You are on page 1of 166

A COMPARATIVE STUDY OF PIPE JACKING TECHNIQUES OF

THE PROVINCIAL WATERWORKS AUTHORITY

2554

2554

.
.
2554





1
2 3
1
2 3


3
2
3

Thesis Title
Name - Surname
Program
Thesis Advisor
Thesis Co - advisor
Academic Year

A Comparative Study of Pipe Jacking Techniques of


The Provincial Water Works Authority
Mr. Sarawut Kongjai
Civil Engineering
Assistant Professor Dr.Thaworn Thirawetchayan
Dr.Kongkoon Tochaiwat
2011

ABSTRACT
Due to the traffic problem in highly populated downtown area of the cities, pipe jacking
methods in waterwork construction projects were employed and adapted by the Provincial
Waterworks Authority (PWA) in order to reduce the traffic congestion caused by the piping work
projects.
There are three types of pipe jacking techniques known as Type 1 Steel Pipe with
Concrete Sleeve, Type 2 Steel Concentric Double Cylinder Pipe (SCP) and Type 3 Reinforced
Concrete Pressure Pipe. Type 1 was the old technique commonly used while this research focused
on comparing the later two techniques. Details from two pipe jacking projects on construction
methods, major equipments, resource lists, assigned crew, and the production rate in the jacking
activities were summarized.
The results of the research showed that Type 3 technique consumed less connection
welding time as the result of time efficiency. The construction cost of Type 2 technique was
minimal due to fewer steps of working process. However, type 3 techniques was more flexible,
easier to adjust to the target path, therefore suitable for curve path. Finally, this research will be
useful for PWA and piping work contractors in selecting the right jacking technique for a workshop.

Keywords: pipe jacking, reinforced concrete pressure pipe, steel concentric double cylinder pipe


.
.
. .
.







..
.
..
...
..
....

1 ...
1.1 ..
1.2
1.3 ..
1.4 ..
1.5 .
2 ..
2.1
2.2 ...
2.3 .
2.4
2.5 ..
3 ...
3.1 .
3.2 ..
3.3 ..
3.4
..

1
1
2
3
3
4
5
5
19
20
36
37
42
42
43
44
45

( )

4 ...... 47
4.1 1
( 2)... 47
4.2 2 2
( 1).... 58
4.3 3
( 2)... 69
4.4
... 79
4.5
(Pipe Jacking) 81
5 .. 83
5.1 83
5.2 84
5.3 . 84
5.4 85
5.5 .. 86
5.6 .. 87
. 88
89

90
( 2)... 107
2 ( 1)... 126
( 2).. 144
.... 155
..

2.1 Sheet Pile. 11


2.2 13
2.3 . 17
2.4 18
2.5 .. 19
2.6 . 20
2.7 (Production Rate) .. 37
2.8
39
3.1 45
3.2 46
4.1 2.. 49
4.2 1 (Cycle) 2 55
4.3
(BOQ) 2. 56
4.4 1... 60
4.5 1 (Cycle) 1 . 66
4.6
(BOQ) 1.. 67
4.7 2... 71
4.8 1 (Cycle) 2 76
4.9
(BOQ) 2.. 77
4.10 80
4.11 (Pipe Jacking) 81

2.1 (Pipe Jacking) ... 5


2.2 (Blind Shield) 6
2.3 Closed Face Shield Earth Pressure Balance (EPB) . 7
2.4 Slurry Shield.. 7
2.5 Remote Control 8
2.6 Skip Car Blind Shield 8
2.7
Closed Face Shield.. 9
2.8 . 9
2.9 Sheet Pile. 10
2.10 . 12
2.11 ( 1) 14
2.12 ( 2) .. 15
2.13 2 ( 1) ... 16
2.14 ( 2) . 16
2.15 . 22
2.16 (Line & Grade) . 23
2.17 (Anode) Zinc Ribbon 24
2.18 . . . 27
2.19 (Line & Grade) . 28
2.20 28
2.21 ... 29
2.22 29

( )

2.23 (Back Thrust Wall) .


2.24 (Guide Rail) Entrance Ring ..
2.25 (Laser) .
2.26 Radiographic Test Liquid Penetrant Test
2.27 (Steel Plate) (Concrete Deck).
2.28 8 ksc. 2 . ..
2.29 .
2.30 ...
2.31 150 . PVC Production Rate
Nishida, et al. .
2.32 (Pipe Jacking) Horizontal Directional Drill (HDD).
3.1 .
4.1 ...
4.2 2...
4.3 ...
4.4 1...
4.5 ...
4.6 2...

30
30
31
31
32
33
35
35
38
40
43
47
54
59
65
69
75


.
.
.
.
.
.
.
1
2
1
2
.
BOQ
CP
CPM
EPB
HDD
HDPE
SCP



Bill of Quantities
Cathodic Protection
Critical Path Method
Earth Pressure Balance
Horizontal Directional Drill
High Density Polyethylene
Steel Concentric Double Cylinder Pipe

1.1
(.)
1
(2550-2554) [1]



(Pipe Jacking)


1 2545
1 [1]






22.00 . 05.00 .
[2]



(Trenchless Technology)
(Pipe Jacking)

2
(Pipe Jacking)
3 ( 2)
( 1)
( 2) 3

1.2
1.2.1 3
( 2) ( 1)
( 2)
1.2.2 3
1.2.3 3
1.2.4
3
1.2.5

3
1.3


1,000 - 1,500 . 3 2
1 2
1,000 .
1
1.3.1

1.3.2
1.4
1.4.1
1.
2.

