Planning Time Fence

Scenario: We have defined a planning Time Fence of 1 day. This will ensure that change in
requirements within time fence will not alter created planned orders & purchase requisitions. In
other words, changes in requirement after time fence will alter planned orders/purchase
requisitions

We will use material : T55831900.


We have to maintain, MRP type as P1 (with firming type1), planning time fence 1 day

We had created PIR on 5th Jan, 6th Jan..

After MRP run, system did not planned material on 5th Jan and proposed it on 6th Jan since
planning time fence was 1 day and it automatically firmed all planned orders which were created
on or before 6th Jan