CONCRETE
DESCRIPTION :
UNIT :
METHOD :
BY HAND
DATA
Material
Cement
Sand
Aggregate
=
=
=
RM16.00 /bag
RM29.00 /m
RM32.00 /m
Labour
Operator
General labour
=
=
RM85.00 /day
RM55.00 /day
Labour Constant
Mixing
Placing
=
=
1.50 hr/m
8.00 hr/m
CALCULATION
RM
RM
RM
A. MATERIAL COST
i) 1m cement
28 bag
m
ii) 2m sand
RM 29.00/m
RM58.00 /2m
RM 32.00/m
RM128.00 /4m
RM634.00 /7m
iii) 4m aggregate x
RM16.00
bag
RM448.00 /m
Add :
50% Shrinkage, Consolidated & Wastage
Cost per 7m
Therefore, Material cost
RM317.00
RM951.00 /7m
RM951.00
7 m
RM135.86 /m
B. LABOUR COST
i) Labour cost for hoisting, transporting, placing & packing concrete.
RM 55.00 /day
8 hours
1 general labour x
8.00 hr
m
RM55.00 /m
1.50 hr
m
RM10.31 /m
1 general labour x
RM65.31 /m
D. TOTAL COST
Cost for material & labour
RM201.17 /m
Add :
15% Profit & Overhead
notes QSD231/syhidi/2011
RM30.18
RM231.35 /m