3.
1.4.2
1.
2.
2 4
3.
4.

4
1.5
1.5.1 3

1.5.2

1.5.3

1.5.4

2

2.1 (Pipe Jacking)
(Driving Pit)
(Receiving Pit)
(Shield)




(Laser)
Microtunneling [3]

2.1 (Pipe Jacking)

6
2.1.1 ( Shield )


3
1.
2. (Blind Shield) (Closed Face Shield)
Earth Pressure Balance (EPB)
3. Slurry Shield
Slurry Shield
EPB Skip Car
Cable Winch

2.2 (Blind Shield)

2.3 Closed Face Shield Earth Pressure Balance (EPB)

2.4 Slurry Shield



EPB Slurry Shield

2-3 ./ 15 ./
EPB
2 . 50-60
.


(Remote Control)

8
(Cable Winch) (Skip Car)


(Gravity Flow)

2.5 Remote Control

2.6 Skip Car Blind Shield

2.7 Closed Face Shield


2.1.2 (Hydraulic Jack)

(Intermediate Jack) Ring
Spacer
[3]

2.8

10
2.1.3
Sheet Pile
2 (Sunken
Shaft) Caisson Diaphragm Wall
(Sunken Shaft)
Sunken Shaft
(Precast Segment)

[2]
(Sunken Shaft)
(Precast Segment)

Sheet Pile Sheet Pile

2.9 Sheet Pile

11
2.1 Sheet Pile [2]

(.)

A1

B1

A1

B1

900

8.00

3.00

4.00

3.00

4.0-6.0

8-12

1,000

8.00

3.00

4.00

3.00

4.0-6.0

8-12

1,200

8.00

3.50

4.00

3.20

4.0-5.5

10-12

1,300

8.00

3.50

4.00

3.30

4.0-5.5

10-12

1,500

8.00

3.50

4.00

3.50

4.0-5.0

10-12

1,800

8.00

3.50

4.00

3.50

4.0-5.0

10-12

Sheet Pile
L

.. 2546
.. 2547


Sheet Pile

Sheet Pile (Stiffness)

Sheet Pile


[2]


200

12
300 Intermediate Jack

Bentonite Slurry Polymer

1 .
50

2.10
2.2 [2]

13

()

(.) A1 B1
T1
D1
T3
900 8.00 2.50 0.5-0.8 8.00 0.4-0.6

()

A2 B2
4.00 2.50

T2
0.3-0.4

D2
4.00

T4
0.3-0.4

L
D () ()
4.0-6.0 8-12

1000 8.00 2.50 0.5-0.8 8.00

0.4-0.6

4.00 2.50

0.3-0.4

4.00

0.3-0.4

4.0-6.0

8-12

1200 8.00 3.00 0.6-0.8 8.00

0.5-0.6

4.00 3.00

0.3-0.4

4.00

0.3-0.4

4.0-5.5

10-12

1300 8.00 3.00 0.6-0.8 8.00

0.5-0.6

4.00 3.00

0.3-0.4

4.00

0.3-0.4

4.0-5.5

10-12

1500 8.00 3.00 0.6-0.8 8.00

0.5-0.6

4.00 3.00

0.3-0.4

4.00

0.3-0.4

4.0-5.0

10-12

1800 8.00 3.00 0.6-0.8 8.00

0.5-0.6

4.00 3.00

0.3-0.4

4.00

0.3-0.4

4.0-5.0

10-12

- 6

2.1.4
4
1. ( 1)




(Spacer)

Cathodic Protection (CP) CP





14

[4]

2.11 ( 1)
2.

(CP)
(Spacer) 3 /.

1,000 1,200
(High Density Polyethylene ; HDPE)


15

2.12 ( 2)
2.1.5 2

1. 2 (Steel Concentric Double Cylinder Pipe ; SCP)
( 1,000 . 1,200
. )
Coating CP

( 3 .)
X - Ray

16

2.13 2 ( 1)
2.

Lining

0.5
(X Ray)

2.14 ( 2)

17

2.14

2.1.6


2
2.3

1 6 ()
2
3 /

18
2.4

1
2
3
4
5
6
7
8 (Air Compressor)
9
10 Sheet Pile
11
12




4






19






(Pipe Jacking)





4
2.2

2.5 [2]

(.)
300
400
800
1,000
1,200
1,500
1,800

(/)
/ Sheet Pile
/

290,100
134,200
300,000
136,700
501,200
238,800
1,539,800
499,300
527,800
246,500
1,663,200
545,200
559,000
264,700
1,804,200
597,200
617,700
287,600
2,013,100
674,900
710,800
312,600
2,227,200
754,800

20
2.6 [2]
(/)

A
B
C
( )
( )
( )
(.)


