
M-138
M-090
M-180
KL
216.000
10.00
3600.00
3000.00
2160.00
M-189
257662.09
347843.83
3826282.09
3644.08
say
Page 2 of 2
P&M-083
P&M-088
29274.13
Note
Remarks/
Input ref.
hour
Cost Rs
3644.10
CHAPTER-7
GEOSYNTHETICS AND REINFORCED EARTH
Sr No
7.1
Ref. to
MoRTH
Spec.
702
Description
Geonets
Geomembrane
Geotextile
Add 2 per cent cost of material for miscellaneous items like
synthetic cord
c) Overhead charges @ 8% on (a+b)
d) Contractor's profit @ 10% on (a+b+c)
Rate per metre = a+b+c+d
Note
702.4
Note
703
Rate Rs
Cost Rs
Remarks/
Input ref.
day
day
day
0.040
0.250
0.500
sqm
sqm
sqm
1.000 input
1.000 input
2.000 input
80.00
100.00
70.00
3.20
25.00
35.00
#VALUE!
#VALUE!
#VALUE!
#VALUE!
say
#VALUE!
#VALUE!
#VALUE!
#VALUE!
80.00
100.00
70.00
3.20
25.00
35.00
L-12
L-15
L-13
M-107
M-106
M-108
7.3
Quantity
7.2
Unit
Page 1 of 5
day
day
day
metre
sqm
day
day
0.040
0.250
0.500
1.000 input
1.250 input
0.800
20.000
#VALUE!
#VALUE!
#VALUE!
say
#VALUE!
#VALUE!
#VALUE!
#VALUE!
80.00
70.00
64.00
1400.00
L-12
L-15
L-13
M-134
M-109
L-12
L-13
Sr No
Ref. to
MoRTH
Spec.
Description
Machinery
Road sweeper 1250 sqm per hour
Pneumatic roller 14 tonnes 2000 sqm per hour
Bitumen pressure distributor 1750 sqm per hour
c) Material
Paving Fabric
Paving Bitumen 80-100
c) Overhead charges @ 8% on (a+b)
d) Contractor's profit @ 10% on (a+b+c)
Cost for 2800 sqm = a+b+c+d+e
Rate per sqm =(a+b+c+d+e)/2800
Unit
Quantity
Rate Rs
Cost Rs
Remarks/
Input ref.
b)
hour
hour
hour
sqm
tonne
2.240
1.400
1.680
230.00
802.00
692.00
515.20
1122.80
1162.56
P&M-031
P&M-037
P&M-004
2940.000 input
2.800
20986.00
#VALUE!
58760.80
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
M-133
M-075
say
7.4
704
b)
Mate
day
0.060
80.00
4.80
L-12
Mazdoor skilled
day
0.500
100.00
50.00
L-15
Mazdoor
day
1.500
70.00
105.00
L-13
Material
Geo grids
sqm
21.000 input
#VALUE!
M-105
Connectors/ Staples
each
50.000 input
#VALUE!
M-085
metre
20.000 input
Polymer braids
Stones with minimum size of 200 mm
cum
3.450
289.00
cum
0.450
289.00
c)
d)
M-003
130.05
M-008
#VALUE!
#VALUE!
M-140
997.05
#VALUE!
7.5
#VALUE!
#VALUE!
say
#VALUE!
80.00
28.80
7.5
3102
(i)
Labour
Mate
day
Page 2 of 5
0.360
L-12
Sr No
Ref. to
MoRTH
Spec.
Description
b)
Unit
Quantity
Rate Rs
Cost Rs
Remarks/
Input ref.
Mazdoor
day
6.000
70.00
420.00
L-13
Mazdoor skilled
day
3.000
100.00
300.00
L-15
Material
metre
450*1.1 input
#VALUE!
M-154
metre
450*1.1 input
#VALUE!
M-153
metre
450*1.1 input
#VALUE!
M-157
metre
450*1.1 input
#VALUE!
M-156
metre
450*1.1 input
#VALUE!
M-155
or
2.Copper Strips
or
3.Aluminium Strips
or
4.Stainless steel strips
or
Type 1
d)
#VALUE!
#VALUE!
#VALUE!
#VALUE!
say
Type 2
2.Copper Strips
c)
d)
#VALUE!
#VALUE!
#VALUE!
#VALUE!
say
Type 3
c)
d)
#VALUE!
#VALUE!
#VALUE!
#VALUE!
say
c)
d)
#VALUE!
#VALUE!
#VALUE!
#VALUE!
say
#VALUE!
#VALUE!
#VALUE!
say
#VALUE!
#VALUE!
7.5(i)
#VALUE!
Type 5
#VALUE!
3.Aluminium Strips
Type 4
#VALUE!
#VALUE!
b)
Labour
Mate
day
0.360
80.00
28.80
L-12
Mazdoor
day
6.000
70.00
420.00
L-13
Mazdoor skilled
day
3.000
100.00
300.00
L-15
Material
Page 3 of 5
Ref. to
MoRTH
Spec.
Sr No
Description
Synthetic Geogrids as per clause 3102.8 and approved
design and specifications.
Add 10 per cent of the cost of reinforcing elements
(synthetic geogrids) for accessories like tie-strips, nuts
and bolts and loops/lugs for joining reinforcing elements
with the facia pannels, overlaps and other protective
elements for synthetic geogrids.
c) Overhead charges @ 8% on (a+b)
d)
Unit
Quantity
sqm
300.000
Rate Rs
46.00
1720.31
18923.41
63.08
say
(ii)
M-181
1274.30
13800.00
Remarks/
Input ref.
1380.00
7.5
Cost Rs
63.00
b)
Labour
Mate
day
0.180
80.00
14.40
L-12
Mazdoor
day
3.000
70.00
210.00
L-13
Mazdoor skilled
day
1.500
100.00
150.00
L-15
hour
6.000
230.00
1380.00
P&M-013
cu.m
13.500
2859.60
38604.60
Item 12.8
(H)
tonnes
0.380
29902.00
11362.76
Item 13.6
Machinery
Light crane with lifting capacity upto 3 tonne
c)
Material
Pre-cast RCC M-35 facing elements of size as per
design and 18 cm thick for 75 sqm. (Refer Item 12.8 (H))
HYSD steel @ 5 kg / sqm (Refer Item 12.6)
999.35
d)
140.35
e)
189.48
53050.93
707.35
say
Note
Page 4 of 5
707.00
Sr No
Ref. to
MoRTH
Spec.
Description
11.Capping beam is to be priced separately as per approved
design. The rate for cement concrete shall be taken from the
chapter of sub-structure in bridge section.
12.The cost of reinforced earth retaining wall shall include
following:
(I) Excavation for foundation including backfilling.
(ii) Foundation concrete as per approved design.
(iii) Cost of facial pannels and their erection .
(iv) Cost of reinforcing elements including their fixing and
joining with the facial pannels.
(v) Drainage arrangement including filter media as per
approved design and drawings.
13. The compacted earth filling to be retained shall form part
of embankment.
Page 5 of 5
Unit
Quantity
Rate Rs
Cost Rs
Remarks/
Input ref.
CHAPTER-8
TRAFFIC SIGNS, MARKINGS & OTHER ROAD APPURTENANCES
Sr No
8.1
Ref. to
MoRTH
Spec.
408
Quantity
Rate Rs
Unit
day
day
day
0.120
1.000
2.000
80.00
100.00
70.00
9.60
100.00
140.00
L-12
L-11
L-13
hour
hour
hour
hour
6.000
1.600
5.000
6.000
200.00
1200.00
506.00
506.00
1200.00
1920.00
2530.00
3036.00
P&M-029
P&M-003
P&M-060
P&M-048
cum
21.790
517.65
11279.59
M-053
cum
tonne
KL
10.900
5.700
30.000
149.00
4400.00
10.00
1624.10
25080.00
300.00
3777.54
5099.68
56096.52
155.82
155.80
M-004
M-081
M-189
say
8.3
801
(i)
Cost Rs
Remarks/
Input ref.
Description
b)
Labour
Mate
day
0.120
80.00
9.60
L-12
Painter
day
2.000
100.00
200.00
L-18
Mazdoor
day
1.000
70.00
70.00
L-13
Litre
0.700
132.24
92.57
M-131
Material
Paint
c)
d)
29.77
40.19
442.14
0.28
say
8.3
(ii)
0.30
Sr No
Ref. to
MoRTH
Spec.
Description
Unit
Quantity
Rate Rs
Cost Rs
Remarks/
Input ref.
b)
Labour
Mate
day
0.070
80.00
5.60
L-12
day
1.250
100.00
125.00
L-18
Mazdoor
day
0.500
70.00
35.00
L-13
Litre
0.500
132.24
66.12
M-131
Material
Paint
c)
d)
18.54
25.03
275.28
801
0.17
say
0.20
69.60
15.03
2715.70
325.88
11.83
Item No.
3.13
Item 12.8
(A)
Item 8.9
a)
b)
i)
cum
0.216
ii)
cum
0.120
iii)
sqm
0.430
27.50
day
0.010
80.00
0.80
L-12
Mazdoor
day
0.250
70.00
17.50
L-13
kg
19.000
30.64
582.16
M-179
/1000
Material
Mild steel angle iron 75 x 75 x 6 mm
(i)
11.64
sqm
0.350
6000.00
2100.00
M-061
sqm
0.156
6000.00
936.00
M-061
sqm
0.283
6000.00
1698.00
M-061
sqm
0.480
6000.00
2880.00
M-061
sqm
0.270
6000.00
1620.00
M-061
sqm
0.360
6000.00
2160.00
M-061
sqm
0.672
6000.00
4032.00
M-061
hour
0.010
231.00
2.31
or
( ii )
60 cm equilateral triangle
or
( iii )
60 cm circular
or
( iv )
80 mm x 60 mm rectangular
or
(v)
60 cm x 45 cm rectangular
or
(vi )
60 cm x 60 cm square
or
( vii )
90 cm high octagon
c)
Machinery
Tractor-trolley
(i)
90 cm equilateral triangle
P&M-053
Sr No
Ref. to
MoRTH
Spec.
Description
d)
e)
Unit
Quantity
Rate Rs
216.22
291.90
3563.63
say
( ii )
d)
e)
123.10
166.19
2180.80
say
d)
e)
184.06
248.48
3086.06
say
d)
e)
278.62
376.14
4490.27
say
d)
e)
177.82
240.06
2993.39
say
d)
e)
221.02
298.38
3634.91
say
d)
e)
370.78
500.56
5858.85
say
8.5
801
3634.90
90 cm high octagon
Note
2993.40
60 cm x 60 cm square
4490.30
60 cm x 45 cm rectangular
3086.10
80 mm x 60 mm rectangular
2180.80
60 cm circular
3563.60
60 cm equilateral triangle
Cost Rs
5858.80
Remarks/
Input ref.
Sr No
Ref. to
MoRTH
Spec.
Description
Unit
Quantity
Rate Rs
Cost Rs
Remarks/
Input ref.
Unit = sqm
Taking output = 0.9 sqm
a)
69.60
15.03
2715.70
325.88
0.430
27.50
11.83
Item No.
3.13
Item 12.8
(A)
Item 8.9
cum
0.216
cum
0.120
sqm
day
0.010
80.00
0.80
L-12
Mazdoor
day
0.200
70.00
14.00
L-13
kg
19.000
30.64
582.16
sqm
0.900
6000.00
5400.00
M-179
/1000
M-061
b)
Material
Mild steel angle iron 75 mm x 75 mm x 6 mm,2.85
metres long
Aluminium sheeting fixed with encapsulated lens type
reflective sheeting of size 0.9 sqm
Add 2 per cent of cost of materials for drilling holes, nuts,
bolts, fabrication etc.
c) Machinery
Tractor-trolley
d)
e)
119.64
hour
0.020
231.00
8.6
801
P&M-053
661.09
Note
4.62
489.70
7624.76
8471.95
say
8472.00
69.60
29.93
2715.70
651.77
23.65
Item No.
3.13
Item 12.8
(A)
Item 8.9
a)
i)
cum
0.430
ii)
cum
0.240
iii)
sqm
0.860
27.50
day
0.010
80.00
0.80
L-12
Mazdoor
day
0.300
70.00
21.00
L-13
kg
38.000
30.64
1164.32
sqm
1.500
6000.00
9000.00
b)
Material
Mild steel angle iron 75 mm x 75 mm x 6 mm, 2.85
metres long, 2 nos
Aluminium sheeting fixed with encapsulated lens type
reflective sheeting
Add 2 per cent of cost of materials for drilling holes, nuts,
bolts, fabrication etc.
c) Machinery
203.29
M-179
/1000
M-061
Sr No
Ref. to
MoRTH
Spec.
Description
Tractor-trolley
d)
e)
Unit
hour
Quantity
0.020
Rate Rs
231.00
802
P&M-053
1122.55
13053.45
8702.30
say
8.7
4.62
Remarks/
Input ref.
