Jul 26, '15

PERBAIKAN GARDU KIJ - 5


PEKERJAAN PERSIAPAN
INSTALASI PENYANGGA BALOK SEMENTARA
GALIAN TANAH PONDASI
PENGECORAN PONDASI
INSTALASI PENYANGGA BALOK

Project: Schedule Perbaikan Balok


Date: Fri 8/7/15

Duration

Start

Finish

5 days
1 day
1 day
1 day
1 day
1 day

Mon 8/3/15
Mon 8/3/15
Tue 8/4/15
Wed 8/5/15
Thu 8/6/15
Fri 8/7/15

Fri 8/7/15
Mon 8/3/15
Tue 8/4/15
Wed 8/5/15
Thu 8/6/15
Fri 8/7/15