1
1
2
1
2
1
2
1
300
7,800
400
9,400
800
24,100 18,700
30,000 26,700
1,000
30,100 21,500 22,600 18,500 38,400 31,700 35,200
1,200
37,600 27,200 27,900 20,200 48,000 38,900 43,800
1,500
53,500 36,200 39,800 28,400 70,700 51,900 64,900
1,800
75,700 54,700 54,600 39,300 99,000 70,500 95,300
(.)
1
2
1 2
2


2
26,600
30,400
39,600
54,700

2.3 (Pipe Jacking)


(Pipe Jacking)
400 .
1,500 .

2 1 2
4
(Pipe Jacking)
3

21
2.3.1
1.


22.00 . 05.00 . /
(Steel Deck)

(Steel Plate)
(Seal)

(Time) (Cost)
2. .
.
.

3.
(Information Sign) (Construction Sign)
(Traffic Sign)



15 50

.

22

2.15
4.

5. (Construction
Schedule) (Breakdown Construction Schedule)
Bar Chart



(Breakdown Construction Schedule)
15
Bar Chart Critical Path Method
(CPM)

Shop Drawing

23
6.

.


(.) .
.

7. (Line & Grade)







2.16 (Line & Grade)

24
8.
(Pipe Jacking)
/

9.



10. (Cathodic Protection System)


(ST)

. 2 (Anode)
Zinc Ribbon

2.17 (Anode) Zinc Ribbon

25
2.3.2


1.




2.


3.



2.3.3



(Pre-Construction
Conference) 2
1.
( ) (
)


26
2.

( )



[4]
2.3.4
.
. .


. . .

1.
(
) (
) ( )
15
(
)
2.
.

7
45
45

27

.
(
)
7
3.
( . )


4. (. . . . )

( . .
)



5.

2.18 . .

28
2.3.5 (Pipe Jacking)
1. (Line Grade)
2.19

2.19 (Line & Grade)


2.

2.20
3.

29

2.21
4.

2.22
5.
6. Jacking System
7. (Back Thrust Wall) (Jacking)

30

2.23 (Back Thrust Wall)


8. (Guide Rail) Entrance
Ring Soft Eye

2.24 (Guide Rail) Entrance Ring


9. (Jacking System)
(Laser)

Muck Tank
Skip Car

31

2.25 (Laser)
10.


2.26 Radiographic Test Liquid Penetrant Test


11.
(Concrete Deck) (Steel Plate)
05.00 . 22.00 .

32

2.27 (Steel Plate) (Concrete Deck)


2.3.6

(Hydrostatic Test)
8 ./..(ksc) 2 .
[4]

33

2.28 8 ksc. 2 .
2.3.7
/




1.





2.
(Field Density)

34
24 . 5 .
20 . 2
2 . 200 .

3.

Dowel Bar Tie Bar








Joint Sealer
4.






[4]

35

2.29
2.3.8
1.

2.30
2. (As-Built Drawing)
(As-Built Drawing)

36
3.



.
.
4.
(.
)
(
)





5.

[4]
2.4


2.8

37
2.7 (Production Rate)


()

/ /


Alignment
1.
2.
3. /
Spacer (2.6 .)
4. 2
5. /
Spacer
2
/

2.5
Nishida, et al. [5] 150 .
PVC Steel Plate Rubber Tube Production
Rate 2.31
Cost
Effectiveness

38

2.31 150 . PVC Production Rate Nishida, et al.


Phien-wej (2002) [6]

10
EPB


NATM

Phien-wej (2002) [6]
3.00 .

1-2 %

39
(2539) [7]


2.7
2.8


6 .

6 . 12

.

12 .

Chalermkiat (2002) [8] (Trenchless


Technology)


Pipe Jacking 3 Sheet Pile

Tennyson M.M. and Daniel J.D.(2004) [9] (Pipe Jacking)
Horizontal Directional Drill (HDD)

(Reamer)

(Reamer)
HDPE

40

2.32 (Pipe Jacking) Horizontal Directional Drill (HDD)


(2545) [10]



(Pipe Jacking System) (Finite Element Method) Empirical

41
Tennyson, et al. (2004) [9]
(224 ) Boston







(Pipe Jacking) (Tunneling)
Construction Engineering


(Pipe Jacking)







3.1
2
4
3.1.1
1. ( 1)

2. ( 2)
.

3.1.2
1. 2 ( 1)
1 2
2. ( 2)
. .
2 2
1 2 1,000 . 1

43
3.2

1,000 1,500
. 2



3.1

3.1

44
3.3
5
3.3.1

3.3.2
2
2

3
2
3.3.3


3.3.4 2
4

3.3.5 (Production Rate)


(Delay)

45
3.4
3.3

3.1
3.1

/
/

/
/

/
/

/
/

/
/

46
3.2
3.2

1
2

2 1,200
1,200 . . 3
6 . .
1,130 .
220 .

1,000 .
9.00 .

1,340 .


3 2 3 2


3
1

4


2
2 1 2 3


4.1 1 ( 2)
4.1.1


1,000 . 9.00 . 1,340 .
344

4.1

48
4.1.2
1,200 . 1,000 .
3.00
250 . Slurry Earth Pressure Balance Bentonite
2
(Steel Concentric Double Cylinder Pipe : SCP)
9.00 2 (SCP) 6



5 .
5 .
1
1,200 .
1,000 .
(Flow Chart) 4.1
2

49
4.1 2

1.