831.52
Note
Cost Rs
8702.30
Labour
Mate
day
0.240
80.00
19.20
L-12
200.00
L-02
L-13
Blacksmith
day
2.000
100.00
day
4.000
70.00
280.00
tonne
1.050
29902.00
31397.10
b)
Material
Aluminium alloy/galvanised steel including 5 per cent
wastage
Add 1 per cent on cost of material for nuts, bolts and drilling
and welding consumables
Add 15 per cent on cost of material for fabrication of trusses
as per approved design
c) Machinery
313.97
4709.57
hour
3.000
230.00
690.00
P&M-013
Truck
hour
0.500
506.00
253.00
P&M-057
d)
e)
3029.03
4089.19
44981.05
say
8.7
M-060
44981.00
Labour
Mate
day
0.020
80.00
1.60
L-12
Blacksmith
day
0.100
100.00
10.00
L-02
Mazdoor
day
0.150
70.00
10.50
L-13
sqm
1.000
200.00
200.00
M-059
b)
Material
Aluminium alloy plate,2 mm thick, fixed with high
intensity grade sheeting vide clause 801.3
Miscellaneous
Add 1 per cent of cost of labour for lifting arrangement, like
ladders, pulleys, ropes etc
c) Overhead charges @ 8% on (a+b)
0.22
17.79
Sr No
Ref. to
MoRTH
Spec.
Description
d)
Unit
Quantity
Rate Rs
264.12
say
8.8
803
Remarks/
Input ref.
24.01
Note
Cost Rs
264.10
b)
Labour
Mate
day
0.120
80.00
9.60
L-12
Painter
day
2.000
100.00
200.00
L-18
Mazdoor
day
1.000
70.00
70.00
L-13
Litre
6.000
132.24
793.44
M-132
Material
0.00
0.00
85.84
115.89
1274.77
31.87
say
8.9
803
31.90
b)
Labour
Mate
day
0.030
80.00
2.40
L-12
Painter
day
0.450
100.00
45.00
L-18
Mazdoor
day
0.250
70.00
17.50
L-13
Litre
1.250
132.24
165.30
M-131
Material
Paint ready mixed approved brand.
1.65
0.00
18.55
25.04
275.44
27.54
say
8.10
803
27.50
Sr No
Ref. to
MoRTH
Spec.
Description
Unit
Quantity
Rate Rs
Cost Rs
Remarks/
Input ref.
b)
Labour
Mate
day
0.030
80.00
2.40
L-12
Painter
day
0.500
100.00
50.00
L-18
Mazdoor
day
0.200
70.00
14.00
L-13
Litre
1.500
132.24
198.36
M-131
Material
Paint ready mixed of approved brand.
1.98
0.00
21.34
28.81
316.89
31.69
say
8.11
803
(i)
31.70
b)
Labour
Mate
day
0.090
80.00
7.20
L-12
Painter
day
0.550
100.00
55.00
L-18
Mazdoor
day
1.550
70.00
108.50
L-13
Litre
1.480
132.24
195.72
M-132
Material
Road marking Paint as per IS :164
c)
d)
29.31
39.57
435.30
43.53
say
8.11
(ii)
43.50
Up to 10 cm in width
Unit = sqm
Taking output = 10 sqm
a)
b)
Labour
Mate
day
0.070
80.00
5.60
L-12
Painter
day
0.350
100.00
35.00
L-18
Mazdoor
day
1.350
70.00
94.50
L-13
Litre
1.480
132.24
195.72
M-132
Material
Road marking paint
c)
d)
26.47
35.73
393.01
Sr No
Ref. to
MoRTH
Spec.
Description
Unit
Quantity
Rate Rs
Remarks/
Input ref.
39.30
say
8.13
Cost Rs
39.30
803
b)
c)
Labour
Mate
day
0.500
80.00
40.00
L-12
Mazdoor
day
2.000
70.00
140.00
L-13
hour
8.000
60.00
480.00
P&M-043
Tractor-trolley
hour
8.000
231.00
1848.00
P&M-053
Litre
1500.000
172.00
258000.00
M-118
kg
200.000
200.00
40000.00
M-152
Machinery
Material
Hot applied thermoplastic compound
Reflectorising glass beads
d)
e)
24040.64
32454.86
357003.50
Note
8.14
804
(i)
557.82
say
557.80
2715.70
6381.90
29.90
660.24
69.60
116.93
32.00
315.20
Item 12.8
(A)
Item 13.6
/1000
Item No.
3.13
Item 8.8
0.20
360.00
Item 8.3
b)
c)
g)
cum
2.350
kg
22.080
cum
1.680
sqm
per cm per
letter
9.850
1800.00
Labour
Mate
day
0.260
80.00
20.80
L-12
Mason
day
0.600
100.00
60.00
L-11
day
6.000
70.00
420.00
L-13
hour
6.000
231.00
1386.00
P&M-053
Machinery
Tractor-trolley
Sr No
Ref. to
MoRTH
Spec.
Description
h)
i)
Unit
Quantity
Rate Rs
(ii)
Remarks/
Input ref.
150.94
203.77
Cost Rs
10075.78
1679.30
say
1679.30
2715.70
10238.19
29.90
787.02
69.60
192.79
b)
c)
g)
(iii)
3.770
kg
26.320
cum
2.770
sqm
per cm per
letter
11.410
1680.000
32.00
365.12
Item 12.8
(A)
Item 13.6
/1000
Item No.
3.13
Item 8.8
0.20
336.00
Item 8.3
Labour
Mate
day
0.320
80.00
25.60
L-12
Mason
day
1.000
100.00
100.00
L-11
Mazdoor
day
7.000
70.00
490.00
L-13
hour
6.000
231.00
1386.00
P&M-053
Machinery
Tractor-trolley
8.14
cum
h)
160.13
i)
216.17
14297.02
1021.22
say
1021.20
2715.70
4290.81
29.90
1973.53
69.60
96.74
32.00
200.64
Item 12.8
(A)
Item 13.6
/1000
Item No.
3.13
Item 8.8
0.20
66.00
Item 8.3
b)
c)
kg
66.000
cum
1.390
sqm
per cm per
letter
6.270
330.000
day
0.340
80.00
27.20
L-12
150.00
L-11
Mason
day
1.500
100.00
Mazdoor
day
7.000
70.00
490.00
L-13
hour
6.000
231.00
1386.00
P&M-053
Machinery
Tractor-trolley
h)
1.580
Labour
Mate
g)
cum
164.26
221.75
9066.92
Sr No
Ref. to
MoRTH
Spec.
Description
Unit
Quantity
Rate Rs
8.15
805
Remarks/
Input ref.
274.76
say
Note
Cost Rs
274.80
Labour
Mate
day
0.040
80.00
3.20
L-12
day
1.000
70.00
70.00
L-13
each
30.000
600.00
18000.00
b)
Material
Cost of approved type of delineators from ISI certified
firm as per the standard drawing given in IRC - 79
Add 10 per cent cost of material for installation
c)
d)
1800.00
1589.86
2146.31
23609.36
Note
8.16
806
M-091
786.98
say
787.00
2715.70
3394.63
29.90
2386.18
69.60
746.11
0.20
456.00
b)
Steel reinforcement
c)
Excavation in soil
d)
cum
1.250
kg
79.800
cum
10.720
per letter
per cm high
Item 12.8
(A)
Item 13.6
/1000
Item No.
3.13
Item 8.3
2280.000
f)
Labour
Mate
day
0.570
80.00
45.60
L-12
Mazdoor
day
14.250
70.00
997.50
L-13
hour
6.000
231.00
1386.00
P&M-053
cum
11.970
289.00
3459.33
M-008
Machinery
Tractor-trolley
g)
Material
Stone spall
h)
471.07
Sr No
Ref. to
MoRTH
Spec.
Description
i)
Unit
Quantity
Rate Rs
13978.37
245.23
say
8.17
807
Remarks/
Input ref.
635.95
Note
Cost Rs
245.20
Labour
Mate
day
0.090
80.00
7.20
L-12
Blacksmith
day
0.250
100.00
25.00
L-02
Mazdoor
day
2.000
70.00
140.00
L-13
kg
31.420
#VALUE!
M-063
kg
80.500
2466.52
M-179
/1000
b)
Material
Barbed wire 335 metres length @ 9.38 kg per 100
metres
MS angle iron 40 mm x 40mm x 6 mm, 23 metres in
length @ 3.5 kg per metre
Add for GI staple binding wire, drilling holes etc. @ 2 per
cent of the cost of material
c) Painting
Applying two coats of painting on exposed surface of
angle iron posts ( Rate as per item no. 8.9)
d) Overhead charges @ 8% on (a+b)
e)
input
30.64
#VALUE!
sqm
2.110
27.50
#VALUE!
#VALUE!
#VALUE!
#VALUE!
say
Note
8.18
807
Labour
58.03
#VALUE!
Item 8.9
Sr No
Ref. to
MoRTH
Spec.
Description
Unit
Quantity
Rate Rs
Cost Rs
Remarks/
Input ref.
Mate
day
0.120
80.00
9.60
L-12
Blacksmith
day
0.400
100.00
40.00
L-02
Mazdoor
day
2.500
70.00
175.00
L-13
kg
40.150
#VALUE!
M-063
kg
152.000
4657.28
M-179
/1000
b)
Material
Barbed wire 428 metres length @ 9.38 kg per 100
metres
MS angle iron 50 mm x 50 mm x 6 mm,33.8 metres in
length @ 4.5 kg per metre
Add for GI staple, binding wire, drilling holes etc. @ 2
per cent of the cost of material
c) Painting
Applying two coats of painting on exposed surface of
angle iron posts
d) Overhead charges @ 8% on (a+b)
e)
input
30.64
#VALUE!
sqm
27.50
3.960
#VALUE!
#VALUE!
#VALUE!
say
8.19
Suggesti
ve
Item 8.9
#VALUE!
Note
108.90
#VALUE!
Labour
Mate
b)
0.120
80.00
9.60
L-12
100.00
L-02
Welder
day
1.000
100.00
Mazdoor
day
2.000
70.00
140.00
L-13
kg
106.000
30.64
3247.84
kg
26.000
30.64
796.64
kg
151.000
M-179
/1000
M-179
/1000
M-191
kg
293.000
Material
day
input
#VALUE!
hour
0.100
231.00
sqm
8.000
27.50
23.10
P&M-053
220.00
Item 8.9
Painting
Painting two coats including priming
e)
f)
#VALUE!
#VALUE!
#VALUE!
Sr No
Ref. to
MoRTH
Spec.
Description
Unit
Quantity
Rate Rs
8.20
808
Cost Rs
Remarks/
Input ref.
#VALUE!
say
#VALUE!
69.60
90.20
2715.70
1759.77
27.50
129.53
Item No.
3.13
Item 12.8
(A)
Item 8.9
27.50
59.40
Item 8.9
L-12
b)
1.296
cum
0.648
sqm
4.710
sqm
2.160
Mate
day
0.010
80.00
0.80
Mazdoor
day
0.250
70.00
17.50
L-13
Plumber
day
0.010
100.00
1.00
L-02
metre
30.000
600.00
18000.00
M-175
30.64
3044.39
M-179
/1000
Material
cum
kg
99.360
60.89
Machinery
Tractor-trolley
d)
e)
hour
0.040
231.00
27527.45
P&M-053
2501.66
8.21
9.24
1853.08
2752.75
say
2753.00
69.60
90.20
2715.70
1759.77
3726.20
1192.38
129.53
cum
1.296
cum
0.648
cum
0.320
sqm
4.710
27.50
Item No.
3.13
Item 12.8
(A)
Item
14.1(A)
Item 8.9
Labour
Mate
day
0.014
80.00
1.12
L-12
Mazdoor
day
0.350
70.00
24.50
L-13
Sr No
Ref. to
MoRTH
Spec.
Description
Plumber
b)
Quantity
Rate Rs
day
0.010
100.00
1.00
metre
30.000
600.00
18000.00
hour
0.250
231.00
d)
L-02
M-175
e)
57.75
P&M-053
1446.75
1953.11
24656.12
Remarks/
Input ref.
Machinery
Tractor-trolley
8.22
Cost Rs
Material
Steel pipe 50 mm dia as per IS:1239
c)
Unit
2465.61
say
2466.00
4084.00
12252.00
a)
M 40 grade concrete
M 40 grade concrete
b)
3.000
day
0.040
80.00
3.20
L-12
day
1.000
70.00
70.00
L-13
tonne
0.280
29902.00
8372.56
M-082
0.320
60.00
19.20
M-144
Labour
Mate
Mazdoor
c)
Material
HYSD steel reinforcement including dowel bars
Pre-moulded asphalt filler board
d)
e)
sqm
677.20
914.22
22308.37
2230.84
say
Note
8.29
Suggesti
ve
Item
14.1(A)
cum
2230.80
Sr No
Ref. to
MoRTH
Spec.
Description
(i)
Unit
Quantity
Rate Rs
Cost Rs
Remarks/
Input ref.
c)
2.360
2300.00
5428.00
Item 12.7
(Addl) B)
Mate
day
0.050
80.00
4.00
Mazdoor
day
1.000
70.00
70.00
L-13
Mazdoor skilled
day
0.250
100.00
25.00
L-15
L-12
metre
20.000
676.10
13521.93
M-151
140.00
1008.00
M-009
1000.00
9000.00
3162.00
63.24
Item 12.6
(B)
231.00
115.50
P&M-053
Material
Reinforced Cement Concrete pipe 300 mm dia
Granular soil with PI less than 6 for bedding and sides
of pipe (0.6 x 0.6 x 20 m)
Collar for joints 300 mm dia
Cement mortar 1:2 for joints
d)
cum
cum
7.200
each
9.000
cum
0.020
hour
0.500
M-083
Machinery
Tractor-trolley
e)
f)
1904.61
2571.23
33711.52
1685.58
say
1685.60
CHAPTER-9
PIPE CULVERTS
Sr No
9.2
Ref. to
MoRTH
Spec.
2900
Description
Unit
Quantity
Rate Rs
Cost Rs
Remarks/
Input ref.
