Cheong Gye Cheon Restoration Project: - A Revolution in Seoul
Cheong Gye Cheon Restoration Project: - A Revolution in Seoul
After
Before
ICLEI 2006
Content
Introduction
Seoul and Cheong Gye Cheon
Background
Outline
Challenges
Progress
ICLEI 2006
Introduction
ICLEI 2006
Seoul at a glance
City Centre
Han river
ICLEI 2006
ICLEI 2006
Early 20C
ICLEI 2006
Problem: sanitation
ICLEI 2006
Solution: covering
ICLEI 2006
10
Covering work
(1958~1977)
ICLEI 2006
11
Cheonggye Highway
(1967~1971)
ICLEI 2006
12
Highway in 1990s
ICLEI 2006
13
ICLEI 2006
14
15
ICLEI 2006
16
17
Safety problem
18
Safety problem
19
ICLEI 2006
20
ICLEI 2006
21
Why restore?
Paradigm shift of urban management
Development High quality of life
Environment-friendly city
ICLEI 2006
22
ICLEI 2006
23
Site location
Total length: 5.84 km
Section 1 (L=2.04km)
Section 2 (L=2.1km)
ICLEI 2006
Section 3 (L=1.7km)
24
Demolition
Covered structure and highway: 5.4 km
Waste (concrete+asphalt): 872,400ton (96% recycled)
Step 1
Step 2
Step 3
ICLEI 2006
25
River design
Design Criteria
Satisfy with the 2nd grade local river standard
Secure the stream capacity for 200 years frequency rainfall (118mm/hr)
HWL (200yrs)
ICLEI 2006
26
Water supply
Waterway plan
Width: more than 20% of main waterway width
Depth: more than 40 cm
Flow velocity: 0.24 m/sec
Measures to prevent water loss
3mg/l or less
SS:
25 mg/l or less
DO:
5 mg/l or less
ICLEI 2006
1 mg/l or less
27
Sewer system
Design Criteria
Combined sewer system for rainfall and wastewater
Capacity : 3 times of estimated wastewater
ICLEI 2006
28
Bridge design
Design
Criteria
Number of bridges: 22
International concept design
competition
ICLEI 2006
29
Landscape design
Concepts
New green belt with waterfront: West to East
Gradual transformation from urban landscape to natural environment
Create ecological biotop and environment
Thematic places: waterfall and fountains
Upstream
A
History
B
Culture + Urban
ICLEI 2006
Downstream
Nature
30
ICLEI 2006
31
- Challenges
- Progress
ICLEI 2006
32
Challenge 1: Transport
Cheonggye road & hwy
Urban backbone corridor
170,000 vehicles/day
ICLEI 2006
33
Solutions to transport
Discourage driving cars in the city centre
Improve traffic system
Cheong Gye Cheon area
Metropolitan area
ICLEI 2006
34
ICLEI 2006
35
Solutions to merchants
Detailed survey on the markets and continu
ous interviews
consultation offices at the markets
regular meeting on the project
Minimize inconvenience f
or business activity
state-of-the-art technolog
y
provide parking space nea
rby
ICLEI 2006
36
Solutions to merchants
Stimulate business activity
Reduce parking fee
Improve parking system for loading & unloading
Promote Cheong Gye Cheon stores
37
- Progress
ICLEI 2006
38
Project delivery
Targets
Keeping the schedule
Best value for money
39
Construction progress
Started on 1 July 2003
ICLEI 2006
40
Construction progress
Stage 1: Scaffolding (July 2003)
ICLEI 2006
41
Construction progress
Stage 2: Highway demolition (Aug 2003)
ICLEI 2006
42
Construction progress
Stage 3: Covered road demolition (Jan 2004)
ICLEI 2006
43
Construction progress
Stage 4: Sewer, road & bridge construction (Sep 2004)
ICLEI 2006
44
Construction progress
Stage 5: Landscaping for the recovered area (May 2005)
ICLEI 2006
45
ICLEI 2006
46
ICLEI 2006
47
Grand opening
1 October 2005
ICLEI 2006
48
ICLEI 2006
49
Monitoring
Changes
Monitoring areas
Land use
CBD Industry
Environment
Ecology
Traffic
Real estate
ICLEI 2006
50
Traffic
Changes
Speed in CBD
Morning peak: 17~18 km/hr
Evening peak: 12 km/hr
not very much worsened
Subway ridership
Central area: +13.7%
ICLEI 2006
51
Environment
Changes
Air
No2:
Water quality
BOD: 100~250 1~2 ppm
ICLEI 2006
52
Cooling effect
Changes
Thermal image
27 July 2005
37o
28o
36o
36o
Average 32.7oC
-3.6oC
Average 36.3oC
Nearby street
ICLEI 2006
53
Environmental improvement
Changes
V improved
Improved
Unchanged
Odour
Daylight
Wind
0%
25%
50%
ICLEI 2006
75%
100%
54
Ecology: Fishes
Changes
3 14 species
ICLEI 2006
55
Ecology: Birds
Changes
18 species
ICLEI 2006
56
Ecology: Insects
Changes
7 41 species
ICLEI 2006
57
ICLEI 2006
Final Remarks
58
ICLEI 2006
59
Economic vitality
Pedestrian oriented street s
ystem
International standard busin
ess district
ICLEI 2006
60
ICLEI 2006
61
Virtual Tour
ICLEI 2006
62
Further information
http://english.seoul.go.kr/cheonggye/
iklee@seoul.go.kr
ICLEI 2006