1-8

Sheet Pile
Bracing

Base Slab

2. Jacking
System

Back Thrust Wall

9 -22

50
4.1 2 ()

3.

24 - 30

Steel Ring



4.

23 - 45

51
4.1 2 ()

Coating

52
4.1 2 ()

46 - 53

5.
(Hydrostatic Pressure
Test)

-
Pressure Guage

8 ksc.

53
4.1 2 ()

6.


Sheet
Pile Bracing

54 - 57

54
4.1.3

( 2)
4.2

4.2 2

55
4.1.4 1 (
2) Time Sheet
1 (Cycle)
( 2)
4.2
4.2 1 (Cycle) 2

/

()
/

8

Alignment
9

19



3
Spacer
3
(2.6 .)
2
20


43



Spacer

2

56

1.
18

2.
5

3.
7

4.
2

5. ( 2.50 )
16

6. ( 9.00 )
9

7. 1,000 . 8 /
4.1.5


4.3
(BOQ) 2

BOQ

()
350,000
392,000
()
150,000
125,000
( /
22,400
19,200
)



57


4.1.6 ( 2)
1. (BOQ)
9
14.30

2.

(Bill of Quantities ; BOQ)
3.
(BOQ)

4. (/)

8




4.1.7
( 2)
1. BOQ




2.
2 .

58
3.

4.

5.
(Monotape)
6. 9.00

7.


8.

9.

10.

11.
(Sheet Pile)

4.2 2 2 ( 1)
4.2.1 2 ( 1)
1 2
- (
) 2 1,200 . 1,130 .

59

4.3
4.2.2 2
1,200 . - (
) 3.50 .
200 . Slurry Earth Pressure Balance
2 6

2




2 1,200 .
(Flow Chart) 4.4
2 ( 1)

60
4.4 1

1.


1


1 - 22

Line & Grade

Sheet Pile
Bracing

Base Slab
Soft Eye

2. Jacking
System

Back Thrust Wall

23 -32

61
4.4 1 ()


1


32 - 62

3.


Dummy RC

Adapter SCP

SCP RC
Dummy

SCP

X-ray

62
4.4 1()

Coating
Primer Monotape


Steel Encasing

Spacer

SCP

4.
(Hydrostatic Pressure
Test)

63 - 68

63
4.4 1 ()

-
Pressure Gauge

8 ksc.

64
4.4 1 ()

5.


Sheet pile Bracing


1


69 - 70

65
4.2.3


2 ( 1) 4.4

4.4 1

66
4.2.4 1 2 ( 1)
Time Sheet
1 (Cycle)
1 2 4.5
4.5 1 (Cycle) 1


Alignment
Spacer

Monotape
Steel Encasing
( 6 .)
Spacer

()
34
26
151
48
164



1. Sheet Pile
15

2. Sheet Pile
10

3.
10

4. 2 ( 6.00 )
6 /

67
4.2.5 2 ( 1)


(Bill of Quantities ; BOQ)
4.6
(BOQ) 1

BOQ

()
350,000
367,500
()
150,000
136,800
( / )
32,000
30,000






4.2.6 2 ( 1)
1.
(BOQ) 6
(Back Thrust Wall)

2.

68
3. (/)
2
2

4.2.7 2 ( 1)

1
1. BOQ
2 6

2. 2

3.


4.

5.

150 1
6. (X-ray)



69
4.3 3 ( 2)
4.3.1
( 2)
2
2 4.2
1
3035 ( )
1,200 . 220 .

4.5
4.3.2

1,200 . 3035 (
) 3.50 .
200 . Slurry Earth Pressure Balance
3 .

70




Push-on


1,200 . (Flow Chart)
4.7
( 2)

71
4.7 2

1.

Line & Grade


2


1 - 16

Sheet Pile
Bracing

Base Slab
Soft Eye
2. Jacking System

14 -23
Back Thrust Wall

72
4.7 2 ()

3.

Steel Ring

Spacer

Liquid
Penetrant
Test


2


24 - 56

73
4.7 2 ()

4.
(Hydrostatic Pressure Test)

-
Pressure Gauge


2


41 - 42 , 57 - 59

74
4.7 2 ()

5.


Sheet
Pile Bracing


2


60 - 62

75
4.3.3


2 4.6

4.6 2

76
4.3.4 1 ( 2)
Time Sheet
1 (Cycle)
2 4.8
4.8 1 (Cycle) 2


Alignment


Spacer (2.6
.)
2

Spacer
2


()
8
15
22

4
4

25

40

/ /







-

Muck Tank
Muck Tank


77



1. Sheet Pile
15

2. Sheet Pile
10

3.
7

4.
10

5. (3.00 ) 9 /
4.3.5 ( 2)


(Bill of Quantities ; BOQ)
4.9
(BOQ) 2

BOQ

()
350,000
394,700
()
250,000
230,000
(/)
39,200
41,000





78

4.3.6 ( 2)
1.
(BOQ)
6

8
4
3


2.
(BOQ)

3. (/)

(BOQ)
(BOQ)
2
-

1


-

3 .

