Professional Documents
Culture Documents
Microsoft Project - Precast Schedule
Microsoft Project - Precast Schedule
Task
Mode
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
Project: msproj11
Date: May 2 '15
Task Name
Duration
Start
Finish
Predecessors
May 3, '15
S
M
Jun 7, '15
T
W
May 2 '15
Dec 2 '15
May 2 '15
May 2 '15
Jul 19 '15
May 4 '15
May 4 '15
May 12 '15
May 12 '15
May 28 '15
May 30 '15
Jun 6 '15
Jun 6 '15
Jun 22 '15
15 days
Jun 23 '15
Jun 27 '15
4 days
Jun 27 '15
Jul 1 '15
Jul 1 '15
Jul 19 '15
Sep 23 '15
Sep 23 '15
Oct 29 '15
Sep 26 '15
10FS+60 days
Sep 26 '15
Oct 29 '15
Oct 29 '15
Oct 29 '15
Dec 2 '15
Dec 2 '15
12
13
13
DESIGN
3 days
7 days
15 days
7 days
4 days
15 days
FABRICATION
2 days
30 days
INSTALLATION
30 days
Task
Project Summary
Inactive Milestone
Deadline
Split
External Tasks
Inactive Summary
Manual Summary
Progress
Milestone
External Milestone
Manual Task
Start-only
Summary
Inactive Task
Duration-only
Finish-only
Page 1