1 WAGE RATES OF CONSTRUCTION WORKERS JANUARY 2014 (DAILY) / KADAR UPAH PEKERJA BINAAN JANUARI 2014 (HARIAN)

SEMENANJUNG
NO.

CATEGORY OF WORKERS / KATEGORI PEKERJA

KEDAH
Maximum

Minimum

RM

RM

PULAU PINANG

Common
Jan 14
RM

Common
July 13
RM

Maximum

Minimum

RM

RM

Common
Jan 14
RM

Common
July 13
RM

General construction worker - building (helper)

1.1.1

General constr. worker Building, Local (helper)

91.00

66.00

80.50

79.50

75.00

40.00

59.50

59.00

1.1.2

General constr. worker Building,Foreign (helper)

72.00

46.00

57.17

56.17

65.00

38.00

48.80

47.80

Concretor

2.1.1

Concretor, Skilled, Local

99.00

91.00

94.33

93.33

155.00

70.00

99.00

99.50

2.1.2

Concretor, Skilled, Foreign

89.00

65.00

80.50

79.50

125.00

50.00

77.50

76.00

2.2.1

Concretor, Semi-skilled,Local

83.00

64.00

75.00

74.00

105.00

55.00

76.00

78.50

2.2.2

Concretor, Semi-skilled, Foreign

79.00

47.00

66.83

65.83

100.00

40.00

62.50

61.00

Bricklayer

3.1.1

Bricklayer, Skilled, Local

97.00

87.00

92.00

91.00

125.00

70.00

98.50

92.50

3.1.2

Bricklayer,Skilled, Foreign

96.00

73.00

84.00

83.00

100.00

55.00

74.00

68.50

3.2.1

Bricklayer,Semi-skilled, Local

82.00

71.00

78.00

77.00

95.00

45.00

70.50

66.60

3.2.2

Bricklayer, Semi-skilled, Foreign

76.00

58.00

66.33

65.33

75.00

40.00

54.70

50.20

Plasterer

4.1.1

Plasterer, Skilled, Local

101.00

87.00

96.00

95.00

120.00

85.00

102.00

101.00

4.1.2

Plasterer, Skilled, Foreign

92.00

75.00

85.00

84.00

105.00

70.00

85.50

81.50

4.2.1

Plasterer, Semi-skilled, Local

86.00

64.00

76.33

75.33

100.00

50.00

76.00

69.50

4.2.2

Plasterer, Semi-skilled,Foreign

77.00

63.00

70.67

69.67

96.00

40.00

55.90

53.90

Tiler

5.1.1

Tiler, Skilled, Local

104.00

98.00

100.17

99.17

135.00

90.00

111.50

108.50

5.1.2

Tiler, Skilled, Foreign

95.00

78.00

88.67

87.67

120.00

60.00

86.50

87.50

5.2.1

Tiler, Semi-skilled, Local

87.00

76.00

81.67

80.67

105.00

55.00

79.50

74.00

5.2.2

Tiler, Semi-Skilled, Foreign

78.00

60.00

70.67

69.67

90.00

45.00

62.00

58.50

Barbender

6.1.1

Barbender, Skilled,Local

98.00

89.00

93.17

92.17

130.00

80.00

102.20

98.20

6.1.2

Barbender,Skilled, Foreign

93.00

66.00

77.67

76.67

95.00

55.00

77.30

71.80

6.2.1

Barbender,Semi-skilled, Local

88.00

63.00

73.00

72.00

85.00

50.00

71.50

69.00

6.2.2

Barbender, Semi-skilled, Foreign

78.00

53.00

62.67

61.67

65.00

40.00

49.70

47.40

Carpenter-Formwork

7.1.1

Carpenter-Formwork, Skiiled, Local

97.00

93.00

94.83

93.83

120.00

75.00

99.80

95.80

7.1.2

Carpenter-Formwork,Skilled, Foreign

92.00

72.00

82.00

81.00

100.00

55.00

76.00

72.50

7.2.1

Carpenter-Formwork, Semi-skilled, Local

91.00

72.00

81.33

80.33

95.00

45.00

73.00

71.50

7.2.2

Carpenter-Formwork, Semi-skilled,Foreign

81.00

69.00

75.17

74.17

80.00

40.00

54.50

54.50

2.1 WAGE RATES OF CONSTRUCTION WORKERS JANUARY 2014 (DAILY) / KADAR UPAH PEKERJA BINAAN JANUARI 2014 (HARIAN)

SEMENANJUNG
NO.