Labour
Mate
Mason
Mazdoor
b) Material
Sand at site
Cement at site
RCC pipe NP-4 /prestressed concrete pipe including
collar at site
Granular material passing 5.6 mm sieve for bedding
c) Overhead charges @ 8% on (a+b)
d) Contractor's profit @ 10% on (a+b+c)
Cost for 12.5 metres = a+b+c+d
Rate per metre = (a+b+c+d)/12.5
Note
9.2
Note
day
day
day
0.180
0.500
4.000
80.00
100.00
70.00
14.40
50.00
280.00
L-12
L-11
L-13
cum
tonne
metre
0.070
0.050
12.500
149.00
4400.00
2804.09
10.43
220.00
35051.13
M-005
M-081
M-149
cum
4.500
140.00
M-009
say
630.00
2900.48
3915.64
43072.07
3445.77
3445.80
day
day
day
0.280
1.000
6.000
80.00
100.00
70.00
22.40
100.00
420.00
L-12
L-11
L-13
cum
tonne
metre
0.090
0.070
12.500
149.00
4400.00
3733.71
13.41
308.00
46671.38
M-005
M-081
M-150
cum
5.000
140.00
700.00
M-009
say
3858.81
5209.40
57303.40
4584.27
4584.30
Sr No
9.3
Ref. to
MoRTH
Spec.
2900
Description
Unit
Quantity
Rate Rs
Remarks/
Input ref.
b)
Labour
Mate
day
0.360
80.00
28.80
L-12
Mason
day
1.000
100.00
100.00
L-11
Mazdoor
day
8.000
70.00
560.00
L-13
Material
Sand at site
cum
0.140
149.00
20.86
M-005
Cement at site
tonne
0.100
4400.00
440.00
M-081
metre
25.000
2804.09
70102.25
M-149
cum
12.500
140.00
1750.00
M-009
c)
d)
5840.15
7884.21
86726.27
9.3
Cost Rs
6938.10
say
b)
Labour
Mate
day
0.560
80.00
44.80
L-12
Mason
day
2.000
100.00
200.00
L-11
Mazdoor
day
12.000
70.00
840.00
L-13
Material
Sand at site
Cement at site
cum
0.180
149.00
26.82
M-005
tonne
0.140
4400.00
616.00
M-081
metre
25.000
3733.71
93342.75
M-150
cum
13.750
140.00
1925.00
M-009
7759.63
10475.50
115230.50
6938.10
9218.44
say
9218.40
CHAPTER- 10
MAINTENANCE OF ROADS
Sr No
10.2
Ref. to
MoRTH
Spec.
3003
Description
Unit
Quantity
Rate Rs
day
day
0.180
4.500
80.00
70.00
14.40
315.00
L-12
L-13
hour
0.250
840.00
210.00
P&M-026
tonne.km
24xL
2.00
b)
c)
hour
12.000
100.00
1200.00
160.27
216.37
2380.04
23.80
23.80
P&M-086
Day
3.760
80.00
300.80
L-12
Mazdoor
Day
90.000
70.00
6300.00
L-13
Mazdoor skilled
Day
4.000
100.00
400.00
L-15
hour
6.000
206.00
1236.00
P&M-001
hour
6.000
15100.00
90600.00
P&M-021
hour
45.000
506.00
22770.00
P&M-048
hour
12.000
269.00
3228.00
P&M-044
cum
184.500
609.00
112360.50
M-052
cum
92.250
609.00
56180.25
M-051
tonne
14.970
20528.00
307304.16
M-074
tonne
2.460
15391.00
37861.86
M-077
Machinery
Material
Bitumen 60/70
Bitumen emulsion for tack coat including vertical sides
of pot hole.
d) Overhead charges @ 8% on (a+b+c)
e)
240.00 Lead =5 km
& P&M-058
24.00
say
3004.2
Remarks/
Input ref.
10.4
Cost Rs
51083.33
68962.49
758587.39
74.01
say
74.00
Sr No
10.6
Ref. to
MoRTH
Spec.
3004.3.3
Description
Unit
Quantity
Rate Rs
Cost Rs
Remarks/
Input ref.
Crack Filling
Filling of crack using slow - curing bitumen emulsion and
applying crusher dust in case crack are wider than 3mm.
Unit = Running Meter
Taking out put = 500m
a)
b)
Labour
Mate
day
0.040
80.00
3.20
L-12
Mazdoor
day
1.000
70.00
70.00
L-13
Kg
33.000
15.25
503.25
M-077
cum
0.020
395.85
7.92
M-021
Material
Slow-curing bitumen emulsion
Stone crusher dust
c)
d)
46.75
63.11
694.23
1.39
say
10.7
3004.4
1.40
Dusting
Applying crusher dust to areas of road where bleeding
of excess bitumen has occurred.
Unit = Sqm
Taking output = 3500 sqm
a)
b)
Labour
Mate
day
0.080
80.00
6.40
L-12
Mazdoor
day
2.000
70.00
140.00
L-13
cum
6.250
395.85
2474.06
M-021
Material
209.64
283.01
3113.11
0.89
say
10.8
10.8
10.9
(C)
3004.5
Slurry Seal
(i)
5 mm thickness
sqm
27.50
(ii)
3 mm thickness
sqm
18.90
(iii)
1.5 mm thickness
sqm
12.10
(D)
3004.6
3005.1
0.90
Item 5.15
Case-I
Item 5.15
Case-II
Item 5.15
Case-III
sqm
41.90
(ii)
sqm
35.60
Labour
Item 5.9
Case-I
Item 5.9
Case-II
Sr No
Ref. to
MoRTH
Spec.
Description
b)
Unit
Quantity
Rate Rs
Cost Rs
Remarks/
Input ref.
Mate
day
0.040
80.00
3.20
L-12
Mazdoor
day
0.500
70.00
35.00
L-13
Chiseller
day
0.500
100.00
50.00
L-05
Material
Epoxy primer
e)
kg
2.500
30.00
75.00
M-097
kg
10.000
200.00
2000.00
M-095
hour
0.050
206.00
10.30
173.88
234.74
2582.12
258.21
say
258.20
P&M-001
CHAPTER-11
HORTICULTURE
Sr No
11.1
11.2
Ref. to
MoRTH
Spec.
307
Description
Spreading of Sludge Farm Yard Manure or/and good
Earth
Spreading of sludge farm yard manure or/ and good earth in
required thickness (cost of sludge, farm yard manure or/and
good earth to be paid for separately)
Unit = cum
Taking output = 15 cum
a) Labour
Mate
Mazdoor
b) Overhead charges @ 8% on (a)
c) Contractor's profit @ 10% on (a+b)
Cost for 15 cum= a+b+c
Rate per cum = (a+b+c)/15
307
(i)
Unit
Quantity
day
day
Rate Rs
0.040
1.000
80.00
70.00
Cost Rs
Remarks/
Input ref.
L-12
L-13
say
3.20
70.00
5.86
7.91
86.96
5.80
5.80
Labour
Mate
Mazdoor for grassing
Mazdoor for maintenance for 30 days
b) Machinery
Water tanker6 KL capacity
c) Material
Doob grass
d) Overhead charges @ 8% on (a+b+c)
e) Contractor's profit @ 10% on (a+b+c+d)
Cost for 100 sqm = a+b+c+d+e
Rate per sqm= (a+b+c+d+e)/100
11.2
(ii)
Note
11.3
307
Page 1 of 9
day
day
day
0.170
0.750
1.000
80.00
70.00
70.00
13.60
52.50
70.00
L-12
L-13
L-13
hour
0.500
506.00
253.00
P&M-060
say
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
kg
100.000 input
M-112
day
day
day
0.220
1.250
1.000
80.00
70.00
70.00
17.60
87.50
70.00
L-12
L-13
L-13
hour
0.750
506.00
379.50
P&M-060
say
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
80.00
70.00
90.00
12.00
35.00
90.00
kg
day
day
day
200.000 input
0.150
0.500
1.000
M-112
L-12
L-13
L-09
hour
hour
cum
kg
0.500
0.010
0.180
100.000 input
506.00
231.00
253.00
2.31
P&M-060
P&M-053
50.00
9.00
#VALUE!
#VALUE!
#VALUE!
#VALUE!
M-167
M-113
say
#VALUE!
307
#VALUE!
Labour
Mali
b)
day
10.000
90.00
900.00
L-09
hour
15.000
506.00
7590.00
P&M-060
KL
90.000
10.00
900.00
M-189
Machinery
Material
Cost of water
d)
e)
751.20
1014.12
11155.32
111.55
say
11.5
307
112.00
Labour
Mate
day
0.250
80.00
20.00
L-12
day
1.000
70.00
70.00
L-13
day
1.500
90.00
135.00
L-09
hour
0.500
506.00
253.00
P&M-060
hour
0.010
231.00
2.31
P&M-053
cum
0.600
50.00
30.00
M-167
#VALUE!
M-113
c)
Material
Supply of farm yard manure at site of work @ 0.6 cum
per 100 sqm
Fine grass
d)
e)
kg
100.000 input
#VALUE!
#VALUE!
#VALUE!
307
#VALUE!
say
#VALUE!
90.00
900.00
Labour
Mali
b)
day
Machinery
Page 2 of 9
10.000
L-09
hour
20.000
506.00
10120.00
KL
60.000
10.00
600.00
Cost of water
d)
e)
1254.96
13804.56
M-189
929.60
11.7
P&M-060
Material
138.05
say
138.00
b)
Labour
Mate
day
1.400
80.00
112.00
L-12
day
10.000
70.00
700.00
L-13
day
4.000
70.00
280.00
L-13
hour
0.500
506.00
253.00
P&M-060
Machinery
Water tanker6 KL capacity
c)
Material
Cost of hedge plants 2 rows at 30 cm apart
each
2x340 input
cum
4.670
Pesticide
kg
0.250 input
Cost of water
KL
3.000
d)
e)
50.00
10.00
M-116
233.50
M-167
#VALUE!
M-136
30.00
M-189
#VALUE!
#VALUE!
#VALUE!
#VALUE!
say
(b)
#VALUE!
#VALUE!
b)
Labour
Mate
day
3.000
80.00
240.00
L-12
Mazdoor
day
30.000
70.00
2100.00
L-13
hour
5.000
506.00
2530.00
P&M-060
cum
2.000
50.00
100.00
M-167
#VALUE!
M-136
Machinery
Water tanker6 KL capacity
c)
Material
Manure sludge/Farm yard manure
Pesticide
kg
Cost of water
KL
e)
each
0.500 input
30.000
10.00
68.000 input
#VALUE!
#VALUE!
say
M-116
#VALUE!
M-189
#VALUE!
#VALUE!
11.8
300.00
Page 3 of 9
#VALUE!
b)
Labour
Mate
day
1.200
80.00
96.00
L-12
Mazdoor
day
12.000
70.00
840.00
L-13
hour
6.000
506.00
3036.00
P&M-060
M-100
Machinery
Water tanker6 KL capacity
c)
Material
Plants
each
200.000 input
#VALUE!
Shrubs
each
800.000 input
#VALUE!
M-166
cum
3182.00
M-167
#VALUE!
M-136
360.00
M-189
Pesticide
kg
Cost of water
KL
63.640
50.00
0.500 input
36.000
10.00
d)
#VALUE!
e)
#VALUE!
#VALUE!
say
11.8
(b)
#VALUE!
b)
Labour
Mate
day
36.000
80.00
2880.00
L-12
Mazdoor
day
365.000
70.00
25550.00
L-13
hour
90.000
506.00
45540.00
P&M-060
cum
10.000
50.00
500.00
M-167
KL
180.000
10.00
1800.00
M-189
M-100
Machinery
Water tanker6 KL capacity
c)
Material
Manure Sludge / farm yard manure at site
Cost of water
each
20.000 input
#VALUE!
Shrubs
each
80.000 input
#VALUE!
M-166
kg
1.500 input
#VALUE!
M-136
Pesticides
d)
#VALUE!
e)
#VALUE!
#VALUE!
say
11.9
307
#VALUE!
b)
Labour
Mate
day
1.700
80.00
136.00
L-12
day
2.000
70.00
140.00
L-13
day
15.000
70.00
1050.00
L-13
hour
2.000
506.00
1012.00
P&M-060
#VALUE!
M-160
47.00
M-167
Machinery
Water tanker6 KL capacity
c)
d)
Material
Sapling 2 m high 25 mm dia
each
cum
Pesticide
kg
Cost of water
KL
Page 4 of 9
10.000 input
0.940
50.00
0.500 input
12.000
10.00
#VALUE!
M-136
120.00
M-189
#VALUE!
#VALUE!
#VALUE!
