Professional Documents
Culture Documents
Session 8
Nama : Muhamad Reza Mahaputra
Binus ID : 1412413653
1. On June 12, 2011, GPU Corporation was awarded a $160,000 contract for testing a
product. The contract consisted of $ 143,000 for labor and material, and the remaining $
17,000 was profit. The contract had a scheduled start date of July 3. The network logic, as
defined by the project manager and approved by the customer, consisted of the following:
Activity
Time (Weeks)
AB
7
AC
10
AD
8
BC
4
BE
2
CF
3
DF
5
EF
2
FG
1
On August 27, 2011, the executive steering committee received the following report
indicating the status of the project at the end of the eighth week :
Activity
% Complete
Actual Cost
AB
AC
AD
BC
BE
100
60
87.5
50
50
$23,500
$19,200
$37,500
$ 8,000
$ 5,500
Time
(Weeks)
0
4
1
2
1
Remaining
The steering committee could not identify the real status of the project from this brief
resport. Even after comparing this brief status report with the project planning budget as
follow, the real status was not readily apparent :
Activity 1
2
3
4
5
6
7
8
9 10 11 12 13 14 15
AB
2K 2K 3K 3K 4K 4K 3K
AC
3K 3K 3K 4K 4K 4K 4K 2K 2K 1K
AD
5K 5K 6K 4K 4K 4K 3K 1K
BC
3k 4K 4K 5K
BE
6K 6K
CF
2k 3K 3K
DF
3K 3K 3K 4K 4K
EF
2K 2K
FG
3K
Assumes that percent is linear with time and nonlinear with cost
Management instructed the project manager to prepare a better status report that depicted
the true status of the project, as well as the amount of profit that could be expected at
project completion. Your assignment is to prepare a table such as below :
Project Costs
1
2
Activity
Percent
Complete
3
Planned
Value
4
Earned
Value
5
Actual
Cost
6
Cost
Variance
(4-5)
7
Schedule
Variance
(4-3)
Total
Cost Variance ($) = Column (4) Column (5) = .....................
Schedule Variance ($) = Column (4) Column (3) = ....................
Cost at Completion = rate spending x Total Budget = (Column 5 / Column 4) x ( )=
...................
Cost to Complete = Cost at Completion Actual Cost = .......................
2. Salah satu metode untuk menghitung biaya proyek perangkat lunak adalah model
COCOMO. Biaya yang dihitung berdasarkan jumlah baris kode program (dalam KLOC,
yaitu Kilo Lines Of Code). Jenis perangkat lunak yang dikembangkan dapat
berupa"console" (misalnya aplikasi yang berjalan dalam MS-DOS), "GUI-based"
(misalnya aplikasi windows), atau "real-time" (misalnya perangkat lunak pengendalian
kendaraan bermotor). (bobot 25%)
Dari pengalaman masa lalu rumus COCOMO yang digunakan adalah:
Console systems:
PM = 2.4 * (KLOC)1.05
GUI-bases systems:
PM = 3.0 * (KLOC)1.12
Real-time systems:
PM = 3.6 * (KLOC)1.20
Berdasarkan hasil analisis system yang akan dikembangkan dengan berbasiskan window
GUI diperoleh perkiraan jumlah baris kode program sebesar 75.000 LOC. Jika
diasumsikan biaya pegawai tiap bulan (PM) sebagai berikut:
System Analyst
Programmer
$6.000 /PM
Tester
$9.000 /PM
Manager
("CM", "QA")
Dan jika diketahui matrik biaya dan tahapan kegiatan proyek sebagai berikut:
Analisa
kebutuhan
sistem (8%)
Perancangan
sistem (18%)
Implementasi
sistem (48%)
Testing dan
integrasi
(26%)
1 Analisis
42%
10%
3%
2%
2 Perancangan
16%
42%
6%
4%
Pembuatan
3 program
10%
14%
55%
48%
Perencanaan
4 pengujian
6%
8%
8%
5%
Verifikasi dan
5 validasi
10%
10%
12%
20%
Manajemen
6 proyek
8%
7%
5%
6%
Manajemen
7 konfigurasi
3%
2%
6%
8%
Penjaminan
8 kualitas
5%
7%
5%
7%
100%
100%
100%
100%
No
Tahapan
Hitunglah total usaha (PM), total biaya dan biaya untuk setiap tahapan dari proyek ini.