CATEGORY OF WORKERS / KATEGORI PEKERJA

KEDAH
Maximum

Minimum

RM

RM

PULAU PINANG

Common
Jan 14
RM

Common
July 13
RM

Maximum

Minimum

RM

RM

Common
Jan 14
RM

Common
July 13
RM

Carpenter-Joinery

8.1.1

Carpenter-Joinery, Skilled, Local

108.00

100.00

103.00

102.00

130.00

75.00

105.00

101.00

8.1.2

Carpenter-Joinery, Skilled,Foreign

98.00

91.00

94.83

93.83

105.00

65.00

84.00

79.00

8.2.1

Carpenter-Joinery,Semi-skilled, Local

95.00

83.00

89.17

88.17

90.00

60.00

73.00

75.00

8.2.2

Carpenter-Joinery, Semi-Skilled, Foreign

88.00

72.00

80.50

79.50

80.00

45.00

62.30

58.80

Roofer

9.1.1

Roofer, Skilled, Local

106.00

98.00

101.17

100.17

135.00

65.00

101.00

100.50

9.1.2

Roofer,Skilled, Foreign

93.00

87.00

90.17

89.17

105.00

60.00

77.00

77.00

9.2.1

Roofer,Semi-skiiled, Local

88.00

74.00

83.33

82.33

100.00

55.00

71.50

70.50

9.2.2

Roofer, Skilled, Foreign

78.00

67.00

72.33

71.33

80.00

40.00

54.50

54.50

10

Steel Structure Fabricator

10.1.1 Steel Structure Fabricator, Skilled, Local

123.00

98.00

105.67

104.67

140.00

80.00

103.50

101.00

10.1.2 Steel Structure Fabricator, Skilled, Foreign

101.00

93.00

97.67

96.67

110.00

60.00

81.50

81.00

10.2.1 Steel Structure Fabricator, Semi-Skilled, Local

95.00

87.00

90.67

89.67

105.00

55.00

74.50

74.00

10.2.2 Steel Structure Fabricator, Semi-skilled, Foreign

86.00

73.00

78.17

77.17

80.00

45.00

56.30

55.80

11.1.1 General Welder, Skilled, Local

102.00

98.00

100.33

99.33

120.00

65.00

88.50

86.50

11.1.2 General Welder, Skilled, Foreign

100.00

88.00

93.33

92.33

90.00

55.00

71.50

70.00

11.2.1 General Welder, Semi-skilled, Local

92.00

78.00

86.50

85.50

90.00

50.00

69.00

69.00

11.2.2 General Welder, Semi-skilled, Foreign

87.00

73.00

79.67

78.67

80.00

40.00

51.00

51.00

11

12

General Welder

Plumber-Building & Sanitary


101.00

97.00

99.17

98.17

140.00

75.00

98.00

99.50

12.1.2 Plumber-Building & Sanitary, Skilled, Foreign

88.00

76.00

83.17

82.17

130.00

55.00

84.50

84.00

12.2.1 Plumber-Building & Sanitary, Semi-skilled, Local

82.00

74.00

78.00

77.00

120.00

55.00

78.00

81.00

12.2.2 Plumber-Building & Sanitary, Semi-skilled, Foreign

79.00

62.00

69.50

68.50

105.00

52.00

67.70

67.20

13.1.1 Plumber-Reticulation, Skilled, Local

123.00

103.00

111.17

110.17

135.00

75.00

105.50

104.00

13.1.2 Plumber-Reticulation, Skilled, Foreign

102.00

98.00

99.67

98.67

120.00

60.00

85.50

81.50

13.2.1 Plumber-Reticulation, Semi-skilled, Local

99.00

93.00

96.00

95.00

110.00

55.00

81.50

79.00

13.2.2 plumber-reticulation, semi-skilled, foreign

85.00

75.00

80.33

79.33

90.00

50.00

63.50

63.50

14.1.1 Building Wiring Installer, Semi-skilled, Local

107.00

98.00

101.83

100.83

140.00

70.00

101.50

99.50

14.2.1 Building Wiring Installer, Semi-skilled, Foreign

101.00

95.00

97.67

96.67

120.00

50.00

71.20

71.20

12.1.1 Plumber-Building & Sanitary, Skilled, Local

13

14

Plumber-Reticulation

Building Wiring Installer

2.1 WAGE RATES OF CONSTRUCTION WORKERS JANUARY 2014 (DAILY) / KADAR UPAH PEKERJA BINAAN JANUARI 2014 (HARIAN)

SEMENANJUNG
NO.

CATEGORY OF WORKERS / KATEGORI PEKERJA

KEDAH

PULAU PINANG

Common
Jan 14
RM

Maximum

Minimum

RM

RM

15.1.1 Electrical Wireman PW2, Skilled, Local

2603.00

2303.00

2471.67

15.2.1 Electrical Wireman PW2, Skilled, Foreign

2403.00

1965.00

2180.00

16.1.1 Electrical Wireman PW4, Skilled, Local

3003.00

2921.00

16.2.1 Elactrical Wireman PW4, Skilled, Foreign

2703.00

2195.00

15

16

17

Common
July 13
RM

Common
Jan 14
RM

Common
July 13
RM

Maximum

Minimum

RM

RM

2470.67

3000.00

1200.00

1950.00

1935.00

2179.00

1700.00

850.00

1345.00

1340.00

2980.83

2979.83

3360.00

1800.00

2656.00

2641.00

2480.00

2479.00

2575.00

1000.00

1738.50

1728.50

Electrical Wireman PW2 (Monthly Salary)

Electrical Wireman PW4 (Monthly Salary)

Scaffolder - Prefabricated
101.00

86.00

92.33

91.33

155.00

60.00

98.00

95.50

17.1.2 Scaffolder - Prefabricated, Skilled, Foreign

88.00

75.00

82.00

81.00

140.00

45.00

82.50

81.00

17.2.1 Scaffolder - Prefabricated, Semi-skilled, Local

83.00

73.00

78.00

77.00

120.00

45.00

69.50

69.50

17.2.2 Scaffolder - Prefabricated,Semi-skilled, Foreign

76.00

69.00

72.33

71.33

105.00

42.00

60.40

60.40

18.1.1 Scaffolder - Tubular, Skilled, Local

98.00

91.00

94.33

93.33

125.00

70.00

94.00

92.00

18.1.2 Scaffolder - Tubular, Skilled, Foreign

92.00

73.00

80.67

79.67

115.00

60.00

81.50

81.00

18.2.1 Scaffolder - Tubular, Semi-skilled, Local

80.00

70.00

75.00

74.00

105.00

55.00

75.00

75.00

18.2.2 Scaffolder - Tubular, Semi-skilled, Foreign

72.00

63.00

67.00

66.00

90.00

35.00

56.00

56.00

19.1.1 Painter - Building, Skilled, Local

92.00

83.00

88.00

87.00

125.00

80.00

99.50

99.00

19.1.2 Painter - Building, Skilled, Foreign

81.00

71.00

76.00

75.00

105.00

55.00

81.80

81.30

19.2.1 Painter - Building, Semi-skilled, Local

77.00

70.00

73.17

72.17

100.00

50.00

72.00

71.50

19.2.2 Painter - Building, Semi- skilled, Foreign

67.00

56.00

61.67

60.67

85.00

40.00

57.00

57.00

20.1.1 General Construction Worker - Civil, Local

81.00

70.00

75.50

74.50

70.00

45.00

58.00

59.50

20.1.2 General Construction Worker - Civil, Foreign

71.00

57.00

64.50

63.50

60.00

35.00

49.00

48.00

17.1.1 Scaffolder - Prefabricated, Skilled, Local

18

19

20

Scaffolder - Tubular

Painter - Building

General Construction Worker - Civil (Helper)

2.1 WAGE RATES OF CONSTRUCTION WORKERS JANUARY 2014 (DAILY) / KADAR UPAH PEKERJA BINAAN JANUARI 2014 (HARIAN)

SEMENANJUNG
NO.

CATEGORY OF WORKERS / KATEGORI PEKERJA

PERAK
Maximum

Minimum

RM

RM

SELANGOR

Common
Jan 14
RM

Common
July 13
RM

Maximum

Minimum

RM

RM

KUALA LUMPUR

Common
Jan 14
RM

Common
July 13
RM

Maximum

Minimum

RM

RM

Common
Jan 14
RM

Common
July 13
RM

General construction worker - building (helper)

1.1.1

General constr. worker Building, Local (helper)

80.00

50.00

67.50

66.17

90.00

40.00

70.00

64.50

80.00

50.00

63.00

63.00

1.1.2

General constr. worker Building,Foreign (helper)

