Solar Tariff & Capex Trends
Solar Tariff & Capex Trends
January 2016
Govt. push coupled with aggressive bidding by developers helps Solar Power achieve grid parity
Capacity Installation and Tariff Trends of Solar Power in India
Capacity (MW)
12.5
10.1
2010
2012
MP II
Chattisgarh
2013
Haryana
100
AP
100
375
5.08
150
Karnataka II
100
Rajasthan
Tn
AP
Punjab
25
Karnataka I
Odisha II
200
375
5.8
5.7
500
5.4
312
4.8
4.35
500
420
2015
2014
NSM - RJ
500
6.5
6.7
NSM - AP
500
1,500
7.5
Telangana II
6.5
6.7
Telangana
6.5
7.3
NSM Ph II B1
6.5
1,000
6.9
NSM Ph II B1
6.9
300
Odisha I
NSM Ph2 B2
150
6.4
6.7
500
MP
350
NSM Ph1 B1
Gujarat
303
7.3
MP
8.4
7.3
2016
2009-10
15.2
2010-11
14.4
2011-12
9.8
2012-13
8.0
2013-14
6.1
6.1
5.0
2014-15
2015-16
2016-17
17.0
With a present installed capacity of 5.1 GW (Jan 2016), Indias plan for 100 GW by 2022 does not seem impossible
Solar Tariffs have reached Grid Parity with latest bids at Rs 4.34/KWh and Capex dropping to <5.5 Cr/MW
Source DB research report
Capital Expenditure for the solar projects has decreased to ~5 Cr/MW from ~17Cr/MW in 2010
Trends in Benchmark Cost of PV Solar Projects CERC (INR Cr/MW)
2011-12
2012-13
2013-14
2014-15
2015-16
2016-17*
Change in 6
years
PV Modules
9.15
8.33
4.94
3.36
3.34
3.32
3.10
-66%
Land Cost
0.05
0.15
0.16
0.17
0.18
0.25
0.25
400%
0.90
0.95
0.90
0.95
0.40
0.50
0.35
-61%
Mounting Structures
0.80
1.05
1.00
1.05
0.50
0.50
0.35
-56%
1.80
1.60
0.98
0.60
0.50
0.45
0.30
-83%
0.85
0.90
1.00
1.05
0.60
0.55
0.40
-53%
1.65
1.44
0.80
0.80
0.60
0.49
0.26
-84%
15.20
14.42
9.78
7.97
6.12
6.06
5.01
-71%
Total
2009-10
17.00
2010-11
Parameter
Source CERC