You are on page 1of 2

Indicative Steel Ratio

Introduction

Architectural design and plans are preliminary and the design is still undergoing further
development, an accurate and true structural steel reinforcement quantities will not be
available unless the whole design has been fully completed and working drawings for all
parts of the building is produced.
However, with the time limit given and as per your requested, we are presenting the
indicative structural rebar ratio of the typical bay to the Architectural Plan and information
we known at the time of preparation for your information as follows:
1.

2.

3.

4.

5.

6.
7.

Precast Floor System (5kPa)


Insitu Slab topping and precast slab plank 75 kg/m3
Precast and partly insitu secondary beam (700x560/260/560) 60 kg/m (weighted
average)
Main beam (750x600) 106 kg/m (weighted average)
Other Beams
Plant Room Area (700x450) 60 kg/m
Edge Beam (750x600) 50 kg/m
Roof
Beam (700x450) 70 kg/m
Slabs 80 kg/m3
Upper Roof
Beams (700x450) 60 kg/m
Slabs 80 kg/m3
Columns
Exterior wall columns (300x1800) 240 kg/m3
Internal Columns 250 kg/m3 (weighted average)
Stair/Core Wall 140 kg/m3 (Average)
Basement
Basement Wall 100 kg/m3
Ground Slab 80 kg/m3
Beam (800x1000) 130 kg/m
Stair/Core Wall 160 kg/m3

8.

Pile Caps
Single Cap 120 kg/m3
Combined Cap 240 kg/m3
Please note that the above steel ratio are based on a preliminary set of design data and
requirements only and only included for the reinforcement required for the design in
accordance to COP2004 Structural Use of Concrete, other reinforcements required for
fabrication or other purpose are not included in the estimate. All steel ratios can only be
verified and confirmed once the design is frozen and detailed design of the structure is
completed and they are subjected to vary from the actual case as the Architectural plans
are still under development.
Disclaimer

The above figures are indicative only


Maunsell|AECOM cannot be responsible for the quantities based on the above ratio
The above figures are information only, and shall be use in care for deriving cost.
Contingencies shall be allowed when formulating predicted cost of any kind.

You might also like