Detailed Working Procedure

Drill 24 Section to top of Jahrum

Distribution:
.

Drill 24 Hole to Top of Jahrum

South Pars
SPD24A-05
PARADISE

Prepared By:
Saeed Ara

Approved by:
Behnam Mirshekari

Drilling 24'' Hole to top of Jahrum.doc

Detailed Working Procedure


Drill 24 Section to top of Jahrum

Pitfalls!

If high torque during drilling or connection, sweep hi-vis pills and circ.

Spot hi-vis pill on all connection.

Pump/Spot pills and start up after connection with 800 GPM

Description

Paralell act.

1.
Pick up enough 5 DP and HWDP to be able to drill to
1200 m.
2. MU BHA:

MU bottom hole assembly according as following;

Use solid float


Verify condition of bit before RIH

24 Tri cone Bit + BIT SUB / F.valve+ TOTCO ring +2 x 9 DC


+24 S.Stab + 5 x 9 DC + X/O + 6 x 8 DC + JAR + 3 x 8 DC
+ X/O + 15 X 5 HWDP
As per Work instruction No: GE 000-0000-DR-WI-9101-00

Insert tooth bit type:23.5"Bit


3.

Space out to be able to drill shoe and rat


hole without connection (btm of rat hole
@ 181 m)

Nobody on T Deck because of possible


H2S gas.

RIH with BHA to approx. 10 m above cement .(Shoe


depth 177 m)

4.
Wash down and tag cement at . m carefully while
pumping at 650-800 gpm & 50 RPM.
As per Work instruction No: GE 000-0000-DR-WI-9105-00

Take caution to prevent falling through shoe with


high WOB, 1-2 ton is enough to minimize weight
transferred to CP.
Continue like this until bottom of rat hole. Increase
pump rate to max 800 gpm when below shoe.
Pump 60 bbls Guar Gum and BU.
Clean out rat hole carefully in steps (3m at the time).

Drilling 24'' Hole to top of Jahrum.doc

Detailed Working Procedure


Drill 24 Section to top of Jahrum
5. Drill down to approx. 545 m TVD.
(Top of Asmari & Jahrum @ 545 m)
As per Work instruction No: GE 000-0000-DR-WI-9110-00

Recommended drilling parameters:


WOB: 0 20 ton (do not run the jar in neutral)
Max. WOB = 35 MT
RPM: 0 80, Back reaming: 30 -50.

STUCK PIPE ABOVE JAHRUM:


If hole pack off DO NOT jar
Stop the pump and bleed off pressure
immediately.
As per Work instruction No: GE 000-0000-DR-WI-9133-00

Break the string free by applying


torque to the string and at the same
time move the pipe up and down close
to neutral weight do not attempt to
circulate.

Rotate and move pipe upwards and


attempt to regain circulation (rack
back a stand if required).

Flow: 1000-1200 GPM


Torque limit set at: 15000 20 000 ft-lb
Pump 30 bbls Guar Gum every Stand Drilled.
Spot 50 bbls PHG prior to Connection

If Partial Losses:
Pump 30 bbls GG at single drilled and 30 bbls PHB
on connection.
Before connection pick up the single to evaluate any
overpull tendency.
If overpull, Back Ream the Stand w/ 40 RPM.

Drilling 24'' Hole to top of Jahrum.doc