You are on page 1of 2

Exercise -3

produce a Gantt Chart;


Activity
ID

Activity description

Duration

Precedent(s)

Refurbish workshop
(NB - Summary task/ workpackage)

Recruit new staff

Choose new basic equipment

Choose new special equipment

Draw new layout

Train new staff

10

Order new basic equipment

Order new special equipment

Make structural alterations

10

Unpack and inspect equipment

7,8

11

Install services

12

Install and commission equipment

10,11

13

Begin workshop operations

0.1

???

produce a Network diagram;


identify the Critical Path, and
determine the project duration and earliest date by which the workshop can be
expected to begin operations.

Take all durations to be in weeks,