Professional Documents
Culture Documents
2554
2554
.
.
2554
1
2 3
1
2 3
3
2
3
Thesis Title
Name - Surname
Program
Thesis Advisor
Thesis Co - advisor
Academic Year
ABSTRACT
Due to the traffic problem in highly populated downtown area of the cities, pipe jacking
methods in waterwork construction projects were employed and adapted by the Provincial
Waterworks Authority (PWA) in order to reduce the traffic congestion caused by the piping work
projects.
There are three types of pipe jacking techniques known as Type 1 Steel Pipe with
Concrete Sleeve, Type 2 Steel Concentric Double Cylinder Pipe (SCP) and Type 3 Reinforced
Concrete Pressure Pipe. Type 1 was the old technique commonly used while this research focused
on comparing the later two techniques. Details from two pipe jacking projects on construction
methods, major equipments, resource lists, assigned crew, and the production rate in the jacking
activities were summarized.
The results of the research showed that Type 3 technique consumed less connection
welding time as the result of time efficiency. The construction cost of Type 2 technique was
minimal due to fewer steps of working process. However, type 3 techniques was more flexible,
easier to adjust to the target path, therefore suitable for curve path. Finally, this research will be
useful for PWA and piping work contractors in selecting the right jacking technique for a workshop.
Keywords: pipe jacking, reinforced concrete pressure pipe, steel concentric double cylinder pipe
.
.
. .
.
..
.
..
...
..
....
1 ...
1.1 ..
1.2
1.3 ..
1.4 ..
1.5 .
2 ..
2.1
2.2 ...
2.3 .
2.4
2.5 ..
3 ...
3.1 .
3.2 ..
3.3 ..
3.4
..
1
1
2
3
3
4
5
5
19
20
36
37
42
42
43
44
45
( )
4 ...... 47
4.1 1
( 2)... 47
4.2 2 2
( 1).... 58
4.3 3
( 2)... 69
4.4
... 79
4.5
(Pipe Jacking) 81
5 .. 83
5.1 83
5.2 84
5.3 . 84
5.4 85
5.5 .. 86
5.6 .. 87
. 88
89
90
( 2)... 107
2 ( 1)... 126
( 2).. 144
.... 155
..
( )
30
30
31
31
32
33
35
35
38
40
43
47
54
59
65
69
75
.
.
.
.
.
.
.
1
2
1
2
.
BOQ
CP
CPM
EPB
HDD
HDPE
SCP
Bill of Quantities
Cathodic Protection
Critical Path Method
Earth Pressure Balance
Horizontal Directional Drill
High Density Polyethylene
Steel Concentric Double Cylinder Pipe
1.1
(.)
1
(2550-2554) [1]
(Pipe Jacking)
1 2545
1 [1]
22.00 . 05.00 .
[2]
(Trenchless Technology)
(Pipe Jacking)
2
(Pipe Jacking)
3 ( 2)
( 1)
( 2) 3
1.2
1.2.1 3
( 2) ( 1)
( 2)
1.2.2 3
1.2.3 3
1.2.4
3
1.2.5
3
1.3
1,000 - 1,500 . 3 2
1 2
1,000 .
1
1.3.1
1.3.2
1.4
1.4.1
1.
2.
3.
1.4.2
1.
2.
2 4
3.
4.
4
1.5
1.5.1 3
1.5.2
1.5.3
1.5.4
2
2.1 (Pipe Jacking)
(Driving Pit)
(Receiving Pit)
(Shield)
(Laser)
Microtunneling [3]
6
2.1.1 ( Shield )
3
1.
2. (Blind Shield) (Closed Face Shield)
Earth Pressure Balance (EPB)
3. Slurry Shield
Slurry Shield
EPB Skip Car
Cable Winch
8
(Cable Winch) (Skip Car)
(Gravity Flow)
2.8
10
2.1.3
Sheet Pile
2 (Sunken
Shaft) Caisson Diaphragm Wall
(Sunken Shaft)
Sunken Shaft
(Precast Segment)
[2]
(Sunken Shaft)
(Precast Segment)
Sheet Pile Sheet Pile
11
2.1 Sheet Pile [2]
(.)