#VALUE!
say
11.10
308
#VALUE!
b)
Labour
Mate
day
0.120
80.00
9.60
L-12
Mazdoor
day
3.000
70.00
210.00
L-13
hour
0.500
506.00
253.00
P&M-060
KL
3.000
10.00
30.00
M-189
Machinery
Water tanker6 KL capacity
c)
Material
Cost of water
d)
e)
40.21
54.28
597.09
308.2
5.97
say
6.00
50.00
50.00
Material
cum
1.000
4.00
5.40
59.40
say
11.12
308.20
quintal
1.000
cum
1.000
308.2
Supplying Sludge
Supplying sludge duly stacked at site/ store
Unit = cum
Taking output = one cum
a) Cost of sludge including carriage, loading,
unloading and stacking at site
b) Overheads@ per cent on (a)
c)
Page 5 of 9
59.40
M-167
11.14
New
b)
Labour
Mate
day
0.050
80.00
4.00
L-12
Mason
day
0.250
100.00
25.00
L-11
Mazdoor
day
0.250
70.00
17.50
L-13
each
230.000
1.86
427.69
M-079
cum
0.025
1512.00
37.80
Item 12.6
(D)
Material
c)
d)
40.96
55.29
608.24
say
11.15
New
608.00
b)
Labour
Mate
day
0.002
80.00
0.16
L-12
Mason
day
0.050
100.00
5.00
L-11
Mazdoor
day
0.050
70.00
3.50
L-13
each
50.000
1.86
92.98
M-079
Material
Brick 2nd class including carriage
c)
d)
8.13
10.98
120.74
12.07
say
11.16
New
12.00
b)
Labour
Mate
day
0.020
80.00
1.60
L-12
Blacksmith
day
0.150
100.00
15.00
L-02
Mazdoor
day
0.070
70.00
4.90
L-13
Material
Empty bitumen drum
each
MS sheet 50 x 0.5 mm
kg
each
1.000 input
0.650
22.000 input
30.64
#VALUE!
M-172
19.92
M-179
/1000
M-158
#VALUE!
d)
#VALUE!
e)
#VALUE!
Page 6 of 9
#VALUE!
New
#VALUE!
Labour
Mate
Blacksmith
day
Mazdoor
b)
0.040
80.00
3.20
L-12
0.200
100.00
20.00
L-02
0.200
70.00
14.00
L-13
Material
Empty bitumen drum
each
MS sheet50 x 0.5 mm
kg
each
kg
1.500 input
0.650
30.64
50.000 input
1.300
M-179
/1000
M-158
39.83
c)
#VALUE!
d)
#VALUE!
M-179
/1000
#VALUE!
say
New
M-172
19.92
#VALUE!
30.64
#VALUE!
#VALUE!
b)
Labour
Mate
day
0.450
80.00
36.00
L-12
day
2.000
100.00
200.00
L-02
day
2.500
70.00
175.00
L-13
quintal
1.050
3064.00
quintal
0.050
(1021.33)
(51.07) M-179/10/3
Material
Add 5 per cent of cost of material for welding rods and other
welding accessories
c) Overhead charges @ 8% on (a+b)
d)
158.31
298.84
403.43
4437.70
say
11.19
New
4437.70
Labour
Mate
day
0.050
80.00
4.00
L-12
Blacksmith
day
0.250
100.00
25.00
L-02
Page 7 of 9
day
0.250
70.00
17.50
L-13
MS iron 25 x 6 mm
kg
19.200
30.64
588.29
MS iron 25 x 3 mm
kg
9.600
30.64
294.14
M-179
/1000
M-179
/1000
Material
44.12
hour
0.040
231.00
9.24
P&M-053
sqm
1.770
27.50
48.68
Item 8.9
Painting
Painting two coats including priming
e)
f)
78.58
106.09
1215.64
say
Note
11.20
New
1215.60
b)
Labour
Mate
day
0.050
80.00
4.00
L-12
Blacksmith
day
0.250
100.00
25.00
L-02
Welder
day
0.250
100.00
25.00
L-02
Mazdoor
day
0.250
70.00
17.50
L-13
MS angle 30 x 30 x 3 mm
kg
13.500
30.64
413.64
MS iron 25 x 3 mm
kg
18.000
30.64
551.52
kg
6.000
52.00
312.00
M-179
/1000
M-179
/1000
M-192
Material
63.86
hour
0.040
231.00
sqm
1.500
27.50
f)
41.25
Item 8.9
153.55
1730.30
say
New
P&M-053
113.74
9.24
Painting
1730.30
Compensatory Afforestation
Planting trees as compensatory afforestation at the rate of
290 trees per hectare at a spacing of 6 m by grubbing and
leveling the ground upto a depth of 150 mm, digging holes
0.9 m dia, 1 m deep, mixing farm yard/sludge manure with
soil, planting of sapling 2 m high with 25 cm dia stem,
backfilling the hole and watering
Unit = Hectare
Taking output = one hectare
a)
Labour
i) Planting
Mate
day
2.500
80.00
200.00
L-12
Mazdoor
day
25.000
70.00
1750.00
L-13
day
5.000
80.00
400.00
L-12
Page 8 of 9
c)
day
50.000
70.00
3500.00
hour
10.000
1592.00
15920.00
P&M-015
hour
3.000
506.00
1518.00
P&M-060
hour
25.000
506.00
12650.00
P&M-060
each
290.000
#VALUE!
each
29.000
#VALUE!
cum
60.900
50.00
3045.00
M-167
cum
4.000
50.00
200.00
M-167
Material
kg
0.500 input
#VALUE!
M-136
kg
1.500 input
#VALUE!
M-136
Cost of water
KL
180.00
M-189
18.000
10.00
d)
#VALUE!
e)
#VALUE!
#VALUE!
say
Note
L-13
Machinery
Page 9 of 9
#VALUE!
CHAPTER-12
FOUNDATIONS
Sr No
12.1
12.1 (I)
Ref. to
MoRTH
Spec.
304
Description
I
B
(i)
Note
12.1 (I) B
(ii)
Unit
Quantity
Rate Rs
day
day
0.32
8.00
80.00
70.00
25.60
560.00
L-12
L-13
hour
6.00
840.00
P&M-026
say
5040.00
1125.12
675.07
7425.79
30.94
30.90
c)
d)
day
day
0.32
8.00
80.00
70.00
25.60
560.00
L-12
L-13
hour
6.00
840.00
5040.00
P&M-026
1125.12
675.07
7425.79
35.36
say
12.1 (I) B
(iii)
Remarks/
Input ref.
Note
Cost Rs
35.40
b)
Labour
Mate
day
0.40
80.00
32.00
L-12
Mazdoor
day
10.00
70.00
700.00
L-13
hour
6.00
840.00
5040.00
P&M-026
Machinery
Hydraulic excavator 1.0 cum bucket capacity
c)
d)
1154.40
692.64
7619.04
42.33
say
42.30
Sr No
Ref. to
MoRTH
Spec.
Description
Note
12.3
304
Unit
Quantity
Rate Rs
Cost Rs
Remarks/
Input ref.
b)
Labour
Mate
day
0.01
80.00
0.80
L-12
Mazdoor
day
0.30
70.00
21.00
L-13
cum
1.20
145.00
174.00
M-006
Material
Sand (assuming 20 per cent voids)
c)
d)
39.16
23.50
258.46
say
12.4
2100
258.50
b)
Labour
Mate
day
0.64
80.00
51.20
L-12
Mason
day
1.00
100.00
100.00
L-11
Mazdoor
day
15.00
70.00
1050.00
L-13
40 mm Aggregate
cum
13.50
438.48
5919.48
M-055
coarse Sand
cum
6.75
149.00
1005.75
M-005
cement
tonne
3.45
4400.00
15180.00
M-081
KL
18.00
10.00
180.00
M-189
hour
6.00
161.00
966.00
P&M-009
Generator 33 KVA
hour
6.00
240.00
1440.00
P&M-079
hour
2.00
506.00
1012.00
P&M-060
Material
Cost of water
c)
Machinery
d)
e)
5380.89
3228.53
35513.85
1500,
1700 &
2100
A
2367.59
say
2367.60
Material
Cement
tonne
4.13
4400.00
18172.00
M-081
Coarse sand
cum
6.75
149.00
1005.75
M-005
Sr No
Ref. to
MoRTH
Spec.
Description
b)
c)
Unit
Quantity
Rate Rs
cum
8.10
438.48
3551.69
M-055
20 mm Aggregate
cum
4.05
517.65
2096.48
M-053
10 mm Aggregate
cum
1.35
609.00
822.15
M-051
Labour
Mate
day
0.86
80.00
68.80
L-12
Mason
day
1.50
100.00
150.00
L-11
Mazdoor
day
20.00
70.00
1400.00
L-13
hour
6.00
161.00
966.00
P&M-009
Generator 63 KVA
hour
6.00
240.00
1440.00
P&M-019
Machinery
e)
f)
1979.00
1186.91
6171.96
3703.17
40734.92
12.8
Remarks/
Input ref.
40 mm Aggregate
Note
Cost Rs
2715.66
say
2715.70
b)
c)
Material
Cement
tonne
5.16
4400.00
22704.00
M-081
Coarse sand
cum
6.75
149.00
1005.75
M-005
40 mm Aggregate
cum
5.40
438.48
2367.79
M-055
20 mm Aggregate
cum
5.40
517.65
2795.31
M-053
10 mm Aggregate
cum
2.70
609.00
1644.30
M-051
Labour
Mate
day
0.86
80.00
68.80
L-12
Mason
day
1.50
100.00
150.00
L-11
Mazdoor
day
20.00
70.00
1400.00
L-13
hour
6.00
161.00
966.00
P&M-009
Generator 33 KVA
hour
6.00
240.00
1440.00
P&M-079
Machinery
2303.00
1381.68
7184.73
4310.84
47419.19
3161.28
say
12.8
12.8 C
3161.30
Sr No
Ref. to
MoRTH
Spec.
Description
b)
c)
Unit
Rate Rs
tonne
41.66
4400.00
183304.00
M-081
cum
54.00
149.00
8046.00
M-004
20 mm Aggregate
cum
64.80
517.65
33543.72
M-053
10 mm Aggregate
cum
43.20
609.00
26308.80
M-051
Labour
Mate
day
0.84
80.00
67.20
L-12
Mason
day
3.00
100.00
300.00
L-11
Mazdoor
day
18.00
70.00
1260.00
L-13
hour
6.00
1440.00
8640.00
P&M-002
hour
6.00
450.00
2700.00
P&M-080
hour
6.00
520.00
3120.00
P&M-017
hour
15.00
600.00
9000.00
P&M-049
tonne.km
300L
1.62
8262.00
165.00
990.00
P&M-050
Lead= 17
km
P&M-007
Machinery
Concrete Pump
hour
2380.00
11421.67
59392.68
35635.61
391991.67
Remarks/
Input ref.
Coarse Sand
12.8 D
Cost Rs
Cement
f)
Quantity
3266.60
say
3266.60
b)
c)
Material
Cement
tonne
47.95
4400.00
210980.00
M-081
Coarse sand
cum
54.00
149.00
8046.00
M-004
40 mm Aggregate
cum
43.20
438.48
18942.34
M-055
20 mm Aggregate
cum
43.20
517.65
22362.48
M-053
10 mm Aggregate
cum
21.60
609.00
13154.40
M-051
Labour
Mate
day
0.84
80.00
67.20
L-12
Mason
day
3.00
100.00
300.00
L-11
Mazdoor
day
18.00
70.00
1260.00
L-13
hour
6.00
1440.00
8640.00
P&M-002
hour
6.00
450.00
2700.00
P&M-080
hour
6.00
520.00
3120.00
P&M-017
hour
15.00
600.00
9000.00
P&M-049
tonne.km
300L
1.62
8262.00
165.00
990.00
P&M-050
Lead= 17
km
P&M-007
Machinery
hour
2566.00
11543.42
Sr No
Ref. to
MoRTH
Spec.
Description
e)
f)
Unit
Quantity
Rate Rs
38324.14
421565.54
Remarks/
Input ref.
63873.57
12.8 E
Cost Rs
3513.05
say
3513.00
b)
c)
Material
Cement
tonne
48.38
4400.00
212872.00
M-081
Coarse sand
cum
54.00
149.00
8046.00
M-004
20 mm Aggregate
cum
64.80
517.65
33543.72
M-053
10 mm Aggregate
cum
43.20
609.00
26308.80
M-051
Labour
Mate
day
0.84
80.00
67.20
L-12
Mason
day
3.00
100.00
300.00
L-11
Mazdoor
day
18.00
70.00
1260.00
L-13
hour
6.00
1440.00
8640.00
P&M-002
hour
6.00
450.00
2700.00
P&M-080
hour
6.00
520.00
3120.00
P&M-017
hour
15.00
600.00
9000.00
P&M-049
tonne.km
300L
1.62
8262.00
6.00
165.00
990.00
P&M-050
Lead= 17
km
P&M-007
Machinery
hour
2626.00
11816.61
65385.27
39231.16
431542.76
3596.19
say
3596.20
b)
c)
Material
Cement
tonne
48.60
4400.00
213840.00
M-081
Coarse sand
cum
54.00
149.00
8046.00
M-004
40 mm Aggregate
cum
43.20
438.48
18942.34
M-055
20 mm Aggregate
cum
43.20
517.65
22362.48
M-053
10 mm Aggregate
cum
21.60
609.00
13154.40
M-051
Labour
Mate
day
0.84
80.00
67.20
L-12
Mason
day
3.00
100.00
300.00
L-11
Mazdoor
day
18.00
70.00
1260.00
L-13
Machinery
Sr No
Ref. to
MoRTH
Spec.
Description
Unit
Rate Rs
hour
6.00
1440.00
8640.00
hour
6.00
450.00
2700.00
P&M-080
hour
6.00
520.00
3120.00
P&M-017
hour
15.00
600.00
9000.00
P&M-049
tonne.km
300L
1.62
8262.00
6.00
165.00
990.00
P&M-050
Lead= 17
km
P&M-007
Concrete Pump
hour
10873.95
64311.67
38587.00
424457.05
P&M-002
2590.00
12.8
Remarks/
Input ref.
