Key Implementation Activities and Deliverables:

AcceleratedSAP
Table D.2-1 ASAP Phases
AcceleratedSAP Phases
Phase 1 Project Preparation
Phase 2 Business Blueprint
Phase 3 Realization
Phase 4 Final Preparation
Phase 5 Go Live and Support
The ASAP Roadmap was developed by SAP to help customers implement SAP software in a
quick, cost-effective manner. Utilizing this approach:
minimizes the length of implementation,
maximizes the utilization of TeamSAP and customer resources,
results in a Repetitive Model that can be used with other implementations of SAP modules
or systems, and
provides a process-oriented approach to Product Training.

EI Toolkit Reference
Document version 1.0, June 2003
Last validated: June 2003

0
EITK0304

Key Implementation Activities and Deliverables:


AcceleratedSAP
Table D.2-2 Project Preparation Key Activities and Deliverables
Key Activities
Deliverables
Finalize Project Team Organization
Project Team Structure Organization Chart

Finalize Project Team Training Plan

Project Team Training Schedule

Define Team Facilities Requirements

Project Team Seating Chart (including


required equipment)

Develop Project Plans

Develop Project Strategies and Scope

Review Existing Implementations

Baseline Project Plans


Initial Activities Planned
Resource Plan
Draft:
o Implementation Strategy
o End-User Training Strategy
o Development Strategies
o Testing Strategy
o Technical Strategies
o Security and Controls Strategy
o High-level Project Scope Document
List of Lessons Learned
Project Management Standards and
Procedures (Issue Mgt Plan, Status Report
Format, Change Control Forms,
Documentation standards, etc,)
Benefits Realization Approach
Risk Management Plan, Report and
recommendations to mitigate project risks,
and summary of Critical Success Factors
Post-Implementation Support Approach
Complete Technical Questionnaires
Define Technical Infrastructure Needs
Size Initial Hardware
Approve Sizing Results
Order Initial Hardware and Software
Order Remote Network Connection
System Landscape Strategy
Established Project Methodologies, Tools
and Governance Standards

Define Project Management Standards and


Procedures

Develop Benefits Realization Strategy


Develop Project Risk Assessment

Define Post-Implementation Support


Perform Technical Requirements Gathering

Procure Hardware

Define System Landscape Strategy


Define Project Methodologies, Tools and
Project Governance Standards

EI Toolkit Reference
Document version 1.0, June 2003
Last validated: June 2003

1
EITK0304

Key Implementation Activities and Deliverables:


AcceleratedSAP

Define Quality Assurance Plan


Develop Communication Strategy and Plan
Confirm Process, Organization and
Technical Scope

Quality Assurance Plan


Communication Plan/Strategy
Sign-off by Customer

Develop and perform Change Readiness


Assessment
Produce and Deliver Program Management
Status Reports
Prepare for Project Kickoff

Change Readiness Assessment Results and


Report
Completed Status Report
Updated Issues Log

Kickoff Meeting

EI Toolkit Reference
Document version 1.0, June 2003
Last validated: June 2003

2
EITK0304

Key Implementation Activities and Deliverables:


AcceleratedSAP
Table D.2-3 Business Blueprint Key Activities and Deliverables
Key Activities
Deliverables
Conduct Project Team Training
Execute Project Team Training Schedule

Define SAP Organizational Structure


Define Global Parameters
Prepare for Blueprint Workshops

SAP R/3 Hierarchy Definitions

Conduct Blueprint Workshops

Finalize Project Scope

Finalize Development Scope

Finalize End-User Training Strategy

Blueprint Workshop Schedule


List of Blueprint Workshop Participants
Blueprint Workshop Agendas
Business Blueprint Report
o Business Process Flows
o Policies and Procedures
o Gaps Identified
Business Process Master List (BPML)
Finalized Scope Document Signed off by
Customer
Development Scope: Reporting, Interfaces,
Conversions, Enhancements
End-User Training Strategy Signed-Off by
Customer
End User Training Requirements and
Materials Standards document

Conform to DoD RICE Concept of


Operations
Perform Cycle Planning for Prototyping
Develop Knowledge Transfer Plan

Develop Communications and Key


Stakeholder Management Plans
Define Business Organization Structure
and Identify Impact Areas
Complete SAP Bolt-On Evaluation
Identify Process Ownership
Create Technical Design
Develop Non-functional Requirements

Evaluation Results of SAP Bolt-Ons


Benefits and Process Owner Organization
Technical Design Document
Non-functional Requirements
Specifications Documentation

Develop Security Requirements

Setup and Install Development

Security Requirements Specifications


Documentation
Installed Development System

EI Toolkit Reference
Document version 1.0, June 2003
Last validated: June 2003

Cycle Plan for Prototyping


Knowledge Transfer Plan signed off by
Customer
Communication and Key Stakeholder
Management Plans
Business Organization Impacts

3
EITK0304

Key Implementation Activities and Deliverables:


AcceleratedSAP

Environment
Risk Assessment Measurement
Conduct Peer/Solution/Technical Reviews
Produce and Deliver Program Management
Status Reports
Business Blueprint Sign-off

EI Toolkit Reference
Document version 1.0, June 2003
Last validated: June 2003

Revised Risk Assessment


Solution/Technical Review Findings
Reports
Completed Status Report
Updated Issues Log
Business Blueprint Documentation and
Phase completion signed-off by Customer

