SURVEY CAMP DIARY

6/7/2015

First Day

Monday

10:00 am

: Camp officer conducted an introduction class useful for survey camp.

10:30 am

: Students were divided into 6 batches and selected plot for each batch.

11:30 am

: Received the instruments for doing whole work.

12:15 pm

: Conducted reconnaissance survey. Cleared work site. Additional points fixed.

2:00 pm

: Prepared location plan and key plan and submitted.

2:30 pm

: Reference points selected and linear measurements were taken.

4:00 pm

: Stopped the days work.

7/7/2015

Second Day

Tuesday

8:30 am

: Reported at the college.

8:45 am
: The group is divided into two. The one for preparing reference sketch and
other for taking traverse using theodolite and then work started.

10:00 am
10:45 am
3:00 pm

: Completed the reference sketch data and plotted the measurements.


: Bearing at a selected station were taken using prismatic compass.
: Submitted the reference sketch.

3:25 pm
:
station points.
4:00 pm

The readings of theodolite traversing are submitted taken from different

: Stopped the days work.

8/7/2015

Third Day

Wednesday

8:30 am

: Reported the college.

12:00 pm : Calculations of theodolite traversing were completed and gayles traverse table
was prepared.
1:00 pm : Plotted the coordinates of latitudes and departures in graph paper and
computed the area
3:30 pm

: Temporary bench mark was established using dumpy level.

4:00 pm

: Stopped third day work.

9/7/2015

Fourth Day

Thursday

8:30 am

Reported at the college.

8:45 am : Started work the batch was divided into two groups. First group started
contouring and second group plane tabling.
3:30 pm :
completed.
4:00 pm

The readings of contouring and plane tabling at one station point each was

: Stopped fourth day work.

10/7/2015

Fifth Day

Friday

8:30 am

Reported at the college.

9:00 am

Continued both plane tabling and contouring as groups.

1:30 am

4:00 pm :

Completed contouring.
Plane tabling was almost complete.

4:20 pm : Stopped fifth day work.

11/7/2015

Sixth Day

Saturday

8:30 am

12:00 pm

Reported at the college.


: Plane tabling was completed.

1:00 pm : Offsetting for finding the area of remaining portion outside traverse was started.
3:00 pm :

Offsetting was completed.

3:45 pm

Calculation of contouring completed.

4:00 pm

Stopped sixth day work.

13/7/2015

Seventh Day

Monday

8:30 am

10:00 am :
11:30 am

Reported at the college.


Completed the chart drawing.

: Submitted survey rough report.

12:30 pm : Returned instruments.