A1
B1
A1
B1
900
8.00
3.00
4.00
3.00
4.0-6.0
8-12
1,000
8.00
3.00
4.00
3.00
4.0-6.0
8-12
1,200
8.00
3.50
4.00
3.20
4.0-5.5
10-12
1,300
8.00
3.50
4.00
3.30
4.0-5.5
10-12
1,500
8.00
3.50
4.00
3.50
4.0-5.0
10-12
1,800
8.00
3.50
4.00
3.50
4.0-5.0
10-12
Sheet Pile
L
.. 2546
.. 2547
Sheet Pile
Sheet Pile (Stiffness)
Sheet Pile
[2]
200
12
300 Intermediate Jack
Bentonite Slurry Polymer
1 .
50
2.10
2.2 [2]
13
()
(.) A1 B1
T1
D1
T3
900 8.00 2.50 0.5-0.8 8.00 0.4-0.6
()
A2 B2
4.00 2.50
T2
0.3-0.4
D2
4.00
T4
0.3-0.4
L
D () ()
4.0-6.0 8-12
0.4-0.6
4.00 2.50
0.3-0.4
4.00
0.3-0.4
4.0-6.0
8-12
0.5-0.6
4.00 3.00
0.3-0.4
4.00
0.3-0.4
4.0-5.5
10-12
0.5-0.6
4.00 3.00
0.3-0.4
4.00
0.3-0.4
4.0-5.5
10-12
0.5-0.6
4.00 3.00
0.3-0.4
4.00
0.3-0.4
4.0-5.0
10-12
0.5-0.6
4.00 3.00
0.3-0.4
4.00
0.3-0.4
4.0-5.0
10-12
- 6
2.1.4
4
1. ( 1)
(Spacer)
Cathodic Protection (CP) CP
14
[4]
2.11 ( 1)
2.
(CP)
(Spacer) 3 /.
1,000 1,200
(High Density Polyethylene ; HDPE)
15
2.12 ( 2)
2.1.5 2
1. 2 (Steel Concentric Double Cylinder Pipe ; SCP)
( 1,000 . 1,200
. )
Coating CP
( 3 .)
X - Ray
16
2.13 2 ( 1)
2.
Lining
0.5
(X Ray)
2.14 ( 2)
17
2.14
2.1.6
2
2.3
1 6 ()
2
3 /
18
2.4
1
2
3
4
5
6
7
8 (Air Compressor)
9
10 Sheet Pile
11
12
4
19
(Pipe Jacking)
4
2.2
2.5 [2]
(.)
300
400
800
1,000
1,200
1,500
1,800
(/)
/ Sheet Pile
/
290,100
134,200
300,000
136,700
501,200
238,800
1,539,800
499,300
527,800
246,500
1,663,200
545,200
559,000
264,700
1,804,200
597,200
617,700
287,600
2,013,100
674,900
710,800
312,600
2,227,200
754,800
20
2.6 [2]
(/)
A
B
C
( )
( )
( )
(.)
1
1
2
1
2
1
2
1
300
7,800
400
9,400
800
24,100 18,700
30,000 26,700
1,000
30,100 21,500 22,600 18,500 38,400 31,700 35,200
1,200
37,600 27,200 27,900 20,200 48,000 38,900 43,800
1,500
53,500 36,200 39,800 28,400 70,700 51,900 64,900
1,800
75,700 54,700 54,600 39,300 99,000 70,500 95,300
(.)
1
2
1 2
2
2
26,600
30,400
39,600
54,700
21
2.3.1
1.
22.00 . 05.00 . /
(Steel Deck)
(Steel Plate)
(Seal)
(Time) (Cost)
2. .
.
.
3.
(Information Sign) (Construction Sign)
(Traffic Sign)
15 50
.
22
2.15
4.
5. (Construction
Schedule) (Breakdown Construction Schedule)
Bar Chart
(Breakdown Construction Schedule)
15
Bar Chart Critical Path Method
(CPM)
Shop Drawing
23
6.
.
(.) .
.
24
8.
(Pipe Jacking)
/
9.
25
2.3.2
1.
2.
3.
2.3.3
(Pre-Construction
Conference) 2
1.
( ) (
)
26
2.
( )
[4]
2.3.4
.
. .
. . .
1.
(
) (
) ( )
15
(
)
2.
.
7
45
45
27
.
(
)
7
3.
( . )
4. (. . . . )
( . .
)
5.
2.18 . .
28
2.3.5 (Pipe Jacking)
1. (Line Grade)
2.19
2.20
3.