55.00

40.00

48.33

48.33

85.00

35.00

57.50

53.50

65.00

40.00

53.00

53.00

Concretor

2.1.1

Concretor, Skilled, Local

140.00

88.00

118.00

117.50

130.00

65.00

96.00

93.00

110.00

60.00

89.50

89.50

2.1.2

Concretor, Skilled, Foreign

120.00

60.00

82.50

82.50

100.00

50.00

74.50

69.00

95.00

40.00

75.00

75.00

2.2.1

Concretor, Semi-skilled,Local

85.00

70.00

78.33

77.50

90.00

45.00

66.50

63.50

80.00

50.00

63.50

63.50

2.2.2

Concretor, Semi-skilled, Foreign

70.00

45.00

56.67

55.92

85.00

40.00

57.50

54.50

75.00

45.00

55.50

55.50

Bricklayer

3.1.1

Bricklayer, Skilled, Local

120.00

80.00

96.33

92.50

130.00

65.00

103.50

99.00

120.00

60.00

90.50

90.50

3.1.2

Bricklayer,Skilled, Foreign

100.00

55.00

76.50

75.00

100.00

55.00

79.50

74.00

100.00

45.00

76.00

76.00

3.2.1

Bricklayer,Semi-skilled, Local

88.00

63.00

73.50

73.33

115.00

45.00

72.50

70.00

90.00

50.00

66.00

66.00

3.2.2

Bricklayer, Semi-skilled, Foreign

69.00

45.00

56.67

56.67

90.00

38.00

59.80

57.80

70.00

38.00

54.30

54.30

Plasterer

4.1.1

Plasterer, Skilled, Local

160.00

90.00

110.00

96.67

150.00

75.00

109.50

111.00

150.00

80.00

102.50

102.50

4.1.2

Plasterer, Skilled, Foreign

120.00

75.00

94.17

85.83

110.00

60.00

87.00

80.00

100.00

60.00

80.00

80.00

4.2.1

Plasterer, Semi-skilled, Local

107.00

70.00

84.50

78.33

105.00

55.00

78.50

74.50

95.00

50.00

72.20

72.20

4.2.2

Plasterer, Semi-skilled,Foreign

95.00

55.00

75.83

69.17

80.00

45.00

63.00

62.00

70.00

40.00

55.80

55.80

Tiler

5.1.1

Tiler, Skilled, Local

120.00

90.00

104.17

98.33

150.00

80.00

116.00

115.00

135.00

90.00

106.70

106.70

5.1.2

Tiler, Skilled, Foreign

100.00

75.00

83.33

76.67

120.00

65.00

91.00

86.00

125.00

55.00

78.30

77.30

5.2.1

Tiler, Semi-skilled, Local

100.00

65.00

78.33

74.17

120.00

55.00

93.50

91.00

115.00

60.00

83.00

83.00

5.2.2

Tiler, Semi-Skilled, Foreign

86.00

55.00

65.67

58.33

100.00

50.00

69.00

67.00

85.00

40.00

57.30

57.30

Barbender

6.1.1

Barbender, Skilled,Local

120.00

77.00

94.00

92.00

130.00

75.00

106.00

104.50

120.00

75.00

96.00

96.00

6.1.2

Barbender,Skilled, Foreign

85.00

55.00

69.33

73.33

110.00

60.00

84.50

79.50

105.00

55.00

73.90

72.90

6.2.1

Barbender,Semi-skilled, Local

85.00

55.00

71.00

75.00

100.00

55.00

77.50

75.00

85.00

50.00

68.00

68.00

6.2.2

Barbender, Semi-skilled, Foreign

65.50

39.00

53.25

57.58

90.00

50.00

65.00

65.00

65.00

38.00

52.30

52.30

Carpenter-Formwork

7.1.1

Carpenter-Formwork, Skiiled, Local

160.00

85.00

122.50

122.50

140.00

75.00

109.00

101.00

150.00

80.00

99.80

99.80

7.1.2

Carpenter-Formwork,Skilled, Foreign

95.00

65.00

81.67

80.00

110.00

55.00

84.00

79.00

90.00

50.00

72.50

72.50

7.2.1

Carpenter-Formwork, Semi-skilled, Local

90.00

60.00

77.50

79.17

100.00

55.00

77.00

74.50

80.00

50.00

66.50

66.50

7.2.2

Carpenter-Formwork, Semi-skilled,Foreign

85.00

45.00

60.00

63.33

90.00

45.00

65.50

63.00

70.00

45.00

55.50

55.50

2.1 WAGE RATES OF CONSTRUCTION WORKERS JANUARY 2014 (DAILY) / KADAR UPAH PEKERJA BINAAN JANUARI 2014 (HARIAN)

SEMENANJUNG
NO.

