HSCL/CFP/UNIT HEAD/2015/215 t:09/03/15
Sub : Awarding of civil work to M/s Steel Tech Engineering Construction.
Ref ; 1.) Civil and structural work of 45 MVA SAF at Chandrapur
2.) Contract No. CFP/Proj/ASMVA/WP-04/2014/10 Dt. 12.08.2014.
The subject work is being carried out by us, by deploying various agencies time to time. A
visit of CEO BSP was conducted on 8/3/15 (Sunday) at about 11.30 am to 1.30 pm at our
chandrapur site. An observation of high dignity was mainly concentrated on civil work and
specially for slow progress of ECR (Electrical Control Room). He emphasized to introduce
additional civil agency to meet the required schedule. It is a well known fact that after lots.
of help to our existing agency M/s Vijay R. Ghate, he has submitted a letter of closure of his
contract and shown his inability to take up the work further. We have tried lots of agencies
in the past, but they have escaped by this way or that and were not interested to work at
‘chandrapur. M/s Steel Tech Engineering Construction is already working as our structural
agency and submitted his willingness to take up the civil work.
‘As per the present situation, the civil work requires boost up by deploying additional
‘manpower, so that required schedule can be achieved with full satisfaction to our client, The
ECRis a 5 storied building which shall involve lots of time for its completion. Keeping in view
of above facts and visualizing the acute pressure of client, itis proposed to issue a Go Ahead
letter to M/s Steel Tech Engineering Construction company on urgent basis to take up the
civil work immediately.
‘Submitted for kind approval in favour to issue the Go Ahead letter for taking up the Civil
Work at SAF, Chandrapur.
CU Shrivastava
DGM HScL
Unit Head , Chandrapur}
j
ILAL
es HEAD/2015/216 09/03/15
b : Request for advance payment to M/s Steel Tech Engineering Constructions
Jef : Structural Work of 45 MVA SAF at Chandrapur
\/s Steel Tech Engineering Construction is executing the structural erection work at
Hhandrapur. The status of work executed by the agency is listed below.
1.) Total Erection done = 125 MT
2.) Total assembly ready for Erection = 70 MT.
1125 MT @ 7953.00 X 90% =Rs. 894712.00
75 % of 894712 = Rs. 671034.00
SAF Furnace work is passing through very critical days and progress of work shall be increased
by supporting the agency financially and technically. in view of above it is proposed to give Rs.
6.5 Lakhs interest bearing advance to M/s Stee! Tech Engineering Construction company so
that the work can be taken up with full swing and smoothly.
CL Shrivastava
Submitted for approval please.
GM, HSCL
Unit Head , ChandrapurWSCL/CFP/UNIT HEAD/2015/217 t:09/03/15
: Award of balance Structural Erection Quantity to M/s Steel Tech Engineering,
‘onstruction.
’ef : 1.) Civil and Structural work of 45 MIVA , SAF Chandrapur
2.) Contract No. CFP/Proj/4S5MVA/WP-04/2014/10 Dt. 12.08.2014
tructural Erection work of SAF is taken up by M/s Steel Tech Engineering Construction and
the agency is doing well as per the fabricated structures transported at the site. Initially we
lhave awarded 600 MT quantity to the agency, since structural erection work shall be taken up
by only one agency to avoid mismatch and front related problems. Hence the balance quantity
may please be awarded to the same agency for smooth running of erection work. Initially the
[quantity awarded was only 500 MT, now it is recommended to award the balance quantity of
1200 MT. Please accord an approval to award the balance quantity to M/s Steel Tech
Engineering Construction, for structural erection work at Chandrapur.
‘Submitted for approval please
CL. Shrivastava
DGM, HSCL
Unit Head , ChandrapurHSCL/CFP/UNIT HEAD/2015/218 r:09/03/15
‘Sub : Issue of work order for cladding work of roof and side sheeting at SAF Chandrapur
Ref : Structural work of 45 MVA SAF at Chandrapur
M/s Steel Tech Engineering Construction is executing the structural erection work at
CFP Chandrapur. We haven't awarded the cladding work to any agency. Its feasible to
award the cladding work to the same agency who is already working as our erection
agency. Kindly accord an approval to issue @ work order for cladding work so that
advance planning can be made to boost up the progress of work.
CL Shrivastava
Submitted for approval please
DEM, HSCL
Unit Head , ChandrapurHSCL/CFP/UNIT HEAD/2015/219 t:09/03/15,
Sub: - releasing of a JCB for Chandrapur unit
Ref: - civil and structural work of 45 MVA, SAF at Chandrapur
Various civil works is being executed by us as per the reference cited above. To provide the
front for structural erection earth filing and leveling required at various places. Work is held
up due to non cooperating behavior of existing civil agency and our erection work sometimes
stand stil for want of leveling. One JCB is required to neutralize this problem. Kindly accord
an approval to release a JCB on urgent basis for Chandrapur unit. It will help us to boost up
the progress of work without causing any hurdle for leveling and filling of earth
Submitted for approval please
(le
CL Shrivastava
GM , HSCL
Unit Head , Chandrapur