Professional Documents
Culture Documents
com
Civil Engineering Department, American University of Sharjah, P.O. Box 26666, Sharjah, United Arab Emirates
Received 24 January 2007; received in revised form 11 July 2007; accepted 12 July 2007
Abstract
This study identies and assesses the signicant risks in the UAE construction industry and addresses their proper allocation. Data
were collected through a questionnaire distributed to construction experts. The study reveals that economic risks such as ination and
sudden changes in prices, shortage in material and labor supply are signicant. Other signicant risks include owner risks such as unrealistic construction schedule, improper intervention and changes in design. Political, social and cultural risks are found to be insignicant. Local and international experts are in agreement as to the ranking of construction risks in the UAE. More risks are allocated to
contractors or shared between contractors and owners with only two risks allocated directly to the owners.
2007 Elsevier Ltd and IPMA. All rights reserved.
Keywords: Risk management; Risk assessment; International construction; UAE construction industry
1. Introduction
The construction business, like any other business, is
risky. However, construction projects are perceived to have
more inherent risks due to the involvement of many
contracting parties such as owners, designers, contractors,
subcontractors, suppliers, etc. Construction projects are
unique and built only once. They also involve a temporary
project team that is assembled from dierent companies,
countries, cultures, etc. Moreover, the size and complexity
of construction projects are increasing which adds to the
risks. This is in addition to the economic, political, social
and cultural conditions where the project is to be undertaken. Project risk can be dened as an uncertain event
or condition that, if it occurs, has a positive or negative
eect on at least one project objective, such as time, cost,
scope, or quality [1]. Risks are related to rewards. Some
risks should be accepted as long as they are in line with
the rewards. Risks are threats to project success [2]. Failure
to adequately deal with risks has been shown to cause cost
and time overruns in construction projects [3,4]. Trying to
*
432
Table 1
Respondents prole
Category
Respondents
Number
Years of experience
>20 years
1020 years
510 years
<5 years
33
19
5
8
50.77
29.23
07.69
12.31
Role
Owner
Designer
Contractor
Construction Manager
13
10
30
12
20.00
15.38
46.15
18.46
Position
Executives
Project Managers
Department Heads
Architect/Engineers
17
23
12
13
26.15
35.38
18.46
20.00
6
10
31
18
09.23
15.38
47.69
27.69
P
6 d2
rs 1 3
N N
433
under the control of the project management team. External risks are those risks that are beyond the control of the
project management team. Other researchers divided projects risks into internal and external [11,13,16]. Aleshin
[16] stated that internal risks are initiated inside the project while external risks originate due to the project environment. Internal risks are then divided according to
the party who might be the originator of risk events such
as owner, designer, contractor, etc. External risks are those
initiated at the macro level [16].
3. Risk identication
The owners category includes owners delayed payments to contractors. Payments from owners are the main
source of revenue for construction contractors. When owners delay payments to contractors, a nancial hardship is
placed on the contractors. Owners often impose tight construction schedules that might be dicult and impractical
to achieve. Owners often improperly intervene in the construction phase. Owners may require lots of design
changes. This may result from poor scope of work denition or simply owners might change their mind during
where
rs
d
N
Project Risks
Internal Risks
Owners
Designers
External Risks
Contractors
SubContractors
Suppliers
Social &
Cultural
Political
Economic
Natural
Delayed
Payments to
Contractors
Defective
Design