CATEGORY OF WORKERS / KATEGORI PEKERJA

PERAK
Maximum

Minimum

RM

RM

SELANGOR

Common
Jan 14
RM

Common
July 13
RM

Maximum

Minimum

RM

RM

KUALA LUMPUR

Common
Jan 14
RM

Common
July 13
RM

Maximum

Minimum

RM

RM

Common
Jan 14
RM

Common
July 13
RM

Carpenter-Joinery

8.1.1

Carpenter-Joinery, Skilled, Local

140.00

115.00

127.50

126.67

140.00

75.00

117.50

116.50

140.00

85.00

108.00

108.00

8.1.2

Carpenter-Joinery, Skilled,Foreign

115.00

80.00

99.17

98.33

120.00

60.00

87.50

86.50

110.00

55.00

79.00

79.00

8.2.1

Carpenter-Joinery,Semi-skilled, Local

110.00

90.00

102.50

101.67

115.00

60.00

81.00

80.00

100.00

50.00

70.50

70.50

8.2.2

Carpenter-Joinery, Semi-Skilled, Foreign

95.00

65.00

79.17

79.17

90.00

40.00

63.50

61.50

90.00

40.00

60.00

60.00

Roofer

9.1.1

Roofer, Skilled, Local

120.00

80.00

95.83

95.83

140.00

70.00

103.00

100.00

120.00

90.00

104.00

104.00

9.1.2

Roofer,Skilled, Foreign

96.00

70.00

83.17

82.50

115.00

50.00

78.50

75.50

100.00

55.00

79.50

79.50

9.2.1

Roofer,Semi-skiiled, Local

90.00

60.00

76.33

75.83

100.00

55.00

75.00

72.70

85.00

55.00

73.50

73.50

9.2.2

Roofer, Skilled, Foreign

80.00

50.00

66.83

66.67

80.00

45.00

55.00

54.50

70.00

45.00

58.50

58.50

10

Steel Structure Fabricator

10.1.1 Steel Structure Fabricator, Skilled, Local

130.00

90.00

108.33

105.00

160.00

75.00

110.50

107.00

145.00

100.00

121.50

121.50

10.1.2 Steel Structure Fabricator, Skilled, Foreign

100.00

72.00

88.17

88.00

120.00

65.00

84.70

82.70

110.00

60.00

88.50

88.50

10.2.1 Steel Structure Fabricator, Semi-Skilled, Local

95.00

72.00

84.00

83.67

115.00

50.00

79.50

75.50

105.00

55.00

82.00

82.00

10.2.2 Steel Structure Fabricator, Semi-skilled, Foreign

85.00

48.00

70.00

69.17

90.00

45.00

65.50

61.50

80.00

45.00

60.20

60.20

11

General Welder
100.00

65.00

84.17

84.17

190.00

95.00

127.50

123.50

145.00

90.00

115.50

115.50

11.1.2 General Welder, Skilled, Foreign

88.00

55.00

76.67

75.83

150.00

65.00

97.00

93.50

105.00

55.00

78.50

78.50

11.2.1 General Welder, Semi-skilled, Local

75.00

55.00

65.50

64.17

135.00

65.00

87.50

86.50

95.00

50.00

68.50

68.50

11.2.2 General Welder, Semi-skilled, Foreign

68.00

50.00

57.17

58.00

100.00

55.00

74.00

68.00

75.00

45.00

55.00

55.00

11.1.1 General Welder, Skilled, Local

12

Plumber-Building & Sanitary


105.00

75.00

90.00

89.17

160.00

80.00

113.50

110.50

140.00

85.00

105.50

105.50

12.1.2 Plumber-Building & Sanitary, Skilled, Foreign

85.00

50.00

66.00

65.83

110.00

60.00

77.50

81.00

100.00

60.00

73.50

73.50

12.2.1 Plumber-Building & Sanitary, Semi-skilled, Local

80.00

55.00

68.17

69.67

100.00

55.00

71.00

75.50

105.00

55.00

71.80

71.80

12.2.2 Plumber-Building & Sanitary, Semi-skilled, Foreign

60.00

40.00

49.83

51.33

80.00

45.00

57.00

60.00

90.00

40.00

54.00

54.00

12.1.1 Plumber-Building & Sanitary, Skilled, Local

13

Plumber-Reticulation
100.00

75.00

83.83

83.33

150.00

80.00

105.00

104.00

150.00

75.00

104.50

104.50

13.1.2 Plumber-Reticulation, Skilled, Foreign

75.00

55.00

61.00

64.17

100.00

60.00

80.50

76.00

100.00

60.00

79.00

79.00

13.2.1 Plumber-Reticulation, Semi-skilled, Local

80.00

60.00

71.83

71.00

105.00

50.00

79.00

74.50

100.00

50.00

70.70

70.70

13.2.2 plumber-reticulation, semi-skilled, foreign

60.00

40.00

48.33

50.00

85.00

50.00

68.50

67.00

85.00

40.00

57.50

57.50

14.1.1 Building Wiring Installer, Semi-skilled, Local

90.00

60.00

72.50

71.67

130.00

75.00

102.50

98.50

120.00

70.00

87.50

87.50

14.2.1 Building Wiring Installer, Semi-skilled, Foreign

77.00

45.00

57.00

55.50

110.00

55.00

80.50

77.50

100.00

45.00

66.00

66.00

13.1.1 Plumber-Reticulation, Skilled, Local

14

Building Wiring Installer

2.1 WAGE RATES OF CONSTRUCTION WORKERS JANUARY 2014 (DAILY) / KADAR UPAH PEKERJA BINAAN JANUARI 2014 (HARIAN)

SEMENANJUNG
NO.

CATEGORY OF WORKERS / KATEGORI PEKERJA

PERAK

SELANGOR

Common
Jan 14
RM

Maximum

Minimum

RM

RM

15.1.1 Electrical Wireman PW2, Skilled, Local

2760.00

1400.00

2038.33

15.2.1 Electrical Wireman PW2, Skilled, Foreign

2450.00

1100.00

1758.33

16.1.1 Electrical Wireman PW4, Skilled, Local

3380.00

2300.00

16.2.1 Elactrical Wireman PW4, Skilled, Foreign

3200.00

2300.00

17.1.1 Scaffolder - Prefabricated, Skilled, Local

150.00

17.1.2 Scaffolder - Prefabricated, Skilled, Foreign

120.00

17.2.1 Scaffolder - Prefabricated, Semi-skilled, Local


17.2.2 Scaffolder - Prefabricated,Semi-skilled, Foreign

15

16

17

18

Common
July 13
RM

KUALA LUMPUR

Common
Jan 14
RM

Maximum

Minimum

RM

RM

2000.00

4300.00

2200.00

3181.00

1741.67

3700.00

1550.00

2320.00

2913.33

2825.00

4500.00

2500.00

2653.33

2550.00

4000.00

1800.00

110.00

128.33

128.33

135.00

85.00

101.67

101.67

120.00

95.00

65.00

80.00

80.00

75.00

55.00

64.17

Common
July 13
RM

Common
Jan 14
RM

Common
July 13
RM

Maximum

Minimum

RM

RM

3154.00

4200.00

1800.00

3000.00

3000.00

2255.00

3600.00

1400.00

2205.00

2205.00

3555.00

3545.00

4350.00

2250.00

3259.70

3259.70

2525.00

2390.00

3750.00

1850.00

2600.80

2600.80

80.00

103.00

99.50

130.00

95.00

109.50

109.50

65.00

85.00

82.50

115.00

65.00

83.50

83.50

115.00

60.00

80.50

78.00

110.00

60.00

79.30

79.30

64.17

100.00

50.00

65.00

62.00

95.00

45.00

63.30

63.30

Electrical Wireman PW2 (Monthly Salary)

Electrical Wireman PW4 (Monthly Salary)

Scaffolder - Prefabricated

Scaffolder - Tubular
130.00

75.00

91.17

88.33

120.00

80.00

98.50

98.00

115.00

75.00

96.50

96.50

18.1.2 Scaffolder - Tubular, Skilled, Foreign

95.00

60.00

75.00

74.17

100.00

60.00

79.50

78.00

95.00

60.00

77.70

77.70

18.2.1 Scaffolder - Tubular, Semi-skilled, Local

87.00

55.00

70.33

70.00

95.00

55.00

76.00

76.50

90.00

50.00

68.70

68.70

18.2.2 Scaffolder - Tubular, Semi-skilled, Foreign

65.00

45.00

55.83

57.50

80.00

40.00

59.50

60.00

70.00

40.00

56.30

56.30

18.1.1 Scaffolder - Tubular, Skilled, Local

19

Painter - Building
100.00

70.00

84.17

84.17

130.00

80.00

101.50

99.50

130.00

75.00

93.50

93.50

19.1.2 Painter - Building, Skilled, Foreign

85.00

55.00

69.33

66.67

95.00

55.00

82.00

75.50

115.00

65.00

77.50

77.50

19.2.1 Painter - Building, Semi-skilled, Local

82.00

50.00

64.33

60.00

90.00

55.00

78.00

74.50

95.00

50.00

65.60

65.60

19.2.2 Painter - Building, Semi- skilled, Foreign

70.00

45.00

55.67

53.33

70.00

50.00

61.00

58.00

75.00

40.00

54.20

54.20

20.1.1 General Construction Worker - Civil, Local

95.00

35.00

69.17

68.33

100.00

55.00

76.50

74.50

80.00

45.00

60.00

60.00

20.1.2 General Construction Worker - Civil, Foreign

85.00

35.00

57.00

50.00

75.00

50.00

59.00

55.00

60.00

40.00

49.50

49.50

19.1.1 Painter - Building, Skilled, Local

20

General Construction Worker - Civil (Helper)

2.1 WAGE RATES OF CONSTRUCTION WORKERS JANUARY 2014 (DAILY) / KADAR UPAH PEKERJA BINAAN JANUARI 2014 (HARIAN)

NO.

CATEGORY OF WORKERS / KATEGORI PEKERJA

SEMENANJUNG

NEGERI SEMBILAN
Maximum

Minimum

RM

RM

Common
Jan 14
RM

MELAKA

Common
July 13
RM

Maximum

Minimum

RM

RM

Common
Jan 14
RM

JOHOR
Common
July 13
RM

Maximum

Minimum

RM

RM

Common
Jan 14
RM

Common
July 13
RM

General construction worker - building (helper)

1.1.1

General constr. worker Building, Local (helper)

78.00

61.00

69.17

68.17

120.00

40.00

72.50

56.17

90.00

55.00

70.00

67.30

1.1.2

General constr. worker Building,Foreign (helper)