79
2
(BOQ)
4.3.7 2

2
1.

3 .
(Butt Weld)

2. BOQ
1.


2

3.


4.
(Cement Lining)

4.4
3

4.10

80



1,000 .

2
1,200 .
2
2 ( 1)
( 2)
4.10

(/)
()
(/)
1




1,000 .


2
1,200 .




1,200 .

8
200-300
30,200
6,540,000

6
200
32,000
6,900,000

9
200-300
39,200
8,340,000

4.10 1
1
15,461 2 2
23,795 3
25,825
(.) 2.6
(.) 2546

81
2
4
(Pipe
Jacking) .



4.5 (Pipe Jacking)

4.11
4.11 (Pipe Jacking)


Sheet Pile


(Steel Circular

Shaft)

1.
Sheet Pile

2.

4.5.1 Sheet Pile Sheet Pile



(Jacking System)

(Thrust Wall Reaction Bock) (Hydraulic Jacks)

82
Sheet Pile
Sheet Pile
4.5.2 Sinking Caisson (In-situ
Casting) (Precast Segment)

Sheet Pile Sheet Pile

Sheet Pile

Sheet Pile


Sheet Pile


4.5.3 (Steel Circular Shaft)
(Receiving Shaft)
3.70 . 3 . 2.00
. H-Beam
Sheet Pile
(Steel Circular Shaft)

(Steel Circular Shaft) Sheet Pile

(Steel Circular Shaft)

5

3


(Pipe Jacking)

5.1
5.1.1 ( 2)






2


5.1.2 2 ( 1)

2
1 2

84
5.1.3 ( 2)



2


0.5

5.2
3
( 2) 9

( 2)
8 2 ( 1)
6
5.3

( 2) 1,000 .
2 1,200 .

2 ( 1)
( 2) 1,200 .
2 1 2
1
1

85
5.4
( 2)


(Point Load)





2 ( 1)

(X-Ray)


2
2

( 2)
(X-Ray) (Liquid Penetrant Test)


Point Load

86
5.5
5.5.1

1 2 2
3 .
(Butt Weld)
5.5.2 2
2

2

5.5.3
200
1 2 1
5.5.4
200
2 2
5.5.5



5.5.6


87
5.6
5.6.1
2 1,000 .
1 2 2
1,200 .
2
2 1,000 .
5.6.2






5.6.3 1 (Cycle)

2

5.6.4 (Cost)





5.6.5
(Risk Management Plan)


[1] , 2547,
, , 1-40.
[2] , , 2546,
, , , 1-16.
[3] , 2539, Pipe Jacking, , 2539, 32-37.
[4] , 2548,
, , 1-53.
[5] Najafi, M., Iseley, D.T., Pumphrey, N.D. and Nishida, Jr.H., 1993, LLB,an Innovative
Microtunneling Propulsion System, Structural Performance of Pipes, Sargard, Mitchell, pp.
107-124.
[6] Phien-wej, N., 2002, Experiences From EPB Shield Tunneling Underneath Existing
Structures in Bangkok Soils (Invited Paper), National Convention of Civil Engineering
(NCCE-8), 23-25
[7] , 2539, ,
2, 22-24 2539, , GTE
213-235.
[8] Chalermkiat, W., 2002, Trenchless Technology: Environmentally Friendly Techniques,
[9] Tennyson, M.M. and Daniel, J.D., 2004, Pipe Jacking in a Complex Urban EnvironmentBoston Massachusetts [Online], Available : http ://www.ascelibrary.org [2005, Febuary 9].
[10] , 2545,
, 8, 23-25
2545,, GTE 357-362



( 2)

3 Sheet Pile

4 Bracing

5 Base Slab

6 Sofe Eye

.1 1,200 . 1,000 ( 2)
91

7 Back Thrust Wall


10

9
Laser

11 Segment

12

92

.1 1,200 . 1,000 ( 2) ()

13 Segment

16

14 Load

17

15 Bracing
Base Slab

18 Muck Tank
2

93

.1 1,200 . 1,000 ( 2) ()

19 Muck Tank
Tank

20 21
1 2

21
1 2

22

23

24

94

.1 1,200 . 1,000 ( 2) ()

25 Steel Ring

26

27

28

29
3

30

95

.1 1,200 . 1,000 ( 2) ()

31

34

32

35 Zinc Ribbon

33

36 Zinc Ribbon

96

.1 1,200 . 1,000 ( 2) ()

37

40 Stock

38

41

39

42
2.80 ksc. 2

97

.1 1,200 . 1,000 ( 2) ()

43 Primer
Monotape

44
1 . Primer
Monotape

45

46

47

48
Ultrasonic Thickness Measurement

98

.1 1,200 . 1,000 ( 2) ()

49

50

52 8 ksc 2
0.35 ksc

53 Pressure Guage

51 Grout

54

99

.1 1,200 . 1,000 ( 2) ()

55
Segment

56

57

100

.1 1,200 . 1,000 ( 2) ()

101



.1 2

12

2
1

Dump
2

Backhoe
1

6
1



1


2


2


1


1

102
.1 2 ()


1500 W
3

6 6
2

5 5
2

6
4

25
1

8
1

2
1

20
2

N.A.