29
2.21
4.
2.22
5.
6. Jacking System
7. (Back Thrust Wall) (Jacking)
30
31
2.25 (Laser)
10.
32
33
2.28 8 ksc. 2 .
2.3.7
/
1.
2.
(Field Density)
34
24 . 5 .
20 . 2
2 . 200 .
3.
Dowel Bar Tie Bar
Joint Sealer
4.
[4]
35
2.29
2.3.8
1.
2.30
2. (As-Built Drawing)
(As-Built Drawing)
36
3.
.
.
4.
(.
)
(
)
5.
[4]
2.4
2.8
37
2.7 (Production Rate)
()
/ /
Alignment
1.
2.
3. /
Spacer (2.6 .)
4. 2
5. /
Spacer
2
/
2.5
Nishida, et al. [5] 150 .
PVC Steel Plate Rubber Tube Production
Rate 2.31
Cost
Effectiveness
38
10
EPB
NATM
Phien-wej (2002) [6]
3.00 .
1-2 %
39
(2539) [7]
2.7
2.8
6 .
6 . 12
.
12 .
40
41
Tennyson, et al. (2004) [9]
(224 ) Boston
(Pipe Jacking) (Tunneling)
Construction Engineering
(Pipe Jacking)
3.1
2
4
3.1.1
1. ( 1)
2. ( 2)
.
3.1.2
1. 2 ( 1)
1 2
2. ( 2)
. .
2 2
1 2 1,000 . 1
43
3.2
1,000 1,500
. 2
3.1
3.1
44
3.3
5
3.3.1
3.3.2
2
2
3
2
3.3.3
3.3.4 2
4
45
3.4
3.3
3.1
3.1
/
/
/
/
/
/
/
/
/
/
46
3.2
3.2
1
2
2 1,200
1,200 . . 3
6 . .
1,130 .
220 .
1,000 .
9.00 .
1,340 .
3 2 3 2
3
1
4
2
2 1 2 3
4.1 1 ( 2)
4.1.1
1,000 . 9.00 . 1,340 .
344
4.1
48
4.1.2
1,200 . 1,000 .
3.00
250 . Slurry Earth Pressure Balance Bentonite
2
(Steel Concentric Double Cylinder Pipe : SCP)
9.00 2 (SCP) 6
5 .
5 .
1
1,200 .
1,000 .
(Flow Chart) 4.1
2
49
4.1 2
1.
1-8
Sheet Pile
Bracing
Base Slab
2. Jacking
System
9 -22
50
4.1 2 ()
3.
24 - 30
Steel Ring
4.
23 - 45
51
4.1 2 ()
Coating
52
4.1 2 ()
46 - 53
5.
(Hydrostatic Pressure
Test)
-
Pressure Guage
8 ksc.
53
4.1 2 ()
6.
Sheet
Pile Bracing
54 - 57
54
4.1.3
( 2)
4.2
4.2 2
55
4.1.4 1 (
2) Time Sheet
1 (Cycle)
( 2)
4.2
4.2 1 (Cycle) 2
/
()
/
8
Alignment
9
19
3
Spacer
3
(2.6 .)
2
20
43
Spacer
2
56
1.
18
2.
5
3.
7
4.
2
5. ( 2.50 )
16
6. ( 9.00 )
9
7. 1,000 . 8 /
4.1.5
4.3
(BOQ) 2
BOQ
()
350,000
392,000
()
150,000
125,000
( /
22,400
19,200
)
57
4.1.6 ( 2)
1. (BOQ)
9
14.30
2.
(Bill of Quantities ; BOQ)
3.
(BOQ)
4. (/)
8
4.1.7
( 2)
1. BOQ
2.
2 .
58
3.
4.
5.
(Monotape)
6. 9.00
7.
8.
9.
10.
11.
(Sheet Pile)
4.2 2 2 ( 1)
4.2.1 2 ( 1)
1 2
- (
) 2 1,200 . 1,130 .
59
4.3
4.2.2 2
1,200 . - (
) 3.50 .
200 . Slurry Earth Pressure Balance
2 6
2
2 1,200 .
(Flow Chart) 4.4
2 ( 1)
60
4.4 1
1.
1
1 - 22
Sheet Pile
Bracing
Base Slab
Soft Eye
2. Jacking
System
23 -32
61
4.4 1 ()
1
32 - 62
3.