68.00

47.00

57.50

56.50

100.00

40.00

60.83

50.00

75.00

38.00

54.80

54.30

Concretor

2.1.1

Concretor, Skilled, Local

92.00

69.00

84.00

83.00

150.00

45.00

92.50

85.00

110.00

60.00

82.50

80.00

2.1.2

Concretor, Skilled, Foreign

89.00

68.00

80.67

79.67

120.00

40.00

73.33

67.50

92.00

45.00

63.20

62.00

2.2.1

Concretor, Semi-skilled,Local

83.00

67.00

76.67

75.67

120.00

45.00

75.83

59.50

78.00

50.00

63.80

62.80

2.2.2

Concretor, Semi-skilled, Foreign

76.00

59.00

67.00

66.00

100.00

40.00

59.17

46.67

68.00

40.00

54.80

54.10

Bricklayer

3.1.1

Bricklayer, Skilled, Local

92.00

83.00

88.50

87.50

160.00

45.00

94.17

84.17

120.00

70.00

92.00

88.50

3.1.2

Bricklayer,Skilled, Foreign

88.00

71.00

81.00

80.00

120.00

40.00

73.33

68.33

110.00

60.00

77.00

73.80

3.2.1

Bricklayer,Semi-skilled, Local

77.00

68.00

74.00

73.00

120.00

45.00

76.67

58.33

95.00

58.00

70.80

69.20

3.2.2

Bricklayer, Semi-skilled, Foreign

71.00

59.00

66.33

65.33

100.00

40.00

61.67

50.00

65.00

40.00

51.00

50.00

Plasterer

4.1.1

Plasterer, Skilled, Local

92.00

86.00

89.00

88.00

150.00

45.00

93.33

92.50

110.00

70.00

88.50

87.00

4.1.2

Plasterer, Skilled, Foreign

81.00

75.00

78.00

77.00

140.00

40.00

76.67

71.67

90.00

45.00

64.50

63.50

4.2.1

Plasterer, Semi-skilled, Local

80.00

74.00

77.00

76.00

135.00

45.00

77.50

62.50

85.00

48.00

65.60

65.60

4.2.2

Plasterer, Semi-skilled,Foreign

70.00

62.00

65.00

64.00

95.00

40.00

57.50

48.33

70.00

40.00

52.80

52.80

Tiler

5.1.1

Tiler, Skilled, Local

102.00

95.00

98.50

97.50

130.00

90.00

106.67

96.67

135.00

75.00

100.00

98.00

5.1.2

Tiler, Skilled, Foreign

95.00

79.00

89.00

88.00

105.00

70.00

85.00

73.83

105.00

60.00

80.50

78.50

5.2.1

Tiler, Semi-skilled, Local

91.00

74.00

84.00

83.00

100.00

55.00

75.50

61.33

95.00

60.00

73.80

72.30

5.2.2

Tiler, Semi-Skilled, Foreign

81.00

61.00

72.17

71.17

90.00

40.00

58.33

48.33

75.00

50.00

59.50

57.50

Barbender

6.1.1

Barbender, Skilled,Local

98.00

78.00

88.17

87.17

130.00

60.00

98.33

82.17

120.00

75.00

90.50

90.50

6.1.2

Barbender,Skilled, Foreign

82.00

71.00

77.33

76.33

120.00

55.00

77.50

65.83

100.00

55.00

73.00

72.00

6.2.1

Barbender,Semi-skilled, Local

81.00

68.00

74.67

73.67

105.00

45.00

72.50

63.00

80.00

52.00

65.00

64.20

6.2.2

Barbender, Semi-skilled, Foreign

71.00

54.00

62.33

61.33

80.00

40.00

55.00

50.67

70.00

45.00

56.00

55.50

Carpenter-Formwork

7.1.1

Carpenter-Formwork, Skiiled, Local

100.00

87.00

94.33

93.33

120.00

90.00

105.83

95.00

110.00

75.00

91.50

89.50

7.1.2

Carpenter-Formwork,Skilled, Foreign

91.00

74.00

82.17

81.17

115.00

65.00

87.50

75.00

95.00

70.00

80.00

77.30

7.2.1

Carpenter-Formwork, Semi-skilled, Local

90.00

74.00

80.83

79.83

90.00

50.00

65.83

58.33

85.00

50.00

63.80

62.80

7.2.2

Carpenter-Formwork, Semi-skilled,Foreign

81.00

70.00

75.00

74.00

70.00

40.00

53.33

49.17

70.00

45.00

54.00

54.00

2.1 WAGE RATES OF CONSTRUCTION WORKERS JANUARY 2014 (DAILY) / KADAR UPAH PEKERJA BINAAN JANUARI 2014 (HARIAN)

NO.

