ID

Task Name

Duration

Start

Finish

Cost

Resource Names

\Advanced payment

1 day

Mon 29.2.16

Mon 29.2.16

554670,94.

2
3


- , , \Excavations, backfill ans sandy
gravel

0 days
40 days

Mon 29.2.16
Tue 1.3.16

Mon 29.2.16
Mon 25.4.16

203220,62.

4
5

\Building foundations

40 days

Tue 1.3.16

Mon 25.4.16

291256,00.

6
7

\Production

50 days

Tue 1.3.16

Mon 9.5.16

AQUARIUS\beams AQUARIUS

50 days

Tue 1.3.16

Mon 9.5.16

\columns

50 days

Tue 1.3.16

Mon 9.5.16

10

"I", "L", "Tr", TT \beams type "I", "L", "Tr", TT panels and plinth
panels

50 days

Tue 1.3.16

Mon 9.5.16

11

\roof cladding

50 days

Tue 1.3.16

Mon 9.5.16

167728,24.

\Assembly of precast concrete


construction

30 days

Tue 26.4.16

Mon 6.6.16

77861,60.

14

AQUARIUS\beams AQUARIUS

30 days

Tue 26.4.16

Mon 6.6.16

15

\columns

30 days

Tue 26.4.16

Mon 6.6.16

16

"I", "L", "Tr" TT \beams type "I", "L", "Tr" and TT panels

30 days

Tue 26.4.16

Mon 6.6.16

0,00.
0,00.
0,00.

17
18

\Monolithic works

30 days

Tue 26.4.16

Mon 6.6.16

108397,92.

19
20

\Plinth panels

80 days

Tue 1.3.16

Mon 20.6.16

14685,89.

21
22

\Facade cladding and steel construction

60 days

Tue 26.4.16

Mon 18.7.16

150140,13.

23
24

\Roof cladding

70 days

Tue 26.4.16

Mon 1.8.16

25

\Skylight and roof finishing works

70 days

Tue 26.4.16

Mon 1.8.16

214890,96.
69294,40.

12
13

February
B
M

March
B
29.2

0,00 .

921208,00.
0,00.
0,00.
0,00.

January
B

Page 1

April
B

May
B

June
B

July
B

August
B