103
Sheet Pile 3.25 x 14.30 x 5.10
Sheet Pile 8 Sheet Pile 40 ./
= 3.25 x 14.30 x 2) / 0.40 = 233
(1) Sheet Pile 60
13,980

(2) - 8 8,000 64,000

(3) H-Beam 300 x 300 Bracing 3 106 18 564


./
26 /. = 564 x 18 x 26 = 263,952 3
87,984

(4) Back Hoe 18 3,500


63,000

(5) 3.25x14.30x0.25x1,800
20,914

(6) 18 1,500
27,000

(7)
5,000

(8) 3.25x14.30x5.10x1.3x260
61,626

(9) 7 800
5,600

9
15 %

7 %

349,104
2,366
401,470
28,103
429,573

104
Sheet Pile 2.00 x 3.70 x 5.10
Sheet Pile 8 Sheet Pile 40 ./
= (2.00 x 3.70 x 2) / 0.40 = 37
(1) Sheet Pile 60
2,220

(2) - 2 8000 16,000

(3) H-beam 300 x 300 Bracing 3 35 6 564 ./


26 /. = 564 x 6 x 26 = 87,984 3
29,328

(4) Back Hoe 7 3,500


24,500

(5) 2.0x3.7x0.25x1800
3,330

(6) 7 1,500
10,500

(7)
3,000

(8) 2.0x3.7x5.1x1.3x260
12,757

(9) 5 800
4,000

9
15 %

7 %

105,635
15,846
121,481
8,504
129,985

105
Segment 3.70
x 5.10
Segment 3.70 x 2.00 3 Concrete Deck
(1) Segment 3,000
9,000

(2) Segment -
3,000

(3) Back hoe 5 3,500


17,500

(4) x3.7x0.25x1800
5,229

(5) 5 1,500
7,500

(6)
3,000

(7) x3.7x5.1x1.3x260
20,028

(8) 5 800
4,000

(9)
10,000

9
15 %

7 %

79,257
11,889
91,146
6,381
97,527

106
1,200 . 2.50
1,000 . 9.00
9

(1) 4
200 //
1
600 //
1
800
/
/

2,200

(2) 1
2,000

(3) (Holiday Test) Coating


2,000

(4) 1
700

(5)
300

(6) 1,500
1,500

(7) 2,000
2,000

(8) Back Hoe 3,500


3,500

(9) 800
800

(10) 800
800

10
15,800 / 9 = 1,755.55
3,830
9,875
15 %

7 %

15,800

1,756 /
15,461
2,320
17,781
1,245
19,026


2 ( 1 )

.1
2 (SSteel Concentric Double
D
Cylinder Pippe : SCP) 1200 . ( 1)
108

7
Shheet Pile

8 Sheet Pile

9 Sheet Pile
P

10 Sheet Pile

11

12

109

.1
2 (SSteel Concentric Double
D
Cylinder Pippe : SCP) 1200 . ( 1) ()

13

14

15

166

17

18

110

.1
2 (SSteel Concentric Double
D
Cylinder Pippe : SCP) 1200 . ( 1) ()

19

22

20

21

23

(Back Thrust Wall)

24

(Back Thrust Waall)

111

.1
2 (Steel Concentric Doouble Cylinder Pippe : SCP) 1200 . ( 1) ()

25 (Guide Rail)
Entrance Ring

26

228

29

27

30

112

.1
2 (SSteel Concentric Double
D
Cylinder Pippe : SCP) 1200 . ( 1) ()

31

32

33

34

35

36


113

.1
2 (SSteel Concentric Double
D
Cylinder Pippe : SCP) 1200 . ( 1) ()

37 Spacer

38 Dumm
my RC Pipe
Driving SCP

39

40

41

422

114

.1
2 (SSteel Concentric Double
D
Cylinder Pippe : SCP) 1200 . ( 1) ()

43

44

455

46 Adapter
SCCP
Dumm
my RC Pipe Driving

47 SCP
Dummy RC Pipe Driving Adapter
A

48 SCP

115

.1
2 (SSteel Concentric Double
D
Cylinder Pippe : SCP) 1200 . ( 1) ()

49 Spacer

50 Dummyy RC Pipe
Drriving

51
5 SCP

552

SCP

53 Number

X-Ray (Radiographic Test)

54 Number

116

.1
2 (SSteel Concentric Double
D
Cylinder Pippe : SCP) 1200 . ( 1) ()

555 X--Ray

56 X-RRay

577 Primer
Monotape

58
Steel
Encasing

59 Steel Encasing

600 Steel Ring


117

.1
2 (SSteel Concentric Double
D
Cylinder Pippe : SCP) 1200 . ( 1) ()

61
Spacer

62

633

64

65

66

118

.1
2 (SSteel Concentric Double
D
Cylinder Pippe : SCP) 1200 . ( 1) ()

67 8 ksc
2 .
0.35
k

68

699

70

119

.1
2 (SSteel Concentric Double
D
Cylinder Pippe : SCP) 1200 . ( 1) ()