CATEGORY OF WORKERS / KATEGORI PEKERJA

SEMENANJUNG

NEGERI SEMBILAN
Maximum

Minimum

RM

RM

Common
Jan 14
RM

MELAKA

Common
July 13
RM

Maximum

Minimum

RM

RM

Common
Jan 14
RM

JOHOR
Common
July 13
RM

Maximum

Minimum

RM

RM

Common
Jan 14
RM

Common
July 13
RM

Carpenter-Joinery

8.1.1

Carpenter-Joinery, Skilled, Local

102.00

99.00

100.67

99.67

145.00

95.00

111.67

101.50

130.00

75.00

103.00

101.00

8.1.2

Carpenter-Joinery, Skilled,Foreign

98.00

89.00

94.17

93.17

135.00

72.00

93.17

75.67

100.00

58.00

80.80

78.80

8.2.1

Carpenter-Joinery,Semi-skilled, Local

93.00

83.00

87.33

86.33

100.00

50.00

72.50

59.17

95.00

55.00

74.00

72.50

8.2.2

Carpenter-Joinery, Semi-Skilled, Foreign

87.00

73.00

80.67

79.67

80.00

40.00

55.00

47.83

80.00

45.00

59.50

59.50

Roofer

9.1.1

Roofer, Skilled, Local

102.00

99.00

100.50

99.50

130.00

85.00

99.17

91.67

120.00

65.00

89.00

88.70

9.1.2

Roofer,Skilled, Foreign

96.00

88.00

90.83

89.83

105.00

65.00

82.50

73.33

105.00

50.00

70.00

68.80

9.2.1

Roofer,Semi-skiiled, Local

91.00

78.00

82.50

81.50

100.00

55.00

73.33

63.33

90.00

48.00

66.80

66.30

9.2.2

Roofer, Skilled, Foreign

81.00

66.00

72.33

71.33

60.00

40.00

59.17

51.33

80.00

40.00

56.00

54.80

10

Steel Structure Fabricator

10.1.1 Steel Structure Fabricator, Skilled, Local

111.00

98.00

105.17

104.17

110.00

80.00

91.67

95.83

120.00

80.00

96.50

95.00

10.1.2 Steel Structure Fabricator, Skilled, Foreign

101.00

93.00

98.33

97.33

95.00

70.00

78.33

78.33

110.00

55.00

79.00

77.00

10.2.1 Steel Structure Fabricator, Semi-Skilled, Local

97.00

86.00

89.67

88.67

75.00

50.00

67.50

70.83

100.00

55.00

74.00

74.00

10.2.2 Steel Structure Fabricator, Semi-skilled, Foreign

91.00

69.00

78.67

77.67

60.00

40.00

50.83

52.00

80.00

40.00

55.50

55.50

11.1.1 General Welder, Skilled, Local

104.00

93.00

98.67

97.67

120.00

65.00

85.00

74.17

125.00

90.00

107.00

108.50

11.1.2 General Welder, Skilled, Foreign

100.00

87.00

93.00

92.00

95.00

54.00

69.00

60.67

95.00

55.00

74.50

75.50

11.2.1 General Welder, Semi-skilled, Local

92.00

83.00

87.33

86.33

80.00

46.00

62.50

56.67

90.00

55.00

72.50

73.50

11.2.2 General Welder, Semi-skilled, Foreign

85.00

74.00

79.50

78.50

75.00

38.00

48.17

44.00

80.00

45.00

58.50

58.50

12.1.1 Plumber-Building & Sanitary, Skilled, Local

92.00

85.00

89.00

88.00

105.00

80.00

90.00

85.00

115.00

70.00

92.00

92.00

12.1.2 Plumber-Building & Sanitary, Skilled, Foreign

88.00

73.00

80.33

79.33

95.00

60.00

72.50

70.00

95.00

55.00

70.00

70.00

12.2.1 Plumber-Building & Sanitary, Semi-skilled, Local

83.00

70.00

76.50

75.50

80.00

45.00

67.50

56.67

80.00

50.00

62.30

62.30

12.2.2 Plumber-Building & Sanitary, Semi-skilled, Foreign

73.00

66.00

69.17

68.17

75.00

40.00

50.83

47.83

65.00

40.00

50.50

50.50

13.1.1 Plumber-Reticulation, Skilled, Local

118.00

103.00

109.67

108.67

100.00

75.00

85.83

84.17

150.00

75.00

97.00

97.00

13.1.2 Plumber-Reticulation, Skilled, Foreign

101.00

92.00

97.33

96.33

80.00

55.00

70.00

66.33

95.00

45.00

67.50

67.50

13.2.1 Plumber-Reticulation, Semi-skilled, Local

100.00

91.00

95.67

94.67

70.00

50.00

57.83

58.67

90.00

55.00

67.50

67.50

13.2.2 plumber-reticulation, semi-skilled, foreign

88.00

74.00

80.50

79.50

55.00

40.00

44.33

46.33

75.00

45.00

55.30

55.30

14.1.1 Building Wiring Installer, Semi-skilled, Local

107.00

99.00

102.67

101.67

125.00

50.00

74.17

58.33

105.00

70.00

88.50

88.50

14.2.1 Building Wiring Installer, Semi-skilled, Foreign

100.00

91.00

95.33

94.33

100.00

40.00

60.00

51.67

90.00

55.00

71.00

71.00

11

12

13

14

General Welder

Plumber-Building & Sanitary

Plumber-Reticulation

Building Wiring Installer

2.1 WAGE RATES OF CONSTRUCTION WORKERS JANUARY 2014 (DAILY) / KADAR UPAH PEKERJA BINAAN JANUARI 2014 (HARIAN)

NO.

CATEGORY OF WORKERS / KATEGORI PEKERJA

Common
Jan 14
RM

Maximum

Minimum

RM

RM

15.1.1 Electrical Wireman PW2, Skilled, Local

2403.00

2142.00

2326.17

15.2.1 Electrical Wireman PW2, Skilled, Foreign

2003.00

1703.00

1843.00

16.1.1 Electrical Wireman PW4, Skilled, Local

3203.00

2870.00

16.2.1 Elactrical Wireman PW4, Skilled, Foreign

2553.00

2203.00

17.1.1 Scaffolder - Prefabricated, Skilled, Local

95.00

17.1.2 Scaffolder - Prefabricated, Skilled, Foreign

91.00

17.2.1 Scaffolder - Prefabricated, Semi-skilled, Local


17.2.2 Scaffolder - Prefabricated,Semi-skilled, Foreign

15

16

17

18

SEMENANJUNG

NEGERI SEMBILAN

MELAKA

Common
July 13
RM

Common
Jan 14
RM

Maximum

Minimum

RM

RM

2325.17

3500.00

1400.00

2075.00

1842.00

2800.00

1000.00

1635.00

2997.50

2996.50

3500.00

1500.00

2380.00

2379.00

2800.00

1000.00

80.00

87.50

86.50

180.00

74.00

82.33

81.33

140.00

83.00

71.00

76.00

75.00

81.00

65.00

72.33

JOHOR
Common
July 13
RM

Common
Jan 14
RM

Common
July 13
RM

Maximum

Minimum

RM

RM

1816.67

4530.00

1950.00

2853.00

2853.00

1526.67

2750.00

1500.00

2070.00

2070.00

2241.67

2208.33

5250.00

2800.00

3770.00

3770.00

1725.00

1683.33

3200.00

1800.00

2465.00

2465.00

80.00

94.17

90.83

120.00

80.00

101.00

101.00

75.00

90.00

75.50

100.00

65.00

82.50

82.50

120.00

60.00

77.17

67.17

100.00

60.00

83.00

83.00

71.33

100.00

50.00

63.67

56.17

90.00

50.00

66.70

66.70

Electrical Wireman PW2 (Monthly Salary)

Electrical Wireman PW4 (Monthly Salary)

Scaffolder - Prefabricated

Scaffolder - Tubular
100.00

88.00

95.67

94.67

130.00

90.00

102.83

95.33

115.00

75.00

93.50

93.50

18.1.2 Scaffolder - Tubular, Skilled, Foreign

92.00

71.00

82.67

81.67

115.00

65.00

83.33

74.17

95.00

60.00

76.00

76.00

18.2.1 Scaffolder - Tubular, Semi-skilled, Local

87.00

67.00

76.17

75.17

90.00

60.00

76.67

71.67

90.00

60.00

75.80

75.80

18.2.2 Scaffolder - Tubular, Semi-skilled, Foreign

78.00

63.00

68.00

67.00

80.00

45.00

62.50

57.50

75.00

40.00

59.50

59.50

19.1.1 Painter - Building, Skilled, Local

87.00

73.00

81.00

80.00

125.00

45.00

95.00

85.33

120.00

60.00

88.00

88.00

19.1.2 Painter - Building, Skilled, Foreign

78.00

67.00

72.83

71.83

85.00

40.00

80.83

70.83

90.00

50.00

66.00

66.00

19.2.1 Painter - Building, Semi-skilled, Local

77.00

66.00

71.50

70.50

75.00

45.00

70.83

65.83

90.00

55.00

67.50

67.50

19.2.2 Painter - Building, Semi- skilled, Foreign

71.00

56.00

62.00

61.00

65.00

40.00

56.67

51.67

70.00

40.00

51.80

51.60

20.1.1 General Construction Worker - Civil, Local

79.00

73.00

75.50

74.50

120.00

45.00

67.00

55.00

85.00

55.00

66.50

66.50

20.1.2 General Construction Worker - Civil, Foreign

67.00

59.00

64.17

63.17

90.00

40.00

58.33

45.83

65.00

38.00

50.30

50.30

18.1.1 Scaffolder - Tubular, Skilled, Local

19

20

Painter - Building

General Construction Worker - Civil (Helper)

2.1 WAGE RATES OF CONSTRUCTION WORKERS JANUARY 2014 (DAILY) / KADAR UPAH PEKERJA BINAAN JANUARI 2014 (HARIAN)

SEMENANJUNG
NO.