12.8 G
Cost Rs
f)
Quantity
3537.14
say
3537.10
b)
c)
Material
Cement
tonne
48.80
4400.00
214720.00
M-081
Coarse sand
cum
54.00
149.00
8046.00
M-004
20 mm Aggregate
cum
64.80
517.65
33543.72
M-053
10 mm Aggregate
cum
43.20
609.00
26308.80
M-051
Labour
Mate
day
0.84
80.00
67.20
L-12
Mason
day
3.00
100.00
300.00
L-11
Mazdoor
day
18.00
70.00
1260.00
L-13
hour
6.00
1440.00
8640.00
P&M-002
hour
6.00
450.00
2700.00
P&M-080
hour
6.00
520.00
3120.00
P&M-017
hour
15.00
600.00
9000.00
P&M-049
tonne.km
300L
1.62
8262.00
6.00
165.00
990.00
P&M-050
Lead= 17
km
P&M-007
Machinery
hour
2642.00
11093.52
65610.25
39366.15
433027.64
3608.56
say
12.8
12.8 H
Material
3608.60
Sr No
Ref. to
MoRTH
Spec.
Description
b)
c)
Unit
Rate Rs
tonne
50.64
4400.00
222816.00
M-081
cum
54.00
149.00
8046.00
M-004
20 mm Aggregate
cum
64.80
517.65
33543.72
M-053
10 mm Aggregate
cum
43.20
609.00
26308.80
M-051
Labour
Mate
day
0.84
80.00
67.20
L-12
Mason
day
3.00
100.00
300.00
L-11
Mazdoor
day
18.00
70.00
1260.00
L-13
hour
6.00
1440.00
8640.00
P&M-002
hour
6.00
450.00
2700.00
P&M-080
hour
6.00
520.00
3120.00
P&M-017
hour
15.00
600.00
9000.00
P&M-049
tonne.km
300L
1.62
8262.00
6.00
165.00
990.00
P&M-050
Lead= 17
km
P&M-007
Machinery
Concrete Pump
hour
2709.00
9751.61
66961.07
40176.64
441943.04
3682.86
say
1100 &
1700
Remarks/
Input ref.
Coarse sand
12.23
Cost Rs
Cement
f)
Quantity
3682.90
Materials
PCC Grade M35
cum
6.62
3798.00
hour
6.00
3525.00
21150.00
P&M-036
230.00
115.00
P&M-013
c)
hour
0.50
hour
hour
156.00
P&M-017
hour
0.30
506.00
151.80
P&M-048
kg
300.00
2.06
618.00
M-071
Mate/Supervisor
day
0.14
80.00
11.20
L-12
Mazdoor
day
3.50
70.00
245.00
L-13
Labour
d)
4489.40
e)
2693.64
Sr No
Ref. to
MoRTH
Spec.
Description
Unit
Quantity
Rate Rs
3651.52
say
1100 &
1700
Remarks/
Input ref.
54772.80
Cost Rs
3651.50
Materials
PCC Grade M35
cum
10.17
3798.00
hour
6.00
3525.00
21150.00
P&M-036
230.00
115.00
P&M-013
c)
hour
0.50
hour
hour
260.00
P&M-017
hour
0.50
506.00
253.00
P&M-048
kg
385.00
2.06
793.10
M-071
Mate/Supervisor
day
0.18
80.00
14.40
L-12
Mazdoor
day
4.50
70.00
315.00
L-13
Labour
d)
e)
4580.10
2748.06
68854.32
7650.48
say
12.37
1100
7650.50
Note
12.38
12.38
1100,
1500
&1700
D
tonne
1.00
300.00
tonne
1.00
5000.00
'12.38D
(ii)
Material
Cement
tonne
6.33
4400.00
27852.00
M-081
Coarse sand
cum
6.75
149.00
1005.75
M-004
Sr No
Ref. to
MoRTH
Spec.
Description
b)
Unit
Quantity
Rate Rs
Cost Rs
Remarks/
Input ref.
20 mm Aggregate
cum
8.10
517.65
4192.97
M-053
10 mm Aggregate
cum
5.40
609.00
3288.60
M-051
Labour
Mate
day
0.16
80.00
12.80
L-12
Mason
day
0.38
90.00
34.20
L-10
day
2.50
70.00
175.00
L-13
day
1.00
70.00
70.00
L-13
hour
0.75
1440.00
1080.00
hour
0.75
450.00
337.50
P&M-018
hour
0.75
520.00
390.00
P&M-017
P&M-049
P&M-002
Concrete Pump
hour
2.00
600.00
1200.00
tonne.km
37.5L
1.62
1032.75
hour
0.75
165.00
1631.81
8485.43
5091.26
56003.81
1100&17
00
Lead =17
km & P&M050
123.75 P&M-007
3733.59
say
3733.60
b)
c)
Material
Cement
tonne
4.13
4400.00
18172.00
M-081
Coarse sand
cum
6.75
149.00
1005.75
M-005
40 mm aggregate
cum
8.10
438.48
3551.69
M-055
20 mm Aggregate
cum
4.05
517.65
2096.48
M-053
10 mm Aggregate
cum
1.35
609.00
822.15
M-051
Labour
Mate
day
0.86
80.00
68.80
L-12
Mason
day
1.50
90.00
135.00
L-10
Mazdoor
day
20.00
70.00
1400.00
L-13
hour
6.00
161.00
966.00
P&M-009
Generator 33 KVA
hour
6.00
240.00
1440.00
P&M-079
Machinery
d)
e)
5931.57
3558.94
39148.39
2609.89
say
12.40
1600
2609.90
Sr No
Ref. to
MoRTH
Spec.
Description
a)
Unit
Quantity
Rate Rs
Cost Rs
Remarks/
Input ref.
Material
HYSD bars including5 per cent overlaps and wastage
Binding wire
tonne
1.05
29902.00
31397.10
M-082
Kg
6.00
39.00
234.00
M-072
day
0.40
80.00
32.00
L-12
Blacksmith
day
2.00
100.00
200.00
L-02
Mazdoor
day
6.00
70.00
420.00
L-13
c)
d)
6456.62
3873.97
42613.69
say
42613.70
CHAPTER-13
SUB-STRUCTURE
Sr No
13.1
13.2
Ref. to
MoRTH
Spec.
1300 &
2200
Description
Brick masonry work in 1:3 in sub-structure complete
excluding pointing and plastering, as per drawing and
Technical Specifications
Unit = cum
Taking output = 1 cum
a) Material
Bricks Ist class
Cement mortar 1:3 (Rate as in Item 12.6 A subanalysis)
b) Labour
Mate
Mason
Mazdoor
Add for scaffolding @ 5 per cent of cost of material and
labour
c) Overhead charges @ 20% on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Rate per cum (a+b+c+d)
1300 &
2200
Unit
each
cum
day
day
day
Quantity
Rate Rs
Cost Rs
500.00
0.24
1.86
2467.00
929.75
592.08
M-079
Item 12.6
(A)
0.06
0.80
0.80
80.00
100.00
70.00
4.80
80.00
56.00
83.13
L-12
L-11
L-13
say
349.15
209.49
2304.41
2304.40
cum
0.03
2467.00
74.01
Item 12.6
(A)
day
day
day
0.04
0.50
0.50
80.00
100.00
70.00
L-12
L-11
L-13
say
3.20
50.00
35.00
32.44
19.47
214.12
21.41
21.40
b)
13.3
Note
1300 &
2200
Remarks/
Input ref.
cum
0.144
2467.00
355.25
Item 12.6
(A)
day
day
day
0.04
0.50
0.50
80.00
100.00
70.00
3.20
50.00
35.00
88.69
53.21
585.35
58.54
58.50
L-12
L-11
L-13
b)
say
Note
13.4
1400 &
2200
A
Sr No
Ref. to
MoRTH
Spec.
Description
Unit = cum
Taking output = 1 cum
a) Material
Stone
Through and bond stone
(7no.x0.24mx0.24mx0.39m = 0.16 cu.m)
Cement mortar 1:3 (Rate as in Item 12.6)
Labour
Mate
Mason
Mazdoor
Add for scaffolding @ 5 per cent of cost of a) Material
and b) Labour
c) Overhead charges @ 20% on (a+b)
Unit
Quantity
Rate Rs
Cost Rs
Remarks/
Input ref.
cum
No
1.00
7.00
289.00
100.00
289.00
700.00
M-148
M-182
cum
0.33
2467.00
814.11
Item 12.6
(A)
day
day
day
0.10
1.20
1.20
80.00
100.00
70.00
8.00
120.00
84.00
100.76
L-12
L-11
L-13
b)
d)
423.17
253.90
2792.94
say
13.4
2792.90
cum
1.10
289.00
317.90
M-148
each
7.00
100.00
700.00
M-182
cum
0.30
2467.00
740.10
Item 12.6
(A)
Labour
Mate
day
0.12
80.00
9.60
L-12
Mason
day
1.50
100.00
150.00
L-11
Mazdoor
day
1.50
70.00
105.00
L-13
101.13
424.75
254.85
2803.32
say
13.4
2803.00
cum
1.11
289.00
320.79
M-169
each
7.00
100.00
700.00
M-182
cum
0.33
2467.00
814.11
Item 12.6
(A)
day
0.20
80.00
16.00
L-12
Mason
day
2.50
100.00
250.00
L-11
Mazdoor
day
2.50
70.00
175.00
L-13
113.80
d)
286.76
477.94
Sr No
Ref. to
MoRTH
Spec.
Description
Unit
Quantity
Rate Rs
13.5
Remarks/
Input ref.
3154.40
say
Note
Cost Rs
3154.00
1500,
1700 &
2200
Unit = cum
Taking output = 1 cum
A
197.90
435.38
261.23
2873.51
say
13.5
2873.50
230.30
506.66
304.00
3343.96
say
13.5
3344.00
256.53
564.37
338.62
3724.82
say
13.5
3724.80
Sr No
Ref. to
MoRTH
Spec.
Description
Unit
Quantity
Rate Rs
Cost Rs
Same as Item 12.8 (F) upto 5 m height with the only change
that the provision of form work shall be 10 per cent instead
of 3.50 per cent of cost of material, labour and machinery.
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (F) Case I
d) formwork
Add 10 per cent of cost of material, labour and
machinery (a+b+c) for Formwork
e) Overhead charges @ 20% on (a+b+c+d)
f)
2572.70
10.00
257.27
565.99
339.60
3735.56
say
13.5 D
(p)
2589.10
10.00
258.91
569.60
341.76
3759.37
say
13.5
3736.00
3759.40
2362.50
10.00
236.25
519.75
311.85
3430.35
say
13.5 E
(p)
2379.60
10.00
237.96
523.51
314.11
3455.18
say
13.5 E
3430.40
3455.20
Remarks/
Input ref.
Sr No
Ref. to
MoRTH
Spec.
Description
Unit
Quantity
Rate Rs
2362.50
12.00
283.50
2.00
47.25
538.65
323.19
3555.09
say
13.5 E
(q)
12.00
285.55
2.00
47.59
542.55
325.53
3580.82
say
(r)
3581.00
Same as Item 12.8 (C) with the following changes: (i) Add 4
per cent of cost of material, labour and machinery excluding
form work to cater for extra lift. (ii) The provision of form
work shall be 15 per cent instead of 4 per cent of cost of
material, labour and machinery.
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (C) Case I
d) formwork
Add 15 per cent of cost of material, labour and
machinery (a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 20% on (a+b+c+d)
f)
2362.50
15.00
354.38
4.00
94.50
562.28
337.37
3711.02
say
13.5 E
(r)
3555.00
2379.60
Cost Rs
3711.00
2379.60
15.00
356.94
4.00
95.18
566.34
339.81
3737.88
say
3738.00
Remarks/
Input ref.
Sr No
Ref. to
MoRTH
Spec.
13.5
Description
F
Unit
Quantity
Rate Rs
Cost Rs
Remarks/
Input ref.
13.5 F
(p)
2626.00
10.00
262.60
577.72
346.63
3812.95
say
3813.00
say
3809.00
2641.40
10.00
264.14
581.11
348.66
3835.31
say
13.5
3835.00
13.5 H
(p)
2776.40
10.00
277.64
610.81
366.48
Section
1600 &
2200
4031.33
say
4031.30
29902.00
31397.10
tonne
1.05
M-082
Sr No
Ref. to
MoRTH
Spec.
Description
Binding wire
b) Labour for cutting, bending, shifting to site, tying
and placing in position
Mate
Unit
kg
Quantity
6.00
Rate Rs
39.00
2706 &
2200
234.00
Remarks/
Input ref.
M-072
day
0.34
80.00
27.20
L-12
Blacksmith
day
2.00
100.00
200.00
L-02
Mazdoor
day
6.50
70.00
455.00
L-13
c)
d)
6462.66
3877.60
Cost Rs
42653.56
say
42653.60
metre
31.50
60.00
1890.00
each.
30.00
4.00
120.00
M-123
each.
10.00
6.00
60.00
M-056/10
cum
0.05
2467.00
123.35
Item 12.6
(A)
Labour
Mate
day
0.03
80.00
2.40
L-12
Mason
day
0.50
100.00
50.00
L-11
Mazdoor
day
0.25
70.00
17.50
L-13
c)
d)
452.65
271.59
2987.49
99.58
say
Note
13.9
M-056
99.60
710.1.4.o
f IRC:78
& 2200
Unit = cum
Taking output = 10 cum
A
Granular material
a)
b)
Labour
Mate
day
0.28
80.00
22.40
L-12
Mazdoor
day
7.00
70.00
490.00
L-13
cum
12.00
140.00
1680.00
M-009
Material
Granular material
c)
Machinery
Sr No
Ref. to
MoRTH
Spec.
