Professional Documents
Culture Documents
Vigas Compuestas
Vigas Compuestas
Steel beams are usually used to carry a metal deck-supported concrete slab. In
non-composite construction, the beam does NOT interact structurally with the
slab the slab is simply dead weight. This is because the slab is not adequately
bonded to the beam.
Non-Composite Construction
The word composite means 2 or more different materials. In composite
construction, the slab is adequately bonded to the steel beam by means of
headed shear studs resulting in a composite beam. The concrete acts like a
large flange in compression, while a much greater portion of the steel beam
acts in tension. The result is a VERY efficient beam as much as 40% to 60%
lighter weight steel than non-composite.
Headed shear studs
welded thru metal deck to
beam flange
Composite Construction
Lecture 7 - Page 1 of 10
Comp.
Comp.
N.A
N.A
Ten.
Ten.
Composite Section
Non-Composite Section
Notice that the neutral axis (N.A.) in the non-composite beam is located in the
middle of the section. This indicates that half of the beam section is in tension
and half is in compression.
In the composite section, the compression is carried ENTIRELY by the concrete,
while the tension is carried by the beam.
Composite Design per LRFD
Metal Deck
Shear stud
Ycon
Beam
Lecture 7 - Page 2 of 10
a
Y2
BeamSpan
8
= smaller of
BeamSpacing
2
Distance to edge of slab
As Fy
0.85 f ' c b
As = Cross-sectional area of beam
= from properties
fc = Specified concrete compressive strength
= 4 KSI (usually)
Y2 = Ycon -
a
2
Lecture 7 - Page 3 of 10
Ycon
The best way to see how the design of a composite beam is accomplished is thru
an example problem:
Example 1 (LRFD)
GIVEN: A floor structure using A992 steel beams and the following
superimposed SERVICE loads:
3@8-0 = 24-0
30-0
Beam A
wu = 1.2D + 1.6L
= 1.2[8(63 PSF + 30 PLF)] + 1.6[8(75 PSF)]
= 1601 PLF
= 1.6 KLF
Mu =
wu L2
8
= 180 KIP-FT
Lecture 7 - Page 4 of 10
M u (12" / ft )
0.85Fy 2 + Ycon 2
= 17.28 PLF
From AISC Table 3-19 p. 3-184 TRY W14x22
Step 3 Determine concrete flange force, Qn:
Qn = AsFy
where: As = Area of beam
= 6.49 in2 (from properties for W14x22)
Lecture 7 - Page 5 of 10
BeamSpan
30' (12" / ft )
=
= 45 USE
8
8
BeamSpacing
8' (12" / ft )
=
= 48
2
2
b = smaller of
a
2
where a =
As Fy
0.85 f ' c b
325KIPS
0.85(4 KSI )(45" )
= 2.12
Y2 = 4 -
2.12"
2
= 2.94
Use Y2 = 3
Step 6 Determine required beam size from AISC Table 3-19:
W14x22
Y2 = 3
Qn = 325 KIPS
Lecture 7 - Page 6 of 10
Page 3-184
Lecture 7 - Page 7 of 10
2Qn
Qn ( stud )
where: Qn = AsFy
= 325 KIPS
Qn(stud) = Nominal horz. shear strength of stud
= From AISC Table 3-21 p. 3-207
= 17.2 KIPS
2(325KIPS )
17.2 KIPS _ per _ stud
= 37.8 studs
Use 38 dia. studs
Step 8 Check beam shear at coped end:
Assume beam is coped 1
1
13.7
W14x22 beam
Girder
Factored beam end reaction =
= 24 KIPS
Lecture 7 - Page 8 of 10
Set up a ratio of vVn for the full W14x22 beam section to the
reduced beam section:
vV n
Full _ depth
vV n
Re duced _ depth
vV n
94.8KIPS
=
13.7"
(13.7"1.5" )
vVn = 84.4 KIPS > 24 KIPS for reduced section OK
Step 9 Draw summary sketch:
38 Dia. shear studs welded
thru metal deck along center of
beam spaced evenly along length
of beam
Lecture 7 - Page 9 of 10
Example 2
GIVEN: The beam from Example 1. All loads and other conditions are
the same.
REQUIRED: Design lightest weight W14 Beam A using NONCOMPOSITE construction.
Step 1 Determine Mu:
Mu = 180 KIP-FT
Step 2 Design lightest weight W14 beam:
From AISC Zx Table p. 3-18:
Use W14x34 bMpx = 205 KIP-FT > 180 KIP-FT
(Note: The W14x34 non-composite beam is 55% heavier
than a W14x22 beam that is used as a composite beam.)
Lecture 7 - Page 10 of 10