CATEGORY OF WORKERS / KATEGORI PEKERJA

PAHANG
Maximum

Minimum

RM

RM

KELANTAN

Common
Jan 14
RM

Common
July 13
RM

Maximum

Minimum

RM

RM

Common
Jan 14
RM

TERENGGANU
Common
July 13
RM

Maximum

Minimum

RM

RM

Common
Jan 14
RM

Common
July 13
RM

General construction worker - building (helper)

1.1.1

General constr. worker Building, Local (helper)

70.00

45.00

59.50

58.33

69.00

60.00

64.83

63.83

73.00

61.00

66.83

65.83

1.1.2

General constr. worker Building,Foreign (helper)

65.00

40.00

47.50

47.50

64.00

52.00

56.33

55.33

67.00

48.00

57.33

56.33

Concretor

2.1.1

Concretor, Skilled, Local

80.00

50.00

66.67

65.83

88.00

71.00

80.83

79.83

92.00

78.00

86.33

85.33

2.1.2

Concretor, Skilled, Foreign

70.00

45.00

57.00

56.17

80.00

68.00

74.17

73.17

83.00

73.00

78.50

77.50

2.2.1

Concretor, Semi-skilled,Local

65.00

45.00

54.67

54.33

78.00

60.00

70.17

69.17

76.00

63.00

70.50

69.50

2.2.2

Concretor, Semi-skilled, Foreign

55.00

40.00

45.83

46.67

71.00

52.00

61.00

60.00

71.00

48.00

63.67

62.67

Bricklayer

3.1.1

Bricklayer, Skilled, Local

90.00

70.00

78.67

78.33

85.00

79.00

82.17

81.17

86.00

76.00

80.50

79.50

3.1.2

Bricklayer,Skilled, Foreign

80.00

50.00

67.50

65.50

79.00

73.00

76.50

75.50

86.00

66.00

75.00

74.00

3.2.1

Bricklayer,Semi-skilled, Local

75.00

55.00

62.83

63.67

77.00

65.00

70.50

69.50

76.00

64.00

69.00

68.00

3.2.2

Bricklayer, Semi-skilled, Foreign

65.00

40.00

48.33

49.17

67.00

58.00

63.17

62.17

71.00

56.00

62.50

61.50

Plasterer

4.1.1

Plasterer, Skilled, Local

90.00

70.00

80.00

78.67

86.00

78.00

82.33

81.33

88.00

78.00

81.33

80.33

4.1.2

Plasterer, Skilled, Foreign

80.00

55.00

65.83

65.00

79.00

70.00

75.33

74.33

77.00

71.00

75.17

74.17

4.2.1

Plasterer, Semi-skilled, Local

75.00

55.00

63.33

62.50

77.00

68.00

72.83

71.83

76.00

67.00

71.00

70.00

4.2.2

Plasterer, Semi-skilled,Foreign

60.00

40.00

47.50

50.00

68.00

63.00

65.67

64.67

74.00

61.00

65.50

64.50

Tiler

5.1.1

Tiler, Skilled, Local

115.00

90.00

104.17

102.67

91.00

86.00

89.00

88.00

97.00

85.00

91.00

90.00

5.1.2

Tiler, Skilled, Foreign

85.00

50.00

78.33

77.50

88.00

75.00

80.67

79.67

90.00

76.00

83.17

82.17

5.2.1

Tiler, Semi-skilled, Local

85.00

60.00

68.33

67.50

81.00

65.00

75.17

74.17

89.00

73.00

80.67

79.67

5.2.2

Tiler, Semi-Skilled, Foreign

60.00

38.00

48.83

52.50

75.00

63.00

68.00

67.00

74.00

66.00

71.00

70.00

Barbender

6.1.1

Barbender, Skilled,Local

80.00

68.00

72.67

71.00

81.00

75.00

78.67

77.67

90.00

76.00

83.00

82.00

6.1.2

Barbender,Skilled, Foreign

75.00

50.00

61.33

61.33

72.00

65.00

69.67

69.00

79.00

73.00

77.17

76.17

6.2.1

Barbender,Semi-skilled, Local

70.00

50.00

59.17

58.00

70.00

63.00

67.00

66.00

77.00

64.00

69.50

68.50

6.2.2

Barbender, Semi-skilled, Foreign

55.00

40.00

45.83

46.67

67.00

49.00

59.50

58.50

66.00

53.00

59.33

58.33

Carpenter-Formwork

7.1.1

Carpenter-Formwork, Skiiled, Local

100.00

65.00

80.50

75.50

89.00

81.00

86.33

85.33

92.00

85.00

88.17

87.17

7.1.2

Carpenter-Formwork,Skilled, Foreign

80.00

55.00

67.83

67.00

85.00

74.00

79.50

78.50

85.00

73.00

79.00

78.00

7.2.1

Carpenter-Formwork, Semi-skilled, Local

70.00

48.00

58.83

58.33

83.00

74.00

77.50

76.50

81.00

72.00

76.50

75.50

7.2.2

Carpenter-Formwork, Semi-skilled,Foreign

60.00

40.00

47.50

50.00

77.00

65.00

69.17

68.17

79.00

66.00

70.17

69.17

10

2.1 WAGE RATES OF CONSTRUCTION WORKERS JANUARY 2014 (DAILY) / KADAR UPAH PEKERJA BINAAN JANUARI 2014 (HARIAN)

SEMENANJUNG
NO.

