MEASUREMENT OF CONSTRUCTION WORKS III

(COST ANALYSIS)

CONCRETE
DESCRIPTION :

UNIT :

METHOD :

BY HAND

Reinforced in-situ concrete Grade 20 in isolated column.

DATA
Material
Cement
Sand
Aggregate

=
=
=

RM16.00 /bag
RM29.00 /m
RM32.00 /m

Labour
Operator
General labour

=
=

RM85.00 /day
RM55.00 /day

Labour Constant
Mixing
Placing

=
=

1.50 hr/m
8.00 hr/m

CALCULATION

RM

RM

RM

A. MATERIAL COST
i) 1m cement

28 bag
m

ii) 2m sand

RM 29.00/m

RM58.00 /2m

RM 32.00/m

RM128.00 /4m
RM634.00 /7m

iii) 4m aggregate x

RM16.00
bag

RM448.00 /m

Add :
50% Shrinkage, Consolidated & Wastage
Cost per 7m
Therefore, Material cost

RM317.00
RM951.00 /7m

RM951.00
7 m

RM135.86 /m

B. LABOUR COST
i) Labour cost for hoisting, transporting, placing & packing concrete.
RM 55.00 /day
8 hours

1 general labour x

8.00 hr
m

RM55.00 /m

1.50 hr
m

RM10.31 /m

ii) Labour cost for mixing


RM 55.00 /day
8 hours

1 general labour x

Therefore, Labour Cost

RM65.31 /m

D. TOTAL COST
Cost for material & labour

RM201.17 /m

Add :
15% Profit & Overhead

RATE CONCRETE GRADE 20

notes QSD231/syhidi/2011

RM30.18

RM231.35 /m