You are on page 1of 33
Hear SAFETY & EnROnMENTAL METVO00 STATEMENT Toniactor Bary Ping Systems Limited | Contract Name! J Contract Scope: Piling Operation Location: 121 BPSUSttN0 HEALTH, SAFETY & ENVIROMENTAL METHOD STATEMENT FRONTSHEET Contractor: Berry Piling Systoms Limited. Contract Name: Daniols Department Store Phat Contract Scope: Piling Operations Revison | pare | writen | APPROVED | CLIENT | COWMENTS By | BYFORBPS | APPROVED 0 | 71010 | B.evans | B.Evane | have read, understood and shall abide by all methods taid out in this method Statement and risk assessments. Furthermore should | see or be made aware of any Unsate working or doviabons from the methede laid out | wil contact the site Sparse immediately NAME IVED | — _ 1g FEB 2001 PLANNING iy Heavy, SAFETY 6 EnWRONMENTAL METHOD STATEMENT ‘ontractr: Barry Piling Systems Limited | Contract ame: Gant Department Stora Phase ‘Contract Scope: Piling Operations Location: 121-125 Peascop Stret, Windsor, Berkshire, SL@ 1.Scove oF WoRKS Berry Piling Systems will carry out pling operations within the confines ofthe sto at 121125 Peascop Street, Windsor, Berkshire, SLA TDP. Al works fo be undertaken within the intemal boundary of the site. ‘Our scope of works includes the following ‘+ To bore and construct approximately 119No. 450mm O/D nominal alameter CFA piles fo form & contiguous embedded reaining wall to two boundaries of the slle which Includes party wall Boundary. Contiguous piles wil be bored ‘and consiucted in a Nit one miss three sequence of al the foreman's {iscretion. Dailing ples in a sequence ofthis nature alows contiguous ples time to cure prior tothe sols direct adjacent being dsturbod ‘+ To bore and construct approximately 103No. 450mm O/D nominal diameter CFA piles to depths no less than 8.0m and no greater than 20.5m to provide foundations for he main superstructure Pile method we intend 10 use is @ Continuous fight auger bored method which is one percussive and none vibraloy. ‘All works are fo be carried out in accordance and within the parameters of the Safe ‘Systom of Work issued by the cit, the agreed sit design and the contracts works ‘drawings and specifications, In this case the cient i Galifors Try Construction, The piling works will be carried out from a single, level piling platform, cutoff levels ‘and pling platform levels to be agreed pir to piling works commencing ‘A Ping operation methodology is attached in APPENDIX A 2. SEQUENCE OF THE WORK To construct piles in a logical sequence but in ine with our sequence detailed in the above scope of works. All sequencing of works tobe discussed and agreed with Galifors Try Construcion prior to pling works commencing. Upon completion of ‘each section of works the pling ares wil be fenced of for 7 days before piles can be broken down. ‘2. PLANT ano MATERIAL DELIVERY Allplant wil be delivered taste on beaver talediiab equipped vehicles ‘At his stage Main Access fo the site for tne rg willbe via 121 - 125 Peascop Steet, ‘Windsor, Berkshire, SLA TOP, ‘Acoass tothe site willbe via the site entrance on 121 - 125 Peascop Steet. Here the Lorries wil unload with the aid of the lory mounted crane to deposit the ancilary ‘equipment close tothe point of pling. The png rg wil be tracked off ts lorry using ‘the beaver tal ramp. Al al sk surfaces must be protected by others prior to the piling mobiisation. The concrete pump'wil be delivered to the rear ofthe store and Setup in the goods vara ‘The Principal Contractor is responsible for ensuring that waste materials and pile spoil arising is removed from sie in aczoreance with their procedures and in ‘accordance wih all environmental requirements, © 2 [ Gontractor Bary Plog Systems Limit ‘Name! Dano ‘Contract Scope: Piling Operation Location: 121- 125 Peascop Street, Windsr, Berkshire, SL@ DP. BPSU46H1/10 —_ “The site has been inspected to allow safe vehicle delivary withthe use of banks men ‘when unloading the ping ig. The rig wil be moved under lis own power, an operator and banks man will bo in postion to achieve this. The ping rig wil ot be moved ‘without an operator er barks man in allendance, ensuring its sale and controled movement. Once delivery is completo the vehices will depart site and the pling ig wil ether be ‘maneuvered to its fst pile posiion or pul in a sale positon unt instructed to Continue by the pancipal contractor's representative onsite. Al. ancilary equipment wil be devoted to site and be located within 20 mates of ho piling operational area. All materials will be dellered to ste and stored in a holding {ompound or at an agreed location on the ste. For the constuction of the pling work, its proposed to uilse the following plant, ‘he technica specicaion of which are shown in APPENDIX 8, Klemm 709 Ping Rig 1No, Container Toolbox (Small) 1No, Diesel Jotwash 1No. 44 Concrete Hoses (60/80m) 1 No, Conerete Pump AN Sundry Equipment “Tracked Excavator (or equivalon!) provided by the Main Contractor 1 No The above to be fully contolled by ping Foreman or rq Banksman to ensure no ‘resh ples are tacked over and damaged. Mess, Drying Room and Welfare in accordance with curent legislation (ols and washing Tacive incuding hot running water) to be provided by the Principal Contractor. This wil be located at King Edward Court Undor ero, Bridgowalr way. 4, Liemmo Eoupwent ‘The pling rig wil have ls curent Certificate for Safe Operation (LOLER), This willbe hele by the site supervisor and a check wil be cariod cut to ensure tat i ie vals ‘and uptodate. Any fing chains or straps wil be fuly certfied. S,PoRTABLe Toots + Angle Grinder Peto riven {Hand tots suchas spanners and cub hammers + Onste welding unt (General frig repars ony). [A todls to be checked by the supervisor each day for fit for use (PUWER 1908: Provision and Use of Work Equipment Regulations). Those tools found unft are to be tagged and removed from ste for repair or disposal Hea. SAFETY & ENWeROMMENTAL METHOD STATEMENT arty Pllig Systems Limited | Contract Name: Daniels Department Store Phase? ‘Gontract Scope: Pling Operations Location: 421 125 Peascop Street, Windsor, Boric | sor: eesieetsi10 S.NOISE AND ViBRaTION ‘The predicted noise and vibration levels are to be kept within the local authority levels using silenced equipment. Please note due to the piling technique being lized on this project no vibration wil be generated Works wil take place during normal working hours 6:00am-600pm Monday to Friday. No weekend working i intended, AiR Quausry aNo Dust ‘The items of plant and processes which emit ar polation are + Diesel Power Pack + Petrol Angle Grinders + Road vehicles ‘The Png Foreman to ensure that exhaust emissions are kept within the lage limits, All venicesipiant tobe parked and engines turned off when notin use, 8. PLN PLarroRM Ful ple platform design wil be required. A further revision of this method statement wl be require fo highight platform thickness and make up. 9. CONCRETE INSTALLATION Pies we be concreted using the open bore method. Pes wil be bored to depth, and ‘concreted using the top fil method; a concrete pump wil be sited so that it can be easily accessed by Ready-mix Lorries. The Concrete willbe discharged into the Conctote pump and tothe head ofthe pile va 4” hoses, Concrete wil be poured t0 ‘round level and the steel reinforcement placed. The concrete Is supplied by others inthis cave. 10, Remrorcewent Reinforcement bar and helical wil be delivered to sito and fabricated on site to the pile design spectications. The minimum cover to the reinforcement will be SOmm (tac) ‘The main ber wil be set up on ste! fixing trestles so that the steel fixer can work in the standing postion, The helca wil be wound onto the main reinforcement bar and tied accordingly using. Cares certificate forthe steal reinforcement to be supplied Please note that a clear and visible segregated area must be erected for the steel fixer to work in safely 1, CO-ORDINATION WITH OTHERS The Following dotals any arrangements for co-ordination with sub-contractors, adjacent contractors and ical authori etc Contactor: Ba Heat, SAFETY & ExvigOMMENTAL MET#O0 STATEMENT ing Systems Limited | Contract Name: Danile Depadimant Store Phase 2 All personnel wil Book into site though the construction ste offices; they wil then receive 8 site induction by te Principal contractors representative onsite. ‘The Bemy pling supervisor will ensure that all personnel involved in the Piling ‘operation are briefed on the contents ofthis method statement and eafe working on ‘or around the pling rigs and any other machinery wih the pling area. The con's Fopreseriatve on ste is responsible for ensuring that al Ste personnel are briefed ‘and made aware ofall rsks involved in wrking on or ound ping operations, 12.Pus Locanions Apling layout has been supplied (No X102021 SK100 REV P2) with a constuction issue at the time of commencament to be held on sie. any davialons from the Instructions on th layout willbe cleared through Bary Ping Management prior fo proceeding. The pling layout drawing wil be checked with the principal contactors Fopresertatve on site to endure It's the last construction issue avaiable before piling works commence. Setting cut of ples willbe the responsibility of others. 