You are on page 1of 2

SL No

TCE comments(22-01-2015)

1. Kindly provide updatedSLD for our


approval along with this submission as per
TCE comments through LOT no. 297,
comments sheet no 5946A-811-ETA-35.R5
dated 26-11-2013

2. Kindly provide ETAP Software File along


with relay setting calculation

3.Page no-6- Kindly cross check transformer


bus no. & correct the same

3. Page 8- few loads are not matching with


loads mentioned in Revision 5 SLD
dated26.9.2013. Kindly correct the same as
per updated SLD and submit the same SLD

4. Page 14- cooling pump other eqiupments


are shown 230v(1ph) where as in Revision 5
SLD dated 26.9.2013. it is mentioned
415V(3Ph) Kindly correct the same as per
updated SLD and same SLD for our
approval.
5.custmised detailed relay settings p-1, few
loads are not matching with SLD R5 as well
as table provided on page no8 of report

correction as recommended

Revised & updated SLD is attached


for your refernce.

Etap software file & relay setting


calculation is attached.

We have followed SLD.

Revised & updated SLD is attached


for your refernce.

Revised & updated SLD is attached


for your refernce.

The Revised calculation are based


on updated SLD attached.