CATEGORY OF WORKERS / KATEGORI PEKERJA

PAHANG
Maximum

Minimum

RM

RM

KELANTAN

Common
Jan 14
RM

Common
July 13
RM

Maximum

Minimum

RM

RM

Common
Jan 14
RM

TERENGGANU
Common
July 13
RM

Maximum

Minimum

RM

RM

Common
Jan 14
RM

Common
July 13
RM

Carpenter-Joinery

8.1.1

Carpenter-Joinery, Skilled, Local

100.00

70.00

83.33

80.83

95.00

90.00

93.00

92.00

96.00

91.00

93.33

92.33

8.1.2

Carpenter-Joinery, Skilled,Foreign

92.00

60.00

72.00

69.17

89.00

81.00

85.33

84.33

91.00

83.00

87.00

86.00

8.2.1

Carpenter-Joinery,Semi-skilled, Local

75.00

55.00

63.33

62.50

87.00

79.00

82.50

81.50

88.00

76.00

81.67

80.67

8.2.2

Carpenter-Joinery, Semi-Skilled, Foreign

60.00

45.00

49.17

52.50

78.00

70.00

74.00

73.00

82.00

71.00

75.00

74.00

Roofer

9.1.1

Roofer, Skilled, Local

100.00

70.00

79.83

79.83

95.00

90.00

92.83

91.83

99.00

92.00

95.17

94.17

9.1.2

Roofer,Skilled, Foreign

75.00

60.00

67.17

68.83

84.00

79.00

82.00

81.00

90.00

82.00

85.83

84.83

9.2.1

Roofer,Semi-skiiled, Local

80.00

55.00

63.33

61.67

81.00

73.00

76.83

75.83

83.00

73.00

78.00

77.00

9.2.2

Roofer, Skilled, Foreign

60.00

43.00

52.17

50.50

69.00

64.00

66.67

65.67

73.00

65.00

67.67

66.67

10

Steel Structure Fabricator


100.00

70.00

85.83

81.67

101.00

91.00

97.17

96.17

102.00

96.00

99.50

98.50

10.1.2 Steel Structure Fabricator, Skilled, Foreign

85.00

65.00

72.50

75.00

98.00

85.00

91.00

90.00

98.00

87.00

91.17

90.17

10.2.1 Steel Structure Fabricator, Semi-Skilled, Local

80.00

60.00

67.83

66.17

88.00

75.00

82.67

81.67

92.00

79.00

85.17

84.17

10.2.2 Steel Structure Fabricator, Semi-skilled, Foreign

60.00

40.00

54.17

51.33

83.00

68.00

73.50

72.50

79.00

67.00

73.83

72.83

10.1.1 Steel Structure Fabricator, Skilled, Local

11

General Welder
105.00

80.00

94.50

95.67

96.00

80.00

88.50

87.50

99.00

86.00

93.83

92.83

11.1.2 General Welder, Skilled, Foreign

80.00

55.00

66.67

68.33

91.00

80.00

85.17

84.17

93.00

82.00

87.33

86.33

11.2.1 General Welder, Semi-skilled, Local

75.00

50.00

65.83

65.83

82.00

75.00

78.83

77.83

84.00

73.00

80.50

79.50

11.2.2 General Welder, Semi-skilled, Foreign

60.00

45.00

53.33

52.50

75.00

67.00

72.17

71.17

81.00

68.00

74.83

73.83

11.1.1 General Welder, Skilled, Local

12

Plumber-Building & Sanitary


100.00

70.00

83.33

80.00

89.00

75.00

82.83

81.83

95.00

78.00

85.67

84.67

12.1.2 Plumber-Building & Sanitary, Skilled, Foreign

75.00

50.00

66.67

65.83

78.00

69.00

74.00

73.00

84.00

71.00

76.67

75.67

12.2.1 Plumber-Building & Sanitary, Semi-skilled, Local

70.00

50.00

61.17

63.33

73.00

65.00

70.00

69.00

75.00

66.00

71.00

70.00

12.2.2 Plumber-Building & Sanitary, Semi-skilled, Foreign

60.00

40.00

49.50

50.33

64.00

60.00

62.33

61.33

71.00

61.00

65.50

64.50

12.1.1 Plumber-Building & Sanitary, Skilled, Local

13

Plumber-Reticulation
100.00

65.00

83.33

78.33

106.00

96.00

101.50

100.50

106.00

99.00

102.33

101.33

13.1.2 Plumber-Reticulation, Skilled, Foreign

85.00

50.00

69.17

65.50

96.00

86.00

91.50

90.50

97.00

88.00

92.83

91.83

13.2.1 Plumber-Reticulation, Semi-skilled, Local

78.00

50.00

67.67

66.00

96.00

81.00

88.67

87.67

93.00

86.00

89.83

88.83

13.2.2 plumber-reticulation, semi-skilled, foreign

60.00

40.00

47.50

49.17

86.00

70.00

77.17

76.17

88.00

71.00

77.17

76.17

100.00

70.00

85.83

80.00

98.00

91.00

94.33

93.33

99.00

94.00

96.50

95.50

75.00

50.00

63.33

61.67

96.00

81.00

88.67

87.67

95.00

83.00

89.50

88.50

13.1.1 Plumber-Reticulation, Skilled, Local

14

Building Wiring Installer

14.1.1 Building Wiring Installer, Semi-skilled, Local


14.2.1 Building Wiring Installer, Semi-skilled, Foreign

11

2.1 WAGE RATES OF CONSTRUCTION WORKERS JANUARY 2014 (DAILY) / KADAR UPAH PEKERJA BINAAN JANUARI 2014 (HARIAN)

SEMENANJUNG
NO.

CATEGORY OF WORKERS / KATEGORI PEKERJA

PAHANG

KELANTAN

Common
Jan 14
RM

Maximum

Minimum

RM

RM

15.1.1 Electrical Wireman PW2, Skilled, Local

2600.00

1600.00

2083.33

15.2.1 Electrical Wireman PW2, Skilled, Foreign

1900.00

1250.00

1633.33

16.1.1 Electrical Wireman PW4, Skilled, Local

2800.00

1950.00

16.2.1 Elactrical Wireman PW4, Skilled, Foreign

2500.00

1620.00

17.1.1 Scaffolder - Prefabricated, Skilled, Local

95.00

17.1.2 Scaffolder - Prefabricated, Skilled, Foreign

85.00

17.2.1 Scaffolder - Prefabricated, Semi-skilled, Local


17.2.2 Scaffolder - Prefabricated,Semi-skilled, Foreign

15

16

17

18

Common
July 13
RM

Common
Jan 14
RM

Maximum

Minimum

RM

RM

2066.67

2269.00

1857.00

2089.67

1620.00

1857.00

1503.00

1671.50

2325.00

2308.33

2903.00

2603.00

2006.67

1995.00

2503.00

1925.00

70.00

81.67

80.33

88.00

55.00

68.33

67.17

79.00

70.00

50.00

59.50

61.17

65.00

45.00

48.33

TERENGGANU
Common
July 13
RM

Common
Jan 14
RM

Common
July 13
RM

Maximum

Minimum

RM

RM

2088.67

2503.00

1894.00

2150.67

2149.67

1670.50

1993.00

1579.00

1781.67

1780.67

2773.00

2772.00

2970.00

2631.00

2791.83

2790.83

2181.67

2180.67

2803.00

1894.00

2213.33

2212.33

78.00

81.00

80.00

100.00

77.00

85.33

84.33

68.00

73.50

72.50

84.00

73.00

76.83

75.83

73.00

63.00

69.33

68.33

75.00

66.00

70.33

69.33

52.50

68.00

60.00

65.17

64.17

74.00

65.00

69.17

68.17

Electrical Wireman PW2 (Monthly Salary)

Electrical Wireman PW4 (Monthly Salary)

Scaffolder - Prefabricated

Scaffolder - Tubular
100.00

70.00

85.00

83.33

92.00

79.00

84.33

83.33

91.00

85.00

88.00

87.00

18.1.2 Scaffolder - Tubular, Skilled, Foreign

90.00

55.00

73.33

73.33

81.00

64.00

73.50

72.50

82.00

69.00

76.00

75.00

18.2.1 Scaffolder - Tubular, Semi-skilled, Local

80.00

55.00

66.67

66.67

71.00

64.00

68.50

67.50

74.00

67.00

70.00

69.00

18.2.2 Scaffolder - Tubular, Semi-skilled, Foreign

65.00

45.00

50.00

54.17

68.00

55.00

61.50

60.50

67.00

59.00

63.83

62.83

18.1.1 Scaffolder - Tubular, Skilled, Local

19

Painter - Building
100.00

75.00

85.00

77.50

80.00

73.00

77.17

76.17

81.00

68.00

75.33

74.33

19.1.2 Painter - Building, Skilled, Foreign

75.00

50.00

61.67

61.67

71.00

66.00

68.00

67.00

75.00

63.00

68.33

67.33

19.2.1 Painter - Building, Semi-skilled, Local

70.00

50.00

62.50

58.83

69.00

60.00

65.50

64.50

72.00

63.00

66.83

65.83

19.2.2 Painter - Building, Semi- skilled, Foreign

55.00

40.00

47.50

47.50

59.00

51.00

56.17

55.17

63.00

53.00

57.17

56.17

20.1.1 General Construction Worker - Civil, Local

70.00

45.00

55.00

54.17

69.00

63.00

66.33

65.33

80.00

63.00

70.50

69.50

20.1.2 General Construction Worker - Civil, Foreign

50.00

40.00

45.00

46.67

59.00

53.00

56.67

55.67

75.00

53.00

61.83

60.83

19.1.1 Painter - Building, Skilled, Local

20

General Construction Worker - Civil (Helper)