413, Lasous Force ‘The folowing max deals the number and level of competency ofthe workforce. Personnel —~ ——— | Hamiber [Level of Compotoney. Contrects Manager: Barry Evans 1 [5 days Site Manager (SMSTS) 7770 963147 2 day FPS Site Supervisor. Project Supervisor OWer Cantle T | 2 day site supervisor safely rained o7r2t set495 Experienced’ and Trained in RigiPiing Operations Piling Foreman: Marin Picket T [2 day site supervisor safely ined Experienced and Trained in Rig _ Oparations " ‘SRIEG pig oparaives S| Experienced and Trained WRI Operations 14 Teams ‘Al Berry Piing personne! wil be trained in safe and competent use of the rg. Only {rained and experienced personnel wil be permiled to operate on or around the pling rg. Bary pling personnel have undergone CSCSICPCS training. Copies of Cenitcates and training records are held at Berry ling main offices. All employees. {ohave tes relative cards ready for inspection atthe ste induction. Hon th job Safety training is necessary it willbe undertaken by Olver Gentle Berry piling Health and Safety representative. The following are o be included into the site induction ‘This Method Statement Working 0 or near pubic services Site Security Equipment Security ‘Working within the vility ofthe general public Emergoncy evacuation pins in the eveat of Fre/Emergency ‘Site setup an¢ locations of Wotfare and fst Ald facies Contract Scape: Piling Operations Location: 121 - 125 Poascop Steet, Windsor, Beishive, SLA | ‘DP, BPSMGI1/10 “} HeALT#, SAFETY & EXVRONVENTAL METHOD STATEMENT [Contractor Besty Piling Systems Limited | Contract Name: Daniols Departrent Stare Phase 2 ‘Contract Scope! ling Operations ‘Location: 121-125 Peassop Strost, Windsor, Berkshire, SUA] PSUsN0 15, PROTECTION oF THe EMPLOvERS ASSETS dently in the table below wunerabie ‘employer assets and deta the method of protection. ‘Brea requiring protection Wathod of Protection Work Area Barriers and signage: Party Wal be praia by ihe Nain Conair " pio to ping works commencing Beiow & ADO GrOURE GONTEES, ‘Service information drawings suppied By the Planning superisodclent. Al ices to be highlighted and. clearly marked out on sit, Prolecon of services Wwhere required by MC. Site Safety briefing to all ping personnel to take place to make Sure care and attention is faken when working close to. the ighighted services. J6. MATERIALS ‘The folowing lst deals materials tobe used forthe contract. Dery ~ diesel for plant Grease (Grout Sand / Cement / Concrete Hydraule Of Engine Oi Al relevant COSHH related documents, such as manufacture's hazardous data heels nd test certificates and assessments (where applicable), wil be available on Site in the ‘Contract Health and Safely Contal fa 417, STORAGE AND HANDLING OF CHEMICALS ‘The following table details the chemicals to be usod forthe contrac: Column 4 references the COSHH assessment for each chemical, which contains information on how the chemical shoulé be slored, handle, used and clsposed of In ‘order fo minimise environmental risks Type of | Guantiies | Projected use | Environmental | COSHH chemical ” | impacts ‘Assessment Petro! Sie Fuel Tor angle | See Above To be ringers altsched 10 site fle ‘OisiLubreant | Various | Slate & Major | See Above To be 5 Plant allached to | 2 Site Fle Grout ‘As roqulred” | Pleshple cap | Bunds wil bo] To be provides attached to site fl 6 HEALTH, SAFETY & ENVIRONMENTAL METHOO STATEMENT _ __ ‘Goniractor Baty Ping Systoms Limited — | Contract Nome: Daniels Department Store Phase? ‘Contract Scope! Piling Operations Location: 421- 128 Peascop Stet, Windsor, Berkshire, SL a ‘bP. BPSUGIIH0 " TROL oF Wonk wir HAZARDOUS SUBSTANCES AND PROCESSES [Assessments or all hazardous substances and all hazardous processes will be lunderiaken. Copes of these assessments are available In the Health and Safety Control File on site. All operatives are made aware ofthese assessments by the Piling Foreman and thor locaton. Ths nication wil be carried outin te form ofa ste induction andlor too box talks throughout the period of works 19, TewPoRagy STRUCTURESIFALSEWORK [A temporary works are to be carried out and compited by the principal contractor. All tomporary works cotficates, drawings and calculaine ara to be made avaiable to Bery Ping 20, Wong a Heroes NA 21, PERMITS AND LICENSES Berry Png Systoms are fo ensure that the cfent has arranged for all necessary licences and construction consents relating tothe project fo Be hela on site and made ‘avaiable for audit. A Permit to Dig wil bo issued by the principal contracio’s reprosentaiveon ste prior o pling works commencing, 22. EXCAVATION No excavations wil take place, completed open bores are to be protected by securing ply sheeting over the holes to acid bps and fals. Exposed reinforcament is tobe boxed and or capped, 23, TEMPORARY LIGHTING AND POWER ‘The pling rig will be powered buy is own desel power pack. Were extra power ie requled for ur pant wil we use a diesel powered generator or power supplied by tha princple contractor. Task lighting may be required power for which wile from site sources and al power to be 110. Where Generators are used they are tobe placed ovin @ bunded area to ensure that ‘any spilages that coud occur are contained, ‘The dlent isto ensure that suitable suficient storage areas are allocated for Ping equipment and materials, these areas are to be tapedtTenced aff rom the rest of he works 25, PERSONAL PROTECTIvE EQUEMENT (PPE) The following PPE isto be used! HeALn, SAFETY & EwvROWMENTAL METHOD STATEMENT ‘Contractor Berry Piling Systoms Limited — | Contract Name: Daniels Depa | Contract Scope: Ping Operations Location: 121-125 Peascop Sires, Windsor, Beriahire, SL& ‘bP, BPS4GI1/10 + High visibly vests $6629 Yellow + Safely helmets EN397 + Safety Boots BS 1870 EN 345 /EN 346 + Safety gogolesiGtasses BS 2092 /ENT6S + Gloves EN420, + Earprotecion EN352 PART 4 + Face masks ENt49 [Altitems marked in RED are mandatory 26.imst AD ‘A fist id box and accident book for the pling gang will bo kept with a nominated ‘operative. The Firs Aid box willbe checked daly fo ensure its contents are stocked ‘and of a usable condition. Each team wil have a tained frst Alder. Olher First Ad ‘arrangements wil be made through the princpal cntraciorsrepresentalve on sie. 27. FRe Provision for adequate fre precautions wil be made on ste by the Piing Foreman and the principal contractor's representative on site, A fire point is to be located Wwitin the immediata work area and to be identfied {0 the work foree in the sit Induction 28, Housexesng Work aroas willbe kept Udy both during and atthe end ofeach shit, Materials wil be stacked tilly and safely so as not to cause obstruction for access, 28. ACCIDENTS, NCDENTS AND REPORTING OF INJURIES, Dis ‘OCCURRENCES (RIDDOR) 1995 ‘All Accidents and incidents willbe reported directy to the principal contractor's representative on site, he wil then inform all hose responsible in accordance with his ‘company procedures. ‘The Boxy Pling site foreman wil be responsible for informing the Bery Ping management of al accidents and incidents mmeciately. The principal Contractor wil be responsible fr al accident investigation and subsequent reporting to HMR [Accidents and incidents (including near mises) wil be reported and managed by the Berry Piing Systams Management team Mr Barry Evans! br Olver Gent and they wil be responsible for carving out investigatons into incidents and reporting the incidentaceident tothe HSE on an F2508 form where required 30, EMERGENCY PRoceDURES Contact the following in the event of an emergency (work, and motile numbers) Chis Beery Managing Director 07785 771709 Barry Evans Contracts Manager — 07770 963147 Olver Gentle Contracts Supervisor - 07721 381405 THSP (H&S advisors) Work 08456 122 144 _ eALT, SAFETY & ExvROMMENTAL MEIHOD STATEMENT ‘Coniraetor- Berry Piling Systems Lirted | Contract Nome’ Daniels Department Store Phas Contract Seape: Ping Operations Location: 121-125 Peascop Street, Windsor, Berkshire, SLE ‘s0P. BPSUGII/10 ‘The sito supervisor will ensure that all employees are aware of the emergency procedures and evacustion and assembly points. Emergency procedures will be {hose adopted by the principal canractor and staff an the site and pre-agroed before works commence. Emergency information wil be held both inthe ‘Contract Health land Safety Conirl file "and en the principal contractors sign boars with al relevant associated information 131, Signs ano Nonces Signs and notices for the works wil be located where necessary to ensure safety requirements. These wil Include No Unauthorised entry anger Men at Werk Hara Hat Ares Rolovant PPE statutoy signs 132, SvsTeMs/Coves oF PRacnce ‘Special systams or code of practice willbe folowed, Thase incl: + BPF Standard Specication + BSEN Code of Pracice + HSE Guidance Notes 33, STATUTORY ReconDs: ‘The following statutory records willbe kopt in ‘Contract Health and Safaty Conta file: 1510 Accident Book 2506 Incident Riddor Forms LOLER PUWER ‘The Site Supervisors responsible for maintaining the records and the location where records will be kept 24. WasTe MaNaceMENT ‘The outputs of materitsby productstwaste products from the contract are + Soll arsings from ping operations + Concrete overspil, ‘The principal contractor wil be responsible forthe disposal ofall waste materials from pling operations. |All Washing oft area's to be agroed with the principal contractor's representative on site, ‘The typos of oftuont, quantities and how the effluent will be managed are described in he table below ° Contact Scope: Ping Operations ocallon: 121 - 125 Peascop Street, Windsor, Beitshive, SU HeALT, SAFETY & EnviRoMwenTAL METHOD STATEMENT 7 Ping Systoms Limited [Contract Name: Daniels Department Store Phaze? = oc Psusttit0 yi —Tavani ‘Clean Water 20 Lites 7 Winuie shor] Normal Construction uration Practices ‘The ste is subject to rainfall and creates storm water run off. The effluent will be controlled by the principal contractor. RAFEIC MANAGEMENT ‘The works traffic wil be mansged by principal contractor’ representative on site In Corder to minimise environmental Impacts, such as noiss, air emission, dust, Mud ‘creation and minimise congeston at ar around the ste ‘ST.CONTAMINATED LANO Iv any contamination 's caused the area affected isto be cleared and