Dummy RC
Adapter SCP
SCP RC
Dummy
SCP
X-ray
62
4.4 1()
Coating
Primer Monotape
Steel Encasing
Spacer
SCP
4.
(Hydrostatic Pressure
Test)
63 - 68
63
4.4 1 ()
-
Pressure Gauge
8 ksc.
64
4.4 1 ()
5.
Sheet pile Bracing
1
69 - 70
65
4.2.3
2 ( 1) 4.4
4.4 1
66
4.2.4 1 2 ( 1)
Time Sheet
1 (Cycle)
1 2 4.5
4.5 1 (Cycle) 1
Alignment
Spacer
Monotape
Steel Encasing
( 6 .)
Spacer
()
34
26
151
48
164
1. Sheet Pile
15
2. Sheet Pile
10
3.
10
4. 2 ( 6.00 )
6 /
67
4.2.5 2 ( 1)
(Bill of Quantities ; BOQ)
4.6
(BOQ) 1
BOQ
()
350,000
367,500
()
150,000
136,800
( / )
32,000
30,000
4.2.6 2 ( 1)
1.
(BOQ) 6
(Back Thrust Wall)
2.
68
3. (/)
2
2
4.2.7 2 ( 1)
1
1. BOQ
2 6
2. 2
3.
4.
5.
150 1
6. (X-ray)
69
4.3 3 ( 2)
4.3.1
( 2)
2
2 4.2
1
3035 ( )
1,200 . 220 .
4.5
4.3.2
1,200 . 3035 (
) 3.50 .
200 . Slurry Earth Pressure Balance
3 .
70
Push-on
1,200 . (Flow Chart)
4.7
( 2)
71
4.7 2
1.
2
1 - 16
Sheet Pile
Bracing
Base Slab
Soft Eye
2. Jacking System
14 -23
Back Thrust Wall
72
4.7 2 ()
3.
Steel Ring
Spacer
Liquid
Penetrant
Test
2
24 - 56
73
4.7 2 ()
4.
(Hydrostatic Pressure Test)
-
Pressure Gauge
2
41 - 42 , 57 - 59
74
4.7 2 ()
5.
Sheet
Pile Bracing
2
60 - 62
75
4.3.3
2 4.6
4.6 2
76
4.3.4 1 ( 2)
Time Sheet
1 (Cycle)
2 4.8
4.8 1 (Cycle) 2
Alignment
Spacer (2.6
.)
2
Spacer
2
()
8
15
22
4
4
25
40
/ /
-
Muck Tank
Muck Tank
77
1. Sheet Pile
15
2. Sheet Pile
10
3.
7
4.
10
5. (3.00 ) 9 /
4.3.5 ( 2)
(Bill of Quantities ; BOQ)
4.9
(BOQ) 2
BOQ
()
350,000
394,700
()
250,000
230,000
(/)
39,200
41,000
78
4.3.6 ( 2)
1.
(BOQ)
6
8
4
3
2.
(BOQ)
3. (/)
(BOQ)
(BOQ)
2
-
1
-
3 .
79
2
(BOQ)
4.3.7 2
2
1.
3 .
(Butt Weld)
2. BOQ
1.
2
3.
4.
(Cement Lining)
4.4
3
4.10
80
1,000 .
2
1,200 .
2
2 ( 1)
( 2)
4.10
(/)
()
(/)
1
1,000 .
2
1,200 .
1,200 .
8
200-300
30,200
6,540,000
6
200
32,000
6,900,000
9
200-300
39,200
8,340,000
4.10 1
1
15,461 2 2
23,795 3
25,825
(.) 2.6
(.) 2546
81
2
4
(Pipe
Jacking) .
4.5 (Pipe Jacking)
4.11
4.11 (Pipe Jacking)
Sheet Pile
(Steel Circular
Shaft)
1.
Sheet Pile
2.
82
Sheet Pile
Sheet Pile
4.5.2 Sinking Caisson (In-situ
Casting) (Precast Segment)
Sheet Pile Sheet Pile
Sheet Pile
Sheet Pile
Sheet Pile
4.5.3 (Steel Circular Shaft)
(Receiving Shaft)
3.70 . 3 . 2.00
. H-Beam
Sheet Pile
(Steel Circular Shaft)
(Steel Circular Shaft) Sheet Pile
(Steel Circular Shaft)
5
3
(Pipe Jacking)
5.1
5.1.1 ( 2)
2
5.1.2 2 ( 1)
2
1 2
84
5.1.3 ( 2)
2
0.5
5.2
3
( 2) 9
( 2)
8 2 ( 1)
6
5.3
( 2) 1,000 .
