ASSIGNMENT NO.

3
Q 1) What is environmental management system (EMS)? Explain basic EMS
framework.
Q 2) Explain ISO 9000 and ISO 14000 in detail.
Q 3) Explain value analysis/value engineering
Q 4)The activities of a project and estimated time in days for each activity are
given below:
Activity
1-2
2-3
2-4
2-5
3-7
4-5
4-7
5-6
6-7

Duration (in Days)


3
4
4
5
4
2
2
3
2

a) Draw network diagram


b) Calculate project duration and critical path.
Q 5) For above problem calculate EST,LST,EFT,LFT & Total float, free float,
independent float