disposed off under the EA 90 wih all waste being disposed of by licensed contraciors. All contamination will be reported through the principal contractor's representative on Sie, Al ste operatives wil be instructed in goos housekoaping and personal hygiene ‘when working in or around such potential risks BLINSPECTION AN ENVIRONMENTAL AUOTING Berry Ping Healtn and Safety Manager wil Visit site on normal routine to ensure that ‘all ervironmertal containment measures are being sed, where there is an fevironmental non conformance then this Will be rected’ and reported to the Principal contractor's representative onsite ‘38, RECORDS ANO DOCUMENTATION, Deals of general legislative requirements can be found in the Bery Pring Managemert System's Legal Register, legal requirements specific to the contract wll be dentiied and communicated by Berry Ping Contracts Manag. HEALTH, SAFETY & ExWiROAMENTAL METHOD STATEMENT Ui Nr r — 125 Peascop Street, Windsor, Berishire, SLA APPENDIX A METHODOLOGY eam, SAFETY & ExwRonMeNTAL MerHon STATEMENT ‘Gontractor: Bart Piling Systems Limited —| Contract Name: Daniela Department Store Phase ? Contract Scope: Pling Operations Location: 421 125, 2 3) 4 5) 8 n 8) 9) 10) 1”) 12) 13) 14) asco Steet, Windsor, ee 1D BPsiast10 METHOD STATEMENT ‘Nominal 450mm diameter CFA File Constuction ‘Track ig into pile position with mastin racking position Manosuvte rig as close to required pile positon as possible. Shut oftlock track controle Operate hydraulic contol and pivot cil mast into vertical mode. Once in vertical positon ralse/ower aril mast so that mast fooUsll guide i frmly seated on ground. Hydraulcally agjust rig with rams to ensure rg and mast are vertical ‘Check mast fot for adequate bearing on ground, Rotate auger unit end fights clockwise at same time as feeding rotation unit downwards snd il auger ino sos, ul excaveted spol to one side for removal by others using hand fools or the allendant excavator ‘Once depth is attained, connect concrete delivery hose coupling to central delivery port coupling and secure, Under pressure, pump concrete from concreting station ‘through’ rotation unit and ‘down nallow auger stem to remove ‘bung’ in lead auger (bi). This then alows concrete into the bore. Pressurse the systom, Ratiove auger fight, rotating 2s necessary roqured at constant rate to ensure slom and bore are constantly filed wih concrete untl all augers are withdrawn, Instl reinforcing cage into pile bore wth wheeled spacers to required depth/pastion. CCeniralise pling cage and brace info posiion unl concrete set Clean siom of all augers. Rplace bung seal in lead augercuting head “Track rig into next pile position. Repeat set up and ding procedure. Please note that all of our pling rigs are fully compliant wth the HSE guidance for Min-pling. All of our machines have an interlocking safety cage. Once the interlocking cage Is opened the rig realises reduced rotating speed, reduced {feed speed and a hold to run controls. The rigs also have Emergency Stop switches fitted. Both the Guard and the “switches are tested atthe start of every shift fo ensure they are in full working order. osu Sar EnyRonwEnaL METI STATA [Contactor Bary Ping Systems Limited | Gontroct Namo: Daniels Department Store Phase™ ontrat Scope: Pillng Operations schon sat 8 Posecap Stoel Windaa Barish, SUP OP. BPSUGI1i10 Hea. SAFETY & EwrmowotenTAL MeTHo0 STATEMENT ‘Contractor: Gory Ping Systema Limited ~ | Contact Ni els Department Store Pi Contract 5 ons Location: 121- 125 Poascop Stret, Windsor sbP, PSI4611/10 APPENDIX C RISK ASSESMENTS prey & ExrRonenTA METHOD STATEMENT Contract Name: Daniels Department Store Pi Location: 12-125 Peascop Street, Windsor, Berkshire, SLA ‘bP- BPSMGI1/10 i T RISK ASSESSMENT SUMMARY PART 1 ‘Sie: Daniels Dopariment Siore Phase 2 [Localon:_121- 125 Peascop Svosi Winder, Beishro, SLa 10P Work Actwvy/Canract Type Road Delvery of equipment and pling operations ~ Persons Exposed - ‘Commens (aude ference Te daabiodainees, 6) Employees = ¥ Other Wares Jv Pubic: — ¥ 7 7: Havas denied Xt presertfeauing contol NW Wabsenina sgnieant [Physical Injury Hazards | Physical Agoats ‘Manual Handling tobi Pan TX [ionising Radin A [anual Handing ry TX oveg Pats of Wacipe | X-[ Lasers N— [Crushing Equpment fais [x Moving Haier [| Uira viet URE N—[ Wiscstaneous Fal rom Heights [| coi pects N—| Wester x ‘Aczoss Equpment [| Hot Objects N— [lone Working nN Sls. Tips. Fals |X | Temperature N— [Confined Spaces N Excavations [X-[Noseribraton X__|Restcea Access [N Pressurized Sime —[ X_| Hazardous Substances Buried Series x Eectical N[Hazardous Substances —[X [Avr Quaiy x Hol Wort [| mew-ogensrs Nl oust x Exposion 1c VerinfWeis Oisease |X| Hypodernienendies [TN iether spoahy OT Fos a Pub RISK EVALUATION = Seore 12 Sonn irr Rak 1 Rosicual is whore not (See Check st Above) (Aer Convo! Measures applied by Part 2) pplcable _ — UnikeiyPoRSBIaT Unethood | Severiy | —RBkNo | Uketnood” | Seventy kN Likely | ttm | Score't3 | Scores | otra | Score | Scores Multipied MoodMoserate! | Score 1-3 wtipied | Scorers | 3 Senous _ Physical iu t : L ‘Mobie Pant 3 2 3 7 z 2 j Mow par of 3 3 9 + 3 3 machine. Moving maverais_|—3 2 a z z ats fom hei | 3 3 8 i 3 3 Sipe Tipe and] 3 2 3 7 2 2 Fal \ | Excavations z z 7 i i 3 Pressurized 3 3 3 7 3 3 systome | Hot Wonare —| 3 z a z 3 Physical Agents > Nowe and z z 7 7 z z | woraton 7 Hazardous Substances [Szsareesana | 3 3 7 3 3 materials Vermin Wes z z 7 7 z z disease L _ _ 15 Depart Sore Phase ——— ‘ereahire, SLT Faisal z z 7 7 7 z equoment _ Miscellaneous Weather z i z z i i Bured sonioos | 5 3 3 1 z = 7 Qually fl 2 2 1 4 i ut 2 2 i z z General Fable | —3 3 3 1 3 3 Chisren 3 3 3 1 sf 2 t ae Fi ae acon o>) ‘CONTROL EASURES SEE RISK ASSESSMENT SUMMARY FORM ZATTACHED: Signed Psion Date | | RISK ASSESSWENT SUMMARY PART 2 —T ‘Site Daniels Daparimant Siow Pasa? | Location: 121-125 Peascop Svan Winds, Bavahe, SLA TOP. “Assossmens for Signifiant risks: Mobile Plant. All plant tobe sted within work area. Al plant to have test certificates. Al plant when mobile Orn use to have banksmer/bariers around rout. Al pling operations fenced off so no untrained personnel ‘ean come into contact with png machinery Moving parts of machinery. Rig drive to be disconnected before cleaning bore sections. Training, instucton, Only use specialized tools for cleaning ensure that rig is disconnected from dive before Ionnectingdisconnecting bore sections When connecting sectional augers using manual handling techniques. the pilg 9 operators wil remove their hands from the contol levers. The iter-Lockng guaré wil be opened, 8 section o fight wil be placed by an operative that operatve wil then stand clear ofthe ping rig and close the Inte-Locking Guard Only then wil the rig operator pace their hand back on the contro levers and resume ‘operating the pling rig, This soquence willbe folowed each ime a seston fs added or removed. | Moving materials. All materials to be moved using mechanical means vere practicable, All materials to be secure before moving Fe from height. All work tobe undertaken from sullable lowers or hand railed areas ‘Slip Trips and Falls. All areas to be kept clear of obstructions at al times. Public access areas tobe clearly signed, Excavations. All excavations in or aroun the work ste are to have secute barriers and vehicle stops placed ‘around them. All personnel be rifled anther locatons. Pressurized systems. Rig and Power Pack and attachments to be checked prior to use for damage. Spray systems tobe checked anc certified fi for use. Noise and Vibration. Generators and compressors tobe silenced, Operatives to wear hearing protection when using noise eriting equipment Hazardous substances. All substances to have an on ste risk assessment which ie tobe elated to all 6 Contradior, Bary Ping System Linited ~ | Contract Name! Oaniela Department Stare Phase 2] ontract Scope: Piling Operations Location: 121 125 Peascop Stree, Windsor, Berishire, SL@ $0P. BPSGII/IO [ Speraives on sie pero the sar ofthe works, Al operainves To woar necessary PPE as Golaled by he Manufacturer and the on silo Risk assessment Exhaust Fumes: lobe controled using exhaust extensions and where practicable extraction systems Vermin Wells disease. Alloperaives to be made aware ofthis risk and lo wear gloves during works. Good personal hygiene. Manual handling, Equipment and materia o be assessed for individual weight and a risk assessment tobe carried out CCrushing/Equipment Falls. | personnel tobe cleared from the iting arc ofthe crane and slung equipment. Good contrls by the erene supervisor and banksmen. All equipment to be secure porto It. All iting equipment to be checked prior to use. Weather, All operatives to have avaiable wet weather protection and cathes Buried services. A CAT Scan to be carried out ofthe areas tobe excavated and results logged and | marked, | Air uatity. At generators/compressors to have in date service records and omission test these areto be | | nel in the sto fla. Equipment tobe replaced atte fist sign of excessive exhausl emission Dust. All Vegetation to be damper! down prior o cutting where practicable. Warning signs to be erected operatives fo wear dust mask dunng operations. General Public. All working aress to have suitable fencing erected and gates to be locked. Al vai | movement external io ence to have trafic menagement personnal in attendance. ‘Arsenic Contamination. All operatives to be made aware of tis risk and fo wear gloves during works, Good personal hygiene oni We Datals of Gontror Measures ‘Documents, “Method Statomont Procedures ete oo _ Taermation Personnel advised oF tho above Tsks and of procedure S51 Oath malod statement Instruction Folow method statement procedure. Training ‘xing in actiaty wih all