2 1,200 .
2 ( 1)
( 2) 1,200 .
2 1 2
1
1
85
5.4
( 2)
(Point Load)
2 ( 1)
(X-Ray)
2
2
( 2)
(X-Ray) (Liquid Penetrant Test)
Point Load
86
5.5
5.5.1
1 2 2
3 .
(Butt Weld)
5.5.2 2
2
2
5.5.3
200
1 2 1
5.5.4
200
2 2
5.5.5
5.5.6
87
5.6
5.6.1
2 1,000 .
1 2 2
1,200 .
2
2 1,000 .
5.6.2
5.6.3 1 (Cycle)
2
5.6.4 (Cost)
5.6.5
(Risk Management Plan)
[1] , 2547,
, , 1-40.
[2] , , 2546,
, , , 1-16.
[3] , 2539, Pipe Jacking, , 2539, 32-37.
[4] , 2548,
, , 1-53.
[5] Najafi, M., Iseley, D.T., Pumphrey, N.D. and Nishida, Jr.H., 1993, LLB,an Innovative
Microtunneling Propulsion System, Structural Performance of Pipes, Sargard, Mitchell, pp.
107-124.
[6] Phien-wej, N., 2002, Experiences From EPB Shield Tunneling Underneath Existing
Structures in Bangkok Soils (Invited Paper), National Convention of Civil Engineering
(NCCE-8), 23-25
[7] , 2539, ,
2, 22-24 2539, , GTE
213-235.
[8] Chalermkiat, W., 2002, Trenchless Technology: Environmentally Friendly Techniques,
[9] Tennyson, M.M. and Daniel, J.D., 2004, Pipe Jacking in a Complex Urban EnvironmentBoston Massachusetts [Online], Available : http ://www.ascelibrary.org [2005, Febuary 9].
[10] , 2545,
, 8, 23-25
2545,, GTE 357-362
( 2)
3 Sheet Pile
4 Bracing
5 Base Slab
6 Sofe Eye
.1 1,200 . 1,000 ( 2)
91
10
9
Laser
11 Segment
12
92
.1 1,200 . 1,000 ( 2) ()
13 Segment
16
14 Load
17
15 Bracing
Base Slab
18 Muck Tank
2
93
.1 1,200 . 1,000 ( 2) ()
19 Muck Tank
Tank
20 21
1 2
21
1 2
22
23
24
94
.1 1,200 . 1,000 ( 2) ()
25 Steel Ring
26
27
28
29
3
30
95
.1 1,200 . 1,000 ( 2) ()
31
34
32
35 Zinc Ribbon
33
36 Zinc Ribbon
96
.1 1,200 . 1,000 ( 2) ()
37
40 Stock
38
41
39
42
2.80 ksc. 2
97
.1 1,200 . 1,000 ( 2) ()
43 Primer
Monotape
44
1 . Primer
Monotape
45
46
47
48
Ultrasonic Thickness Measurement
98
.1 1,200 . 1,000 ( 2) ()
49
50
52 8 ksc 2
0.35 ksc
53 Pressure Guage
51 Grout
54
99
.1 1,200 . 1,000 ( 2) ()
55
Segment
56
57
100
.1 1,200 . 1,000 ( 2) ()
101
.1 2
12
2
1
Dump
2
Backhoe
1
6
1
1
2
2
1
1
102
.1 2 ()
1500 W
3
6 6
2
5 5
2
6
4
25
1
8
1
2
1
20
2
N.A.