120



.1 1

40


12

Dump
2

Backhoe
1

6
1

1.5
1

Compact Jump
2



1


2


2

121
.1 1 ()


65 KVA
2

300 A
6

1500 W
3

6 6
2

5 5
2

25
2

5
2

8
1

2
1

20
2

3.2 . YAWATA
10

4 . YAWATA
10

LB 52 KOBE (3.2 X 350)


10

122
.1 1 ()


LB 52 KOBE (4 X 400)
10

LB 52U KOBE (3.2 X 400)


10

(Monotape)
50

(Epoxy) 10
5

123
Sheet Pile 3.50 x 8.20 x 6.00
Sheet Pile 9 Sheet Pile 40 ./
= (3.50 x 8.20 x 2) / 0.40 = 144
(1) Sheet Pile 60
8,640

(2) - 5 8,000 40,000

(3) H-Beam 300 x 300 Bracing 3 70 12 564 ./


26 /. = 564 x 12 x 26 = 175,968 3
58,656

(4) Back hoe 15 3,500


52,500

(5) 3.5x8.2x0.25x1,800
12,915

(6) 15 1,500
22,500

(7)
5,000

(8) 3.5x8.2x6x1.3x260
58,204

(9) 7 800
5,600

9
15 %

7 %

264,015
39,603
303,618
21,254
324,872

124
Sheet Pile 2.30 x 4.30 x 6.00
Sheet Pile 9 Sheet Pile 40 ./
= (2.30 x 4.30 x 2) / 0.40 = 50
(1) Sheet Pile 60
3,000

(2) - 2 8000
16,000

(3) H-Beam 300 x 300 Bracing 3 40 7


564 ./
26 /. = 564 x 7 x 26 = 102,648 3
34,216

(4) Back Hoe 7 3,500


24,500

(5) 2.3x4.3x0.25x1800
4,450

(6) 7 1500
10,500

(7)
3,000

(8) 2.3x4.3x6x1.3x260
20,057

(9) 5 800
4,000

9
15 %

7 %

119,723
17,959
137,682
9,638
147,320

125
2 1,200 . 6
2
(1) 4 200 //
1
600 //
1
800 //
2 2,200
4,400

(2) 1
4,000

(3) X-Ray
4,000

(4) 1
700

(5)
300

(6)
200

(7) 2 1500
3,000

(8) 2 2000
4,000

(9) Back Hoe 2 3500


7,000

(10) 2 800
1,600

(11) 2 800
1,600

11
30,800 / 6 = 5133.33
Segment 18,660 /
15 %

7 %

30,800
5,135
23,795
3,570
27,365
1,915
29,280


( 2)

.1 1,200 . ( 2)
127

128

.1 1,200 . ( 2) ()

129

.1 1,200 . ( 2) ()

130

.1 1,200 . ( 2) ()

131

.1 1,200 . ( 2) ()

.1 1,200 . ( 2) ()
132

.1 1,200 . ( 2) ()
133

.1 1,200 . ( 2) ()
134

.1 1,200 . ( 2) ()
135

.1 1,200 . ( 2) ()
136

.1 1,200 . ( 2) ()
137

138



.1 2




12

36

Dump
2

Backhoe PC200
1

Backhoe
1

6
1

1.5
1

Compact Jump
2



1


2


2

139
.1 2 ()

65 KVA
1

1500 W
3

6 6
2

5 5
2

6
4

25
1

5
2

8
1

2
1

20
2

3.2 . YAWATA
1

4 . YAWATA
1

LB 52 KOBE (3.2 X 350)


1

140
.1 2 ()


LB 52 KOBE (4 X 400)
1

LB 52U KOBE (3.2 X 400)


1

(Monotape)
50

(Epoxy) 10
2

141
Sheet Pile 3.00 x 10.00 x 8.00
Sheet Pile 14 Sheet Pile 40 ./
= (3.00 x 10.00 x 2) / 0.40 = 150
(1) Sheet Pile 60
9,000

(2) - 5 8000
40,000

(3) H-Beam 300 x 300 Bracing 4 104 18 564 ./


26 /. = 564 x 18 x 26 = 263,952 3
87,984

(4) Back Hoe 15 3500


52,500

(5) 3.0x10.0x0.25x1800
13,500

(6) 15 1500
22,500

(7)
5,000

(8) 3.0x10.0x8x1.3x260
81,120

(9) 7 800
5,600

9
15 %

7 %

317,204
47,581
364,785
25,535
390,320

142
Sheet Pile 3.00 x 5.00 x 8.00
Sheet Pile 14 Sheet Pile 40 ./
= (3.00 x 5.00 x 2) / 0.40 = 75
(1) Sheet Pile 60
4,500

(2) - 3 8000
24,000

(3) H-Beam 300 x 300 Bracing 4 64 11


564 ./ 26 /. = 564 x 11 x 26 = 161,304
3
53,768

(4) Back Hoe 10 3,500


35,000

(5) 3.0x5.0x0.25x1800
6,750

(6) 10 1500
15,000

(7)
3,000

(8) 3.0x5.0x8x1.3x260
40,560

(9) 7 800 5,600


9
15 %

7 %

188,178
28,227
216,405
15,149
231,554

143
1,200 .
3
3
(1) 6
200 //
1
600 //
1 800 //

2,600

(2) Liquid Penetrant Test 3


6,000

(3) 3
3,000

(4)
900

(5) 1,500
1,500

(6) 2,000
2,000

(7) Back Hoe 3,500


3,500

(8) 800
800

(9) 800
800

9
21,100 / 9 = 2,344.44


15 %

7 %

21,100
2,345
23,480
25,825
3,874
29,699
2,079
31,778

145

146

A Comparative Study of Pipe Jacking Techniques of the Provincial Waterworks Authority
1 2 3