4
EITK0304

Key Implementation Activities and Deliverables:


AcceleratedSAP
Table D.2-4

Realization Key Activities and Deliverables


Key Activities
Deliverables
Define Master Data
Master Data Definitions
Baseline Configuration Completed
Baseline Configuration and Documentation
Conduct Unit Testing
Completed Unit Testing and Associated
Scripts and Results

Final Configuration Completed

Create Security Authorizations


Develop Custom Design Specifications
(functional specs)
Develop Technical and Functional
Specifications
Coding and Unit Test for Conversions,
Reports, Interfaces and Enhancements

Conversion Planning (Cutover) and


Preparation
Develop New Procedures and Policies

Finalize Implementation Strategy

Finalize End-User Training Strategy


Establish Training Environment
Train Power Users
Plan SAP early watch Go-Live Quality
Assurance / Check
Plan and Execute System Test

Execute Cycle Testing


Develop Integration Test Plan(s)
Execute Integration Test
Design and Deliver Instructor Training
Material (if applicable)
Create End-User Training Programs and
Training Materials

EI Toolkit Reference
Document version 1.0, June 2003
Last validated: June 2003

Configured SAP System and Related


Documentation
Configured SAP User Profiles and Roles
Functional Specifications
Technical and Functional Specifications
Documentation and Associated Approvals
Completed Unit Testing for Development
Objects
Object Code for Development Objects
Initial Conversion (Cutover) Plan
Draft Legacy Retirement Plan
New Procedures and Policies
Documented/Approved
Implementation Strategy, including Site
Readiness Assessment and Change Process
Improvement
Approved End-User Training Strategy
Installed Training System
Trained Power Users and Trainers

System Test Plan


Volume and Stress Tested System
Cycle Testing Complete
Integration Test Plan
Integration Test Complete
Instructor Training Material

End-User Training Curriculum


End-User Training Materials
End-User Training Schedule
Facilities Reservations
5

EITK0304

Key Implementation Activities and Deliverables:


AcceleratedSAP

Create Technical Design


Establish Data Archiving Plan

Technical Design Document


Data Archiving Plan

Installed Quality Assurance System

Setup and Install Quality Assurance (QA)


Environment
Risk Assessment Measurement
Deliver Knowledge Transfer Status
Execute Communications Plan

Revised Risk Assessment

Conduct Peer/Solution/Technical Reviews

Produce and Deliver Program Management


Status Reports

EI Toolkit Reference
Document version 1.0, June 2003
Last validated: June 2003

Presentations
Newsletters
Solution/Technical Review Findings
Reports
Completed Status Report
Updated Issues Log

6
EITK0304

Key Implementation Activities and Deliverables:


AcceleratedSAP
Table D.2-5
Key Activities
Perform System Tests

Final Preparation Key Activities and Deliverables


Deliverables
Execute Stress, Volume, Disaster Recovery
and Backup Tests
Technical Processes Tested
Assess Going-Live Check
Implement Going-Live Check
Recommendations
Recommendations
Finalize Cutover (Conversion) Plan
Cutover Workplan
Develop Contingency Plan
Contingency Plan
Refine and Execute Production Support
Plan
Execute Change Plan
Production Readiness Review
Obtain Cutover Approval
Refine and Execute Legacy Retirement
Plan
Perform Training Program Evaluation
Deliver End-User Training
Complete Process and Organizational
Changes
Execute SAP Going-Live Check
Develop Technical Operations Manual

Training Program Evaluation


Trained End Users
Process and Organizational Changes
Performed
Going Live Check Assessment
Technical Operations Manual

Setup and Install Production


Environment(s)
Configure and Execute System
Administrator Functionality
Establish Service Level Agreements
Risk Assessment Measurement
Conduct Peer/Solution/Technical Reviews

Installed Production System(s)

Tuned SAP System

Produce and Deliver Program Management


Status Reports
Final Preparation Sign-off

Service Level Agreements


Revised Risk Assessment
Solution/Technical Review Findings
Reports
Completed Status Report
Updated Issues Log
Go-Live Approved

EI Toolkit Reference
Document version 1.0, June 2003
Last validated: June 2003

Commence Initial Production Support


Activities (which occur prior to go-live)
Organization Change Plan
Execute Cutover/Conversion Plan
Legacy Retirement Plan

7
EITK0304

Key Implementation Activities and Deliverables:


AcceleratedSAP
Table D.2-6 Go-Live and Support Key Activities and Deliverables
Key Activities
Deliverables
Provide Production Support (Help Desk)
Production Support (Help Desk)
Established
Execute Daily Operation Support and
Production-Ready Systems Environment
Administration
Optimize System Tuning
Validate Live Business Process Results
Business Process Results
Monitor Transactions, Interfaces and
System tuning and Procedural Updates
Procedures
Execute Ongoing Security Administration Security Administration

Provide Ongoing Training Support


Develop Continuous Improvement Plan
Produce and Deliver Program Management
Status Reports
Post Implementation Review

EI Toolkit Reference
Document version 1.0, June 2003
Last validated: June 2003

Execute Ongoing Training Support


Continuous Improvement Plan
Completed Status Report
Updated Issues Log
Post Implementation Findings Reports

8