Jawab :
1. Menentukan PV, dalam soal tersebut K~ ribu dollar
Activity
AB
AC
AD
BC
BE
CF
DF
EF
FG
1
2K
3K
5K
2
2K
3K
5K
3
3K
3K
6K
4
3K
4K
4K
5
4K
4K
4K
6
4K
4K
4K
7
3K
4K
3K
10
11
2K
1K
3k
6K
2K
1K
4K
6K
4K
5K
3K
3K
3K
2K
12
13
14
2k
4K
2K
3K
4K
3K
15
3K
Total
PV
21 K
30 K
32 K
16 K
12 K
8K
17 K
4K
3K
143 K
Hasil PV lalu di masukkan kedalam table project cost dan dengan menggunakan rumus EV, CV,
dan SV ;
Project Costs
1
Activity
AB
AC
AD
BC
BE
CF
DF
EF
FG
Total
2
Percent
Complete
100
60
87,5
50
50
0
0
0
0
3
Planned
Value
21000
30000
32000
16000
12000
8000
17000
4000
3000
143000
4
Earned
Value
21000
18000
28000
8000
6000
0
0
0
0
81000
5
Actual
Cost
23500
19200
37500
8000
5500
0
0
0
0
93700
6
Cost
Variance
(4-5)
-1500
-1200
-9500
0
500
0
0
0
0
-12700
7
Schedule
Variance
(4-3)
0
-12000
-4000
-8000
-6000
-8000
-17000
-4000
-3000
-62000
Answer No. 2
Diketahui ;
-
Nilai PM
= 3.0 * (KLOC) 1.12
= 3.0 * (75)1.12
= 377.73 ~ 378 PM
Asumsi baiaya pegawai tiap bulan (PM) :
Cost in $
Position
Salary cost
System analyst
10000/PM
Programmer
6000/PM
Tester
9000/PM
Manager
12000/PM
Support team
7000/PM
Function
Analiyze requirement
Design, programming
Plan Test, V&V
Project manager
QA
Perancangan
sistem (18%)
Implementasi
sistem (48%)
Testing dan
integrasi
(26%)
1 Analisis
42%
10%
3%
2%
2 Perancangan
16%
42%
6%
4%
3 Pembuatan
10%
14%
55%
48%
No
Tahapan
program
Perencanaan
4 pengujian
6%
8%
8%
5%
Verifikasi dan
5 validasi
10%
10%
12%
20%
Manajemen
6 proyek
8%
7%
5%
6%
Manajemen
7 konfigurasi
3%
2%
6%
8%
Penjaminan
8 kualitas
5%
7%
5%
7%
100%
100%
100%
100%
Perancangan system
Implementasi system
2.
Perancangan system
Implementasi system
3.
Perancangan system
Implementasi system
4.
Perancangan system
Implementasi system
5.
Perancangan system
Implementasi system
6.
Perancangan system
Implementasi system
7.
Perancangan system
Implementasi system
8.
Perancangan system
Implementasi system
Tahapan
kebutuhan
sistem (8%)
Perancangan
Implementasi
Testing dan
sistem (18%)
Total
1 Analisis
127008
68040
54432
19656
269136
2 Perancangan
29030.4
171460.8
65318.4
23587.2
289396.8
18144
57153.6
598752
283046.4
957096
16329.6
48988.8
130636.8
44226
240181.2
27216
61236
195955.2
176904
461311.2
29030.4
57153.6
108864
70761.6
265809.6
7 Manajemen konfigurasi
6350.4
9525.6
76204.8
55036.8
147117.6
8 Penjaminan kualitas
10584
33339.6
63504
48157.2
155584.8
263692.8
506898
1293667.2
721375.2
3 Pembuatan program
4 Perencanaan pengujian
5 Verifikasi dan validasi
6 Manajemen proyek
TOTAL Keseluruhan
2785633.2
Sehingga didapatkan total biaya project (dijabarkan per tahapan) adalah sebagai berikut:
Tahapan
Analisis
Perancangan
Pembuatan program
Perencanaan pengujian
$240181.2
$461311.2
Manajemen proyek
$265809.6
Manajemen konfigurasi
$147117.6
Penjaminan kualitas
$155584.8
Total Keseluruhan
$2785633.2