personnel tobe made eware of method statement and risk ‘assessment content | Supowison ~~] Sugprisr to oaek tata personnal Fave raqured PPE aid are aware Fal | aati procectres. Aetess ‘Ensure was of work ae Soar ofrubBshinatoras ote. and ae opt ean, Good hhousekoeping to be employed etal times. | Enanmmant Tol appa — [Emergencies | First Ala Kit and First Aider to be on sie af alimes ‘COSHH eam, Super Contac Bony pig Stems Lnted | rat Scope: Pig | $DP. BPSIABTI10 PPE “Ais required by manufacturer and Local RiGk Ass@ssmonis ‘Other Procedures | New Road and Steot Works At Manufactures Guidance _ Heavy SAFETY & EnvRonMENTAL METHOD STATEMENT [[Conactor” Barry Piling Systoms Limited | Contract Name: Dante Department Store Pha Contract Scope’ Pling Operations Location: 121 125 Peascop Street, Windsor, 40P, BPSI4611/10 BERRY PILING SYSTEMS LIMITED k Assessment Interface Worksheet (Sheet 1 of 2) Job No BPSHOI1/I0 Reference: Daniels Department Store Phase 2 Design Elements): Piling o Trtartace T eiatng | aa | Causes & | sone | Control | Proposed action | Estimate | Confirmed actions! Ret, | Hazard | Elementiniraces | “fatres” | Consequence | affected | Risk ‘oneloment | Following | earled forward eading to er | eetimate | “lesigners | ‘Design hazard ‘tions _| z z L S[cre. Sur BPS! |Prelntataton | Sto | Plog |ncorec: Si | minoriniry [Ping 0] 8|mM|Roviewsoisana ole |e investiga orsgnieant Operators ‘ensure ancher ton Stference esigrers ave sols Stermaton fo alow roceagn of anchare BPSZ_| Pie rsisiaion | Sia | Pig | adoquaie | Najorinury | Sa’ —[C]C[M [Ensure adequate [DO] Preparat pe peepareton of sing fen orate Bitom atom BPST_| Pre etalaton|| Ping | Parg | Inearect | Majoriqury | Ping | ©] CW [Erre wiaie TO] OTC handing of Operators feuipmert is being boring uns ‘od & correty cages BPS] Pie saison | Ping | Spat —[inconeat — ajormuay | Ping |} © FW | Esra suatie bins | O[O] removal | handing / Opsrators skis ang moving bepoea of Teta equipment spot ‘valenle and uses - iy eat, SAFETY & EWvRoNMeXTAL METHOD STATEMENT [Contactor ‘Berry Piling Systems Limited | Contract Name: Daniels Dopartant Store Phase ‘Contract Scape: Ping Operations Location: 121 - 125 Peascop Steet, Windsor, Berkshire, SU | ABP. BPSUGLIIG Key S=SovertyRating —L=Lkelnood Rating R= Risk Rating (See Severy Likelihood and Rsk Rating Tales) ‘Severity, Lkelnood and Risk Rating Teble Tikanood Risk ‘A Death st persons [ram ‘A [Regia occurrence Tigh H Fah ‘8 | Wajorinury to persons Madam [8 | Frequent occurence | Medurm | W Toston ‘C— [War inuryo one pson—| Medium | C| Occasional oceurends [Medan Low ‘3 —[ ino inunyies ow 1D | Possbie occurence [Law EL Trvl muri Low E_mprobabe oocurenca [Law 20 HEALTH, SAFETY A ExRONENTAL MeTH00 STATEMENT [Contractor Bary Ping Systems Limited | Contract Name: Daniels Department Store PhaseZ ————] ‘Gontract Scope: Piling Operations ‘Location: 121 - 125 Peaseop Strest, Windsor, Berkshire, SL Lape: epsiesisi10 BERRY PILING SYSTEMS LIMITED Designer Risk Assessment Worksheet (Sheets 1 of 2) JobNe BPSi4611I10 Reference: __Darlels Department Store Phase 2 Design Element iting re] Lite cycle, Persona | Control | Risk Contr! Contiemed Ret | Phace/Mode | Hazard Consequences | Affected | “Risk ‘Measures Actions!Garied Estimate Forward - Sit fe Rect | Bored ale Irstating ples | ncoreet stor | sionicant | Contactors | 0 | 8 || cecksoss Consiicton Seuteart | adcnonal pte | Stat arsings erence | engin! pes heck movement tole, requires owl revise design FG? | Bored Pie insiatng ples | Falureto ——] Pingratala [Ping [©] ©] W] Ensure Ping Constrveton prove em & | over Operators Platorm caety feet ping Inetales ptt RFGS [atone ‘Unoading ane Uneatabe | Tay se DYE fm | Convaror Ecupment | movamertat | handing operatives! fxcavaton sage 1 detvery mmateras! | metress Sit | Pratection of equipment ‘ecavaton stage 1 FGI [Bored Fie ‘Spalerioval_| Wang ols | inry Sie TLE [we Conraror Construction (aot sabe operatives ‘excavation stage 2 spol Protection of heapstoins ‘excavation stage 2 a ( (Contractor Bary Ping Systems Limited | Heat, SAFETY & EwRomwenrAL MET0D STATEMENT ‘Gootract Name: Daniels Department Store Phae 7 — ‘Contact Seape: Png Operations Location: 121 ~ 125 Peascop Sires, Windsor, Berkshire, SL® BERRY] PILING) = csnsmoronane | CONTRACT AMET |__| BPSHETIO | RISK ASSOCIATED WITH | PRECAUTIONS TO BE TAKEN TO REDUCE | PPE. REQUIREMENTS AND “ACTIVITY THE RISK COMMENTS: Gontaat with moving Trafio Toles around ste to be delineated to machinery voit calision Tonlact wih ve Sevens | Perio Dig Wo obiain To ncicate presence and Proxrnity ofall known sonvces Perit to ig be sued “Faling materais “Ruger tobe Geared ofa hverads Fam he ground Fal fom aight ‘iy work above Zh opstaives lo Gah proper aodess and safety harnesses wern and tached when no protecion is avaiable, bya competent person Safaty Faresses tobe checked before use and regular intervals Toe ‘Contaminated ground] Piant Faure | Ear protection to be wor Fassesamant incites levels above 858A | Ground condiions tobe cheawed for —— ‘contamination. Full decontamination faciity maybe required | Ragilar nspaaions to cary ou on a ina ‘equipment statement including erection and cismanting of the rig, and craneage where necessary: Please refer o specie risk assossmonis os [rogues “Ths work wil be covered by spoctie matnod | assessed ~ | BRE as assensod and vequved, weekly ‘Test Carica 2 ‘Roproptate ear protection 85 to be kept in Ste Offens ~[Foequiveiani to Be completed —| __fRECEWE5} —___. 