103
Sheet Pile 3.25 x 14.30 x 5.10
Sheet Pile 8 Sheet Pile 40 ./
= 3.25 x 14.30 x 2) / 0.40 = 233
(1) Sheet Pile 60
13,980
(5) 3.25x14.30x0.25x1,800
20,914
(6) 18 1,500
27,000
(7)
5,000
(8) 3.25x14.30x5.10x1.3x260
61,626
(9) 7 800
5,600
9
15 %
7 %
349,104
2,366
401,470
28,103
429,573
104
Sheet Pile 2.00 x 3.70 x 5.10
Sheet Pile 8 Sheet Pile 40 ./
= (2.00 x 3.70 x 2) / 0.40 = 37
(1) Sheet Pile 60
2,220
(5) 2.0x3.7x0.25x1800
3,330
(6) 7 1,500
10,500
(7)
3,000
(8) 2.0x3.7x5.1x1.3x260
12,757
(9) 5 800
4,000
9
15 %
7 %
105,635
15,846
121,481
8,504
129,985
105
Segment 3.70
x 5.10
Segment 3.70 x 2.00 3 Concrete Deck
(1) Segment 3,000
9,000
(2) Segment -
3,000
(4) x3.7x0.25x1800
5,229
(5) 5 1,500
7,500
(6)
3,000
(7) x3.7x5.1x1.3x260
20,028
(8) 5 800
4,000
(9)
10,000
9
15 %
7 %
79,257
11,889
91,146
6,381
97,527
106
1,200 . 2.50
1,000 . 9.00
9
(1) 4
200 //
1
600 //
1
800
/
/
2,200
(2) 1
2,000
(4) 1
700
(5)
300
(6) 1,500
1,500
(7) 2,000
2,000
(9) 800
800
(10) 800
800
10
15,800 / 9 = 1,755.55
3,830
9,875
15 %
7 %
15,800
1,756 /
15,461
2,320
17,781
1,245
19,026
2 ( 1 )
.1
2 (SSteel Concentric Double
D
Cylinder Pippe : SCP) 1200 . ( 1)
108
7
Shheet Pile
8 Sheet Pile
9 Sheet Pile
P
10 Sheet Pile
11
12
109
.1
2 (SSteel Concentric Double
D
Cylinder Pippe : SCP) 1200 . ( 1) ()
13
14
15
166
17
18
110
.1
2 (SSteel Concentric Double
D
Cylinder Pippe : SCP) 1200 . ( 1) ()
19
22
20
21
23
(Back Thrust Wall)
24
(Back Thrust Waall)
111
.1
2 (Steel Concentric Doouble Cylinder Pippe : SCP) 1200 . ( 1) ()
25 (Guide Rail)
Entrance Ring
26
228
29
27
30
112
.1
2 (SSteel Concentric Double
D
Cylinder Pippe : SCP) 1200 . ( 1) ()
31
32
33
34
35
36
113
.1
2 (SSteel Concentric Double
D
Cylinder Pippe : SCP) 1200 . ( 1) ()
37 Spacer
38 Dumm
my RC Pipe
Driving SCP
39
40
41
422
114
.1
2 (SSteel Concentric Double
D
Cylinder Pippe : SCP) 1200 . ( 1) ()
43
44
455
46 Adapter
SCCP
Dumm
my RC Pipe Driving
47 SCP
Dummy RC Pipe Driving Adapter
A
48 SCP
115
.1
2 (SSteel Concentric Double
D
Cylinder Pippe : SCP) 1200 . ( 1) ()
49 Spacer
50 Dummyy RC Pipe
Drriving
51
5 SCP
552
SCP
53 Number
X-Ray (Radiographic Test)
54 Number
116
.1
2 (SSteel Concentric Double
D
Cylinder Pippe : SCP) 1200 . ( 1) ()
555 X--Ray
56 X-RRay
577 Primer
Monotape
58
Steel
Encasing
59 Steel Encasing
117
.1
2 (SSteel Concentric Double
D
Cylinder Pippe : SCP) 1200 . ( 1) ()
61
Spacer
62
633
64
65
66
118
.1
2 (SSteel Concentric Double
D
Cylinder Pippe : SCP) 1200 . ( 1) ()
67 8 ksc
2 .
