'Non-compliance' of scheme with RBK's Eden Quarter Development Brief SPD. 'Existing assets inform the quality of new buildings' - examples from elsewhere in Kingston. Proposal for TOPO is entirely unrelated to the existing assets, in style, scale, form and materials. 'No. Of storeys greatly exceeds the SPD guidance, throughout the site.'
'Non-compliance' of scheme with RBK's Eden Quarter Development Brief SPD. 'Existing assets inform the quality of new buildings' - examples from elsewhere in Kingston. Proposal for TOPO is entirely unrelated to the existing assets, in style, scale, form and materials. 'No. Of storeys greatly exceeds the SPD guidance, throughout the site.'
'Non-compliance' of scheme with RBK's Eden Quarter Development Brief SPD. 'Existing assets inform the quality of new buildings' - examples from elsewhere in Kingston. Proposal for TOPO is entirely unrelated to the existing assets, in style, scale, form and materials. 'No. Of storeys greatly exceeds the SPD guidance, throughout the site.'
KINGSTON UPON THAMES Presentation to Development Control Committee 14th October 2015 Alec Bound
Non-Compliance of St George Scheme with
RBKs Eden Quarter Development Brief SPD, dated March 2015
This presentation makes reference to:
SPD Section 2 Development Principles SPD Section 3 Urban Design Framework SPD Section 4 Place-making
Non-Compliance of Scheme with RBKs SPD
SPD Section 2 - Development Principles
Non-Compliance of Scheme with RBKs SPD
o Existing assets inform the quality of new buildings
Good examples from elsewhere in Kingston
Non-Compliance of Scheme with RBKs SPD
o Existing assets inform the quality of new buildings Examples from St Georges proposals for TOPO
The proposed new buildings
are entirely unrelated to the existing assets, in style, scale, form and materials
Non-Compliance of Scheme with RBKs SPD
SPD Section 3 Urban Design Framework o Section 3.5 Heights, Scale and Massing
Non-Compliance of Scheme with RBKs SPD
o Section 3.5 Heights, Scale and Massing
12 11
Proposed no. of storeys
greatly exceeds the SPD guidance, throughout the site
8 11
10 8 16
10
Non-Compliance of Scheme with RBKs SPD
SPD Section 4 - Place Modelling
Non-Compliance of Scheme with RBKs SPD
Section 4 - Place Modelling Composite View of TOPO and Eden Walk
Proposed open space
will be overwhelmed by surrounding tall buildings. 9
Non-Compliance of Scheme with RBKs SPD
Section 4 - Place Modelling Almost no sun at all for 6 months of the year
Partly sunny on Mid-Summers Day
2-Hour Sun Shading Analysis: 21 March & 21 June
(provided by St George)
10
Non-Compliance of St George Scheme with
RBKs Eden Quarter Development Brief SPD, dated March 2015 Conclusion: SPD Section 2 Development Principles Non-Compliant SPD Section 3 Urban Design Framework Non-Compliant SPD Section 4 Place-making Non-Compliant