15 FEB 2001 KLEMM KR 709-1 PLANNI Bohrtechnik Die KLEMM KR 709-1 wrde epee {tr Pahbavungen im Decmessor Ki43 geandestet Aterdem best dle Me 16500 mm Single Paes, a Guat at nine twee Sue 2 (COM? /EPAS) ‘arta ange to Ey 00 mm (128) 4 Nn ptemare i uneraas Besos ie 1 KR 7004 cay be ee or et rot ap Seep 204 ' KLEMM KR 709-1 es Bohrtechnik alee Typ 20213 mt sat versciabarer Sehiten {i mea type 202/13 wt sige shit te ‘Gomnrefechveriiung Typ, is 508 mm “amangtreating deves pe ford. 809 mm eerebap LEM KH 40 Opton Soratataes! ptonal: sound pot coer KLEMM | KR 709-1 Bohrtechnik ie Garacinamatx exaust den Ausglch von Bodenunebenhaten sowie das Batren von Pern er Negung The kiomatics ofthe KR 709-1 lw fo ads fr uneven tein and alo tod under ange ‘Schwenkbereiche / Mast Movements S| | vas h / = Pa) | KLEMM KR 709-1 Bohrtechnik ‘Abmessungen | Dimensions mit Lafette Typ 202/13 (4400 mm) with drill mast type 202/13 (4400 mm) Greantinge over angts 248mm 1 Geramnone. vant ght Samm KLEMM KR 709-1 Bohrtechnik ‘Abmessungen / Dimensions mit Lafette Typ 202 (8000 mm) with drill mast type 202 (8000 Gasaringe ovenengh 3 mn Seaemhane’ ovat hire 335"rm Seman ‘ise wes cn 204 KLEMM KR 709-1 Bohrtechnik ‘Abmessungen / Dimensions mit Lafette Typ 310 und 4 Gittermasten - HDI-Ausfihrung with drill mast type 310 and 4 lettice masts - HPI-version pantie Pee Bilary reste Sebo Sige ewer et oe KR 709-1 Bohrtechnik es Technische Daten | Technical Specifications Motor Engine cat car 3056 EATAAG zeifizen nach ceonifed by ‘cow EPA2 mediumgektit ‘medium cooled max. Leistung ‘max. power ouiput —KWIhp 1295/1768 Lessig be 2900 Utin rated ouput at 2300 rpm KW IM 42085178 Diesettnk fuel tank capacity 240 Hydeauliksystem Hydraulic system Hygreuikpumpen hydraulic pumps 1 kresiaut Tatoreut Uimin 148, 2 krestaut 2nd creut limin 445 3: kreslaut Sra cxeut limin 38 4 kreslaut “ah orcut umn 2 Systomeruck operating pressure bar 250 Hyaraulkiank hyde oftank capacity 00 Raupenfahrwerk ——_Grawlor base Lauwerk crewier type B Zugkrati max. towing force kN 400 Fanrgeschwindigket crawler speed kovh 2.55 ‘Spez Bodencruck ground pressure Nem 47 Gosamtrote vera with mm 2400 3-Steg Sodenrlatien web track shoes mm 500 Lange der Fahrschtle length ofcrewier units mm 3350 Lange (Achsabstand) length axle axle) mm 2768 Bodenfrehelt ground clearance mm 320 Bohrlaftte Typ Drit mast type 22 202s rmit2-stuigem with speed Vorsenubgetiebe ‘feed motor zul Drehmement max permissbe torque kNm 3040 Worschubiange foedienath mm 6000 2400 Son Wiest banemacce ‘ecxoynn 2004 7 soy KR 709-1 KLEMM Bohrtechnik Technische Daten / Technical Specifications Bohriafette Typ Vorschuibkratt Rockzugkraft Vorschubgeschwindigkelt foed r Rockzuggeschwindigkelt retraction rato Drill mast type 202 202K. feed force kN 100130 retraction force KN 100130 491105 | 491105 | Vorsehub sehnel, fast feed rate 16,2047 Ruckzug schnell fast retraction rate mimin 168133,6 16,2134,7 Hydrautkhammer Hydraulic deifter ‘empfonien| recommended KD 1624/KD 1828 R/ KD 2728 R Hydr.Kraftdrehkopt Hyd. Rotary head cempto recommended KH 16/KH27/ KH 43 Gewicht Weights Bahigeratkomplett dif ig complete Utns 1318 ‘THOROUGH EXAMINATION OF MECHANICAL EQUIPMENT ‘The particulars below are in accordance with the lifting operations & ling equipment Regulations 1998 CERTIFICATENUMBER: BPSV0I2/10 DATE OFINSPECTION: 260472010, {EQUIPMENT DESCRIPTION: MINI PILING RIG ON METAL TRACKS ‘MANUFACTURER; KLEMM MARK: 20014 ‘MODEL: 700-1 COMPANY NAME & ADDRESS: (CUSTOMER SITE: BERRY PILING SYSTEMS LIMITED 45.85 GEE STREET, LONDON C1 DETAILS OF THOROUGH EXAMINATION CARRIED OUT: NO PARTS OPENED pee {hereby declare that he gupmentin his ecard was thoroughly exanine,o tested and ‘arog exanbned in accordance with he appropriate provisions and found be fom ay defect likely to affect safety fff$AV4/10_and the above particulars are correct SIGNATURE: ~~ ‘Stephen Thatcher plant engineer workshop manager DATE OF LAST INSPECTION: 28/04/2009 LAST INSPECTION NUMBER: BPS/™272009 DATE OF NEXT INSPECTION: 277042011 Reding rks Proc pple um anaao att eanam eo eT cOPEOM ID MEER cmDSARaTS SPECIFICATIONS PUMP SPECIFICATIONS Tenor i Pope Be Fa Ts ea en Oe ie Geaee Oas anaes i aoe aS ‘Caen ae iepertnn ‘pr gy be TO ‘Gasiomman tm eg DT i Der he ae ‘aoreme ta oR get aoa Farah oh oak

You might also like