(Pipe Jacking)
3 1)
2) 2 3)

3


2

: , ,
Abstract
Because of the traffic problem and physical conditions of the high population zones in some provinces, pipe jacking
techniques are adopted by the Provincial Waterworks Authority (PWA) in order to mitigate the problems caused by the waterwork
projects in the congested areas. This research studied and compared three types of pipe jacking construction projects, i.e. 1) steel
pipe with concrete sleeve pipe 2) Steel Concentric Double Cylinder Pipe, and 3) reinforced concrete pressure pipe. Data of the pipe
jacking construction time, cost, and the problems in the jacking activities of each technique are summarized.
The result of the research showed that reinforced concrete pressure pipe could be installed with the shortest construction
time because of its non-welding connections. The inner connections of concrete sleeves were done by the push-on connectors. The
cost of construction of the Steel Concentric Double Cylinder Pipe (SCP) is minimal because there are fewer construction steps.
Concerning on the efficiency of installation, reinforced concrete pressure pipe is the best one, because it could be installed
accurately and is suitable to install in a curve path. This research is very useful for PWA in selecting the right jacking technique for
a job.
Keywords: pipe Jacking, reinforced concrete pressure pipe, push-on
1



3


2

147
1.
(.)


1 )..2550-2554(



(Pipe Jacking)


[3]



(Pipe Jacking) 3

2.
2.1 (Pipe Jacking)

(Launching Shaft)
(Receiving
Shaft) 1
1 [1]

1 (Launching Shaft)
(Receiving Shaft) [1]

2.2


1,000 . 3
1.


2

2.

1,000 .



3

148
3.
1,000
.
4
0.5

2.4




3
1. (Sheet Pile)

6

4

2.3 ( Shield )

(Slurry Shield) 5

1,000 .


[4]

6 (Sheet Pile)
2.
(.)

7

7
5 Slurry Shield [4]

149
3.
3.70
3 . 2.00
H-Beam
8 [3]











[2]

3.

8
2.5
Phien-wej (..2002)

10





[5]
(..2546)



(Sheet Pile)

1,000 1,500 . 3 1)
2)
3)

3.1

1)


1,000 . 9.00 .
1,340.
2)


1,200 . 6 .
1,130 .
1,200 .
3 . 220.

150



1,200 .

3.2
1)



2)


3)

4)

5)



1 1
1,000
.

1.
18
2.
5
3.
7
4.
2
5. (2.50 .) 16
6. ( 9.00 .)
9
7.
8 /
1,000 .

2
1,000 .


BOQ*
()
()
350,000
()
150,000
(/)
30,200
1 ()
6,540,000
* (Bill of Quality;BOQ)

4.

3
4.1

1
1
2

151
4.2
1
3
4
3 1
1, 2 00.

1.
15
2.
10
3.
10
4. 2
( 6.00 )
6 /

4
1,2 00.


BOQ*
()
()
350,000
()
150,000
(/)
32,000
1 ()
6,900,000
* (Bill of Quality;BOQ)

10

4.3
1
5
6
5 1
1, 2 00.

1.
15
2.
10
3.
7
4.
9 /
(3.00 )
6
1, 2 00.


BOQ*
()
()
350,000
()
250,000
(/)
39,200
1 ()
8,340,000
* (Bill of Quality;BOQ)

11

152



1,000 .



1,200
.


2


7

1,2 00.
1, 2 00.
( / (
6
9
)(
200
200-300
)/(
32,000
39,200
1
6,900,000
8,340,000



2


-



200






350,000

150,000
200 x 32,000 = 6,400,000
6,900,000

1

200


3
8

153
8


1. 1.


2.
2.
3. (Point Load)

3.

4.

1. 1.


2.
( X Ray)

2

2.

1. 1.


(X-Ray)
2. (Liquid Penetrant Test)


3. 2.

(Rigid)
4. 3.
(Point Load)

154
5.



)Rigid)
















( X Ray)






0.5

(X-Ray) (Liquid
Penetrant Test)

( Point Load)




6.
[1] , 2547,

, , 1-40.
[2] ,
, 2546,
,
,
, 1-16.
[3] , 2553,
,
, 1-53.
[4] , 2539, Pipe
Jacking, , 2539, 32-37.
[5] Phien-wej, N.,2002, Experiences From EPB
Shield Tunneling Underneath Existing Structures
in Bangkok Soils (Invited Paper), National
Convention of Civil Engineering (NCCE-8), 2325

155



15 2524
236 12 57170

.. 2548
.. 2548 -

You might also like