Unit
hour
2.50
100.00
250.00
P&M-086
Water Tanker
hour
0.05
506.00
25.30
P&M-060
d)
e)
Quantity
Rate Rs
493.54
296.12
3257.36
325.74
say
13.9
325.70
Sandy material
a)
b)
Labour
Mate
day
0.28
80.00
22.40
L-12
day
7.00
70.00
490.00
L-13
cum
12.00
145.00
1740.00
M-006
hour
2.50
100.00
250.00
P&M-086
Water Tanker
hour
0.06
506.00
30.36
P&M-060
Material
Sand
c)
Machinery
d)
e)
303.93
3343.24
506.55
334.32
say
13.10 710.1.4.o
f IRC:78
and
2200
Cost Rs
Remarks/
Input ref.
Description
334.30
b)
Mate
day
0.32
80.00
25.60
L-12
day
7.00
70.00
490.00
L-13
Mazdoor (Skilled)
day
1.00
100.00
100.00
L-15
cum
12.00
609.00
7308.00
M-012
hour
0.06
506.00
Material
e)
954.48
10499.23
1049.92
say
13.14
2000 &
2200
30.36
1590.79
1049.90
P&M-060
Sr No
Ref. to
MoRTH
Spec.
Description
Unit
Quantity
Rate Rs
Cost Rs
Remarks/
Input ref.
b)
Labour
Mate
day
0.06
80.00
4.80
L-12
Mazdoor
day
1.00
70.00
70.00
L-13
Mazdoor (Skilled)
day
0.50
100.00
50.00
L-15
each.
1.00
23000.00
23000.00
Material
230.00
4670.96
2802.58
30828.34
1.61
say
13.16
2000 &
2200
M-066
1.60
b)
Mate
day
0.08
80.00
6.40
L-12
Mazdoor
day
1.50
70.00
105.00
L-13
Mazdoor (Skilled)
day
0.50
100.00
50.00
L-15
each.
1.00
19049.00
19049.00
Material
190.49
3880.18
2328.11
25609.17
102.44
say
102.40
M-068
CHAPTER-14
SUPER-STRUCTURE
Sr No
14.1
Ref. to
MoRTH
Spec.
1500
&1600
1700
Description
A
14.1A
Unit
Quantity
Rate Rs
Cost Rs
Remarks/
Input ref.
b)
c)
Material
Cement
tonne
40.92
4400.00
180048.00
M-081
Coarse sand
cum
54.00
149.00
8046.00
M-004
20 mm Aggregate
cum
64.80
517.65
33543.72
M-053
10 mm Aggregate
cum
43.20
609.00
26308.80
M-051
Labour
Mate
day
0.84
80.00
67.20
L-12
Mason
day
3.00
100.00
300.00
L-11
Mazdoor
day
18.00
70.00
1260.00
L-13
hour
6.00
1440.00
8640.00
P&M-002
hour
6.00
450.00
2700.00
P&M-080
Loader
hour
6.00
520.00
3120.00
P&M-017
hour
15.00
600.00
9000.00
P&M-049
tonne.km
300L
1.62
8262.00
6.00
165.00
Machinery
Concrete Pump
hour
(i)
(p)
282286.00
f)
for
282286.00
20
56457.20
67748.64
40649.18
447141.02
3726.18
say
14.1A
Case II
Lead =17
km & P&M050
990.00 P&M-007
3726.20
Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c)
120 cum
d) Formwork and staging 25 per cent of (a+b+c)
e)
f)
for
282286.00
25
70571.50
70571.50
42342.90
465771.90
3881.43
say
3881.40
Sr No
14.1A
Case II
(ii)
Ref. to
MoRTH
Spec.
Description
(q)
Unit
Quantity
Rate Rs
e)
f)
for
282286.00
30
84685.80
73394.36
44036.62
484402.78
4036.69
say
(r)
e)
f)
for
282286.00
35
98800.10
76217.22
45730.33
503033.65
4036.70
14.1B
Remarks/
Input ref.
Height 5m to 10m
14.1A
Case II
(ii)
Cost Rs
4191.95
say
4191.90
b)
c)
Material
Cement
tonne
47.95
4400.00
210980.00
M-081
Coarse sand
cum
54.20
149.00
8075.80
M-004
20 mm Aggregate
cum
64.80
517.65
33543.72
M-053
10 mm Aggregate
cum
43.20
609.00
26308.80
M-051
Labour
Mate
day
0.84
80.00
67.20
L-12
Mason
day
3.00
100.00
300.00
L-11
Mazdoor
day
18.00
70.00
1260.00
L-13
hour
6.00
1440.00
8640.00
P&M-002
hour
6.00
450.00
2700.00
P&M-080
Loader
hour
6.00
520.00
3120.00
P&M-017
hour
15.00
600.00
9000.00
P&M-049
tonne.km
300L
1.62
8262.00
6.00
165.00
Machinery
Concrete Pump
hour
(i)
(p)
Lead =17
km & P&M050
990.00 P&M-007
313248.00
for
313248.00
20
62649.60
Sr No
Ref. to
MoRTH
Spec.
Description
e)
f)
Unit
Quantity
Rate Rs
45107.71
496184.83
4134.87
say
(q)
e)
f)
for
313248.00
25
78312.00
78312.00
46987.20
516859.20
4307.16
say
(r)
e)
f)
for
313248.00
30
93974.40
81444.48
48866.69
537533.57
4307.20
14.1C
4134.90
Height 5m to 10m
14.1B
Case II
(i)
Remarks/
Input ref.
75179.52
14.1B
Case II
(i)
Cost Rs
4479.45
say
4479.40
RCC Grade M 30
b)
c)
Material
Cement
tonne
48.79
4400.00
214676.00
M-081
Coarse sand
cum
54.60
149.00
8135.40
M-004
20 mm Aggregate
cum
64.80
517.65
33543.72
M-053
10 mm Aggregate
cum
43.20
609.00
26308.80
M-051
Labour
Mate
day
0.88
80.00
70.40
L-12
Mason
day
3.00
100.00
300.00
L-11
Mazdoor
day
19.00
70.00
1330.00
L-13
hour
6.00
1440.00
8640.00
P&M-002
hour
6.00
450.00
2700.00
P&M-080
Loader
hour
6.00
520.00
3120.00
P&M-017
hour
15.00
600.00
9000.00
P&M-049
tonne.km
300L
1.62
8262.00
6.00
165.00
Machinery
Concrete Pump
Basic Cost of Labour, Material & Machinery (a+b+c)
for 120 cum
For formwork and staging add the following:
hour
317077.00
Lead =17
km & P&M050
990.00 P&M-007
Sr No
14.1C
Case II
Ref. to
MoRTH
Spec.
Description
(i)
(p)
Unit
Quantity
Rate Rs
f)
for
317077.00
20
63415.40
76098.48
45659.09
502249.97
4185.42
say
14.1C
Case II
(i)
(q)
e)
f)
for
317077.00
25
79269.25
79269.25
47561.55
523177.05
4359.81
say
(r)
e)
f)
for
317077.00
30.00
95123.10
82440.02
49464.01
544104.13
4534.20
say
(ii)
(p)
Height upto 5m
e)
f)
for
317077.00
25.00
79269.25
79269.25
47561.55
523177.05
4359.81
say
(q)
4534.00
14.1C
Case II
(ii)
4359.80
14.1C
Case II
4185.40
Height 5m to 10m
14.1C
Case II
(i)
Cost Rs
4360.00
Height 5m to 10m
f)
for
317077.00
30.00
95123.10
82440.02
49464.01
544104.13
4534.20
say
4534.00
Remarks/
Input ref.
Sr No
14.1C
Case II
(ii)
Ref. to
MoRTH
Spec.
Description
(r)
Unit
Quantity
Rate Rs
e)
f)
for
317077.00
35.00
110976.95
85610.79
51366.47
565031.21
Remarks/
Input ref.
14.1
Cost Rs
4708.59
say
4709.00
b)
c)
Material
Cement
tonne
6.33
4400.00
27852.00
M-081
Coarse sand
cum
6.75
149.00
1005.75
M-005
20 mm Aggregate
cum
8.10
517.65
4192.97
M-053
10 mm Aggregate
cum
5.40
609.00
3288.60
M-051
Labour
Mate
day
0.90
80.00
72.00
L-12
Mason
day
1.50
100.00
150.00
L-11
Mazdoor
day
21.00
70.00
1470.00
L-13
hour
6.00
161.00
966.00
P&M-009
Generator 33 KVA
hour
6.00
240.00
1440.00
P&M-079
Machinery
(i)
(p)
40438.00
f)
for
40438.00
18.00
7278.84
9543.37
5726.02
62986.23
4199.08
say
14.1D
Case I (i)
(q)
Height 5m to 10m
f)
for
40438.00
23.00
9300.74
9947.75
5968.65
65655.14
4377.01
say
14.1D
Case I (i)
(r)
4199.00
4377.00
Sr No
Ref. to
MoRTH
Spec.
Description
Basic Cost of Labour, Material & Machinery (a+b+c)
15 cum
d) Formwork and staging 28 per cent of (a+b+c)
e)
f)
Unit
Quantity
Rate Rs
for
40438.00
28.00
11322.64
10352.13
6211.28
68324.04
4554.94
say
14.1D
Case I
(ii)
(p)
Height upto 5m
e)
f)
for
40438.00
23.00
9300.74
9947.75
5968.65
65655.14
4377.01
say
(q)
e)
f)
for
40438.00
28.00
11322.64
10352.13
6211.28
68324.04
4554.94
say
(r)
e)
f)
for
40438.00
33.00
13344.54
10756.51
6453.90
70992.95
4732.86
say
(iii)
(p)
e)
f)
for
40438.00
38.00
15366.44
11160.89
6696.53
73661.86
4910.79
say
(q)
4733.00
14.1D
Case I
(iii)
4555.00
14.1D
Case I
4377.00
Height 5m to 10m
14.1D
Case I
(ii)
4555.00
14.1D
Case I
(ii)
Cost Rs
Height 5m to 10m
4911.00
Remarks/
Input ref.
Sr No
Ref. to
MoRTH
Spec.
Description
Basic Cost of Labour, Material & Machinery (a+b+c)
15 cum
d) Formwork and staging 48 per cent of (a+b+c)
e)
f)
Unit
Quantity
Rate Rs
for
48.00
19410.24
11969.65
7181.79
78999.68
5266.65
say
(r)
Remarks/
Input ref.
40438.00
14.1D
Case I
(iii)
Cost Rs
5267.00
f)
for
40438.00
58.00
23454.04
12778.41
7667.04
84337.49
5622.50
say
5622.00
b)
c)
Material
Cement
tonne
50.64
4400.00
222816.00
M-081
Coarse sand
cum
54.00
149.00
8046.00
M-004
20 mm Aggregate
cum
64.80
517.65
33543.72
M-053
10 mm Aggregate
cum
43.20
609.00
26308.80
M-051
Labour
Mate
day
0.88
80.00
70.40
L-12
Mason
day
3.00
100.00
300.00
L-11
Mazdoor
day
19.00
70.00
1330.00
L-13
hour
6.00
1440.00
8640.00
P&M-002
hour
6.00
450.00
2700.00
P&M-080
Loader
hour
6.00
520.00
3120.00
P&M-017
hour
15.00
600.00
9000.00
P&M-049
tonne.km
300L
1.62
8262.00
6.00
165.00
Machinery
Concrete Pump
hour
(i)
(p)
Lead =17
km & P&M050
990.00 P&M-007
325127.00
f)
for
325127.00
18.00
58522.86
76729.97
46037.98
506417.82
4220.15
Sr No
Ref. to
MoRTH
Spec.
Description
Unit
Quantity
Rate Rs
say
14.1D
Case II
(i)
(q)
e)
f)
for
325127.00
23.00
74779.21
79981.24
47988.75
527876.20
4398.97
say
(r)
e)
f)
for
325127.00
28.00
91035.56
83232.51
49939.51
549334.58
4577.79
say
(ii)
(p)
Height upto 5m
e)
f)
for
325127.00
23.00
74779.21
79981.24
47988.75
527876.20
4398.97
say
(q)
e)
f)
for
325127.00
28.00
91035.56
83232.51
49939.51
549334.58
4577.79
say
(r)
4399.00
Height 5m to 10m
14.1D
Case II
(ii)
4578.00
14.1D
Case II
(ii)
4399.00
14.1D
Case II
4220.00
Height 5m to 10m
14.1D
Case II
(i)
Cost Rs
4578.00
f)
for
325127.00
33.00
107291.91
86483.78
51890.27
570792.96
4756.61
say
4757.00
Remarks/
Input ref.
Sr No
14.1D
Case II
Ref. to
MoRTH
Spec.
Description
(iii)
(p)
Unit
Quantity
Rate Rs
e)
f)
for
325127.00
38.00
123548.26
89735.05
53841.03
592251.34
4935.43
say
(q)
e)
f)
for
325127.00
48.00
156060.96
96237.59
57742.56
635168.11
5293.07
say
(r)
e)
f)
for
325127.00
58.00
188573.66
102740.13
61644.08
678084.87
5293.00
14.1E
4935.00
Height 5m to 10m
14.1D
Case II
(iii)
Remarks/
Input ref.