0.35
k
68
699
70
119
.1
2 (SSteel Concentric Double
D
Cylinder Pippe : SCP) 1200 . ( 1) ()
120
.1 1
40
12
Dump
2
Backhoe
1
6
1
1.5
1
Compact Jump
2
1
2
2
121
.1 1 ()
65 KVA
2
300 A
6
1500 W
3
6 6
2
5 5
2
25
2
5
2
8
1
2
1
20
2
3.2 . YAWATA
10
4 . YAWATA
10
122
.1 1 ()
LB 52 KOBE (4 X 400)
10
(Monotape)
50
(Epoxy) 10
5
123
Sheet Pile 3.50 x 8.20 x 6.00
Sheet Pile 9 Sheet Pile 40 ./
= (3.50 x 8.20 x 2) / 0.40 = 144
(1) Sheet Pile 60
8,640
(5) 3.5x8.2x0.25x1,800
12,915
(6) 15 1,500
22,500
(7)
5,000
(8) 3.5x8.2x6x1.3x260
58,204
(9) 7 800
5,600
9
15 %
7 %
264,015
39,603
303,618
21,254
324,872
124
Sheet Pile 2.30 x 4.30 x 6.00
Sheet Pile 9 Sheet Pile 40 ./
= (2.30 x 4.30 x 2) / 0.40 = 50
(1) Sheet Pile 60
3,000
(2) - 2 8000
16,000
(5) 2.3x4.3x0.25x1800
4,450
(6) 7 1500
10,500
(7)
3,000
(8) 2.3x4.3x6x1.3x260
20,057
(9) 5 800
4,000
9
15 %
7 %
119,723
17,959
137,682
9,638
147,320
125
2 1,200 . 6
2
(1) 4 200 //
1
600 //
1
800 //
2 2,200
4,400
(2) 1
4,000
(3) X-Ray
4,000
(4) 1
700
(5)
300
(6)
200
(7) 2 1500
3,000
(8) 2 2000
4,000
(10) 2 800
1,600
(11) 2 800
1,600
11
30,800 / 6 = 5133.33
Segment 18,660 /
15 %
7 %
30,800
5,135
23,795
3,570
27,365
1,915
29,280
( 2)
.1 1,200 . ( 2)
127
128
.1 1,200 . ( 2) ()
129
.1 1,200 . ( 2) ()
130
.1 1,200 . ( 2) ()
131
.1 1,200 . ( 2) ()
.1 1,200 . ( 2) ()
132
.1 1,200 . ( 2) ()
133
.1 1,200 . ( 2) ()
134
.1 1,200 . ( 2) ()
135
.1 1,200 . ( 2) ()
136
.1 1,200 . ( 2) ()
137
138
.1 2
12
36
Dump
2
Backhoe PC200
1
Backhoe
1
6
1
1.5
1
Compact Jump
2
1
2
2
139
.1 2 ()
65 KVA
1
1500 W
3
6 6
2
5 5
2
6
4
25
1
5
2
8
1
2
1
20
2
3.2 . YAWATA
1
4 . YAWATA
1
140
.1 2 ()
LB 52 KOBE (4 X 400)
1
(Monotape)
50
(Epoxy) 10
2
141
Sheet Pile 3.00 x 10.00 x 8.00
Sheet Pile 14 Sheet Pile 40 ./
= (3.00 x 10.00 x 2) / 0.40 = 150
(1) Sheet Pile 60
9,000
(2) - 5 8000
40,000
(5) 3.0x10.0x0.25x1800
13,500
(6) 15 1500
22,500
(7)
5,000
(8) 3.0x10.0x8x1.3x260
81,120
(9) 7 800
5,600
9
15 %
7 %
317,204
47,581
364,785
25,535
390,320
142
Sheet Pile 3.00 x 5.00 x 8.00
Sheet Pile 14 Sheet Pile 40 ./
= (3.00 x 5.00 x 2) / 0.40 = 75
(1) Sheet Pile 60
4,500
(2) - 3 8000
24,000
(5) 3.0x5.0x0.25x1800
6,750
(6) 10 1500
15,000
(7)
3,000
(8) 3.0x5.0x8x1.3x260
40,560
188,178
28,227
216,405
15,149
231,554
143
1,200 .
3
3
(1) 6
200 //
1
600 //
1 800 //
2,600
(3) 3
3,000
(4)
900
(5) 1,500
1,500
(6) 2,000
2,000
(8) 800
800
(9) 800
800
9
21,100 / 9 = 2,344.44
15 %
7 %
21,100
2,345
23,480
25,825
3,874
29,699
2,079
31,778
145
146
A Comparative Study of Pipe Jacking Techniques of the Provincial Waterworks Authority
1 2 3
(Pipe Jacking)
3 1)
2) 2 3)
3
2
: , ,
Abstract
Because of the traffic problem and physical conditions of the high population zones in some provinces, pipe jacking
techniques are adopted by the Provincial Waterworks Authority (PWA) in order to mitigate the problems caused by the waterwork
projects in the congested areas. This research studied and compared three types of pipe jacking construction projects, i.e. 1) steel
pipe with concrete sleeve pipe 2) Steel Concentric Double Cylinder Pipe, and 3) reinforced concrete pressure pipe. Data of the pipe
jacking construction time, cost, and the problems in the jacking activities of each technique are summarized.
