S.No.

Dealer Name

Facility Type

City

Tirupati

3S

kanpur

Alcon

3S

Goa

OSL

3S

Cuttack

Aldiam

3S

Vadodara

Rudra

3S

Asansoi

JSV

3S

Lucknow

Abhishek

3S

Chhindwara

Natraj

3S

Jhansi

K.R.

3S

Berhampur

Pace

3S

Jammu

Togo

3S

Leh

AMG Rohtana

3S

Vadakara

Surjeet

3S

Bhopal

Shah

3S

Gulbarga

Rennovation

Status for the month of September


State

S.I Vendor

C.I Vendor

Payment

Item

Uttar Pradesh

HDG

VVT

NA

SI

Goa

HDG

USPL

NA

SI
CI

Odisha

HDG

NGB

NA

SI
CI

Gujrat

HDG

Classic

NA

West Bengal

HDG

NGB

NA

SI
CI
SI
CI

Uttar Pradesh

Geeken

VVT

NA

M.P

HDG

USPL

NA

Uttar Pradesh

HDG

VVT

NA

SI
CI
SI
CI
SI
CI

West Bengal

HDG

NGB

NA

SI
CI

Jammu Kashmir

Geeken

ANS

Jammu Kashmir

HDG

Next Step

Geeken

DDSPL

Madhya Pradesh

Geeken

USPL

karnataka

HDG

DDSPL

Y
Y
Y
Y
Y
Y
N
Y
Y
Y

SI
CI
SI
CI
SI
CI
SI
CI
SI
CI

ember
Dispatch Date

Arrival date

Installtion Date

13-Oct-15

15-Oct-15

20-Oct-15

Completed

Completed
Completed

Completed
Completed
Completed

Completed

Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed

Remarks
CI Finished except entrance gate dealer
is doing civil work for gate and gate will
dispatched on 26th oct. SI installation
complete except chairs and sofa
Waiting for dealer consent on the
amount .
Dealer has not given any consent
on the amount.
production started and dispatch on
4th nov 2015
Dealer has not even started the
civil work and the dealer has not
given on the consent on the
. consent on
Dealer have amount
given the
amount on 22nd october and
material will be dispatched on 2nd
CI completed
nov.
Dealer consent
penidng on the
amount.
Site finished, except the H-Promise
Received consent on 19th october
on SI quotation and material will
dispatched on 1st nov
CI completed
Innocen visited at site on 16th oct.
There are some changes in layout
and we will share the revised
layout by 24th oct.
Completed