SAVING MATERIAL AND TIME
Larsen & Toubro Ltd opted for Tekla’s BIM software for modelling and detail drawing preparation for
the 496 square meters Sinter Plant unit in Chennai.
STORAGE BUILDING: NUMBER
CRUNCHERS
85 meters long, 8 meters wide and
25 meters high
Sinter Storage capacity: 8400 cubic
meters in volume
Total RCC quantity: 7800 Cubic
meters
Project Duration: 4 months design
to delivery
Tonnage of rebar usage: 1150 MT
arsen & Toubro Ltd chose to
use Tekla’s BIM software for
modelling and detail draw-
ing preparation for the 496
square meters Sinter Plant unit in
Chennai. The Sinter Storage Building,
complicated Reinforced Cement Con-
crete technological building houses a
large amount of process equipment in-
cluding belt conveyors, vibratory feed-
ers, rack-pinion gates, hoists and stone
box arrangement made of 1800 Metric
ton structural steel
‘The Sinter Storage Building is a massive
RCC building with an RCC raft founda-
tion. This building consists of 11 ba
each bay having the ability to hold 760
cubic meters of sinter having a density of
18 MT cubic meters. Every bay accom-
modates one structural steel, stone box
structure with bolted construction which
restricts the freefall height of sinter and
thereby helps sinter quality to remain
unchanged. Above the foundation level,
the elevated building is supported by 24
freestanding columns of which each car-
ries a1900 MT combined load.
Larsent and Toubro did the entire rebar
detailing, including conflict check, effec-
tively by using Tekla software. Junction
locations of the foundation raft, columns
Sa
and at upper levels of the bottom slab,
side walls, roof, slab and integration of
the side walls with beams and column
projection all along the height have
‘massive rebar arrangements with lots of
interfaces from each component rebar.
Many structural steel insert plates had
been fixed all along the Sinter Storage
building at the soffits and the insides of
hopper slabs and at the side walls and
beams. The interface check for all these
inserts became a herculean task for the
design engineers.
A team of two design engineers,
‘one designer and two modelers tack-
led the challenge by modelling with
Tekla software for approximately
2500 man-hours. The entire accurate
and constructable 3D model of this
unit, integrated with rebar arrange-
‘ment, equipment, piping, cable trays
and access routes, all needed details.
‘The potentially huge task of checking
the interface of various components to
avoid clashes was actually smooth with
Tekla's 3D modelling software and was
done in much less time than it would
have been without Tekla — and with fall
accuracy. The software helped manage
the large file size smoothly while the
team worked on the model.
“We also shared the Tekla 3D mod-
el with the field project manager and
construction personnel, so they could
have an accurate idea of the structure
and good reference for their work. The
operations persornel are using this
information to plan concrete pours,”
notes Arun Kr Verma, Chief Engineer-
ing Manager (Civil and Structural), En«
gineering Design and Research Centre,
Larsen & Toubro Limited.
‘Tekla provides a BIM (Building Infor-
mation Modeling) software environ-
‘ment that contractors, structural engi-
neers and detailers and fabricators of all
materials can share. Tekla BIMsight is
a free professional tool for construction
Project collaboration. Anyone can com-
bine models, check for clashes and share
information using the same easy-to-use
3D environment. With Tekla BIMsight
project participants can identify and
solve issues already in the design phase.