Professional Documents
Culture Documents
0
6
Activity A
0 6 6
TF= 0
FF= 0
0
0
START
0 0 0
TF= 0
FF= 0
0
2
Activity B
1 2 3
TF= 1
FF= 0
6
9
Activity C
6 3 9
TF= 0
FF= 0
9
10
Activity F
11 1 12
TF= 2
FF= 2
12
15
Activity I
12 3 15
TF= 0
FF= 0
2
4
Activity D
5 2 7
TF= 3
FF= 2
9
12
Activity G
9 3 12
TF= 0
FF= 0
12
13
Activity J
14 1 15
TF= 2
FF= 2
15
17
Activity L
15 2 17
TF= 0
FF= 0
2
6
Activity E
3 4 7
TF= 1
FF= 0
6
12
Activity H
7 6 13
TF= 1
FF= 0
12
13
Activity K
13 1 14
TF= 1
FF= 0
13
16
Activity M
14 3 17
TF= 1
FF= 1
Legend:
Forward pass: EF = ES + D
ES
EF
Activity Description
LS
earliest start
earliest finish
latest start
latest finish
duration
Total Float (or Total Slack)
Free Float (or Free Slack)
ESA=0; EFA=ESA+DA
1
2
3
4
5
TF of J =
TF of F =
TF = LF - EF = LS - ES
8
9
FF of E =
FF of D =
0
2
10
# of critical paths =
LF
ES:
EF:
LS:
LF:
D:
TF:
FF:
Backward pass: LS = LF - D
EF of G = 12
ES of H = 6
project duration = 21
LF of J = 15
LS of D = 5
17
21
Activity N
17 4 21
TF= 0