Construction
Accidents
Poor
Performance
Material
Quality
Problems
War Threats
Criminal Acts
Inflation
Unexpected
Inclement
Weather
Unreasonably
Imposed Tight
Schedule
Deficiency in
Drawings
Poor Quality
Breach of
Contract
Delay of
Material
Supply
Labor Strikes
Substance
Abuse
Currency
Fluctuation
Unforeseen
Site Conditions
Changes in
Laws
Conflicts due
to Differences
in Culture
Shortage in
Material
Availability
Improper
Intervention
Changes in
Design
Low
Productivity
Change of
Design
Documents not
Technical
Issued on
Problems
Time
Lack of Scope
Definition
Contractors
Incompetence
Delays in
Obtaining Site
Access
Lack or
Departure of
Qualified Staff
Corruption &
Bribes
Shortage in
Manpower
Availability
Delays in
Approvals
Shortage in
Equipment
Availability
Others
Delays in
resolving
contractual
issues
Delays in
Resolving
Litigation
Unfairness in
Tendering
Local
Protectionism
Difficulty in
Claiming
Insurance
Breach of
Contract
Sudden
Bankruptcy
434
435
Table 2
Overall risk signicance
Risk
Description
Probability
RII
Rank
RII
Rank
Value
Rank
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
3.05
3.52
3.28
3.29
3.00
2.57
2.55
1.72
2.32
2.94
2.94
2.83
2.54
2.62
2.74
2.55
3.06
3.17
3.32
2.95
3.23
2.77
1.62
2.06
2.28
2.08
3.20
1.52
1.75
2.20
3.62
2.25
3.08
3.14
2.77
1.77
2.40
3.17
2.80
2.68
2.58
2.65
13
2
5
4
14
27
28
40
32
16
17
18
30
25
22
29
12
8
3
15
6
20
41
37
33
36
7
42
39
35
1
34
11
10
21
38
31
9
19
23
26
24
3.58
3.60
3.65
3.71
3.57
3.25
3.46
3.97
3.37
3.34
3.43
3.38
2.80
3.20
3.45
3.25
3.58
3.75
3.85
3.55
3.86
3.38
3.60
3.37
3.02
2.83
3.74
2.43
2.38
2.55
4.15
3.18
3.60
3.80
3.52
2.80
3.18
3.40
3.20
3.31
2.85
3.11
13
10
9
8
15
28
18
2
24
26
20
22
38
30
19
29
14
6
4
16
3
23
11
25
35
37
7
41
42
40
1
32
12
5
17
39
33
21
31
27
36
34
11.18
13.32
12.38
12.63
11.38
8.95
9.14
7.05
8.29
10.48
10.31
10.12
7.54
8.97
9.97
8.85
11.31
12.15
13.2
10.74
12.8
9.78
6
7.42
7.37
6.51
12.32
4.02
4.52
6.34
15.48
7.78
11.83
12.37
10.17
5.32
8.15
11.38
9.55
9.2
7.83
8.71
14
2
6
5
11
26
24
36
29
16
17
19
33
25
20
27
13
9
3
15
4
21
39
34
35
37
8
42
41
38
1
32
10
7
18
40
30
12
22
23
31
28
Table 3
Ten most signicant risks in the UAE construction industry
Risk
Rank
RII
1
2
3
4
5
6
7
8
9
10
15.48
13.32
13.20
12.80
12.63
12.38
12.37
12.32
12.15
11.83
Impact
Rating
436
Table 4
Ten most signicant risks according to international companies
Risk
Rank
RII
1
2
3
4
5
6
7
8
9
10
16.14
14.82
14.32
14.32
13.82
13.36
12.73
12.64
12.64
12.64
Risk
Rank
RII
1
2
3
4
5
6
7
8
9
10
15.14
12.91
12.88
12.56
12.30
12.21
11.91
11.77
11.63
11.42
Table 5
Ten most signicant risks according to local companies
Probability
4.00
3.00
2.00
1.00
1.00
2.00
3.00
4.00
Impact
Fig. 2. Probability-impact matrix.
5.00
437
Table 6
Risk allocation
Risk
Description
Owner (%)
Contractor (%)
Shared (%)
Allocation
13
15
18
16
19
20
35
17
21
14
34
24
22
33
37
8
4
23
28
39
29
25
32
26
38
41
36
31
9
42
30
5
10
2
40
12
11
6
7
3
27
1
3.08
0.00
1.54
1.54
1.54
3.08
0.00
6.15
0.00
4.62
1.54
4.62
1.54
0.00
3.08
53.85
50.77
10.77
1.54
6.15
1.54
4.62
3.08
4.62
4.62
15.38
1.54
6.15
26.15
1.54
3.08
30.77
16.92
20.00
30.77
32.31
35.38
24.62
27.69
29.23
30.91
32.31
87.69
83.08
81.54
78.46
75.38
75.38
75.38
66.15
66.15
64.62
64.62
63.08
60.00
52.31
50.77
18.46
10.77
7.69
26.15
24.62
32.31
29.23
32.31
32.31
33.85
23.08
41.54
38.46
18.46
46.15
44.62
18.46
33.85
32.31
21.54
23.08
21.54
33.85
30.77
29.23
30.91
36.92
9.23
16.92
16.92
20.00
23.08
21.54
24.62
27.69
33.85
30.77
33.85
32.31
38.46
47.69
46.15
27.69
38.46
81.54
72.31
69.23
66.15
66.15
64.62
63.08
61.54
61.54
56.92
55.38
55.38
52.31
52.31
50.77
49.23
47.69
47.69
44.62
43.08
41.54
41.54
41.54
38.18
30.77
Contractor
Contractor
Contractor
Contractor
Contractor
Contractor
Contractor
Contractor
Contractor
Contractor
Contractor
Contractor
Contractor
Contractor
Contractor
Owner
Owner
Shared
Shared
Shared
Shared
Shared
Shared
Shared
Shared
Shared
Shared
Shared
Shared
Shared
Shared
Shared
Undecided
Undecided
Undecided
Undecided
Undecided
Undecided
Undecided
Undecided
Undecided
Undecided
438