Project: msproj11
Date: May 2 '15

Task Name

Duration

SCHEDULE OF WORKS PERTAINING 192 days


TO PREACAST
DESIGN
70 days
Receipt of Architectural
3 days
drawings from AJEC
Sending enquiries to Precast
7 days
Subcontractors
Reciept of Quotation from
15 days
Subcontractor & Finalisation
Issuance of PO to Precast
7 days
Supplier
Receipt of Load calculations
15 days
from Precast subcontractors
Finalisation of precast &
4 days
architectural drawings
Submission of Civil base design 4 days
documens to SEC
Approval of Civil Base design
15 days
documents by SEC
FABRICATION
32 days
Issuing Manufacturing clearance 2 days
to the subcontractor
Manufacuring
30 days
INSTALLATION
30 days
Erection of Precast
30 days

Start

Finish

Predecessors

Mar 29, '15


F
S

May 3, '15
S
M

Jun 7, '15
T
W

Jul 12, '15


F
S

May 2 '15

Dec 2 '15

May 2 '15
May 2 '15

Jul 19 '15
May 4 '15

May 4 '15

May 12 '15

May 12 '15

May 28 '15

May 30 '15

Jun 6 '15

Jun 6 '15

Jun 22 '15

15 days

Jun 23 '15

Jun 27 '15

4 days

Jun 27 '15

Jul 1 '15

Jul 1 '15

Jul 19 '15

Sep 23 '15
Sep 23 '15

Oct 29 '15
Sep 26 '15

10FS+60 days

Sep 26 '15
Oct 29 '15
Oct 29 '15

Oct 29 '15
Dec 2 '15
Dec 2 '15

12
13
13

Aug 16, '15


S
M

Sep 20, '15 Oct 25, '15


T
W
T
F
S

Nov 29, '15 Jan 3, '16


Feb 7, '16
Mar 13, '16
S
M
T
W
T
F
S
S
SCHEDULE OF WORKS PERTAINING TO PREACAST

DESIGN
3 days
7 days
15 days
7 days

4 days
15 days
FABRICATION
2 days
30 days
INSTALLATION
30 days

Task

Project Summary

Inactive Milestone

Manual Summary Rollup

Deadline

Split

External Tasks

Inactive Summary

Manual Summary

Progress

Milestone

External Milestone

Manual Task

Start-only

Summary

Inactive Task

Duration-only

Finish-only

Page 1

You might also like