Scenario: We have defined a planning Time Fence of 1 day. This will ensure that change in
requirements within time fence will not alter created planned orders & purchase requisitions. In
other words, changes in requirement after time fence will alter planned orders/purchase
requisitions
After MRP run, system did not planned material on 5th Jan and proposed it on 6th Jan since
planning time fence was 1 day and it automatically firmed all planned orders which were created
on or before 6th Jan