Created (12.10.

15)
Music Video
All Research
Finish
Storyboarding
Recce
Casting &
Costume
Risk
Assessments
Equipment &
Call Sheet
Filming (with
actor)
Filming
(without actor)
Post Production

Week 1
(12 Oct)

Week 2
(19 Oct)

Week 3
(26 Oct)

Week 4
(2 Nov)

Week 5
(9 Nov)

Filming
Deadline
(13 Nov)

Week 6
(16 Nov)

Week 7
(23 Nov)

Week 8
(30 Nov)

First Edit
Deadline
11th Dec

(Updated 27.10.15)
Music Video

Week 1
(12 Oct)

Week 2
(19 Oct)

Week 3
(26 Oct)

Week 4
(2 Nov)

Week 5
(9 Nov)

Filming
Deadline
(13 Nov)

Week 6
(16 Nov)

Week 7
(23 Nov)

Week 8
(30 Nov)

First Edit
Deadline
11th Dec

All Research
Finish
Storyboarding
Recce
Casting &
Costume
Risk
Assessments
Equipment &
Call Sheet
Filming (with
actor)
Filming
(without actor)
Post Production

Changes made: I decided to push forward the time I start to film with my actor as it is more convenient when for
when I and the actor are free.

(Updated 5.11.15)
Music Video

Week 1
(12 Oct)

Week 2
(19 Oct)

Week 3
(26 Oct)

Week 4
(2 Nov)

Week 5
(9 Nov)

Filming
Deadline
(13 Nov)

Week 6
(16 Nov)

Week 7
(23 Nov)

Week 8
(30 Nov)

Assembled
Edit for Hot
Desking 4th
Dec

All Research
Finish
Storyboarding
Recce
Casting &
Costume
Risk
Assessments
Equipment &
Call Sheet
Filming (with
actor)
Filming
(without
actor)
Post
Production

Easton 3rd
London
5th

Changes made:
I added the scheduled day for filming in Easton, and in London - this filming will be done for visual matter.

First Edit
Deadline
11th Dec

(Updated 8.11.15)
Music Video

Week 1
(12 Oct)

Week 2
(19 Oct)

Week 3
(26 Oct)

Week 4
(2 Nov)

Week 5
(9 Nov)

Filming
Deadline
(13 Nov)

Week 6
(16 Nov)

Week 7
(23 Nov)

Week 8
(30 Nov)

Assembled
Edit for Hot
Desking 4th
Dec

First Edit
Deadline
11th Dec

All Research
Finish
Storyboarding
Recce
Casting &
Costume
Risk
Assessments
Equipment &
Call Sheet
Filming (with
actor)
Filming
(without
actor)

Easton 3rd
London 5th
Easton 7th
Longwater
8th

Post
Production

Changes made:
I added the scheduled day for filming in Easton again, and in Longwater - this filming will be done for visual matter.

(Updated 13.11.15)
Music Video

Week 1
(12 Oct)

Week 2
(19 Oct)

Week 3
(26 Oct)

Week 4
(2 Nov)

Week 5
(9 Nov)

Filming
Deadline
(13 Nov)

Week 6
(16
Nov)

Week 7
(23
Nov)

Week 8
(30 Nov)

Assembled
Edit for Hot
Desking 4th
Dec

All Research
Finish
Storyboarding
Recce
Casting &
Costume
Risk
Assessments
Equipment &
Call Sheet
Filming (with
actor)
Filming
(without
actor)

Norwich
13th
Easton 3rd
London 5th
Easton 7th
Longwater
8th

Norwich
11th
Easton 12th

Post
Production

Changes made:
I added the scheduled day for filming in Norwich both for visual based footage and with my actor in. I also
scheduled a time for filming in Easton which will be for cloud filming.