14.1D
Case II
(iii)
Cost Rs
5650.71
say
5651.00
Material
Cement
tonne
51.60
4400.00
227040.00
M-081
Coarse sand
cum
54.00
149.00
8046.00
M-004
20 mm Aggregate
cum
64.80
517.65
33543.72
M-053
10 mm Aggregate
cum
43.20
609.00
26308.80
M-051
kg
206.40
40.00
8256.00
M-180
c)
Labour
Mate
day
0.94
80.00
75.20
L-12
Mason
day
3.50
100.00
350.00
L-11
Mazdoor
day
20.00
70.00
1400.00
L-13
hour
6.00
1440.00
8640.00
P&M-002
hour
6.00
450.00
2700.00
P&M-080
Loader
hour
6.00
520.00
3120.00
P&M-017
hour
15.00
600.00
9000.00
P&M-049
Machinery
Sr No
Ref. to
MoRTH
Spec.
Description
Unit
tonne.km
Concrete Pump
hour
(i)
(p)
Rate Rs
300L
1.62
6.00
165.00
e)
f)
18
79704.75
47822.85
526051.36
4383.76
say
4383.80
Height 5m to 10m
f)
for
337732.00
23
77678.36
83082.07
49849.24
548341.68
Lead =17
km & P&M050
990.00 P&M-007
60791.76
14.2
8262.00
337732.00
(q)
Remarks/
Input ref.
14.1E
Case II
(i)
Cost Rs
337732.00
Quantity
4569.51
say
4569.50
Material
HYSD bars including 5 per cent for laps and wastage
Binding wire
b)
Labour for cutting, bending, tying and placing in
position
Mate
Blacksmith
Mazdoor
tonne
1.05
29902.00
31397.10
M-082
Kg
8.00
39.00
312.00
M-072
day
0.44
80.00
35.20
L-12
day
3.00
100.00
300.00
L-02
8.00
70.00
560.00
L-13
day
Basic Cost of Labour & Material (a+b)
c)
d)
32605.00
6520.86
3912.52
43037.68
say
14.3
1800
43037.70
Sr No
Ref. to
MoRTH
Spec.
Description
Unit
Quantity
Rate Rs
Cost Rs
Remarks/
Input ref.
tonne
0.385
35000.00
13475.00
M-119
metre
42.00
60.00
2520.00
M-165
each
2.00
322.00
644.00
M-187
tonne
0.125
4400.00
550.00
M-081
859.45
day
0.16
80.00
12.80
L-12
Blacksmith
day
1.00
100.00
100.00
L-02
Mazdoor
day
3.00
70.00
210.00
L-13
Mate/Supervisor
day
0.05
80.00
4.00
L-12
day
0.25
90.00
22.50
L-08
Mazdoor
day
1.00
70.00
70.00
L-13
day
day
0.05
0.25
80.00
100.00
4.00
25.00
L-12
L-11
day
1.00
70.00
70.00
L-13
hour
2.50
83.00
207.50
P&M-040
hour
hour
1.00
3.50
230.00
240.00
230.00
840.00
M-111
P&M-079
d)
e)
Machinery
3968.85
2381.31
2702
say
26194.41
69481.19
69481.20
2642.30
Material
d)
cum
1.00
2642.30
tonne
0.075
32604.30
day
0.15
70.00
Item
14.1(C)
2445.32 Item 14.2 A
10.50
1019.62
611.77
6729.52
say
6729.50
L-13
Sr No
14.5
Ref. to
MoRTH
Spec.
515 &
2702
Description
Unit
Quantity
Rate Rs
Cost Rs
Remarks/
Input ref.
Mastic Asphalt
Providing and laying 12 mm thick mastic asphalt
wearing course on top of deck slab excluding prime
coat with paving grade bitumen meeting the
requirements given in table 500-29, prepared by using
mastic cooker and laid to required level and slope after
cleaning the surface, including providing antiskid
surface with bitumen precoated fine grained hard stone
chipping of 9.5 mm nominal size at the rate of 0.005cum
per 10 sqm and at an approximate spacing of 10 cm
center to center in both directions, pressed into surface
when the temperature of surfaces not less than 100 deg.
C, protruding 1 mm to 4 mm over mastic surface, all
complete as per clause 515.
Unit = sqm
Taking output = 72.46 sqm (2 tonnes)(0.869 cum)
assuming a density of 2.3 tonnes/cum.
a) Labour
b)
Mate
day
0.49
80.00
39.20
L-12
Mazdoor
day
11.00
70.00
770.00
L-13
Mazdoor (Skilled)
day
1.25
100.00
125.00
L-15
hour
0.06
230.00
13.80
P&M-031
hour
0.06
206.00
12.36
P&M-001
hour
6.00
1442.00
8652.00
P&M-030
hour
6.00
128.00
768.00
P&M-005
hour
1.00
231.00
231.00
P&M-053
tonne
0.204
20528.00
4187.71
M-074
cum
0.39
395.85
154.38
M-021
tonne
0.36
11000.00
3960.00
M-188
cum
0.55
609.00
334.95
M-051
cum
0.036
4000.00
144.00
M-142
kg
1.05
20.53
21.55
M074/1000
Machinery
e)
3882.79
2329.67
25626.42
353.66
say
Note
353.70
Sr No
14.6
Ref. to
MoRTH
Spec.
Description
Unit
Quantity
Rate Rs
Cost Rs
Remarks/
Input ref.
2703,
1500,
1600 &
Material
i) M30 Grade Reinforced Cement Concrete
cum
4.092
2642.30
tonne
0.87
32604.30
8306.68
4984.01
54824.10
14.7
2703,
1500,
1600 &
1700
1977.78
Note
Item
14.1(C)
540.61
10812.29
1142.17
say
1142.20
2642.30
10812.29
Material
i) M30 Grade Reinforced Cement Concrete
cum
4.092
Item
14.1(C)
Sr No
Ref. to
MoRTH
Spec.
Description
Unit
Quantity
Rate Rs
Cost Rs
Remarks/
Input ref.
1297.47
tonne
0.87
32604.30
b)
8062.50
c)
4837.50
53212.48
Note
1108.59
say
1108.60
14.9
2705
b)
Material
Corrosion resistant Structural steel including 5 per cent
wastage
GI pipe 100mm dia
Kg
4.00
29.90
119.61
metre
6.00
60.00
360.00
GI bolt 10 mm Dia
each
6.00
1.50
9.00
M-110
each
2.00
10.00
20.00
M-101
M087/1000
M-056
Labour
For fabrication
Mate
day
0.02
80.00
1.60
L-12
day
0.02
100.00
2.00
L-02
Mazdoor
day
0.02
70.00
1.40
L-13
day
0.01
80.00
0.80
L-12
Mason
day
0.01
100.00
1.00
L-11
Mazdoor
day
0.20
70.00
14.00
L-13
26.47
111.18
66.71
733.76
say
Note
733.80
Sr No
14.10
Ref. to
MoRTH
Spec.
2700
Description
Unit
Quantity
Rate Rs
Cost Rs
Remarks/
Input ref.
14.11
1500,160
0,1700 &
2704
cum
1.00
2612.30
2612.30
say
2612.30
2641.40
2641.40
Item 12.8
(A)
Material
cum
1.00
52.83
tonne
0.05
32604.30
518.93
5708.26
say
14.12
1600
Note
14.15
800
14.18
14.18
2605
Filler joint
(iii)
Item 12.8
(G)
5708.30
Sr No
Ref. to
MoRTH
Spec.
Description
Unit
Quantity
Rate Rs
Cost Rs
Remarks/
Input ref.
Taking output = 12 m
a)
b)
Labour
Mate
day
0.01
80.00
0.80
L-12
Mazdoor
day
0.20
70.00
14.00
L-13
Mazdoor (Skilled)
day
0.10
100.00
10.00
L-15
sqm
3.60
80.00
288.00
M-141
Material
62.56
37.54
412.90
2600
34.41
say
34.40
80.00
4.16
Labour
Mate
b)
0.052
day
1.00
70.00
70.00
L-13
Mazdoor (Skilled)
day
0.30
100.00
30.00
L-15
cum
0.75
609.00
456.75
M-052
kg
77.50
20.99
1626.42
kg
113.00
30.81
3481.53
M-078/
1000
M-103
Material
56.69
Machinery
Mastic cooker 1 tonne capacity
hour
1.00
1442.00
hour
0.50
269.00
1442.00
P&M-030
134.50
P&M-044
d)
e)
876.25
9638.70
1460.41
803.22
say
Note
L-12
Mazdoor
c)
day
803.00
Sr No
14.21
Ref. to
MoRTH
Spec.
2600
Description
Unit
Quantity
Rate Rs
Cost Rs
Remarks/
Input ref.
Labour
Mate
Mazdoor
Mazdoor (Skilled)
Material
1. Galvanised angle sections 100mm x 100mm of 12mm
thickness weldable structural steel as per IS: 2062, 2
nos. of 12 m length each @ 17.7 kg/m and 5 per cent
wastage.
Add 5 per cent of cost of above for structural steel for
anchorage, welding and other incidentals.
Preformed continuous chloroprene elastomer or closed
cell foam sealing element with high tear strength,
vulcanised in a single operation for the full length of a
joint to ensure water tightness.
Add 1 per cent of cost of sealing element for lubricantcum-adhesive and other consumables.
c) Overhead charges @ 20% on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Cost for 12 m = (a+b+c+d)
Rate per m = (a+b+c+d)/12
day
day
day
0.036
0.60
0.30
80.00
70.00
100.00
2.88
42.00
30.00
L-12
L-13
L-15
kg
446.00
0.00
0.00
M-103
b)
0.00
metre
12.00
4928.00
14.22
2607
M-143
591.36
say
Note
59136.00
11960.45
7176.27
78938.96
6578.25
6578.00
b)
Labour
Mate
day
0.05
80.00
4.00
L-12
Mazdoor
day
1.00
70.00
70.00
L-13
Mazdoor (Skilled)
day
0.25
100.00
25.00
L-15
metre
12.00
8600.00
103200.00
Material
5164.95
21692.79
13015.67
143172.41
11931.03
M-178
Sr No
Ref. to
MoRTH
Spec.
Description
Unit
Quantity
Rate Rs
say
Note
Cost Rs
11931.00
Remarks/
Input ref.
CHAPTER - 15
RIVER TRAINING AND PROTECTION WORKS
Sr No
15.1
Ref. to
MoRTH
Spec.
2503
Description
15.2
2503
*
Note
15.3
2503
Quantity
Rate Rs
Cost Rs
Remarks/
Input ref.
*
Note
Unit
cum
cum
1.00
0.20
289.00
289.00
289.00
57.80
M-003
M-008
day
day
day
0.04
0.35
0.75
80.00
100.00
70.00
L-12
L-11
L-13
say
3.20
35.00
52.50
87.50
52.50
577.50
577.50
sqm
22.00
input
#VALUE!
M-102
cum
cum
5.63
1.13
289.00
289.00
1627.07
326.57
M-003
M-008
day
day
day
0.18
1.50
*3.00
80.00
100.00
70.00
L-12
L-15
L-13
say
14.40
150.00
210.0
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
2715.70
2715.70
Item 12.8
(A)
cum
1.00
Sr No
Ref. to
MoRTH
Spec.
Description
Unit
Quantity
Rate Rs
2504
say
2770.01
2770.00
15.4
Remarks/
Input ref.
54.31
Cost Rs
cum
cum
1.00
0.20
289.00
289.00
289.00
57.80
M-003
M-008
day
day
day
0.04
0.35
0.75
80.00
100.00
70.00
L-12
L-11
L-13
say
3.20
35.00
52.50
87.50
52.50
577.50
577.50
2715.70
2715.70
Item 12.8
(A)
cum
1.00
54.31
2504
2770.01
say
2770.00
609.00
730.80
Material
Graded stone aggregate of required size
b)
cum
1.20
Mate
day
0.05
80.00
4.00
L-12
Mazdoor (Skilled)
day
0.25
100.00
25.00
L-15
Mazdoor *
day
1.00
70.00
70.00
L-13
c)
d)
165.96
99.58
1095.34
say
15.6
700 &
2504
M-012
Labour
1095.30
Sr No
Ref. to
MoRTH
Spec.
Description
Unit
Quantity
Rate Rs
Cost Rs
Remarks/
Input ref.
b)
Labour
Mate
day
0.02
80.00
1.60
L-12
Mazdoor
day
0.30
70.00
21.00
L-13
Mazdoor (Skilled)
day
0.10
100.00
10.00
L-15
sqm
11.00
46.00
506.00
M-181
Material
107.72
64.63
710.95
2504.4
71.10
say
71.10
Toe protection
A toe wall for toe protection can either be in dry rubble
masonry in case of dry rubble pitching or pitching with
stones in wire crates or it can be in PCC M15 nominal mix if
cement concert block have been used for pitching . Rates
for toe wall can be adopted from respective clauses
depending upon approved design. The rate for excavation
for foundation, dry rubble masonry and PCC M15 have been
analysed and given in respective chapters.
15.8
2505
d)
cum
0.33
2467.00
814.11
cum
0.33
1979.00
653.07
14.67
Stone
cum
1.00
289.00
289.00
M-003
Stone Spalls
cum
0.20
289.00
57.80
M-008
Labour
Mate
day
0.08
80.00
6.40
L-12
Mason
day
0.50
100.00
50.00
L-11
day
1.50
70.00
105.00
L-13
e)
f)
264.46
158.68
2413.19
say
Item 12.6
(A)
Item 12.8
(A)
2413.20
Sr No
Ref. to
MoRTH
Spec.
15.8
Description
B
2506
Quantity
Rate Rs
Cost Rs
Remarks/
Input ref.
