You are on page 1of 1

Sewer Separation Look Ahead

Compiled by Quinn Lonczak- WPC Project Supervisor

West Aldenville Project


F & J Incorporated
October 13th- October 23rd
Installation of sewer services on Providence St., moving to Arcade St.
Installation of sanitary sewer on Marcelle St. from Grattan St. to Arcade St.

Chicopee Falls Project- Broadway St. and Beauchamp Terr. Area


F & J Incorporated
October 19th- October 23rd
Intermittent work taking place to correct punch-list items. Minimal disruptions
anticipated on Medford St. at Broadway St.

North Aldenville and Montgomery/Sheridan Sts. Project


Ludlow Construction Company
October 13th- October 23rd
Miscellaneous restoration of entire project area
Construction of sidewalks on Taylor St. (October 14th-16th)
Reconstruction and paving of Fair St. east of Dale St. (October 19th-23rd)

North Willimansett Project


Albanese Brothers Incorporated
October 13th- October 23rd
Installation of sanitary sewer on Caroline St. (October 14th-15th)
Installation of sanitary sewer on Philathea St. (October 19th-20th)
Installation of sanitary sewer on Grattan St. (October 21st-22nd)
Installation of sanitary sewer on Artisan St. (October 13th-21st)
Installation of sanitary sewer on Norman St. (October 22nd)
Installation of sanitary sewer on Thomas St. (October 14th-22nd)
Installation of sewer service lines on Whitman St. (October 13th-20th)
Installation of sewer service lines on Warregan St. (October 19th-21st)
Installation of sewer service lines on Skeele St. (October 21st)
Installation of sewer service lines on Nash St. (October 22nd)
Installation of sewer service lines on Pickering St. (October 22nd)
Installation of water main on Shepherd St. (October 14th-15th)
This information is provided by the respective contractor, and is subject to change due to
unforeseen conditions. Every effort has been made to make sure it is correct.
Questions? Concerns? Please contact the Chicopee Water Pollution Control at (413) 594-3585

Building Better Neighborhoods

You might also like