The result of the research showed that reinforced concrete pressure pipe could be installed with the shortest construction
time because of its non-welding connections. The inner connections of concrete sleeves were done by the push-on connectors. The
cost of construction of the Steel Concentric Double Cylinder Pipe (SCP) is minimal because there are fewer construction steps.
Concerning on the efficiency of installation, reinforced concrete pressure pipe is the best one, because it could be installed
accurately and is suitable to install in a curve path. This research is very useful for PWA in selecting the right jacking technique for
a job.
Keywords: pipe Jacking, reinforced concrete pressure pipe, push-on
1
3
2
147
1.
(.)
1 )..2550-2554(
(Pipe Jacking)
[3]
(Pipe Jacking) 3
2.
2.1 (Pipe Jacking)
(Launching Shaft)
(Receiving
Shaft) 1
1 [1]
1 (Launching Shaft)
(Receiving Shaft) [1]
2.2
1,000 . 3
1.
2
2.
1,000 .
3
148
3.
1,000
.
4
0.5
2.4
3
1. (Sheet Pile)
6
4
2.3 ( Shield )
(Slurry Shield) 5
1,000 .
[4]
6 (Sheet Pile)
2.
(.)
7
7
5 Slurry Shield [4]
149
3.
3.70
3 . 2.00
H-Beam
8 [3]
[2]
3.
8
2.5
Phien-wej (..2002)
10
[5]
(..2546)
(Sheet Pile)
1,000 1,500 . 3 1)
2)
3)
3.1
1)
1,000 . 9.00 .
1,340.
2)
1,200 . 6 .
1,130 .
1,200 .
3 . 220.
150
1,200 .
3.2
1)
2)
3)
4)
5)
1 1
1,000
.
1.
18
2.
5
3.
7
4.
2
5. (2.50 .) 16
6. ( 9.00 .)
9
7.
8 /
1,000 .
2
1,000 .
BOQ*
()
()
350,000
()
150,000
(/)
30,200
1 ()
6,540,000
* (Bill of Quality;BOQ)
4.
3
4.1
1
1
2
151
4.2
1
3
4
3 1
1, 2 00.
1.
15
2.
10
3.
10
4. 2
( 6.00 )
6 /
4
1,2 00.
BOQ*
()
()
350,000
()
150,000
(/)
32,000
1 ()
6,900,000
* (Bill of Quality;BOQ)
10
4.3
1
5
6
5 1
1, 2 00.
1.
15
2.
10
3.
7
4.
9 /
(3.00 )
6
1, 2 00.
BOQ*
()
()
350,000
()
250,000
(/)
39,200
1 ()
8,340,000
* (Bill of Quality;BOQ)
11
152
1,000 .
1,200
.
2
7
1,2 00.
1, 2 00.
( / (
6
9
)(
200
200-300
)/(
32,000
39,200
1
6,900,000
8,340,000
2
-
200
350,000
150,000
200 x 32,000 = 6,400,000
6,900,000
1
200
3
8
153
8
1. 1.
2.
2.
3. (Point Load)
3.
4.
1. 1.
2.
( X Ray)
2
2.
1. 1.
(X-Ray)
2. (Liquid Penetrant Test)
3. 2.
(Rigid)
4. 3.
(Point Load)
154
5.
)Rigid)
( X Ray)
0.5
(X-Ray) (Liquid
Penetrant Test)
( Point Load)
6.
[1] , 2547,
, , 1-40.
[2] ,
, 2546,
,
,
, 1-16.
[3] , 2553,
,
, 1-53.
[4] , 2539, Pipe
Jacking, , 2539, 32-37.
[5] Phien-wej, N.,2002, Experiences From EPB
Shield Tunneling Underneath Existing Structures
in Bangkok Soils (Invited Paper), National
Convention of Civil Engineering (NCCE-8), 2325
155
15 2524
236 12 57170
.. 2548
.. 2548 -