15.9
Unit
cum
1.00
2715.70
2715.70
cum
0.33
2715.70
896.18
Item 12.8
(A)
Item 12.8
(A)
36.12
3648.00
say
3648.00
b)
Material
Stone
cum
1.00
289.00
289.00
M-003
Stone Spalls
cum
0.20
289.00
57.80
M-008
Labour
Mate
day
0.10
80.00
8.00
L-12
Mason
day
0.50
100.00
50.00
L-11
mazdoor
day
1.50
70.00
105.00
L-13
1.63
102.29
61.37
2507.2
15.10
15.11
2507.2
say
675.10
2715.70
2715.70
say
2715.70
Note
675.09
cum
1.00
Item 12.8
(A)
b)
Material
Stone
cum
1.00
289.00
289.00
M-003
Stone Spalls
cum
0.20
289.00
57.80
M-008
Labour
Mate
day
0.05
80.00
4.00
L-12
Mason
day
0.25
100.00
25.00
L-11
Mazdoor
day
1.00
70.00
70.00
L-13
4.46
90.05
54.03
594.34
Sr No
Ref. to
MoRTH
Spec.
Description
Unit
Quantity
Rate Rs
say
Cost Rs
594.30
Remarks/
Input ref.
CHAPTER-16
REPAIR AND REHABILITATION
Sr No
16.1
Ref. to
MoRTH
Spec.
2809
Description
16.3
2809
2807
Quantity
Rate Rs
Cost Rs
Remarks/
Input ref.
16.2
Unit
day
day
0.06
1.00
80.00
70.00
4.80
70.00
L-12
L-13
hour
1.00
206.00
206.00
P&M-001
hour
0.50
231.00
P&M-053
say
115.50
118.89
51.52
566.71
56.67
56.70
day
day
0.03
0.75
80.00
70.00
2.40
52.50
L-12
L-13
hour
hour
0.75
0.40
206.00
231.00
P&M-001
P&M-053
say
154.50
92.40
90.54
39.23
431.57
43.16
43.20
M081/1000
M-005
M-192
M-095
M-180
kg
16.00
4.40
70.40
cum
kg
kg
kg
0.04
2.00
0.67
0.64
149.00
52.00
200.00
40.00
5.96
104.00
134.00
25.60
6.80
b)
day
day
day
0.01
0.04
0.14
80.00
100.00
70.00
0.80
4.00
9.80
L-12
L-11
L-13
Sr No
Ref. to
MoRTH
Spec.
Description
Unit
2806
hour
Quantity
0.10
Rate Rs
Cost Rs
500.00
50.00
say
123.41
53.48
588.24
588.20
4.40
4.84
Remarks/
Input ref.
P&M-076
Material
Cement including 10 per cent wastage
c)
kg
1.10
@ 20 per
0.97
Mate
day
0.08
80.00
6.40
L-12
Mazdoor (Skilled)
day
0.10
100.00
10.00
L-15
Mazdoor
day
0.10
70.00
7.00
L-13
hour
0.10
230.00
23.00
M-111
Machinery
Grout pump with agitator and accessories
d)
e)
15.66
6.79
M081/1000
45.45
say
45.40
Material
Cement including 10 per cent wastage
kg
0.55
4.40
2.42
kg
0.55
0.10
0.05
c)
@ 20 per
0.48
Mate
day
0.08
80.00
6.40
L-12
Mazdoor (Skilled)
day
0.10
100.00
10.00
L-15
Mazdoor
day
0.10
70.00
7.00
L-13
hour
0.10
230.00
23.00
M-111
Machinery
Grout pump with agitator and accessories
d)
e)
14.81
6.42
70.58
say
16.6
2800
M081/1000
M005/1500
70.60
Sr No
Ref. to
MoRTH
Spec.
Description
b)
Unit
Quantity
Rate Rs
day
0.06
80.00
4.80
L-12
Mazdoor (Skilled)
day
0.75
100.00
75.00
L-15
Mazdoor
day
0.75
70.00
52.50
L-13
kg
315.00
200.00
63000.00
M-145
2.00
230.00
460.00
M-111
Material
e)
hour
19077.69
8267.00
90936.99
16.7
2803
Remarks/
Input ref.
Mate
Note
Cost Rs
9093.70
say
9093.70
200.00
220.00
This item is a proprietory item available in market as prepacked polymer concrete and is required to be applied as
per instructions of the manufacturer.
Sealing of crack / porous concrete with Epoxy Grout by
injection through nipples complete as per clause 2803.1.
Unit = kg
Taking output = 1 kg
a)
Material
Epoxy including 10 per cent wastage
b)
c)
kg
1.10
Mate
day
0.08
80.00
6.40
L-12
Mazdoor (Skilled)
day
0.10
100.00
10.00
L-15
Mazdoor
day
0.10
70.00
7.00
L-13
hour
0.10
500.00
50.00
P&M-078
Machinery
Epoxy Injection gun
d)
e)
88.02
38.14
419.56
say
16.9
2807
M-095
Labour
419.60
b)
Mate
day
0.04
80.00
3.20
L-12
Mazdoor
day
0.50
70.00
35.00
L-13
Mazdoor (Skilled)
day
0.50
100.00
50.00
L-15
hour
1.00
206.00
206.00
P&M-001
Shotcreteing equipment
hour
1.00
500.00
500.00
P&M-076
hour
0.02
506.00
10.12
P&M-060
Machinery
Sr No
Ref. to
MoRTH
Spec.
Description
c)
Unit
Quantity
Rate Rs
Remarks/
Input ref.
Material
Cement
kg
120.00
4.40
528.00
M081/1000
M-005
Sand
cum
0.15
149.00
22.35
cum
0.15
401.94
60.29
M-024
kg
2.50
160.00
400.00
M-147
Water
KL
0.10
10.00
1.00
M-189
d)
e)
544.79
236.07
2596.82
Cost Rs
259.68
say
259.70
kg
9.60
200.00
1920.00
M-095
cum
3.60
3170.80
11414.88
Item
14.1(C)
day
0.26
80.00
20.80
L-12
Mazdoor
day
6.00
70.00
420.00
L-13
Mazdoor (Skilled)
day
0.50
100.00
50.00
L-15
c)
d)
4147.70
1797.34
19770.72
1647.56
say
Note
16.18
1647.60
day
0.20
80.00
16.00
L-12
day
5.00
70.00
350.00
L-13
hour
1.00
231.00
231.00
P&M-053
Machinery
Tractor-trolley for disposal of dismantled material
c)
d)
179.10
77.61
853.71
85.37
say
Note
16.19
85.40
Sr No
Ref. to
MoRTH
Spec.
Description
Unit
Quantity
Rate Rs
Cost Rs
Remarks/
Input ref.
Taking output = 10 M
a) Labour
Labour for dismantling old railing and disposal of dismantled
material.
Mate
Mazdoor
b)
day
0.40
80.00
32.00
L-12
day
10.00
70.00
700.00
L-13
hour
1.00
231.00
231.00
P&M-053
Machinery
Tractor-trolley for disposal of dismantled material
c)
d)
288.90
125.19
1377.09
137.71
say
Note
16.20
137.70
day
0.16
80.00
12.80
L-12
day
4.00
70.00
280.00
L-13
hour
1.00
231.00
231.00
P&M-053
Machinery
Tractor-trolley for disposal of dismantled material
c)
d)
157.14
68.09
749.03
74.90
say
16.21
74.90
day
0.04
80.00
3.20
L-12
Mazdoor
day
1.00
70.00
70.00
L-13
cum
0.30
3170.80
951.24
Item
14.1(C)
21.96
9.52
1055.92
105.59
Sr No
16.22
Ref. to
MoRTH
Spec.
Description
Unit
Quantity
Rate Rs
Cost Rs
say
105.60
317.08
Remarks/
Input ref.
Material
cum
0.10
3170.80
tonne
0.013
32604.30
Mate
day
0.016
80.00
1.28
L-12
mazdoor
day
0.20
70.00
14.00
L-13
Item
14.1(C)
423.86 Item 14.2 A
4.58
1.99
762.79
76.28
say
76.30
Ref. to
MoRTH
Spec.
Description
(ii)
Unit
Quantity
Rate Rs
Cost Rs
Remarks/
Input ref.
b)
c)
cum
0.424
kg
25.410
cum
2.770
2715.70
1150.10
29.90
759.81
69.60
192.79
Item 12.8
(A)
Item 13.6
/1000
Item No.
3.13
g)
Labour
Mate
day
0.320
80.00
25.60
Mason
day
1.000
100.00
100.00
L-12
L-11
Mazdoor
day
7.000
70.00
490.00
L-13
hour
6.000
231.00
1386.00
P&M-053
Machinery
Tractor-trolley
h)
i)
160.13
216.17
4480.60
320.04
say
320.00
2
3
Description
Earth work Excavation
For Structure
PCC (M15) levelling course
Below Raft
RCC M20
Box Portion
For Raft
For Walls
For Slab
For Hanch
HYSD Bar
Rein. @ 60kg/cum
Nos
Length
(L)
Breadth
(B)
Height (H)
Unit
Quantity
1.000
2.200
0.350
Cum
0.770
0.770
30.90
23.79
Rate
Amount
1.000
2.200
0.150
Cum
0.330
2609.90
861.27
1
2
1
4
1.000
1.000
1.000
1.000
1.900
0.200
1.600
0.150
0.200
1.000
0.200
0.150
Cum
Cum
Cum
Cum
0.380
0.400
0.320
0.090
1.190
3455.20
4111.69
71.400
0.071
42613.70
3042.62
60.000
1.190
Kg
MT
Say,
8039.37
8039.40
Description
Breadth
(B)
Height (H)
Unit
Quantity
1.000
1.900
0.600
Cum
1.140
1.140
Rate
Amount
Nos
Length
(L)
30.90
35.23
2609.90
1117.04
0.490
3455.20
1693.05
19.600
19.600
0.020
42613.70
835.23
PCC (M15)
For base slab
1.000
1.900
0.200
Cum
0.380
Inside drain
1.000
1.200
0.040
Cum
0.048
0.428
RCC M20
Box Portion
For Walls
1.000
0.200
0.850
Cum
0.340
For Slab
1.000
1.500
0.100
Cum
0.150
HYSD Bar
Skin Rein. @ 40kg/cum
40.000
0.490
Kg
Kg
MT
Say,
3680.54
3680.50
S No
1
Description
Analysis for 10m
PCC M-20
For Structure
Grating
AC Pipe
Nos
10.000
0.250
0.250
Cum
No.
0.300
MT
Quantity
Rate
0.625
0.625
3344.00
1.000
1.000
45.70
0.300
87.80
Amount
2090.00
45.70
26.34
2162.04
216.20
216.20
S No
Description
Analysis for
C/W Width
Shoulder width
Crust Detail
WMM
GSB
Rate
0.1 m
0.15 m
100.000
6.500
GSB
100.000
4.100
0.150 Cum
61.500
61.500
WMM
100.000
3.800
0.100 Cum
38.000
939.60
143.70
Earthen Shoulder
100.000
1.000
Premix carpeting
100.000
3.500
Sqm 350.000
350.000
4.500
12.000
Rm
1.500
0.400 Cum
412.30
38.000
70.50
71.00
4.500
4.500
3445.80
7.200
2715.70
Amount
22912.50
25356.45
35704.80
14370.00
24850.00
15506.10
19553.04
158252.89
1582.53
1582.50
Description
Unit
Sqm
Per cm
per letter
No
0.3
0.3
.
200
Qty
Rate
0.18 31.90
200
0.20
Description
Unit
Sqm
No
Qty
Rate
0.5
.
1.5
31.90
4000
0.20
Say
Amount
5.742
40
45.742
45.80
Amount
47.85
800.00
847.85
282.62
282.60
Unit
No
Cum
0.0067
Qty
Rate
Amount
.
2
Sqm
19
2.5
0.15
7.13
557.8
3974.33
5252.48
say
5253
Rate
Amount
Description
Unit
No
Cum
0.247
Sqm
19
3.5
0.15
Qty
.
9.98
557.8
5564.06
13417.4
say
13418
Toll booth
Unit
No
Sqm
6.66
2.05
Qty
Rate
Amount
27.3
6162
168,259.57
29.1
6162
179,006.10
20
6162
123,240.00
100000
400,000.00
200000
200,000.00
.
2
Office building
Electric room
Sqm
Sqm
LS
Electrification
LS
LS
100,000.00
Total cost
1,170,505.67
say
1,170,506.00
Description
Nos
2
1
1
1
1
2
1
2
2
2
4
2
Length Breadth
(L)
(B)
8.250
12.400
2.202
5.500
8.100
8.250
13.350
13.350
8.100
8.100
0.813
0.400
1.400
1.800
1.350
2.300
0.700
1.400
1.800
Height
(H)
0.800
0.660
0.300
0.300
0.300
0.150
0.520
-0.426
0.825
0.400
1.700
0.400
0.159
0.400
1.000
Quantity
Rate
Amount
Cum
Cum
Cum
Cum
Cum
Cum
18.48
14.73
0.89
3.80
1.70
39.60
30.9
1223.60
Cum
Cum
Cum
Cum
3.47
12.50
-11.36
4.60
5.00
2367.6
11838.00
Cum
Cum
Cum
Cum
Cum
22.72
2.59
-0.52
0.32
25.12
2715.7
68206.46
Rmt
60
676.10
40565.80
Cum
0.92
120.4
111.20
0.231
1.721
0.150
Cum
1.03
1049.9
1084.18
7 Pitching on Slopes
1.721
0.300
Cum
2.07
577.5
1192.71
30
Unit
124221.95